•Dry Storage of N Reactor and Single-Pass Reactor Fuel
•Site-Wide Fuel Consolidation• Fast Flux Test Facility Fuel• Oregon State University Fuel
•Disposition of Cesium and Strontium Capsules
Hanford Spent Nuclear Fuel Status
![Page 3: Hanford Spent Nuclear Fuel and Cesium/Strontium Capsule Status Presented by Sen Moy - RL National SNF Meeting November 8, 2005](https://reader036.vdocument.in/reader036/viewer/2022082818/56649eac5503460f94bb25fb/html5/thumbnails/3.jpg)
Hanford Spent Nuclear Fuel Status
• Removal of Canistered Fuel at K Basins Complete– Fuel loaded into 386 Multi-Canister
Overpacks, dried, and transferred to Canister Storage Building for final closure weld and interim storage
– Sludge and debris retrieval activities on-going at K Basins
![Page 4: Hanford Spent Nuclear Fuel and Cesium/Strontium Capsule Status Presented by Sen Moy - RL National SNF Meeting November 8, 2005](https://reader036.vdocument.in/reader036/viewer/2022082818/56649eac5503460f94bb25fb/html5/thumbnails/4.jpg)
Dry Storage of N Reactor and Single-Pass Reactor Fuel
• Up to 3 additional MCO(s) anticipated for fuel and scrap discovered during sludge removal, some found fuel– Fuel inventoried as unknown SPR, likely PRTR fuel– 2+ SPR elements at B/C Reactor burial grounds– SPR elements/pieces and N Fuel element at KW Basin
• Welding (with N Stamp) completed for 397 MCOs (includes 18 containing Shippingport SNF) – No defects to date – 7 MCOs in sampling/monitoring program will be welded
in future; remaining 1-3 MCOs from K Basins will be welded at that time
![Page 5: Hanford Spent Nuclear Fuel and Cesium/Strontium Capsule Status Presented by Sen Moy - RL National SNF Meeting November 8, 2005](https://reader036.vdocument.in/reader036/viewer/2022082818/56649eac5503460f94bb25fb/html5/thumbnails/5.jpg)
Site-Wide Fuel Consolidation
• Deinventory of Fuel from Fast Flux Test Facility On-going
– Loading of non-sodium bonded fuel into Interim Storage Casks ~90% complete; scheduled transfer of remaining fuel to 200 Area in March 2006
– Schedule transfer of sodium bonded fuel to INL beginning in FY2006; Modification of Certificate of Compliance for T-3 Cask on-going
• Oregon State University TRIGA Fuel Retrieval and Transfer to 200 Area Interim Storage Area scheduled to start April 2006.
![Page 6: Hanford Spent Nuclear Fuel and Cesium/Strontium Capsule Status Presented by Sen Moy - RL National SNF Meeting November 8, 2005](https://reader036.vdocument.in/reader036/viewer/2022082818/56649eac5503460f94bb25fb/html5/thumbnails/6.jpg)
Disposition of Cesium/Strontium Capsules
• Hanford baseline assumes direct disposal of capsules at Yucca Mountain beginning in 2018
• 1,936 cesium and strontium capsules currently in wet storage at Hanford Site
– 1335 capsules containing cesium chloride
– 601 capsules containing strontium fluoride
– 127 million curies in August 2003
• YMP EIS include capsule inventory within Immobilized High Level Waste. Draft YMP License Application do not address capsule inventory.
![Page 7: Hanford Spent Nuclear Fuel and Cesium/Strontium Capsule Status Presented by Sen Moy - RL National SNF Meeting November 8, 2005](https://reader036.vdocument.in/reader036/viewer/2022082818/56649eac5503460f94bb25fb/html5/thumbnails/7.jpg)
![Page 8: Hanford Spent Nuclear Fuel and Cesium/Strontium Capsule Status Presented by Sen Moy - RL National SNF Meeting November 8, 2005](https://reader036.vdocument.in/reader036/viewer/2022082818/56649eac5503460f94bb25fb/html5/thumbnails/8.jpg)
Disposition of Cesium/Strontium Capsules
• Tri-Party Agreement milestone due June 2007 to assess viability of direct disposal and submit change request to establish enforceable milestones to achieve cesium and strontium disposition by 2028
• Capsules are designated as RCRA regulated
• RL strategy is to pursue direct disposal to YMP and complete regulatory strategy to exempt/de-list hazardous constituents to allow disposal at YMP
• Complete performance assessment in FY 2006 to support viability assessment