health, safety, and environmental (hse) manual rizzo

59
HSE Manual Rev. 1 © RIZZO Proprietary and Confidential Work Product Page 1 of 44 HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO INTERNATIONAL, INC. (RIZZO) REVISION 1 JULY 12, 2018 REVIEWED AND APPROVED BY: Originator(s) Signature Effective Date: Corporate QHSE Officer Dee M. Xenakis July 12, 2018 Reviewer(s) Signature Senior Director of Project Management John Paul Giunta, P.E., PMP July 12, 2018 Chief Operating Officer Michael J. Edwards, P. E. July 12, 2018 Verifier(s) Signature Verification method: Independent Review Chief Geologist Rolando J. Benitez, P. G. July 12, 2018 Responsible Manager Signature President Rachelle Rizzo July 12, 2018 Approval of the Responsible Manager signifies that the document and all required reviews are complete, and the document is released for use.

Upload: others

Post on 08-Apr-2022

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

Page 1 of 44

HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL 

RIZZO INTERNATIONAL, INC. (RIZZO) REVISION 1 

JULY  12, 2018 

REVIEWED AND APPROVED BY: 

Originator(s)   Signature  Effective Date: 

Corporate QHSE Officer 

Dee M. Xenakis  July 12, 2018 

Reviewer(s)  Signature

Senior Director of Project Management 

John Paul Giunta, P.E., PMP  July 12, 2018 

Chief Operating Officer  

Michael J. Edwards, P. E.  July 12, 2018 

Verifier(s)  Signature  Verification method:  Independent Review 

Chief Geologist

Rolando J. Benitez, P. G.   July 12, 2018 

Responsible Manager  Signature

President 

Rachelle Rizzo  July 12, 2018 

Approval of the Responsible Manager signifies that the document and all required reviews are complete, and the document is released for use.    

Page 2: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 2 of 44 

TABLE OF CONTENTS PAGE 

 

1.0  SCOPE, PURPOSE, AND APPLICABILITY ................................................................... 5 

1.1  QHSE POLICY ................................................................................................. 5 

1.2  OBJECTIVES ..................................................................................................... 6 

1.3  HEALTH, SAFETY AND ENVIRONMENTAL ELEMENTS ................................................. 6 

1.4  CULTURE ........................................................................................................ 6 

1.5  ROLES AND RESPONSIBILITIES ............................................................................. 7 

1.6  HSE TRAINING ................................................................................................ 8 

2.0  GENERAL HEALTH, SAFETY, AND ENVIRONMENTAL RULES ................................... 9 

2.1  INJURY AND ILLNESS REPORTING ......................................................................... 9 

2.2  RULES FOR PERSONNEL CONDUCT ....................................................................... 9 

2.3  PERSONAL PROTECTIVE EQUIPMENT (PPE) ......................................................... 11 

2.4  SITE COMMUNICATIONS .................................................................................. 15 

2.5  SITE ENTRY/EXIT ............................................................................................ 15 

2.6  EQUIPMENT .................................................................................................. 15 

2.7  TOOLBOX SAFETY AND ENVIRONMENTAL MEETINGS ............................................. 16 

2.8  VIOLATING HEALTH, SAFETY AND ENVIRONMENTAL PROCEDURES ............................ 17 

2.9  DRUG AND ALCOHOL ABUSE ............................................................................ 17 

3.0  SLIPS, TRIPS, AND FALLS ........................................................................................ 18 

3.1  TYPES OF FALLS .............................................................................................. 18 

3.2  CONTRIBUTING FACTORS ................................................................................. 18 

3.3  FALLS FROM VEHICLES AND EQUIPMENT ............................................................. 18 

3.4  SHOES AND BOOTS ......................................................................................... 18 

4.0  EMERGENCY RESPONSE/PLANNING ..................................................................... 19 

4.1  TABLE:  EMERGENCY TELEPHONE NUMBERS/DIRECTIONS TO HOSPITAL .................... 19 

4.2  EVACUATION PROCEDURES .............................................................................. 19 

4.3  MEDICAL EMERGENCY .................................................................................... 19 

4.4  FIRE EMERGENCY ........................................................................................... 20 

4.5  SPILL/RELEASE OF HAZARDOUS MATERIAL .......................................................... 20 

Page 3: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 3 of 44 

5.0  ENVIRONMENTAL ................................................................................................. 21 

5.1  GENERAL WILDLIFE MEASURES ......................................................................... 21 

5.2  DUST CONTROL ............................................................................................. 21 

5.3  NOISE .......................................................................................................... 21 

5.4  PETROLEUM, OIL, LUBRICANT AND CHEMICAL HANDLING AND STORAGE .................. 21 

5.5  WASTE MANAGEMENT ................................................................................... 23 

5.6  EROSION, SURFACE AND GROUNDWATER POLLUTION PREVENTION AND CONTROL ...................................................................................................... 24 

5.7  SITE DEMOBILIZATION ..................................................................................... 24 

6.0  UTILITIES ................................................................................................................ 25 

6.1  PRE‐EXCAVATION/DRILLING ............................................................................. 25 

6.2  EXCAVATION/DRILLING ................................................................................... 25 

6.3  MARKING PRESERVATION ................................................................................ 25 

6.4  FACILITY DAMAGE NOTIFICATION ...................................................................... 25 

6.5  NOTIFICATION OF EMERGENCY ......................................................................... 25 

6.6  EXCAVATION/DRILLING OBSERVER .................................................................... 26 

6.7  EXCAVATION/DRILLING TOLERANCE ZONE........................................................... 26 

6.8  OVERHEAD POWER LINES ................................................................................ 26 

7.0  EXCAVATION, DRILLING, AND RIGGING SAFETY ................................................... 28 

7.1  EXCAVATION ................................................................................................. 28 

7.2  NATURAL GASES ............................................................................................ 28 

7.3  GENERAL DRILLING SAFETY .............................................................................. 29 

8.0  FIRE PREVENTION PROGRAM ............................................................................... 34 

8.1  FIRE PREVENTION AND MINIMIZATION ............................................................... 34 

8.2  FIRE EXTINGUISHING EQUIPMENT ...................................................................... 36 

9.0  SEVERE WEATHER PLAN ........................................................................................ 37 

9.1  HEAT RELATED ILLNESSES ................................................................................. 37 

9.2  TABLE:  STAGES, SYMPTOMS, AND FIRST AID MEASURES FOR HEAT STRESS ....................................................................................................... 38 

10.0  HSE INSPECTIONS .................................................................................................. 39 

10.1  TABLE:  HSE INSPECTIONS ............................................................................... 39 

Page 4: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 4 of 44 

11.0  TABLE:  JOB HAZARD ANALYSIS FOR SUBSURFACE INVESTIGATION .................... 40 

12.0  TABLE:  JOB HAZARD ANALYSIS FOR SITE VISITORS .............................................. 43 

13.0  FORMS ................................................................................................................... 44 

14.0  CHANGE MANAGEMENT RECORD ........................................................................ 44 

 

Page 5: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

Page 5 of 44

1.0 SCOPE, PURPOSE, AND APPLICABILITY 

This Health, Safety, and Environmental Manual (hereafter known as the HSE) Manual, has been 

developed to comply with regulatory,  industry, statutory, and client requirements  imposed by 

clients or regulatory agencies for items and services provided by RIZZO world‐wide operations.  

This HSE Manual describes RIZZO’s commitments to: 

identify and control the environmental impact of its activities, products or services,

identify and control job hazards and other risks that may impact the health and safety of

RIZZO employees, contractors, customers or visitors to our sites,

improve its HSE performance continually, and

implement  a  systematic  approach  to  setting,  achieving  and documenting HSE  related

objectives and targets.

RIZZO’s  commitment  to  health,  safety,  and  the  environment  ranks  equally  with  all  other 

primary business objectives.  Compliance with this policy is the responsibility of every employee 

and contractor.  Our goal is to prevent all injuries and eliminate or minimize health, safety, and 

environmental risks in our operations.  All employees are responsible for HSE compliance.  

This HSE Manual serves as a directive  for organizations  in establishing necessary policies and 

procedures that comply with the  following requirements as approved by RIZZO  for applicable 

locations and projects, as well as applicable local or country specific regulations:   

● International  Atomic  Energy  Agency  (IAEA)  GSR  Part  2,  “Leadership  and

Management for Safety”

● ISO 14001, “Environmental Management Systems Requirements”

● OHSAS 18001, “Occupational Health and Safety Standard”

● Occupational  Safety  and Health  Administration  (OSHA)  standards  (29  Code  of

Federal Regulations [CFR]) 1910 General Industry and 1926 Construction.

1.1 QHSE POLICY  

The RIZZO QHSE Policy  is that employees strive to: “Meet or exceed client requirements, and 

seek to continuously improve our Quality, Health, Safety and Environment (QHSE)”.  

Page 6: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 6 of 44 

 

RIZZO Management  is  responsible  for ensuring  that  this policy  is communicated, understood, 

and  implemented  at  all  levels  of  the  organization,  and  is  regularly  reviewed  for  continuing 

suitability.    All  employees  are  expected  to  perform  their  responsibilities  in  accordance with 

applicable QHSE requirements, and to strive for client satisfaction and continual improvement.  

Maintaining  an  atmosphere  of  integrity  and  responsiveness  is  one  of  the  most  important 

attributes  of  the  work  environment.    All  employees  are  encouraged  to  openly  express  all 

concerns for the safety and quality of RIZZO items and services. 

 

1.2 OBJECTIVES  

The RIZZO Goals, Plans, and Objectives involve short‐term and longer‐term issues identified by 

RIZZO management.  The QHSE policy provides a framework for establishing and reviewing the 

company  objectives.    The  objectives  are measurable  and  consistent  with  the  QHSE  policy.  

Methods are in place as required to track, update, revise and review the plans and objectives to 

ensure  that  the  plans  are  adhered  to  and  communicated  throughout  the  organization  as 

appropriate.   

 

1.3 HEALTH, SAFETY AND ENVIRONMENTAL ELEMENTS  

The fundamental elements of the HSE Management System are as follows: 

• Policy and principles; 

• Planning, including the means of assessing HSE aspects and risks, consideration of legal 

and other requirements, setting objectives and targets and the means to achieve them, 

and reporting on HSE performance; 

• Implementation  and operation,  including  key  roles  and  responsibilities,  the means  to 

maintain  competency  and  adequate  resources,  communication,  documentation,  and 

operational controls; 

• Checking,  including monitoring and measurement, performance assessments,  incident 

investigations and corrective actions, and control of related records; and 

• Management review. 

 

1.4 CULTURE 

HSE Culture is defined as the core values and behaviors resulting from a collective commitment 

by leaders and individuals to emphasize HSE over competing goals to ensure the protection of 

Page 7: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 7 of 44 

people and the environment. Many of the elements of the HSE Management System, including 

the QHSE Policy promote and support a strong HSE culture by: 

• Providing  the  means  by  which  the  organization  supports  individuals  and  teams  in 

carrying out  their  tasks and work processes  in a safe and environmentally  responsible 

manner,  taking  into account  the  interaction between  individuals,  technology, and  the 

organization; 

• Providing  the  framework  in  which  leaders  demonstrate  their  commitment  to  HSE 

through their values and actions and individuals take personal accountability for HSE; 

• Reinforcing a  learning and questioning attitude at all  levels of the organization, where 

opportunities to learn about ways to ensure HSE are sought out and implemented; 

• Providing for a safety‐conscious work environment (freedom to raise concerns without 

fear of retribution); 

• Providing the system(s) for HSE problem identification and resolution; 

• Providing  the  means  by  which  the  organization  continually  seeks  to  develop  and 

improve  its HSE culture,  including  its commitment to compliance and a strong nuclear 

safety culture; and 

• Providing a framework for decision making which reflects safety first. 

 

1.5 ROLES AND RESPONSIBILITIES  

The resources, roles, responsibilities, accountability and authority are described  in  the 

RIZZO  QHSE Management  System.    In  general,  RIZZO management  shall  ensure  the 

availability of resources essential to establish, implement, and improve the HSE System.   

 

While  management  has  the  prime  responsibility  for  establishing  safety  policies, 

procedures, and working conditions, most of what is planned and established affects the 

employees  on  the  job.  The  supervisor  is  responsible  for  the  direct  oversight,  and  to 

communicate and enforce all safety rules, policies, and procedures. 

 

1.5.1 Site Supervisor  

The supervisor has the following HSE responsibilities:  

a. Instruct their employees concerning the hazards of their job, how to avoid injury, 

emergency evacuation and applicable HSE emergency procedures.  

b. Conduct periodic HSE appraisals of the job site.  

Page 8: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 8 of 44 

c. Ensure personnel protective equipment (PPE) is provided for each employee.  

d. Communicate  to employees  that willful violations of established HSE  rules will 

not be tolerated.  

e. Ensure all injuries and incidents are reported immediately to HSE management.  

f. Investigate HSE issues, identify causes, and implement corrective action.  

g. Conduct HSE observations within the employee’s area of responsibility.  

 

1.5.2 Employee Responsibility  

Each employee has the following responsibilities: 

a. Follow safe working practices as directed by the supervisor. 

b. Comply with all HSE rules and procedures. 

c. Report immediately to the supervisor any unsafe activities . 

d. Know and understand the QHSE Policy, and applicable procedures . 

e. Wear all assigned PPE when required.  

f. If  uncertain  about  an  activity  or  condition,  check  with  the  supervisor  for 

instructions before proceeding.  

g. Immediately report all accidents or injuries to the supervisor.  

 

1.6 HSE TRAINING  

RIZZO shall establish and  implement the training of employees, contractors, visitors, and sub‐

contractors  in  environmental  awareness  and  the  recognition,  avoidance,  and  prevention  of 

unsafe work practices and conditions during an initial site orientation.  It is the responsibility of 

the supervisor  to  identify potential  training needs and  timetables so  that  these requirements 

are met.  Documentation of training shall be maintained in the RIZZO files.  

Page 9: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 9 of 44 

 

2.0 GENERAL HEALTH, SAFETY, AND ENVIRONMENTAL RULES 

 

2.1 INJURY AND ILLNESS REPORTING 

The supervisor is responsible for ensuring that all work‐related incidents, including injuries and 

illnesses, property damage, and “near misses” are recorded on the Occupational Injury & Illness 

Report and Near Miss Incident Report Form.  The supervisor shall ensure that the incidents are 

investigated; the extent of the investigation will depend on the severity of the accident.  These 

incidents  shall  be  reported  to  the QHSE management  and  designated  personnel  as  soon  as 

reasonably possible.   

2.1.1 Immediately  report  all  injuries  and/or  incidents,  no  matter  how  slight,  to  your 

supervisor.   Any  injury should be examined and/or  treated at  the nearest appropriate 

medical  facility/clinic.   Medical  reports  from  off‐site  visits must  be  provided  to  the 

designated QHSE management for record‐keeping purposes.   

2.1.2 When  injury and/or damage are sustained, barricade the area and give necessary help 

to the injured person.  Equipment/materials must not be moved unless causing a serious 

obstruction or blocking emergency access routes. 

 

2.2 RULES FOR PERSONNEL CONDUCT 

2.2.1 Do not operate equipment  that you have not  first been  trained and/or authorized  to 

operate. 

2.2.2 Horseplay and fighting on RIZZO sites are strictly prohibited. 

2.2.3 Reading materials are allowed during  lunch or scheduled work breaks, provided that  it 

does not distract personnel from performing their job functions. 

2.2.4 Cameras are not permitted on any client site without written approval  from the client 

representative. 

2.2.5 Sleeping on site (including in parking areas) is prohibited. 

2.2.6 It is permitted to listen to radios at low volume such that it will not distract co‐workers 

or interfere with the ability to hear the paging system and alarms.  Headphones are not 

permitted during  field activities, and/or when operating equipment such as measuring 

and testing equipment (M&TE) unless authorized by the employee’s supervisor. 

Page 10: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 10 of 44 

2.2.7 Individuals  are  required  to  respect  the  rights of each other.   Using abusive  language, 

ethnic slurs with racial overtones, etc., is strictly prohibited. 

2.2.8 While conducting RIZZO business, the driver and all passengers  in a vehicle must wear 

seatbelts.   The driver  is responsible for ensuring that passengers are wearing seatbelts 

prior to putting the vehicle in motion. 

2.2.9 The use, possession, transportation, or sale of  illegal drugs,  firearms, deadly weapons, 

or  unauthorized  explosives while  on  RIZZO  premises, worksites,  in  RIZZO  vehicles  or 

while traveling is strictly prohibited. 

2.2.10 Smoking is permitted in designated areas only. 

2.2.11 When ascending or descending  stairways, use  the handrail, always walk on  the  right‐

hand side of the stairway, and only take one step at a time. 

2.2.12 Running in work or office areas, except for emergency purposes, is strictly prohibited. 

2.2.13 When  lifting  loads, use proper  lifting  techniques,  such as bending of knees, obtaining 

assistance, and mechanical lifting aids. 

2.2.14 Barricades must be erected around areas of hazardous work, such as holes  in decking 

flooring  and  work  areas,  trenches,  overhead  activities,  open  unattended  vessels,  or 

dangerous storage.  Only the person in charge may grant permission for entry into these 

areas. 

2.2.15 Climbing  or  standing  on  equipment  is  discouraged.    Scaffolding,  ladders,  or  a  safety 

harness and  lanyard  shall be used  if  the working height  is greater  than 2 meters  (m) 

(approximately 6 feet [ft]) from ground level. 

2.2.16 Walking on  tank  roofs  is prohibited  except  in designated walking  areas or where  fall 

protection equipment or barriers are provided. 

2.2.17 The use of  cell phones not having  “Hands‐Free”  capability  is  strictly prohibited when 

operating vehicles. 

2.2.18 Drivers must follow posted road safety signs.   Road or weather conditions may require 

reduced speed or restriction on travel. 

Page 11: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 11 of 44 

 

2.3 PERSONAL PROTECTIVE EQUIPMENT (PPE) 

The following section establishes minimum requirements for the selection and use of personal 

protective equipment (PPE) to provide employees with eye, face, head, arm, hand, body, foot, 

and ear protection for all RIZZO sites. Respiratory protection, fall protection, and electrical 

hazard protection are covered in lower level procedures.  

The following PPE are the standard requirements at all RIZZO sites except office areas unless 

the client and/or supervisor authorize alternative PPE requirements: 

Hardhat 

Safety glasses 

Hearing protection in high noise areas 

Reflective vest 

Work gloves when there is a potential for hand injury 

Full length pants 

Approved safety footwear with a substantial sole 

Other PPE may be required depending on specific work activities 

Long pants

Page 12: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 12 of 44 

2.3.1 Eye and Face Protection:  ANSI Z87.1, American National Standard Practice for 

Occupational and Educational Eye and Face Protection (or equivalent) 

2.3.1.1 Safety glasses must be worn at all times when on project sites and field 

related activities.  Safety glasses must have rigid side shields.  Safety glasses 

need not be worn in administrative areas.    

2.3.1.2 Employees shall use appropriate eye or face protection when exposed to 

eye or face hazards from flying particles, molten metal, liquid chemicals, 

acids or caustic liquids, chemical gases or vapors, or potentially injurious 

light radiation.  

2.3.1.3 Welding helmets or face shields should be used only over primary eye 

protections (safety glasses or goggles).   

2.3.1.4 Caution should be exercised in the use of metal frame protective devices in 

electrical hazard areas.   

2.3.1.5 Care should be taken to recognize the possibility of multiple and 

simultaneous exposure to a variety of hazards.  Adequate protection against 

the highest level of each of the hazards must be provided.   

2.3.1.6 Employees who wear prescription lenses while engaged in operations that 

involve eye hazards shall wear eye protection that incorporates the 

prescription in its design, or shall wear eye protection that can be worn over 

the prescription lenses without disturbing the proper position of the 

prescription lenses or the protective lenses.  

2.3.1.7 Welding & Laser Operations: If working with or near sources of potentially 

injurious light radiation (i.e., welding, cutting, and lasers) appropriate work 

procedures or directions shall stipulate the type of filter lenses to be used 

for these types of work.  

2.3.1.8 Protection from light radiation is directly related to filter lens density.  Select 

the darkest shade that allows optimum task performance.   

2.3.1.9 Tinted and shaded lenses are not filter lenses unless they are marked or 

identified as such. These must be approved and certified before use on the 

job, by the safety coordinator and manager/supervisor.  

2.3.1.10 Regular inspection and cleaning of the eye protection lenses is required.   

 

2.3.2 Head Protection:  ANSI Z89.1 American National Standard for Industrial Head 

Protection. Suggested type is Type 2, Class G for general use. 

Page 13: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 13 of 44 

Electrical Helmets: ANSI Z89.2 for the head protection of employees exposed to 

high voltage electrical shock and burns. 

Welding helmets and filter plates: ASNI Z49.1 

2.3.2.1 Employees who are assigned to site projects or perform field related work 

activities shall be provided with and required to wear head protection at all 

times while performing field tasks.  The need for additional PPE will be 

addressed through hazard assessments and site safety and health plans. 

2.3.2.2 Employees shall wear head protection (hard hats) when working in areas 

where there is a potential for injury to the head from falling or flying objects 

and overhead hazards.  

2.3.2.3 Operators of vehicles and equipment are required to wear hard hats during 

the operation of such equipment except in enclosed cabs. 

2.3.2.4 Where there is a risk of injury from hair entanglements in moving parts of 

machinery, combustibles, or toxic contaminants, employees shall confine 

their hair to eliminate the hazard. 

2.3.2.5 When using a face shield, welding hood, or sandblasting hood, the type 

which combines with a hard hat shall be used. 

2.3.2.6 Clearance must be maintained between the hard hat shell and suspension. 

Employees shall ensure nothing is carried inside a hard hat that will reduce 

the clearance. 

2.3.2.7 Hard hats are grouped into three classes (G, E, and C) and two types (1 and 

2) according to how they meet various criteria for protection from impact, 

penetration, electrical conductivity, flammability, and other safety hazards.  

Class G hard hats are intended to protect the head from the force of 

impact of falling objects and from electrical shock during contact with 

exposed low voltage conductors. 

Class E hard hats are intended to protect the head from the force of 

impact of falling objects and from electrical shock during contact with 

exposed high voltage conductors. 

Class C hard hats are intended to protect the head from the force of 

impact of falling objects. 

2.3.2.8 Type 1 hard hats have a full brim.  

2.3.2.9 Type 2 hard hats have no brim but may include a peak. 

Page 14: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 14 of 44 

2.3.2.10 Hard hats shall be maintained in a fully functional and clean condition free 

of defects or damage. All components, shells, suspensions, and any 

accessories should be visually inspected regularly for signs of dents, cracks, 

penetration, or any other damage that might reduce the degree of safety 

originally provided. 

2.3.3 Hand and Arm Protection: Selection is to be based upon the tasks to be performed and 

the performance and construction characteristics of the glove material. For protection 

against chemicals, glove selection must be based on the chemicals encountered, the 

chemical resistance and the physical properties of the glove material. 

2.3.3.1 Employees shall wear hand protection (gloves) when exposed to hazards 

such as skin absorption of harmful substances, severe cuts or lacerations, 

severe abrasions, punctures, chemical burns, thermal burns, and harmful 

temperature extremes. 

2.3.3.2 Glove type shall be designed to protect against specific hazards.  Hand 

protection may include gloves made of leather, Kevlar, rubber, neoprene, 

etc.  Gloves suitable for the task must be chosen. 

2.3.3.3 Employees who are required to operate drill presses, power saws, bench 

grinders, and similar rotating machinery shall be aware of the hazards of 

rotating equipment while wearing gloves.  

2.3.4 Safety vests/shirts must be worn at all times unless inside a RIZZO or subcontractor’s 

office trailer, or other area designated as not requiring a safety vest, by the supervisor 

or QHSE staff.  Safety vests/shirts must be ANSI/ISEA 107‐2010 rated and include retro‐

reflective material (bands) on the front and back of the vest.  Safety t‐shirts may be 

worn, as long as they are ANSI rated and include retro‐reflective material. 

2.3.5 Hearing protection is required in high noise areas (85 decibels, A‐weighting [dB(A)] or 

higher), or where posted.  High noise areas are required to be posted with signs.  Double 

protection is recommended for extended occupancy of areas with noise levels above 

100 dB(A).   

Due consideration will be given to the use of effective engineering and 

administrative controls to reduce employee exposure to occupational noise 

hazards. 

Hearing PPE shall be provided in the form of ear plugs or ear muffs. 

2.3.6 Any person whose clothing becomes saturated with flammable liquid or chemicals 

should immediately go to a safe area away from fire hazards, change clothes, and take 

Page 15: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 15 of 44 

appropriate steps to wash skin areas contacted by the liquid or chemical.  Should the 

skin become red or inflamed, the individual should seek medical attention immediately. 

2.3.7 Finger rings, loose clothing, unsecured long hair, metal‐banded wristwatches, loose 

accessories, or other electrically conducive items are not to be worn when within the 

arm’s reach of unguarded operating machinery or electrical switchgear. 

2.3.8 No person shall enter a confined space or toxic gas cloud, not even for personnel rescue, 

without first notifying back‐up personnel and donning appropriate breathing apparatus 

and other personal protective equipment.  Only personnel trained in confined space 

entry may enter a confined space. 

 

2.4 SITE COMMUNICATIONS  

When  workers  are  on‐site,  the  supervisor  must  follow  RIZZO  communication/notification 

protocols, so that the number of workers on‐site is known at all times.  RIZZO employees are to 

have a cell phone and/or two‐way radio transceiver (walkie‐talkie) available for use at all times.   

 

2.5 SITE ENTRY/EXIT  

A single entry point is to be established where possible with a site entry/exit log for workers to 

sign for entry to and exit from the site.  Each time a worker enters and exits the site throughout 

the day, the log is required to be filled in so that the supervisor will have an accurate count of 

the number of workers on‐site.   

 

2.6 EQUIPMENT 

2.6.1 Fire extinguishers, eyewash stations, First Aid Kits, and other emergency equipment is to 

be maintained  in  good working  condition,  inspected  regularly,  and  kept  clear  of  any 

obstruction. 

2.6.2 Operation of equipment having a “DANGER, DO NOT OPERATE” tag is prohibited. 

2.6.3 Under  normal  operations,  operating machinery  and  electrical  switch  gear must  have 

required safety guards, switches, and alarms in place and functional.   

2.6.4 Compressed air may not be used for cleaning purposes above 30 pounds per square inch 

(psi), with  the  exception  of  abrasive  sand  blasting.   Do  not  apply  compressed  air  to 

yourself or others at any time.  Only compressed air shall be used for pneumatic tools. 

Page 16: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 16 of 44 

2.6.5 Every  floor or grating, working platform, or surface opening shall be properly guarded 

and maintained to protect against trips or falls. 

2.6.6 Whenever a  safety device  is  removed  from  service or otherwise placed  in a  “bypass” 

mode,  the appropriate  supervisor  is  to be notified,  the device  tagged, and  the action 

properly documented. 

2.6.7 Use only proper tools and equipment for each job and make sure these are maintained 

in  good  working  condition.    Handmade  tools  are  strictly  prohibited  at  any  RIZZO 

operated site unless approved by the supervisor. 

 

2.7 TOOLBOX SAFETY AND ENVIRONMENTAL MEETINGS  

Toolbox  Safety  and Environmental Meetings  are  an  important element of RIZZO’s  site work.  

They are an effective  training aid and an essential means of  increasing an employee’s hazard 

awareness and improving job performance.  The site supervisor is responsible for ensuring that 

a Toolbox Safety and Environmental Meeting  is conducted at  the beginning of each shift and 

document  the  required  form.     The Toolbox Safety and Environmental Meeting  topics should 

include the following:  

2.7.1 Review  of  pertinent  safety  and  environmental bulletins, weather  forecasts  and  other 

important topics that relate to work at the site. 

2.7.2 Review  of  planned  operations  for  the  day, work  assignments,  expected  visitors,  and 

events. 

2.7.3 Instructions on the safe and efficient planning and performance of work. 

2.7.4 Review or discussion of project accidents,  injuries,  illnesses, near misses, hazards, and 

safe/unsafe acts that occurred on previous shifts. 

2.7.5 Discussion of other  suggestions, observations, and comments  regarding  safety‐related 

topics. 

2.7.6 Safety Conscious Work Environment  

2.7.7 Emergency Response and Spill Containment Procedure 

Site  personnel  attending  the  Toolbox  Safety  and  Environmental  Meetings  include  RIZZO 

personnel,  its  sub‐contractors,  site  visitors,  and  representatives of  the  client  as  appropriate.  

Page 17: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 17 of 44 

Sub‐contractors  are  responsible  for  ensuring  that  their  personnel  comply  with  the  topics 

covered  in  the  Toolbox  Safety  and  Environmental Meetings.    The  subject material  shall  be 

pertinent  to  the  site work.    The  Toolbox  Safety  and  Environmental Meeting  Forms  are  be 

maintained by the site supervisor.   

 

2.8 VIOLATING HEALTH, SAFETY AND ENVIRONMENTAL PROCEDURES  

RIZZO has  the  right  to  remove any employee or  subcontractor who violates  safety practices.  

Disciplinary measures are  implemented at the discretion of the site supervisor commensurate 

with the severity of the infraction.  It is the responsibility of each individual to understand and 

comply with safety procedures and request clarification as needed.  Supervisors carry additional 

oversight and enforcement  responsibilities and,  consequently, disciplinary measures directed 

toward them will be more severe.  The following guidelines apply for minor infractions:  

 

First infraction:  Verbal and written warning with no further action if 

individual corrects infraction immediately and acknowledges 

the infraction. 

Second infraction:   Individual will be sent off‐site for a minimum of three 

working days.  

Third infraction:    Individual will be sent off‐site for the remainder of the 

project, and may be face employment termination 

depending on the severity of the infraction.  

 

Willful negligent acts or serious safety violations may result in immediate removal from the site 

and employment termination.  

 

2.9 DRUG AND ALCOHOL ABUSE 

Alcohol and drug  (non‐prescription) use  is strictly prohibited while on‐site.   Any employee or 

subcontractor found in possession or under the influence of drugs or alcohol while on‐site will 

be removed from the site and will be subject to appropriate disciplinary actions. 

 

Page 18: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 18 of 44 

 

3.0 SLIPS, TRIPS, AND FALLS 

 

3.1 TYPES OF FALLS  

Falls are of two basic types: elevated falls and same‐level falls. 

a. Same‐level falls:  high frequency – low severity. 

b. Elevated falls:  lower frequency – high severity. 

Same‐level  falls  are  generally  slips  or  trips  in which  the  individual  is  injured when  he  hits  a 

walking or working surface, or strikes some other object during the fall. 

 

3.2 CONTRIBUTING FACTORS  

Proper housekeeping in work and walking areas can contribute to safety and the prevention of 

falls.  These areas must also be kept free of obstacles.  These areas should never be obstructed 

by  objects  of  any  kind.    Adequate  lighting  to  ensure  proper  vision  is  also  important  in 

prevention and must be provided.  

 

3.3 FALLS FROM VEHICLES AND EQUIPMENT  

Unless seats or protected work areas are provided on the equipment, extra riders shall never 

be permitted. 

 

Whenever  mounting  or  climbing  on  a  vehicle  or  machine,  have  a  good  hand‐hold  before 

stepping up.  Always face the vehicle or equipment when mounting and dismounting. 

 

3.4 SHOES AND BOOTS  

The most important protection is to wear the proper footwear for your work and environment.  

In most occupations, the work boots should provide three major types of protection: 

The soles and heels should be slip‐resistant.  

The toe of the boot should resist crushing injuries.  

The work boot should support the ankle.  

 

Page 19: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 19 of 44 

 

4.0 EMERGENCY RESPONSE/PLANNING 

 

4.1 TABLE:  EMERGENCY TELEPHONE NUMBERS/DIRECTIONS TO HOSPITAL  

Emergency  contacts  for  the  site  are  to  be  determined,  documented  on  the  required  form, 

posted, and issued to personnel prior to site activities.   

 

4.2 EVACUATION PROCEDURES  

If evacuation  from  the  site  is  required due  to an emergency  such as a  fire or explosion,  the 

following action should be taken:  

First person  recognizing need  for evacuation will  immediately notify all on‐

site via voice, air horn, or other means.   Three short blasts of the air horn – 

EVACUATE; one long blast – ALL CLEAR.  

Leave  the  area  and  report  to  a  designated  rally  point  established  by  the 

supervisor.   This evacuation point may vary daily based upon  site activities 

and weather conditions.  Location will be discussed at the Toolbox Safety and 

Environmental Meeting.  

Notify Emergency Medical Service (EMS).  

Supervisor to account for all site personnel.  

Contact RIZZO administration; contact the client as soon as practical.  

Establish  site  security  and  control  measures  for  site  until  emergency 

responders arrive and take control.  

In  the  event  of  a  site  emergency  that  could  potentially  involve  evacuation  or mustering  of 

personnel, the client site representative may provide direction to RIZZO. 

 

4.3 MEDICAL EMERGENCY  

Response to a medical emergency:  

4.3.1 Initially survey the situation; do not enter an area that could jeopardize your safety.  

4.3.2 Establish  the  level of  consciousness  and  then  call  for help,  informing  the  EMS of  the 

patient’s condition.  

Page 20: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 20 of 44 

4.3.3 If  the  person  is  unconscious,  perform  a  primary  assessment  by  checking  for  airway, 

breathing, and  circulation  (only  trained First Aid/CPR Personnel  should perform  these 

tasks; state that you are medically trained).  

4.3.4 Conduct  a  secondary  assessment  to  the  conscious  patient  by  checking  for  bleeding 

(control with direct pressure) and monitoring for vital signs.  

4.3.5 Do not move the person unless the location is hazardous.  

4.3.6 Provide First Aid to the level trained.  First Aid Kit will be maintained on‐site.  

4.3.7 Contact the supervisor as soon as practical, document the incident on the Occupational 

Injury & Illness Report Form, and forward to the supervisor. 

4.3.8 Notify the client Technical Representative as soon as practical. 

 

4.4 FIRE EMERGENCY  

Response to a fire emergency:  

4.4.1 Evacuate the area immediately and notify emergency personnel.  

4.4.2 Extinguish small fires with an all‐purpose fire extinguisher, provided that you have had 

training in the use of an extinguisher.  

4.4.3 Report  the  incident  to  the  supervisor  and  document  the  incident;  document  for  the 

Project file and send a copy to the PM.  

4.4.4 Notify the client Technical Representative as soon as practical. 

 

4.5 SPILL/RELEASE OF HAZARDOUS MATERIAL  

In the event of a spill or release of hazardous materials, immediately notify the supervisor and 

implement the Emergency Response and Spill Containment Procedure. 

Page 21: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 21 of 44 

 

5.0 ENVIRONMENTAL 

 

RIZZO is committed to ensuring that our employees and subcontractors comply with applicable 

regulations and requirements.  This section of the HSE describes the environmental protection 

plans that are to be followed to protect water quality and the environment. 

 

5.1 GENERAL WILDLIFE MEASURES 

5.1.1 RIZZO  employees  and  subcontractors  shall  not  feed,  harass,  harm,  or  intentionally 

interfere with wildlife. 

5.1.2 Where  protected wildlife  species  are  encountered,  interaction  shall  be minimized  by 

avoiding the wildlife where possible. 

5.1.3 No one shall disturb, move, or destroy migratory bird nests.   

 

5.2  DUST CONTROL 

The Contractor shall implement dust control measures as needed.  Only water is to be used for 

dust control. 

 

5.3 NOISE 

Noise levels during site activities are to be kept to a minimum.  Employees and subcontractors 

are expected to make every effort to carry out the work  in a manner which causes minimum 

noise generation. 

 

5.4 PETROLEUM, OIL, LUBRICANT AND CHEMICAL HANDLING AND STORAGE 

The  site  supervisor  is  responsible  for  ensuring  that  the  type  and  amount  of  any  chemicals 

(including fuel) to be brought on‐site is determined and authorized prior to delivery to the site. 

All MSDS sheets for chemicals required on site will be provided to the site supervisor and client 

as  requested.    No  hazardous materials may  be  brought  onto  the  site  unless  necessary  for 

contracted work and authorized  site  supervisor and  client as  requested.       General  chemical 

handling and storage measures include: 

Page 22: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 22 of 44 

Equipment used will  be mechanically  sound with  no  oil  or  gas  leaks.    The 

Contractor  shall  undertake  frequent  inspection  of  equipment  and  repair 

leaks immediately. 

Servicing activities will be  limited to those necessary to complete the onsite 

work and in an environmentally sound manner. 

Spill  clean‐up materials  shall  be  accessible  and maintained  in  the  areas  of 

fuel and chemical storage. 

Spill kits are to be available  in the vehicles.   Any spilled fuel or  lubricants or 

other  hazardous  material  are  to  be  immediately  reported  to  the  site 

supervisor,  contained  and  cleaned  up  consistent  with  the  Emergency 

Response and Spill Containment Procedure. 

During drill rig placement, a plastic sheet will be placed under the rig and tied 

to  the  rig  to  form a  simple berm  to  collect any  leaks  (bentonite  should be 

added to absorb these drips) and disposed of properly in marked containers. 

All chemical containers are closed at the end of each work day. 

Use of temporary hoses is carefully planned. 

Storage drums,  if empty,  should be  turned upside down and  located  in an 

area that is labeled “empty drums.” 

Storage drums should be placed on pallets. 

Fuel  and  oil  tanks  used  by  all  contractors,  and  not  on  vehicles, must  be 

placed in secondary containment. 

Following work and prior to start‐up, all contractors and subcontractors must 

ensure  that all valves, man‐ways, and pipelines are closed  if appropriate  to 

minimize risk of spills. 

All chemicals required to be maintained onsite will be properly labeled, kept 

in  the  appropriate  container,  and  stored  in  an  approved  manner.    All 

containers will be kept closed when not in use. 

Page 23: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 23 of 44 

 

5.5 WASTE MANAGEMENT 

a) The site dumpster should be one or more (as needed) 50 to 55 gallon plastic 

or metal drums with tight‐fitting lids.   

b) Waste  from  site  activities  including  food waste  is  to  be  placed  in  covered 

trash receptacles which are labeled as “General Trash” and emptied into the 

site dumpster regularly. 

c) Oily  rags  and  absorbent  pads  used  in  equipment maintenance  and  other 

potentially combustible materials will be kept in a labeled container separate 

from  the  above materials  until  the  combustible material  can  be  removed 

from site for disposal.   

d) Scrap steel will be recycled through a local recycler or transported off site by 

drilling Sub‐Contractor. 

e) All waste containers are to be labeled properly.  

f) Absorbent materials  and  rags used  to  respond  to  a  significant  spill will be 

handled with any petroleum contaminated soil. 

5.5.1 Waste Minimization 

RIZZO employees and subcontractors are responsible for reducing the production of waste in all 

site activities.  The following waste minimization measures should be taken:    

Purchasing items with minimal packaging; 

Use of “green” products as much as possible; 

Bringing  on‐site  only  the  amount  of  chemicals  that  will  be  used  on  the 

project; 

Utilizing a digital geologic logging system instead of paper field forms; and  

Separating out recyclable waste (water bottles, aluminum cans, etc.).   

Page 24: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 24 of 44 

 

5.6 EROSION, SURFACE AND GROUNDWATER POLLUTION PREVENTION AND CONTROL 

Where required, silt fence should be  installed along the outer edge of drilling pads to prevent 

sediment and  loose material  from eroding.   The drilling system should be closed  loop, where 

the water and fluids are continually circulated between well and mud system. 

 

5.7 SITE DEMOBILIZATION 

The  site  supervisor  is  responsible  for  ensuring  that  a  post  site walk‐down  is  conducted  to 

document the following: 

a) That all equipment and excess materials have been removed. 

b) All temporary erosion control measures (silt fence, etc.) have been removed. 

c) All dumpsters, waste containers, debris and any items left from the site 

activities have been removed. 

d) Ensure that any environmental issues are addressed.

Page 25: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 25 of 44 

 

6.0 UTILITIES 

 

6.1 PRE‐EXCAVATION/DRILLING  

Prior to on‐site activities, RIZZO will request information from the client regarding identification 

of utility locations.  Such utilities include, but are not limited to:  

Gas 

Electric 

Fiber optic communication 

Major pipe or water lines 

6.2 EXCAVATION/DRILLING  

Upon arrival at the excavation/drilling site prior to the start of each borehole, the supervisor, 

should:  

Check for any visible signs of underground utilities, such as pedestals, risers, 

meters, and new trench lines, and for any utilities. 

Review the location of underground utilities. 

Record the area inspection for utilities on the Drill Rig Safety Checklist Form. 

6.3 MARKING PRESERVATION  

Site  personnel  shall  protect  and  preserve  the  staking,  marking,  or  other  designations  for 

underground utilities until no longer required for proper and safe excavation/drilling. 

 

6.4 FACILITY DAMAGE NOTIFICATION 

Site  personnel  discovering  or  causing  damage  to  underground  utilities  shall  notify  their 

supervisor  and,  follow  site  communications  protocol.    The  utility  owner/operator  will  be 

notified as soon as possible.   

 

6.5 NOTIFICATION OF EMERGENCY  

If  the protective  covering of  an electrical  line has been penetrated or  if  gases or  liquids  are 

escaping  from  a  broken  line,  site  personnel  should  immediately  contact  local  emergency 

Page 26: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 26 of 44 

agencies to report the damage  location.   This practice minimizes the danger to  life, health, or 

property  by  notifying  the  proper  authorities  to  handle  the  emergency  situation.    In  these 

situations,  local  authorities  are  able  to  evacuate  as  appropriate  and  command  substantial 

resources unavailable to site personnel or the owner/operator of underground utility. 

 

6.6 EXCAVATION/DRILLING OBSERVER  

Site  personnel  shall  use  a  spotter  when  excavating  or  drilling  around  known  underground 

utilities.   This worker will be designated  to watch  the excavation/drilling activity  to warn  the 

operator if a utility line is seen while excavating or drilling. 

 

6.7 EXCAVATION/DRILLING TOLERANCE ZONE  

Site personnel will observe a tolerance zone which is comprised of the width of the utility plus 

18 inches (on either side of the outside edge of the underground utility in a horizontal plane).  

 

When excavation/drilling is to take place within the specified tolerance zone, site personnel will 

exercise  such  reasonable  care  as may  be  necessary  for  the  protection  of  any  underground 

utility in or near the excavation/drilling area.  

 

Methods to consider, based on certain climate or geographical conditions, include:  

Hand digging, when practical (pot holing) 

Soft digging 

Vacuum excavation methods 

Pneumatic hand tools  

Other mechanical methods with the approval of the utility owner/operator, 

or other technical methods that may be developed  

 

6.8 OVERHEAD POWER LINES 

If it is necessary that the drilling activities occur closer than 10 ft. (3 m) to any overhead power 

line,  the  electrical  company  that  owns  or  controls  the  power  line  shall  be  notified,  and  the 

power  line will be de‐energized and grounded  for  the duration of  the work at  that  location.  

Page 27: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 27 of 44 

Protective measures  (such  as  guarding,  isolating,  or  insulating)  shall  be  put  into  practice,  in 

order to prevent employees from bodily contacting such lines directly or indirectly.   

 

Any conductive materials or equipment  that are  in contact with any part of a worker’s body 

shall  be  handled  in  a  manner  that  will  prevent  those  materials  from  contacting  exposed 

energized  conductors  or  circuit  parts.    If  long  dimensional  conductive  objects  (pipes,  rods, 

ducts)  must  be  handled  around  exposed  live  circuits,  work  practices,  to  include  guarding, 

insulating, or safe material handling techniques, shall be used to remove the hazard.    

 

Never  get  closer  than  10  ft  (3 m)  to  an  overhead  power  line.    The minimum  safe  distance 

around overhead power lines are: 

Line Voltage up to 50,000 volts = 10 ft (3 m) 

Line Voltage 50,000 to 200,000 volts = 15 ft (4.5 m) 

Line Voltage 200,000 to 350,000 volts = 20 ft (6 m) 

Line Voltage 350,000 to 500,000 volts = 25 ft (7.6 m) 

Line Voltage 500,000 to 700,000 volts = 35 ft (10.6 m) 

Line Voltage 750,000 to 1,000,000 volts = 45 ft (13.7 m) 

 

Page 28: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 28 of 44 

 

7.0 EXCAVATION, DRILLING, AND RIGGING SAFETY 

 

7.1 EXCAVATION 

For the purpose of this HSE Manual, the term “excavation” will include any earthwork, trench, 

or open pits. 

 

All  practicable  steps  shall  be  taken,  where  necessary,  to  prevent  danger  to  any  person, 

including, where necessary, the provision of support or battering to ensure that: 

 

Any excavation or part of an excavation does not collapse. 

No material from a side or roof of, or adjacent to, any excavation is dislodged 

or falls.  

No  person  is  buried  or  trapped  in  an  excavation  by  material  which  is 

dislodged or falls. 

Suitable  and  sufficient  steps  shall  be  taken  to  prevent  any  person, work  equipment,  or  any 

accumulation of material from falling into any excavation. 

 

7.2 NATURAL GASES 

Methane and hydrogen sulfide occur naturally underground and may discharge from boreholes 

during  drilling  operations.    It  is  important  that  the  drill  crew  and  RIZZO  personnel  respond 

rapidly  and  correctly  to  any  encounters with  gas  to maintain  a  safe workplace.    Thoroughly 

document  the encounter  to  indicate  the  type of  gas encountered, manner  and  approximate 

rate of discharge, and at what point  in  the drilling process  (depth below ground surface)  the 

discharge occurred.  

 

7.2.1 Methane 

Methane  is  an  odorless  gas,  lighter  than  air,  and  combustible  when  mixed  with  air  in 

concentrations between 5 and 15 percent.  A portable combustible gas detector may be used to 

monitor  the atmosphere  for methane.   A methane concentration  in air near 100 percent will 

read  zero  on  the meter.    Take  readings  by  holding  the  gas  detector  over  the  borehole,  or 

downwind  near  casing  level, within  about  15  to  20  centimeters  (cm)  of  the  casing.   Do  not 

Page 29: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 29 of 44 

extend the meter into the borehole, as the borehole atmosphere may be oxygen‐deficient and 

incapable of combustion.  

 

Record  any  indications  of methane  on  the  boring  log,  such  as  duration  of  gaseous  phase 

discharge, frequency, and magnitude of combustible gas detector readings, size, and frequency 

of bubbles  in drilling  fluids, and other evidence.   Do not  risk  injury  to make observations of 

methane discharges.  

 

7.2.2 Hydrogen Sulfide 

Hydrogen sulfide is a highly toxic gas that causes harmful effects in concentrations above about 

100  parts  per million  (ppm).    The  allowable  exposure  limit  is  10  ppm.    In  concentrations 

between about 0.02 and 100 ppm, the gas smells like rotten eggs.  Exposure to concentrations 

above  about  100  ppm  quickly  dulls  the  sense  of  smell;  giving  the mistaken  impression  that 

exposure was transient.  Disappearance of the odor is not an indication of disappearance of the 

gas.   Hydrogen sulfide  is generated by bacterial decomposition of organic matter  in soils and 

sedimentary rocks.  Bacterial hydrogen sulfide occurs only as a solution phase in groundwater.  

It does not occur  in  concentrations high enough  to  support gaseous phase accumulations or 

bubbles.  

 

A portable gas detector may be used to monitor the atmosphere for hydrogen sulfide.  Record 

any  indications of hydrogen sulfide on  the boring  log, such as  the  intensity of odor, detector 

reading,  or  other  evidence.    Do  not  risk  injury  to  make  observations  of  hydrogen  sulfide 

discharges. 

 

7.2.3 Other 

A  portable  gas  detector may  be  used  to monitor  the  atmosphere  for  hazardous  chemicals.  

Water  samples may  also be  taken  for  further  analysis.    If  the  atmosphere or water  samples 

indicate hazardous chemicals during drilling operations, operations will be suspended pending 

further investigation and instructions from the supervisor or client. 

 

7.3 GENERAL DRILLING SAFETY  

7.3.1 Drill Rig Stabilization  

Page 30: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 30 of 44 

The drilling contractor  is responsible for ensuring that the rig  is properly set up.   This  includes 

such tasks as stabilizing the rig, clearing the location of overhead obstructions that may contact 

the mast as it is being raised or is in the fully raised position, and raising the mast.  Rig stability 

is essential for conducting safe drilling operations.  Components to assuring proper stabilization 

include rig placement (or location), use of hydraulic leveling jacks, use of blocking (or cribbing), 

and use of wheel chocks.  The following practices should be used when setting up the drill rig:  

When the rig moves into position at a boring location, a plastic sheet or tarp 

shall be placed under  the  rig  to contain drips and/or  spills.   Add bentonite 

powder  or  absorbent  pads  if  necessary  to  clean  spills,  and  dispose  the 

material in accordance procedures. 

Chock the wheels of the rig remaining in contact with the ground.  

Chock wheels of all support equipment and trailers.  

Before raising the mast, check for overhead obstructions or wires.  

Remove all loose objects, such as equipment and tools, from the mast and 

inspect for damaged parts.  

Raise  the mast only  after  the  leveling  jacks  are down.   Do not  raise  the 

jacks until the mast has been lowered completely.  

Before  raising  the  mast,  all  drill  rig  workers  (with  exception  of  the 

operator) and visitors should be cleared from the area surrounding the rig.  

No other activities should be conducted in the vicinity of the rig, while the 

mast is being raised or lowered.  

Only operators qualified as drillers may raise or lower the mast, or operate 

any of the rigs controls. 

Raise the mast a few centimeters  in order to check brakes, before raising 

the mast to vertical.  

Once the rigs mast is vertical, the rig should remain stationary, other than 

leveling the rig using the hydraulic  jacks.   The rig should never drive with 

the mast partway or fully vertical. 

7.3.2 Drill Rig Operation  

Identify potential pinch points and hazards that could injure fingers and toes.  

Page 31: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 31 of 44 

While drilling activities are  in progress, visitors are not permitted within the 

taped  barricade without  proper  PPE  and  permission  from  the  operator  or 

RIZZO personnel.   All site personnel must be wearing PPE at all times within 

the barricade.  Smoking is prohibited inside the barricade. 

Effective  communication  (hand  signals),  especially  under  high  noise 

conditions,  is  essential  to  safety.    Clarify  the meaning  of  hand  signals  in 

advance of their use.  

Do not climb the rig mast while equipment  is running.   Shut down/lock out 

equipment  and  use  full  body  safety  harness  if  climbing  the mast,  over  a 

height of 6 ft is necessary.  

The operator of a drilling rig should only operate the rig from the position of 

the controls.  

The  operator  should  shut  down  the  drilling  rig  engine  before  leaving  the 

vicinity of the rig.  

Never operate the drill rig with any of the machinery guards removed.  

Attach safety chains or cables to all swivel, air, and other pressure hoses.  

7.3.3 Adding and Removing Drill Rods  

Only  the  drill  operator  will  brake  or  set  the  chucks,  as  to  eliminate  the 

possibility of engaging the transmission prior to removing the chuck wrench.   

Do  not  use  the  chucks  as  a  brake  on  a  string  of  drill  rods  that  are  being 

lowered  into  a hole.   Breaking  the drill  string with  the  chuck will  result  in 

metal  slivers  on  the  exterior  surface  of  the  drill  rods,  resulting  in  possible 

hand injuries and losing the drill rod down the hole.  

Check the chuck jaws periodically and replace them as necessary.   

Never place hands on wrenches where  they  can  get  trapped between  the 

wrench and any part of the drill rig.  

Ensure that wrenches are removed from rods before rotating the drill stem.  

Do not take hold of the male thread end of drill rods.  Watch for sharp burrs 

on rods and casing, and file sharp edges off rods when necessary.  

Page 32: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 32 of 44 

Clean  drill  rods with  a  rubber wiper  or  other  suitable  device when  being 

removed from a hole.  

Allow drilling  fluids  to drain  from drill  rods  into  the mud pit before  setting 

the  rod  to  the  side, as  to minimize  the chances of  slip hazards around  the 

work area.   

The operator shall know the capacity of the hoist and mast and the weight of 

the drill rod to prevent the hoist capacity from being exceeded. 

The drill rig operator must exercise care to  lower the hoist slowly while the 

drill rod is being carried away from the hole, allowing the drillers assistants to 

safely carry rods back to the holding basket. 

There should be at all times at least three wraps of hoisting line on the hoist 

drum  to  prevent  a  line  load  from  being  applied  directly  to  the  fastening 

clamp.  

Do not guide or hold onto moving wire line work cables with bare hands. 

7.3.4 Rigging Safety 

Wire  rope,  chains,  slings,  and  other  forms  of  rigging  shall meet  all  criteria  set  forth  by  the 

standards established from regulatory agencies such as OSHA and ANSI. 

 

All synthetic slings shall be properly labeled,  identifying the manufacturer, rated capacities for 

the  type of hitch,  and  the  type of material used  in  the  sling.    Slings  shall be  removed  from 

service  if  burns,  punctures,  tears,  cuts,  broken  or  worn  stitches,  excessive  wear,  or  any 

combination of these conditions exist.  Most synthetic slings have a wear thread of a different 

color that indicates when the sling is no longer safe to use. 

 

Chain slings will have a permanently affixed identification tag stating size, grade, rated capacity, 

and manufacturer.  Only alloy steel chains with this tag affixed are acceptable for lifting. 

 

Wire rope rigging  is based on the number of strands of wire, core material, size of the strand, 

and the configuration of the strands. 

 

Page 33: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 33 of 44 

All  rigging  equipment  shall  be  inspected  each  day  before  use  and more  often  if  conditions 

warrant.    Inspections  should  be  documented.    Each  component  of  the  rigging  should  be 

critically inspected according to the manufacturers’ specifications.  Any part of the rigging that 

does not pass inspection shall be removed from service immediately. 

 

7.3.5 Pressuremeter Testing Safety 

The  pressuremeter  test  uses  high  pressure  compressed  gas,  deployed  cable,  and  110v 

alternating current electric power.   The  instrument  is also heavy especially when mated up to 

drilling rods.  The drilling environment also has inherent hazards including overhead lifting and 

many others which are site specific.  The SCUBA bottles are to be used with anti‐roll stabilizing 

attachments and stored flat on the ground so they cannot tip over, fall, or be tripped over  in 

the normal course of work flow.  The 110v electric lines should be kept out of moisture and be 

properly grounded.   The data cable  is orange  for high visibility and  should be deployed on a 

route that minimizes the possibility of tripping.   During testing, the possibility of a membrane 

rupture exists, and this can forcefully evacuate the hole of drilling mud.   Personnel should be 

kept  away  from  the  back  of  the  drilling  rig  during  high  pressure  inflation.    The  drilling  rods 

should always be held with a positive locking device and not lowered into the hole or held with 

a device which may slip and allow the instrument to free‐fall into the hole. 

Page 34: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 34 of 44 

 

 

8.0 FIRE PREVENTION PROGRAM 

 

This  Section  applies  to  all who work with  or whose  job  responsibilities  require  them  to  be 

familiar with the fire prevention and fire hazards at the site.   

 

8.1 FIRE PREVENTION AND MINIMIZATION  

8.1.1 Hazard Determination and Communication  

The following fire hazards, prevention measures, and safety precautions should be followed by 

all on‐site personnel:  

Consideration  must  be  given  to  storage  and  use  of  flammable  liquids, 

combustible materials, construction material, and  locations of welding or 

other spark‐producing or open‐flame processes. 

All means of exit and fire protection should be located and communicated 

to site personnel. 

 

8.1.2 Engineering Controls  

Fire extinguishers and employee training serve as engineering controls. 

 

Combustible and flammable liquids are controlled both in the amount and method of storage.  

(i.e., UL or FM approved cabinets and cans).   Combustible and flammable  liquids shall NOT be 

left unattended on the jobsite. 

 

8.1.3 Administrative Controls  

Open flame or spark producing work requires a trained Fire Watch with an extinguisher during 

the  work  and  a  minimum  of  30  minutes  after  completion.    Open  flame  leak  testing  is 

prohibited. 

 

Regular  inspections  shall  be  conducted  by  the  supervisor  or  designee,  for  the  proper 

maintenance  and  care  of  all  firefighting  equipment  and  proper  storage  of  all  flammable 

Page 35: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 35 of 44 

materials.   Additional controls  include  the  storage of  flammable and combustible  liquids and 

materials  in  approved  and  properly  labeled  containers,  approved  site‐specific  emergency 

evacuation plans, and communication with local emergency response preparedness teams.   

 

8.1.4 General Fire Prevention Measures  

The  site  personnel  has  the  responsibility  to  ensure  that  hazardous  accumulations  of 

combustible materials are controlled so that a fast‐developing fire, rapid spread of toxic smoke, 

or an explosion will not occur.  

 

Some of the fire preventive measures that site personnel should employ are:  

Practice good housekeeping in all work areas.   

Immediately report and repair all leaks of flammable liquid or gas. 

In the event of a flammable liquid or gas leak, extinguish all fires and remove 

other  sources  of  ignition  immediately.    Shut  down  engines  and  other 

potential  sources of  ignitions.   Report  the  leak promptly  to  the  supervisor.  

Shut off fuel supply or process, if possible. 

Fires and open flame devices shall not be left unattended. 

Use gasoline as a motor fuel only.  

Keep  all  buildings  in  which  solvents  or  chemicals  are  being  handled  well 

ventilated at all times. 

Transport  flammable  liquid  only  in  approved,  clearly‐marked  safety 

containers.    Volatile  liquids  shall  be  stored  in  containers  made  for  their 

purpose.    Never  place  flammable  liquid  containers  inside  car  or  truck 

passenger compartments. 

Unplug electric coffee pots, hot plates, and like appliances at the end of each 

work day. 

Turn off electrical equipment when not  in use and at  the end of  the work 

day. 

Avoid overloading electric circuits. 

Page 36: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 36 of 44 

Be  careful  that  light  bulbs  do  not  come  into  contact with  combustibles  in 

storage areas. 

Smoking is only permitted in designated safe areas. 

Do not discard smoking materials into wastebaskets at any time.  Dispose of 

smoking materials in designated smoking area buckets only. 

8.2 FIRE EXTINGUISHING EQUIPMENT 

The site personnel shall make fire extinguishers of at least five pound ABC available throughout 

the  site.    Site personnel  shall be  familiar with  the  location  and proper use of  all  firefighting 

equipment.   

 

Classes of Fires and Correlating Extinguishers:  

CLASS A – Ordinary Combustibles  

CLASS B – Flammable Liquids  

CLASS C – Electrical Equipment  

CLASS D – Combustible Metals  

 

Most fire extinguishers are labeled, indicating the type of fire the device can extinguish.  

 

8.2.1 Out of Service Equipment  

Non‐functioning firefighting equipment should be clearly marked “out of service.”  

 

Replace  all  fire  extinguishers  immediately  upon  removal  from  service  (including  service  for 

recharging, inspection, or replacement), so that an adequate quantity is available for use. 

Page 37: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 37 of 44 

 

9.0 SEVERE WEATHER PLAN 

 

The  following Severe Weather Plan  (SWP) has been prepared  to  identify appropriate actions 

and precautions  to be  implemented when  there  is a potential  for  severe weather.   The SWP 

details  procedures  for  monitoring  weather  conditions  and  suspending  operations.    The 

supervisor  will  evaluate  the  conditions  being  encountered  during  operations  and  make  a 

determination as to whether the operations can proceed in a safe manner.  

 

High Winds:   Of particular concern during periods of high winds are drill rig mast stability and 

dust and materials blowing around  the work area.   With regard  to drill  rig mast stability,  the 

Driller will be consulted with and if wind speeds are excessive to the rated stability of the drill 

rig, drilling will be suspended.  

 

Heavy Rains and Storms, Tropical Storms, and Hurricanes:  In the event of heavy rains (where 

visibility is obscured) all operations will be suspended until the heavy rains end and it is found 

that operations can proceed in a safe manner. 

 

Thunderstorms:    Operations  will  cease  when  it  is  determined  that  thunderstorm  cells  are 

within 8 km (5 miles) of the site, based on weather information, or if lighting is observed from 

any location.  All equipment will be secured and all site personnel will seek shelter.  Operations 

will  be  allowed  to  continue  30 minutes  after  the  last  lightning  bolt  is  observed,  unless  the 

Weather Station indicates other storms approaching.  

 

9.1 HEAT RELATED ILLNESSES 

The stress of working  in areas of high heat, humidity and  radiant heat can cause a variety of 

strains  on  the  body,  including  heat  exhaustion  or  heat  stroke;  the  latter  can  be  fatal.    The 

symptoms of heat stress need to be recognized and necessary actions implemented when they 

occur. 

 

To minimize  the potential  for heat  stress problems at  the  job  site,  these guidelines on heat‐

related  illnesses  should  be  reviewed  by  employees  prior  to  job  assignments  so  that  early 

Page 38: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 38 of 44 

symptoms  of  heat  stress  are  recognizable  by  all  employees  and  prompt  corrective  first  aid 

measures can be taken to minimize the potential for more serious heat‐related illnesses. 

 

In the preliminary stages of heat stress, rashes, cramps, discomfort and drowsiness can occur 

resulting  in  impaired  functional  ability  that  threatens  the  safety  of  both  the  individual  and 

coworkers.  Continued heat stress can lead to heat stroke and death.  Avoiding overprotection, 

careful  training,  and  frequent monitoring of workers who wear protective  clothing,  strategic 

scheduling of work and  rest periods, and  frequent  replacement of  fluids  can protect against 

heat stress hazards. 

 9.2 TABLE:  STAGES, SYMPTOMS, AND FIRST AID MEASURES FOR HEAT STRESS 

STAGE  SYMPTOMS  FIRST AID MEASURES 

Heat Cramps Sweaty skin  Painful muscle spasms  Normal body temperature  

Give fluids Gently massage cramped muscles  

Heat Exhaustion 

Clammy or pale skin Weakness and fatigue Profuse sweating  Nausea  Vomiting  Disorientation Headache  Normal or slightly elevated body temperature 

Remove victim from heat Loosen clothing  Sponge skin with cool water  Fan victim, but stop if victim shivers or develops goose bumps Give fluids Solution of one pint water and one teaspoon salt every 30 minutes until victim recovers  Obtain medical help if victim does not improve 

Heat Stroke 

Unconsciousness or mental confusion Dizziness Staggered walk Appears to be agitated Hot, dry skin Extremely high body temperature; could reach or exceed 105º F 

Get emergency medical aid immediately Remove victim from heat Remove clothing, place victim in a cool bath, or apply cool compresses Do not give any fluids Do not leave victim alone Do not allow victim to become so cold that victim shivers Do not give aspirin or other medication in an attempt to lower fever 

Page 39: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 39 of 44 

 

10.0 HSE INSPECTIONS    

All safety and environmental  inspections are conducted by the supervisor and/or an assigned 

competent  person  on  a  daily  basis  and  documented  on  the  RIZZO  Field  Activity  Daily  Log.  

Inspection forms are to be used during the  initial setup of each drill rig for each borehole and 

will be kept at the site.  The matrix below provides a list of the inspections to be conducted, the 

individual responsible for performing the inspections, and how often the inspections are to be 

performed.   

 10.1 TABLE:  HSE INSPECTIONS 

MATERIAL TO BE INSPECTED PERSON RESPONSIBLE FOR 

INSPECTION FREQUENCY OF INSPECTION 

HSE Field Inspections  Site supervisor  Regular site inspections  

PPE  User of PPE  Daily inspection before usage

Equipment (generators, trucks, vehicles, etc.) 

Assigned Qualified Person Daily inspection before 

operation 

 

 

 

 

 

Page 40: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 40 of 44 

 11.0 TABLE:  JOB HAZARD ANALYSIS FOR SUBSURFACE INVESTIGATION 

 

Job Hazards Analysis (JHA) is required to be prepared as appropriate for work activities, such as 

at a construction site.  The JHA is required to evaluate known or anticipated hazards as well as 

control measures as needed.  In the event that an unforeseen situation occurs, a specific JHA on 

the situation may be required.   

MINIMUM PPE REQUIREMENTS SAFETY GLASSES, HARD HAT, REFLECTIVE VEST, SAFETY‐TOED BOOTS 

POTENTIAL SAFETY/HEALTH 

HAZARDS RECOMMENDED HAZARD CONTROL MEASURES 

PERSONAL PROTECTIVE EQUIPMENT 

Struck By/Against Heavy Equipment, Flying Debris, Protruding 

Objects 

Use reflective vests when exposed to vehicular traffic.  Make eye contact with operators before approaching equipment.  Barricade or enclose the drilling area.  Restrict entry to the drilling area to authorized personnel.  Wear PPE at all times.  Understand and review hand signals, if applicable.   

Safety vests, hard hat, safety glasses, goggles, 

face shield 

Sharp Objects and Hot Surfaces 

Wear cut resistant work gloves when the possibility of lacerations or other injury may be caused by sharp edges or objects.  Wear heat resistant work gloves when there is possibility of contact with hot surfaces.  Ensure that the location of mufflers and other hot surfaces are known and guarded, if possible. 

Work gloves 

Sun Exposure 

When working outdoors, wear minimum SPF 30, as appropriate.  Wear UVA/UVB protective safety glasses.  Limit exposure in direct sunlight if possible.   

Sunscreen, tinted/dark safety glasses 

Underground/Above ground Utilities 

Identify all underground and overhead utilities around the site before work commences.  All equipment will stay a minimum of 10 ft from power lines.  This distance will increase as the voltage of the power lines increase.  Cease work immediately if unknown utility markers are uncovered.   

 

High Noise Levels Use hearing protection when exposed to excessive noise levels (greater than 85 dB(A) over an 8‐hour work period).   

Ear plugs or muffs 

Page 41: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 41 of 44 

MINIMUM PPE REQUIREMENTS SAFETY GLASSES, HARD HAT, REFLECTIVE VEST, SAFETY‐TOED BOOTS 

POTENTIAL SAFETY/HEALTH 

HAZARDS RECOMMENDED HAZARD CONTROL MEASURES 

PERSONAL PROTECTIVE EQUIPMENT 

Handling Heavy Objects 

Observe proper lifting techniques.  Obey sensible lifting limits (40‐lb. maximum per person manual lifting).  Use mechanical lifting equipment (hand carts, trucks) to move large, awkward loads. 

Mechanical lifting 

equipment (hand 

carts/trucks, etc.) 

Caught In/Between Moving/Rotating Parts 

Identify and understand parts of equipment which may cause crushing, pinching, rotating, or similar injuries.  Assure guards are in place to protect from these parts of equipment during operation.  Provide and use proper work gloves when the possibility of crush, pinch, or other injury may be caused by moving/stationary edges or objects.  Maintain all equipment in a safe condition.  Keep all guards in place during use.  De‐energize and lock‐out machinery before maintenance or service.   

Work gloves 

Slips, Trips, Falls 

Clear walkways, work areas of equipment, drilling overburden, debris and other materials.  Be careful of soft, moist subsurface materials.  Mark or barricade obstructions.   

 

Inhalation and Contact with Hazardous Substances 

Provide workers proper skin, eye, and respiratory protection based on the exposure hazards present.  Review hazardous properties of site contaminants with workers before operations begin.   

Tyvek coveralls, Nitrile gloves 

dependent upon contaminants 

Vehicular Traffic 

Spotters will be used when backing up trucks and moving equipment.  All vehicles and equipment are to be operated at a reasonable speed (e.g. ten MPH) while on‐site roadways.  Be aware of surroundings at all times.   

Reflective safety vests 

Page 42: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 42 of 44 

MINIMUM PPE REQUIREMENTS SAFETY GLASSES, HARD HAT, REFLECTIVE VEST, SAFETY‐TOED BOOTS 

POTENTIAL SAFETY/HEALTH 

HAZARDS RECOMMENDED HAZARD CONTROL MEASURES 

PERSONAL PROTECTIVE EQUIPMENT 

Wildlife/Insect/Snake Bites 

Avoid insect nests areas, likely habitats outside work areas.  Emphasize “Buddy System” where such injury potential exists.  Use insect repellant, wear PPE to protect against sting/bite injuries.  Check for ticks exiting heavily vegetated/wooded areas.   

Insect repellent 

Overhead Hazards 

All ground personnel will stay clear of all overhead loads.  Where applicable, overhead wires will be appropriately marked.  All equipment will stay a minimum of 10 ft from power lines.  This distance will increase as the voltage of the power lines increase.   

Hard hat 

Contact Dermatitis 

Wear PPE to avoid skin contact with contaminated soil, plant, or other skin irritants.  Identify and review poisonous plants with workers.   

Pants, long sleeves 

High/Low Ambient Temperature 

Monitor for heat/cold stress.  Provide fluids to prevent worker dehydration.   

Proper clothing for 

temperatures 

 

Page 43: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 43 of 44 

 12.0 TABLE:  JOB HAZARD ANALYSIS FOR SITE VISITORS 

 

MINIMUM PPE REQUIREMENTS:  (SAFETY GLASSES, REFLECTIVE VEST, AND PROTECTIVE SHOES) 

POTENTIAL SAFETY/HEALTH 

HAZARDS RECOMMENDED HAZARD CONTROL MEASURES 

PERSONAL PROTECTIVE EQUIPMENT 

Weather If severe weather will affect site activities, visitors will be notified and told to take shelter.   

None needed 

Struck By/Against Heavy Equipment, Flying Debris, 

Protruding Objects 

Do not approach equipment.  Stay out of the drilling area.  Stay with Project Supervision. 

Hard hat, safety glasses, 

gloves 

Sun Exposure 

Wear minimum SPF 30 when working outdoors, regardless of cloud cover.  Wear long sleeve shirts, if applicable.  Wear UVA/UVB protective safety glasses.  Limit exposure in direct sunlight, if possible.  Use portable shades if weather conditions permit. 

Sunscreen, portable shades 

High Noise Levels Use hearing protection when exposed to excessive noise levels (greater than 85 dB(A) over an 8‐hour work period). 

Ear plugs or muffs 

Slips, Trips, Falls Be aware of uneven ground and stay with Project Supervisor. 

None needed 

Wildlife/Insect/Snake Bites 

Review injury potential and types of snakes for area.  Avoid insect nests areas, likely habitats of wildlife outside work areas.  Use insect repellant, wear PPE to protect against sting/bite injuries. 

Insect repellent 

Driving Hazards 

Vehicles must be able to pull through parking area or back in, so that the vehicle can move forward as it leaves the parking space.  All will stay clear of all vehicles while backing.   

None needed 

Page 44: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

HSE Manual Rev. 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 44 of 44 

13.0 FORMS 

FORM NUMBER  TITLE 

HSEM‐01  Occupational Injury & Illness Report Form 

HSEM‐02  Near Miss Incident Report Form 

HSEM‐03  HSE Incident Log 

HSEM‐04  Environmental Field Inspection Form 

HSEM‐05  Toolbox Safety and Environmental Meeting Form 

HSEM‐06  Drill Rig Safety Checklist 

HSEM‐07  On‐site Emergency Contacts 

HSEM‐08  Daily Sign In/ Sign Out Sheet 

   

    

14.0 CHANGE MANAGEMENT RECORD 

REVISION NO.  DATE  DESCRIPTIONS OF CHANGES/AFFECTED PAGES 

0  May 9, 2014  New issue to combine HSE  

1  July 12, 2018  Revised Company Name and editorial changes. 

     

 

Page 45: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

Form HSEM‐01, Rev 1  © RIZZO Proprietary and Confidential Work Product 

  Page 1 of 2

OCCUPATIONAL INJURY & ILLNESS REPORT FOR RIZZO STAFF USE ONLY

Comp Non Comp

All occupational injuries and illnesses must be reported to supervision as soon as possible. This form must be sent to QHSE Department with all questions answered by supervision within 5 working days of an accident. Type or use pen to complete this form. (Please Print. If space is insufficient, attach additional sheet.)

Occupational Injury

Occupational Illness

Ergonomic

OSHA Log Stats

Attention: this form contains information relating to employee health and must be used in a manner that protects the confidentiality of employees to the extent possible while the information is being used for occupational safety and health purposes.

CLASSIFICATION:

FA MED RWC

LWC

EMPLOYER 1. Name of Employer 2. Employer Mailing Address

3. Employee’s Work Reporting Location

INJURED OR ILL EMPLOYEE Employee Number 4. Date of Hire ____/____/____ 5. Date of Birth ____/____/____

6. Name – First Middle Last

7. Home Address

No. & Street City State Zip Code

8. Sex M F 9. Phone No.

10. Dept. Name and Number 11. Job Title

INJURY OR OCCUPATIONAL ILLNESS 12. Date of Injury or Occupational Illness ____/____/____ Time of Injury or Occupational Illness ___ ___ : ___ ___ AM PM

If time cannot be determined, check here

13. Time employee began work ___ ___ : ___ ___ AM PM

14. Was place of injury on employer’s property? YES NO

15. Place of Injury or Illness: Company Location

Other than Company Location

(If accident occurred at an identifiable address, give that address. If it occurred on a public highway or at any other place which cannot be identified by number & street, please provide place references locating the place of injury as accurately as possible.)

16. If environmental conditions contributed to the accident or illness, note reason(s). Rain Snow Ice Cold Heat

Other

17. What was the employee doing just before the incident occurred? Describe the activity, as well as the tools, equipment, or material the employee was using. Be specific. Examples: “climbing a ladder while carrying roofing materials,” spraying chlorine from hand sprayer,” “daily computer key-entry”

18. What happened? Tell how the injury occurred. Example: “When ladder slipped on wet floor worker fell 20 feet,” “Worker was sprayed with chlorine when gasket broke during replacement,” “Worker developed soreness in wrist over time.”

19. What was the injury or illness? Tell us the part of the body that was affected and how it was affected; be more specific than “hurt,” “pain,” or “sore.” Examples: “strained back,” “chemical burn, hand,” “carpal tunnel syndrome.”

Page 46: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

Form HSEM‐01, Rev 1  © RIZZO Proprietary and Confidential Work Product 

  Page 2 of 2

OCCUPATIONAL INJURY & ILLNESS REPORT

20. Was first aid treatment given? Yes No Sent to a Doctor? Yes No Sent to a Hospital/Clinic? Yes No

Was Employee Hospitalized? Yes No Fatality? Yes No Date of Death: ____/____/____

21. Name & Address of Physician or other health care professional, hospital or clinic

22. Should a Fitness for Duty Evaluation be performed? Yes No (If not, why?)

INVESTIGATION

23. Do standard methods/procedures exist? Yes No Were methods/procedures followed? Yes No

Was activity a normal part of job? Yes No Was person adequately trained? Yes No

HU FACTORS:

Time Pressure Vague/Interpretive Guidance Physical Environment Communications

Distraction/ Interruption First Shift/Late Shift Mental Stress

Multiple Tasks Peer Pressure Assumptions

Overconfidence Change/Off Normal Lack of Supervision/Oversight

24. How could this accident have been prevented?

25. What changes are recommended to prevent recurrence?

26. List action(s) being taken to prevent recurrence.

Action(s) Person(s) Responsible for

Action Date to be

Accomplished Date Accomplished

[Dept. use only]

27. Issue Report Number:

Additional Comments by employee or supervisor. (If continuing from a section on front, use corresponding number) Attach additional sheet if necessary.

I HAVE READ THE ABOVE REPORT, FRONT AND BACK, AND THE INFORMATION PROVIDED IS TRUE AND CORRECT.

Injured Employee’s Signature

Date

Date of Report

Supervisor’s Signature

Supervisor’s Employee No.

Prepared by – Name / Title Phone / Date

Approved – Dept. Manager’s Signature

FOR CORPORATE USE ONLY

Incident Number/OSHA Case Number Class OSHA Class

Reviewed by Verified by

Page 47: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

Form HSEM‐02, Rev 1 

© RIZZO Proprietary and Confidential Work Product 

  Page 1 of 1

NEAR MISS INCIDENT REPORT  

1.    Submitted by:              Employee Number:              Date:             

2.    Work Group(s) Involved:   

           

3.    Incident Location:             

4.    Date of Incident:              Time (AM/PM):             

5.    Brief description of incident and immediate corrective actions/compensatory measures taken:   

            

6.    How could this incident have resulted in injury?  How serious could the injury have been?   

           

7.    Recommendations:   

           

8.    What were the causes of the incident?   

           

9.    Is this applicable to other work areas or work activities?   

           

10.  Should a Fitness for Duty Evaluation be performed?  If not, why?     

           

11.  List Actions Taken to Prevent Recurrence: 

Action(s)  Responsible Person Estimated 

Completion Date Date Completed 

                                               

                                               

                                               

12.  Investigation Completed By:              Date:             

13.  Should a Prompt Investigation Be Performed?               Yes            No  IR#:             

14.  General Supervisor Signature:   

 

Date:             

FORWARD ORIGINAL TO THE RIZZO QHSE STAFF  

Page 48: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

Form HSEM‐03, Rev 1 

© RIZZO Proprietary and Confidential Work Product  

Page 1 of 1 

 

HSE INCIDENT LOG 

DATE  TIME  NAME  COMPANY  DESCRIPTION OF EVENT 

         

         

         

         

         

         

         

         

         

         

         

         

 

Page 49: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

ENVIRONMENTAL FIELD INSPECTION FORM 

Form HSEM‐04, Rev 1 

© RIZZO Proprietary and Confidential Work Product 

Page 1 of 6

 

Facility:   

 

Date: 

Instructions: I. Walk site and review each of the following areas. II. Explain each “No” answer in the comment section.  Suggest corrective action. III. Sign completed form and ensure records are maintained as required.   

GENERAL ENVIRONMENTAL MANAGEMENT  Yes  No  N/A 

1.  Is housekeeping in all areas in good condition?  All areas should be neat, orderly, and clean. 

     

2.  Are spill cleanup materials and equipment in good condition and in close proximity to where they might be needed? 

     

3.  Does security appear adequate?  Fencing, locks, and lighting are in good condition. 

     

Comments: 

 

 

 

 

WASTE MANAGEMENT  Yes  No  N/A 

4.  

Are trash receptacles free of the following hazardous, universal, or recyclable waste? 

Aerosol cans 

Containers with product (e.g., paint, solvent) 

Saturated oily rags or absorbent pads 

Rags or absorbent pads with solvent odor 

Discarded equipment that contains refrigerant 

Universal waste (mercury containing lamps, batteries, pesticides, thermostats) 

Recyclable items (aluminum cans, metal, glass, plastic, cardboard, paper, etc.) 

Tires (should be recycled) 

     

Page 50: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

ENVIRONMENTAL FIELD INSPECTION FORM 

Form HSEM‐04, Rev 1 

© RIZZO Proprietary and Confidential Work Product 

Page 2 of 6

5.  

Is waste properly contained in drums? 

Bungs closed and no open funnels 

Lids sealed tight  

Clearly labeled with contents 

Where contents are flammable, drum is grounded 

Drums not stacked 

Outside of drum clean; no evidence of waste product 

     

6.  

Are drums in good condition (includes empty drums)? 

Free of dents 

Free of holes 

Free of rust 

Free of bulges or leaks 

     

7.  

Is hazardous waste secondary containment in good condition? 

Free of cracks, gaps, waste product, and no breaching 

Containment drains closed 

     

8.  Is hazardous waste secondary containment free of product or 

water? 

     

9.  

Is the emergency equipment in the hazardous waste storage area in working order? 

Telephone or paging system (radio) must work properly 

There must be a fire extinguisher present that is inspected monthly 

Spill cleanup equipment must be present and in good condition.  

If the facility is a small quantity generator, emergency response information must be posted near the communication system. 

     

10.  

Will the aisles in the hazardous waste satellite and accumulation (storage) areas allow for movement of emergency response equipment?  

Must be able to see all sides of drum for markings and drum conditions. 

     

11.  Is the accumulation start date on all drums in hazardous waste storage/disposal area? 

     

12.  Are used oil drums and tanks properly marked with the words "Used Oil"? 

     

13.  Are used batteries and mercury containing lamps stored in designated area? 

     

14.  Are used batteries and mercury containing lamps marked with accumulation start date? 

     

Page 51: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

ENVIRONMENTAL FIELD INSPECTION FORM 

Form HSEM‐04, Rev 1 

© RIZZO Proprietary and Confidential Work Product 

Page 3 of 6

15.  Are crushed or broken mercury containing lamps contained to prevent release of mercury? 

     

16.   Are leaking batteries contained to prevent release of acid?       

17.   Are Port‐O‐Lets secure and free from leaks?       

Comments: 

 

 

 

CHEMICAL/PRODUCT MANAGEMENT  Yes  No  N/A 

18.  

Are new products properly stored in labeled containers? 

Labeled with contents and appropriate hazard warnings 

Containers kept closed 

No open top buckets/pails with product 

The original manufacturer's label intact and readable MSDS available 

     

19.  Are flammable liquids and aerosols stored in nonflammable cabinets? 

     

20.   Is the quantity of gasoline storage inside a building < 25 gallons?       

21.   Are the "No Smoking" areas free from any evidence of smoking?       

22.  Are hazardous materials properly stored away from storm drains or pervious surfaces? 

     

23.  

Are storm drains free of hazardous materials? 

No staining, discoloration 

No odors 

No visible sheen 

     

Comments: 

 

 

 

 

AIR EMISSIONS MANAGEMENT  Yes  No  N/A 

24.  Is the facility area free from any evidence of particulate fallout from stack emissions? 

     

25.  Are fugitive emissions minimized and area sources minimized?  (Sandblast curtains, slow vehicle speeds, water truck operating, adequate shell rock/aggregate cover, etc.) 

     

26.   Is the area free from any objectionable odors?       

Page 52: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

ENVIRONMENTAL FIELD INSPECTION FORM 

Form HSEM‐04, Rev 1 

© RIZZO Proprietary and Confidential Work Product 

Page 4 of 6

27.   Is excessive noise minimized?       

Comments: 

 

 

 

 

EROSION/SEDIMENT CONTROL  Yes  No  N/A 

28.  

Silt Fence Conditions (where required) 

Are fences free of tears? 

Are fences secure to posts? 

Is sediment less than 1/3 of fence height? 

Is base/bottom edge of silt fence secured below ground? 

     

29.  Are construction entrances / exits mostly free of mud, dirt, and 

rock? 

     

Comments: 

 

 

 

 

WATER QUALITY MANAGEMENT  Yes  No  N/A 

30.  

Do the water discharge areas look clean? 

Free of foam 

No oil/grease sheen 

Each outfall clearly labeled 

     

31.  Is the area free from evidence of industrial wastewater discharging to the ground?  (e.g., reverse osmosis reject, etc.) 

     

Comments: 

 

 

 

 

TANKS/PIPELINES  Yes  No  N/A 

32.   Are the tanks or pipes free from any signs of leakage or spillage?       

33.  Are the areas on ground around tanks or piping free from evidence of staining or dying vegetation? 

     

Page 53: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

ENVIRONMENTAL FIELD INSPECTION FORM 

Form HSEM‐04, Rev 1 

© RIZZO Proprietary and Confidential Work Product 

Page 5 of 6

34.  Are oil piping systems properly aligned and are supports/foundations in good condition? 

     

35.  

Do all above ground tank structures look sound? 

No buckling, cracks, wetting, discoloration, blistering 

No significant corrosion 

No cracks in base/apron 

No signs of settlement 

     

36.  Are storage tank/piping release detection systems free of oil?              (e.g., double‐bottom tank, monitoring wells, etc.) 

     

37.  Is the cathodic protection working properly?  Electrical box shows that amps of current is flowing 

     

38.  

Is secondary containment for tanks in good condition? 

Concrete secondary containment should be free of cracks or penetrations. 

Earthen dikes should be free of erosion, oil stains, trash accumulation, or undergrowth. 

Temporary containments sound? 

     

39.   Is secondary containment for tanks free of product and water?       

40.   Are transformers in proper containment and free of leaks?       

Comments: 

 

 

 

 

PROTECTED SPECIES MONITORING  Yes  No  N/A 

41.   Are Threatened and Endangered species conservation and monitoring plans being implemented effectively? 

Surveys of construction area conducted for protected species? 

     

42.   Is the site free of any dead animals?       

Comments: 

 

 

 

 

 

Page 54: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

ENVIRONMENTAL FIELD INSPECTION FORM 

Form HSEM‐04, Rev 1 

© RIZZO Proprietary and Confidential Work Product 

Page 6 of 6

Good Practices: 

 

 

 

Improvement Opportunities: 

 

 

 

 

Actions required for “NO: Responses (What, Who, When) 

 

 

 

 

 

 

Inspector’s Signature: 

 

 

Inspector’s Name: 

 

 

Inspector’s Title: 

 

 

NOTE: 

 A. This is not a comprehensive environmental inspection sheet.  Other country, federal, state, 

and local requirements may apply to the site.  This form is not to be used as a substitute for a full compliance audit. 

B. A "No" answer indicates a situation that requires immediate action.  Specify what action will be taken, by whom, and when. 

 

Page 55: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

Form HSEM‐05, Rev 1 

© RIZZO Proprietary and Confidential Work Product 

Page 1 of 1  

TOOLBOX SAFTEY AND ENVIRONMENTAL MEETING FORM  

DATE     

MEETING CONDUCTED BY :   

PROJECT NUMBER     

PROJECT SITE     

HSE TOPICS REVIEWED AND INFORMATION DISCUSSED: 

 

 

FOLLOW‐UP ACTION AND COMMENTS   

 

 

  

ATTENDEES: 

NAME (PRINT)  SIGNATURE  REPRESENTING 

1     

2     

3     

4     

5     

6     

7     

8     

9     

10     

11     

12     

Page 56: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

DRILL RIG SAFETY CHECKLIST 

Form HSEM‐06, Rev 1 

© RIZZO Proprietary and Confidential Work Product 

Page 1 of 2

Date: 

 

Performed by: 

 

Contractor/subcontractor results discussed 

with: 

Location: 

Check “Yes” if an item is complete/correct. 

Check “No” if an item is incomplete/deficient.  Deficiencies shall be brought to the attention of the Site Supervisor.  Any issue involving immediate danger to personnel or equipment shall be stopped immediately.   

Section 2 must be completed for all items checked “No.” 

Check “N/A” if an item is not applicable. 

SAFE WORK PRACTICES  YES  NO N/A

1. Only authorized personnel operating drill rig       

2. Area cleared prior to rig start‐up       

3. Personnel clear of rotating parts       

4. Personnel not positioned under hoisted loads       

5. Loose clothing and jewelry removed       

6. Instructed not to approach equipment that has become electrically energized 

     

7. Smoking only in designated areas       

8. Wearing appropriate PPE, per HSEP       

DRILL RIG PLACEMENT  YES  NO N/A

9. Location of underground utilities evaluated and identified       

10. Safe clearance distance maintained from power lines       

11. Drill pad established, when necessary       

12. Drill rig leveled and stabilized       

DRILL RIG TRAVEL  YES  NO N/A

13. Mast lowered and secured prior to rig movement       

14. Tools and equipment secured prior to rig movement       

15. Personnel seated in cab during movement       

16. Safe clearance distance maintained while traveling under overhead power lines 

     

17. Backup alarm or spotter used when backing rig       

DRILL RIG OPERATION  YES  NO N/A

18. Kill switch clearly identified and operational       

19. All machine guards are in place       

20. Rig ropes not wrapped around body parts       

21. Pressurized lines and hoses secured from whipping hazards       

22. Drill operation stopped during inclement weather       

23. Air monitoring conducted per HSEP for hazardous atmospheres       

24. Rig placed in neutral when operator not at drilling controls       

Page 57: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

DRILL RIG SAFETY CHECKLIST 

Form HSEM‐06, Rev 1 

© RIZZO Proprietary and Confidential Work Product 

Page 2 of 2

DRILL RIG MAINTENANCE  YES  NO N/A

25. Defective components repaired immediately       

26. Lockout/tagout procedures used prior to maintenance       

27. Equipment leaking fluids, lubricants or other fluids       

28. Drill rig ropes, hoses and cables in clean, sound condition       

29. Fall protection used for fall exposures of 6 ft or greater       

30. Rig in neutral & augers or rods and barrels stopped rotating before cleaning 

     

31. Good housekeeping maintained on and around rig       

32. Fire Extinguisher located and inspected       

33. First Aid Kit located and inspected       

 

SECTION 2 COMPLETE THIS SECTION FOR ALL ITEMS CHECKED “NO” IN SECTION 1.  DEFICIENT ITEMS MUST BE CORRECTED IN A 

TIMELY MANNER. 

ITEM #  DESCRIPTION OF ISSUE & CORRECTIVE ACTION PLANNED/TAKEN  DATE COMPLETED 

     

     

     

     

     

  _____  Allow to work.  _____  No work until repairs made/activities adjusted.     ________________________________________________   ___________________ Name / Signature                Date Site supervisor or designee  

Page 58: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

Form HSEM‐07, Rev 1 

© RIZZO Proprietary and Confidential Work Product 

Page 1 of 1

ON‐SITE EMERGENCY CONTACTS 

 

CONTACT  NAME  PHONE NUMBER 

Client Representative     

Nearest Hospital     

Fire Department     

Police Department     

Ambulance     

Highway Emergencies     

Poison Control Center     

Spill Response     

Utility One‐Call System     

RIZZO Project Manager     

RIZZO site supervisor     

RIZZO QHSE Staff     

RIZZO Administration     

Subcontractor(s) Representative     

Page 59: HEALTH, SAFETY, AND ENVIRONMENTAL (HSE) MANUAL RIZZO

Project Number: 

Site Name: 

Sheet                              of  

Form HSEM‐08, Rev. 1  © RIZZO Proprietary and Confidential Work Product 

   

DAILY SIGN IN/SIGN OUT SHEET  

DATE  NAME  COMPANY  TIME IN  TIME OUT