HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
HELICOPTER
PRE-DESIGN PROCESS
IMPROVEMENT
M. GREILLER (Eurocopter)
VIVACE Forum 1, Warwick UK, 20-21 September 2005
-
8/11/2019 Helicopter Design Roadmap
2/26
Page: 2 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
Table of contents
HELICOPTER INDUSTRY PARTICULARITIESMultiple customers and missionsMarket characteristicsHeavy development
DEVELOPMENT PROCESS DESCRIPTIONGeneral development processPre-Design process
USE CASE DESCRIPTIONAS-IS pre-design processTO-BE pre-design processBenefits
SCENARIOSMastering uncertaintyGeneral architectureLife Cycle CostVisualisation & selection
ROADMAP
WhyVIVA
CE
forhelicop
ter
VIVACE
Actions
Photos EUROCOPTER
-
8/11/2019 Helicopter Design Roadmap
3/26
Page: 3 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
HELICOPTER INDUSTRY PARTICULARITIES
Commercial companies offering regularflights (Off-shore, commuters)
Customers :
Charter or private owners
Military or public customers
Multiple customers and missions
Search and Rescue
Missions :
Off-shore or commuter
Military missions
Photos EUROCOPTER
-
8/11/2019 Helicopter Design Roadmap
4/26
Page: 4 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
Very small seriesMany versions for the same type of helicopter
Low self financing capacityDue to the small series, the recurrent costs and the sale prices cant bereduced.
Fewer major national programsDecrease of great National contracts
(usually military ones)
Market characteristics
HELICOPTER INDUSTRY PARTICULARITIES
Photos EUROCOPTER
-
8/11/2019 Helicopter Design Roadmap
5/26
Page: 5 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
Complex air wake generated by themain rotor
Behavior simulation difficulties
Numerous modifications during thedevelopment phase due to:
- Vibrations
- Flight qualities
- Icing
- Wake interactions
Parts generally reworked :
- Position of the horizontal stabiliser
- Anti-vibration devices
- Air intakes
- Upper cowlings
Heavy development
HELICOPTER INDUSTRY PARTICULARITIES
Photos EUROCOPTER
-
8/11/2019 Helicopter Design Roadmap
6/26
Page: 6 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
DEVELOPMENT PROCESS
General development process
Feasibility
Pre-Development Development
Industrialisation
Service life support
Pre-Design process
Photos EUROCOPTER
-
8/11/2019 Helicopter Design Roadmap
7/26
Page: 7 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
Feasibility (Managed by Pre-project team)Actors:- Pre-project team,
- Strategy,
- Marketing and sales,
- Finance.
Results:- Top level requirements,
- Technical feasibility document,
- Business case.
PRE-DESIGN PROCESS
Pre-Development (Managed by Program team)Actors (those above and):
-Project management
-Technical specialists
-Purchasers
-Production
Results:
-Global aircraft and major sub-
systems specification frozen.
-Major interfaces frozen,
-Major subcontractors chosen,
-Risk management Plan,
-Business case (complete)
-
8/11/2019 Helicopter Design Roadmap
8/26
Page: 8 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
AS-IS Pre-design process
USE CASE DESCRIPTION
TO-BE Pre-design process
Main risks andopportunities:
Identification
and assessmentwith a new
process
General architecture definition:
- Customers requirements fulfillment
- Simplification of the helicopter
integration
Costs evaluation :
Assessment andoptimization for a
large panelofcustomers and/or
mission
Main risks andopportunities:
Coming from
experience of somespecialists
Costs evaluation :
For eachcustomer and/or
mission
General architecture definition:
- New products derived from existing
products.
- Not complete pre-design phase, with
high level of risks.
-
8/11/2019 Helicopter Design Roadmap
9/26
Page: 9 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
USE CASE DESCRIPTION
BENEFIT
Spend more time and money during this first phase, in order to avoid a re-
design later.
HOW
By using the 4 following scenarios
1. Mastering the uncertainty
2. General architecture
3. Life Cycle Cost
4. Visualisation and selection
-
8/11/2019 Helicopter Design Roadmap
10/26
Page: 10 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
SCENARIO 1. Mastering uncertainty
Scope :
AS-IS Process
TO-BE Process
Data provided without assessment of their uncertainty.All values could be very lower or higher than the good data.
Its mandatory to identify, categorise and quantify themain risks or opportunities before sending data
Provide common methodology to express andassess the uncertainty of numerical data.
-
8/11/2019 Helicopter Design Roadmap
11/26
Page: 11 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
- 1 - Identifyand categorise
all the types ofrisks
- 2 - Map thoseRisks and trace their
interdependencies.
- 3 - Evaluate theexisting probabilistic
tool and make aselection.
- 4 - Builda technicalexample
- 5 - Performsensitivity analysisof the example
- 6 - Conclude withthe benefit and thelimits of the method
Scenario description :
SCENARIO 1. Mastering uncertainty
-
8/11/2019 Helicopter Design Roadmap
12/26
Page: 12 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
Today referenceArithmetical sum of the elementary margins to
ensure usual level of confidence for sub-parts
Objective
Save 20-30% of the standard margins
Criteria - Metrics
Identify and quantify
R-O*Categorise R-O* and trace
their interdependencies
Aggregate elementary
R-O*
Service functions
CriteriaMargin to ensure usual level of confidence
(90%)
Perform sensitivity
analysis Link back-up solutions
* R-O = Risks orOpportunities
SCENARIO 1. Mastering uncertainty
-
8/11/2019 Helicopter Design Roadmap
13/26
Page: 13 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
This scenario is linked with WP3.3 through the
following activities
(Design to Decision Objectives)
Analyse the state
of art and propose
adapted solutions
Help to identify,
categorise and map the
generic risks and
opportunities
Evaluate the existing
probabilistic tool and
propose a selection
Contributions
Help for sensitivity
analysis
SCENARIO 1. Mastering uncertainty
-
8/11/2019 Helicopter Design Roadmap
14/26
Page: 14 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
Scope
To
formalise
To
make
explicit
The purpose
of this
scenario is
The steps of the elaboration process fora global aircraft architecture
and
SCENARIO 2. General Architecture
Photos EUROCOPTER
-
8/11/2019 Helicopter Design Roadmap
15/26
Page: 15 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
TO-BE process :
Pre-Projectteam
Experience
feed-backdata base
and tools
Elaboration of balanced architectures for new helicopters
40% 60%
Experience
of involvedpeople
The definition
Result of pre-project phase
The technical
specifications
Context HypothesisChoices
Forgotten parameters
AS-IS process
SCENARIO 2. General Architecture
-
8/11/2019 Helicopter Design Roadmap
16/26
Page: 16 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
- 1 -Collectingthe Know-Howof specialists
- 2 - Collectingmain justifications ofgeneral architecture
- 3 - Formalisingthese informationsfor a further re-use
- 4 -Developing ofa tool to link the
inter-connectedsubjects
- 6 - Defining and
formalising thecriteria to assess anarchitecture.
- 5 - Identifying themajor topics or
problematics,addressed by thegeneral architectureprocess
Scenario description
SCENARIO 2. General Architecture
Photos EUROCOPTER
-
8/11/2019 Helicopter Design Roadmap
17/26
Page: 17 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
Criteria
Time to elaborate a new architecture
Today reference
About 1 year for experienced people
Objective
About 9 months
Criteria - Metrics
Service functions of the developed tool
Identify and capitalise
the Know-How of
experienced people
Make this Know-How
usable for non-specialists
Propose a formal model
to elaborate an
architecture
Service functions
SCENARIO 2. General Architecture
-
8/11/2019 Helicopter Design Roadmap
18/26
Page: 18 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
This scenario is linked with WP3.3 through thefollowing activities
(Design to Decision Objectives)
Define an adequate
structure for the
Know-How data-base
Define the tools to
link the inter-
connected subjects
Formalise the
general architecture
process
Contributions
SCENARIO 2. General Architecture
-
8/11/2019 Helicopter Design Roadmap
19/26
Page: 19 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
Scope
Optimising the technical definition of a helicopter for :- Different customers -
- Different requirements -- Opposite profiles -
AS-IS &TO BE processes
Market analysis for many
customers, for only one definition
Cost estimation based on the
most critical mission
Economical impact estimation for
all the categories of customers
Market analysis for all
customers and all missionsAS-IS TO-BE
Technical choices
(which involve a cost aspect)
SCENARIO 3. Life Cycle Cost
-
8/11/2019 Helicopter Design Roadmap
20/26
Page: 20 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
- 1 - Definethe categoriesof customer
- 2 - Adapt the sizingmodels of NLR and EC:find a common list oftechnical parameters
- 3 - Developthe cost model
- 4 - Perform sensitivityanalysis on a limitednumber of parameters
- 5 - Optimise helicopterdefinition for LCC of 1customer first.
- 6 - Define a criteriato combine LCC ofmultiple customers &
missions
- 7 - Optimisehelicopter definitionfor this composite
criteria
Scenario description
SCENARIO 3. Life Cycle Cost
-
8/11/2019 Helicopter Design Roadmap
21/26
Page: 21 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
CriteriaTime to perform combined technical & market analysis
Today reference1 2 weeks
(Models not complete or not connected)
Objective
1 Day
Criteria - Metrics
Service functions of the developed tool
Estimate the LCC of any
technical definition for
any customers profile
Perform sensitivity
analysis
Optimise helicopter
definition for LCC of 1 or
multiple customers &missions
Service functions
SCENARIO 3. Life Cycle Cost
-
8/11/2019 Helicopter Design Roadmap
22/26
Page: 22 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
Adapt the sizing
tool for cost
calculations
Connect the
sizing tool with
the cost model
Define the multi-
criteria optimisation
method
Contributions
This scenario is linked with WP3.2 through thefollowing activities
(Multidisciplinary Design & Optimisation)
Perform the
sensitivity
analysis
SCENARIO 3. Life Cycle Cost
-
8/11/2019 Helicopter Design Roadmap
23/26
Page: 23 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
Scope :
Visualisation of complete helicopter geometric models with:- Short access time -
- Focusing only on interesting areas -- High precision -
AS-IS &TO BE processes :
The size of the models are too much
important for a complete helicopter
Models are too long to be visualised
with usual CAD tools
Capability to visualise any part of
an helicopter in its context.
Perform general architecture studiesAS-IS TO-BE
Only used for details studies, or with
rough models for complete helicoptersVisualisation of an entire digital
mock-up
SCENARIO 4. Visualisation and selection
-
8/11/2019 Helicopter Design Roadmap
24/26
Page: 24 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
Scenario description:
- 1 - Evaluateexistingvisualisation
tools- 2 - Definemethodology to usethose models
- 3 - Select an existingtool or write an userspecification forfurther tools.
SCENARIO 4. Visualisation and selection
Photos EUROCOPTER
-
8/11/2019 Helicopter Design Roadmap
25/26
Page: 25 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
CriteriaTime to visualise typical complete helicopter model
Today reference
About 1 hour
Objective
Few seconds
Criteria - Metrics
Service functions of the developed tool
Visualise and animate
models of completehelicopters,
Refine selected
areas up to
elementary items
Service functions
Automatically
simplify native
models
SCENARIO 4. Visualisation and selection
-
8/11/2019 Helicopter Design Roadmap
26/26
Page: 26 2004 VIVACE Consortium Members.
Al l r ights reserved
HELICOPTER
PRE-DESIGN PROCESS IMPROVEMENT
Warwick UK, 20 &21 September 2005VIVACE Forum-1
ROADMAP
First
prototype
release
Solutions
assessment &
selectionSEEMAGE software evaluation in
progress.
Requirements
and
specifications
report
DONE
4. Visualisation and selection
First
prototype
release
Solutions
assessment &
selection
A helicopter Life Cycle Cost model
was sent to NLR in order to integrate
it into the NLR sizing tool SPEAR
tool.
Requirements
and
specifications
report
DONE
3. Life Cycle Cost
First
prototyperelease
Solutions
assessment &selection
Assessment of a forecasted solut ion
using INGENIUM sof tware, in
progress
Requirements
and
specificationsreport
DONE
2. General arch itecture
First
prototype
release
Solutions
assessment &
selectionWP3.3 solutions assessment in
progress.
Requirements
and
specifications
report
DONE
1. Mastering the uncertainty
M30(Deliverable)
M24(Deliverable)
M21M12
(Deliverable)SCENARIO