HIGH RADIATION TO MATERIALS: HIRADMAT STATUS HiRadMat Scientific Board, 23/4/2012 Outline Location Status Beam line Infrastructure Exp. Area Surface lab Control room Bunker A. Pardons, S. Evrard EN-MEF EDMS

Upload: paloma

Post on 22-Feb-2016

67 views

Category:

Documents


0 download

DESCRIPTION

Outline Location Status Beam line Infrastructure Exp. Area Surface lab Control room Bunker. Hi gh Rad iation to Mat erials: HiRadMat status . HiRadMat Scientific Board, 23/4/2012. A. Pardons, S. Evrard EN-MEF EDMS. HiRadMat Location. HiRadMat Location. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Hi gh  Rad iation to  Mat erials: HiRadMat  status

HIGH RADIATION TO MATERIALS: HIRADMAT STATUS

HiRadMat Scientific Board, 23/4/2012

Outline Location Status

Beam line Infrastructure Exp. Area

Surface lab Control room Bunker

A. Pardons, S. EvrardEN-MEF  

EDMS

Page 2: Hi gh  Rad iation to  Mat erials: HiRadMat  status

HRM Sci. Board, 23rd of April, 2012

2

HiRadMat Location

S. EVRARD

Page 3: Hi gh  Rad iation to  Mat erials: HiRadMat  status

3

HiRadMat shares the same extraction from SPS as the TI2 line to LHC

The experimental area will be upstream the old T9 target for the West Area Neutrino Facility - WANF

HRM Sci. Board, 23rd of April, 2012S. EVRARD

HiRadMat Location

Page 4: Hi gh  Rad iation to  Mat erials: HiRadMat  status

S. EVRARD

4

HRM Sci. Board, 23rd of April, 2012

Control room

Surface lab

HRM Sci. Board, 23rd of April, 2012S. EVRARD

HiRadMat Location

Page 5: Hi gh  Rad iation to  Mat erials: HiRadMat  status

HRM Sci. Board, 23rd of April, 2012S. EVRARD

5

Test Laboratory

Control room

BA7

Access to underground(person + light tooling)

Entrance

Access to undergroundEquipment by elevator

HiRadMat Location

Page 6: Hi gh  Rad iation to  Mat erials: HiRadMat  status

6

‣WANF dismantling completed‣ 95t of waste, 323 m3‣ 800t of blocks moved around

‣Beam line (TT66) installation completed‣ 25 magnets, 13 power converters‣ 17 beam instrumentation elements‣ 200m of new vacuum, + TI2 vacuum adaptation‣ 460 new cables, 4 km, 300 old cables removed‣ Dry run (April ’11), LI beam commissioning (June ’11), HI commissioning (September ’11)

‣Infrastructure & Experimental area ready for first experiment‣ Beam dump installed‣ Tables for experiments installed and tested. ‣ Ventilation system working, tested and accepted‣ Access system working, tested and accepted‣ RAMSES monitoring fully commissioned and operational‣ Control room and laboratory ready in BA7

Status as of today

HiRadMat Status

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 7: Hi gh  Rad iation to  Mat erials: HiRadMat  status

7

HiRadMat Status

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 8: Hi gh  Rad iation to  Mat erials: HiRadMat  status

8

vital to check beam line components, instrumentation and optics

Low Intensity beam commissioning

Wed. 22 June. First pilot sent reached the end of the beam line: Energy matching and trajectory

correction performed;Check of: Beam instrumentation

response Logging Aperture measurement Optics change Radiation monitor response

Courtesy of Malika Meddahi

HiRadMat Status

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 9: Hi gh  Rad iation to  Mat erials: HiRadMat  status

9 Low Intensity beam commissioning: orthogonal steering

The beam was steered independently in both planes within the range +/- 4 mm, as specified in the HiRadMat specs. (last BTV screen)

Courtesy of Malika Meddahi

HiRadMat Status

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 10: Hi gh  Rad iation to  Mat erials: HiRadMat  status

Radiation monitoring10

1 x stray rad. Station (includes cabin + infrastructure) Ventilation station 8 x PMI monitors (for the HIRADMAT area and the

neighbouring tunnel, accurate position to be defined)

2 x IG5 monitors (hydrogen type), 1 x IG5 monitors (argon type)

3 Alarm Units (UA) 1 x hand foot monitor 1 x material control monitor

BA7

TCC6B.846

TNC

TT61

EPIC ERC

Stray radiationMonitoring

VGM - VAS

VentilationMonitoring

PCM

PMIIG5

HiRadMat Status

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 11: Hi gh  Rad iation to  Mat erials: HiRadMat  status

11 Low Intensity beam commissioning: radiation monitor response

Readings (Sv/h) of the residual dose rate monitor PMIHR05 installed next to the dump in the HiRadMat experimental.

Courtesy of Malika Meddahi

HiRadMat Status

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 12: Hi gh  Rad iation to  Mat erials: HiRadMat  status

12 High intensity beam commissioning

LHC nominal with 144 bunches

Courtesy of C. Theis HRM Sci. Board, 23rd of April, 2012S. EVRARD

HiRadMat Status

Page 13: Hi gh  Rad iation to  Mat erials: HiRadMat  status

Access13

HiRadMat Status

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 14: Hi gh  Rad iation to  Mat erials: HiRadMat  status

Cooling & Ventilation14

1- Run mode2- Flushing mode3- Access mode4- Cold smoke extraction mode

HiRadMat Status

HRM Sci. Board, 23rd of April, 2012S. EVRARD

TNC

Page 15: Hi gh  Rad iation to  Mat erials: HiRadMat  status

15

Question Procedure EDMSHow to get access authorized to the HiRadMat facility ?

Preparatory steps to take before accessing to HiRadMat

1154948

How to get access to HiRadMat Access procedure 1155061How to escape from the facility ? Escape procedure 1153056How to patrol the facility ? Patrol procedure 1152694How to deal with activated material ?

Activated material management procedure

1146265

How to handle alarms from HRM ? Alarm management procedure 1152693How to maintain the facility ? Maintenance plan 1154793How to deal with incidents ? Faulty situation and incident

analysis1154637

How to manage fire risk ? Fire prevention and fire risk management

1146217

Operation part

HiRadMat Safety file

Green light from authorities

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 16: Hi gh  Rad iation to  Mat erials: HiRadMat  status

Experimental area16

3 positions are foreseen for the test object: stand A, B and C

Base tables carryservices (water, signal, motorisation)

Base tables arefixed to tunnel floorand aligned w.r.t. beam

Test object will be onan interface table thatconnects to the base

Test zone in TNC – Base Tables

HRM Sci. Board, 23rd of April, 2012S. EVRARD

A

BC

Page 17: Hi gh  Rad iation to  Mat erials: HiRadMat  status

Experimental area17 Integration in tunnel

Reminder: Test objects must be contained, cable feed-throughs and portholes must be tight

Installation of table is 100% remoteEach access to TNC must be duly justified. They must be requested before the test table installation.

Tables compatible with different sizes and types of test objects

After the beam test, the test table will be moved remotely to a downstream location in TNC for a cool-down time defined by the radioprotection team.

After the cool-down time, the object will be transported to the surface and brought to an adapted (CERN-RP) lab for dismantling. HiRadMat project recovers the mobile table, the user is responsible for treatment of the test object.

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 18: Hi gh  Rad iation to  Mat erials: HiRadMat  status

18 Experimental area: Plug-in test

Experimental area

Tested equipment will be remotely handled

Crane driver training completed

3 interface table ready

5 additional ones in the pipeline

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 19: Hi gh  Rad iation to  Mat erials: HiRadMat  status

Experimental area19 Services available in 2012

On passage-side wall opposite to test stand: - Manual gas connector for neutral gas (He or N2 – on request)

In TA7- TJ7, at ~25m from test stands- Power (230V)- Signal rack for testing signal &

motorisation connections

Services available in

irradiation areaIn 2012

Plug-in on base-table:- Cooling circuit (30kW, 3m3/h,

9bar)- Power (4 kV/2.5kA) - Signal cables (50V/2A e.g. for

camera, motorization, vibration measurement )

Tables A,B,C are all equipped

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 20: Hi gh  Rad iation to  Mat erials: HiRadMat  status

Surface lab20

Replica of test stand like in TNC

Preparation area for the experiment mounting, alignment, test with cables/readout

Base table has all connectors, signals read in control room

Test table is aligned (CERN surveyors) w.r.t. virtual beam

No radioactive objects allowed!

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 21: Hi gh  Rad iation to  Mat erials: HiRadMat  status

Control Room21

All cables arrive there: 1 rack/stand + 1 rack for surface lab

Beam terminal and info from SPS (beam control from CCC only)

All exp. monitoring during beam test from control room

Network and timing signal available

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 22: Hi gh  Rad iation to  Mat erials: HiRadMat  status

Bunker in TJ722

Protect analysis hardware (fast camera, vibrometer)

230V power supply, network and timing signal available

HRM Sci. Board, 23rd of April, 2012S. EVRARD

Page 23: Hi gh  Rad iation to  Mat erials: HiRadMat  status

HRM Sci. Board, 23rd of April, 2012

23

Thank you for your attention – Any questions?

HD pictures of the HRM facility available hereLayouts consultation: 3DVIA composer (under construction)