hi gh rad iation to mat erials
DESCRIPTION
part of the EUCARD FP7 program. Outline The HiRadMat facility – Why, What, When, Where Status WANF (*) dismantling Primary beam line installation Planning: Installation & Commissioning in 2011 Irradiation Area Layout & Operation Summary. Hi gh Rad iation to Mat erials . - PowerPoint PPT PresentationTRANSCRIPT
HIGH RADIATION TO MATERIALS
Ans Pardonsfor the HiRadMat project team
IEFC Workshop, March 22, 2011
Outline The HiRadMat facility – Why, What, When, Where Status
WANF(*) dismantling Primary beam line installation
Planning: Installation & Commissioning in 2011 Irradiation Area Layout & Operation Summary
EDMS No: 1136640
Thanks to: I. Efthymiopoulos, S. Evrard, M. Meddahi, C. Hessler, C.Theis, N. Conan, Y. Algoet, Ph. Trilhe, C. Magnier, M. Lazzaroni, O. Choisnet, D. Grenier, J.-L. Grenard, N. Charitonidis
part of the EUCARD FP7 program
(*)West Area Neutrino Facility
The HiRadMat Facility
IEFC Workshop Mar. 22, 2011
2 Why, What & When Luminosity increases in particle accelerators materials of near-beam
equipment must be able to withstand the higher beam intensity Need for a facility to test materials in an intense pulsed beam to investigate
damage effects from heat & radiation with increasing intensity. analyze the threshold of destructive effects to find material limitations
HiRadMat = Facility to study the impact of intense pulsed beams on materials Thermal management (heating) & thermal shock (pressure waves) Radiation damage to materials - change of mechanical properties
Beam extracted from SPS (450GeV/c): provides 1011 protons per bunch, 288 bunches per pulse, 30 pulses per user 1015 protons per user, ~2.4MJ/pulse
Beam size 0.1-0.5mm (1σ) at impact. Aim for 2011: 3 users - LHC phase 2 collimator (jaw materials), tungsten powder
(as high-power target for future neutrino beams), beam windows. Interest expressed for > 2011: protection devices, machine components,
material studies, irradiation tests of electronics.
Why
Wha
tW
hen
Ans Pardons
The HiRadMat Facility3 Where
SPS
TI 2
TT60
Beam
End of common partwith TI 2 transfer line
50 m
Beam
TT66 new line
Access to HiRadMat intrinsically linked to LHC (injection)
TI2 LHC
HiRadMat test objects
TT61 (to former West Area)
TNC (former WANF target hall)
IEFC Workshop Mar. 22, 2011Ans Pardons
The HiRadMat Facility
IEFC Workshop Mar. 22, 2011
4
T1 - former West Area primary target & shielding & MTR magnets: dismount
TNC - former neutrino target hall with secondary beam elements: replace services, dismount beam elements & complete HRM beam dump
Where & Location of main dismantling activities
BA7
TCC6 B.846TNC
WANF target chamberWith secondary beamline
T9: former neutrino beam target: dismount target & collimators and install HRM beam dump in and behind former T9 shielding castle
T1
TI2
Former beamline targets radiation
T9
HiRadMat User Experimental Area
TJ7
Ans Pardons
HiRadMat User Experimental Area
TJ7
TNC
Status – WANF dismantling5 General dismantling
IEFC Workshop Mar. 22, 2011
Hot objects & high remnant radiation dose Remote handling tools
Cameras on renovated crane and in TNC Automatic hook for standard blocks Shielded fork lift Several custom-made hooks & lifting beams
Shielding during intervention & transport
Ans Pardons
Status - WANF dismantling6
Horn and support manually dismounted from TNC and sent to waste storage in ISR(*)
Collimator and support 80% remotely dismounted and sent to waste storage in ISR
Example 1: WANF Horn & collimator removal
IEFC Workshop Mar. 22, 2011Ans Pardons
(*) Intersecting Storage Rings
Status - WANF dismantling7 Example 2: T9 dismantling (transformation)
IEFC Workshop Mar. 22, 2011
T9 target station (installed 1993, 5 years of beam)
T9: transformation to HiRadMat beam dump:1. Remove target, all collimators & monitor2. Replace upstream collimator with new collimator3. Replace other items with TED(*)-type beam dump4. Close shielding and complete HRM beam dump
Ste
el u
pstre
am c
ollim
ator
ν-p
rodu
ctio
n ta
rget
Cop
per d
owns
tream
col
limat
or b
lock
s
Dow
nstre
am m
onito
r
Ans Pardons
(*) Target External Dump
8
Dose rate near target and upstream collimator
Items designed in 1993 for remote removal! Remote removal, transport to ISR in shielded containers
or on shielded trailers
Target & upstream collimator
Status - WANF dismantling
Dose rate (mSv/h) measured at contact with target container and cradles (12.01.11)
3.5 1657.5 15 25Upstream collimator
ν-production target
Downstreamcollimator
IEFC Workshop Mar. 22, 2011Ans Pardons
9
Dose rate in & near copper collimator blocks
Reminder: forbidden area if dose rate > 100mSv/h The collimator blocks’ geometry brings several challenges
Each block (2.7t) has hot outer surface Axis of 2 blocks is outside range of overhead crane Items not designed for remote handling!!!
4 threaded holes per block 1993: installed manually with forklift, lifting rings and straps
Downstream collimator blocks dismantling: Challenges
Status - WANF dismantling
60@5cm4301000
20@40cm
Dose rate (mSv/h) measured inside and near the collimator (12.01.11)
IEFC Workshop Mar. 22, 2011Ans Pardons
10 ALARA Level 3 committee
Status - WANF dismantling
Following > 100mSv/h dose rate measurement, the case of T9 dismantling was presented to the ALARA L3 committee
Results & consequences: Review took place of detailed dismantling procedure by CERN safety
specialists from outside the project (M. Tavlet & P. Bonnal) Detailed risk analysis established Decision taken to NOT remove the copper blocks out of TNC (yet)
Blocks with handling plates will be placed in custom-build containers in a 40cm thick iron sarcophagus downstream TNC
The evacuation of the blocks from TNC will be carefully planned by EN/MEF & DGS/RP and executed in the “near” future (e.g. shut-down 2013)
Green light from reviewers and hierarchy obtained to start T9 dismantling on 2/2. Dismantling work took ~10 days,
collective dose of ~1.2mSvIEFC Workshop Mar. 22, 2011Ans Pardons
11 Downstream collimator blocks dismantling: Solutions
Status –WANF dismantling
Lifting & shielding plates fixed manually on copper blocks Custom-made lifting beam takes 2 blocks at the time Shielding in place for all manual interventions Extensive tests on mock-up
Optimise tools Define camera positions for handling Training interveners
Minimise risk & dose personnel
IEFC Workshop Mar. 22, 2011Ans Pardons
12 T9 downstream collimator dismantling in pictures
Status –WANF dismantling
Lifting test before closing roof
Placing block in container
Separating blocks 21
Fixing plates on lower blocks
Moving upper blocks with fixed lifting plates
Blocks in temporary storage location
Sarcophagus withcontainers ready
IEFC Workshop Mar. 22, 2011Ans Pardons
Status - WANF Dismantling
S. Evrard - IEFC Feb.11,2011
Waste management13
• Radioactive waste is treated in several steps:1. Rough cleaning in WANF (specialized
company ENDEL Nucléaire)2. Removal from WANF TT61 TT43. In TT4: thorough decontamination and
disassembling4. Volume reduction in RP waste
workshop in building 5735. Convenient conditioning for long term
storage6. Long term storage in ISR
Volume reduction x 10
Contaminated objects: Adapted closed containers
Long term storage ISR
WANFTT4
ISR
573
BA7
Disposal path
Status - Primary beamline installation
IEFC Workshop Mar. 22, 2011
14 Installation progress of TT66 beamline
Equipment Status Comments
Magnets 25/25 installed
Vacuum system 88% installed 77% leak tested
Electrical feeds 95%
Cooling connections 85%
Power converters 7/13 installed Last one: End of March
Beam instrumentation & Control 15/17 installed BPKG, 1 BTV to install weeks 13/19
Machine interlocks almost ready Link to power converters not yet commissioned
Survey 90% Remaining work during week 13 or short accesses
Summary table status mid March 2011 (upstream line TT60/TI2 is 100% installed)Ans Pardons
Ans Pardons
Planning 2011
IEFC Workshop Mar. 22, 2011
15 Installation & commissioning
Shutdown works: dismount air ducts, dismount horn, collimators & T9 target,
install beamline magnets, install general services, ...)
Short accesses (linked to LHC injection
activity): install doors, beam instr., vacuum,
align beam elements, ... • T9 transformed (no
TED)• Beam line installed
& elements connected (incl. beam instrumentation)
• TED dump core and downstream muon dumps installed
• Ventilation operational (challenge!)
• Beam line under beam vacuum
• Exp area in TNC installed & operational (cabling, services, ...)
• Surface preparation lab & control room ready
Ans Pardons
Planning 2011
IEFC Workshop Mar. 22, 2011
16 Installation & commissioning• Installation & handling
equipment & procedures ready, tested & approved
• Downstream cool-down area ready
Parameter ValueExperiments in 2011 ~3Maximum intensity per experiment
1×1015 protons<30 full intensity pulses
Waiting time after experiment for de-installation
≥ 2 weeks
Access during experiment (except urgent interventions)
no
Control of experiment and data taking
remote
Maximum intensity per year <<1×1016 protons
Commissioning plans
IEFC Workshop Mar. 22, 2011
17
Hardware commissioning on-going: powering tests, etc. Dry runs to check the overall beam equipment functionality
without beam (week 14):Control applications, interlock, magnets/power converters, beam instrumentation.
Commissioning of the facility with beam (weeks 20 and 21): Tests with probe beams:
Aperture checks, beam parameter checks, steering, beam size / focal point position adjustment, position / intensity stability, BI (calibration, etc.), controls, logging, interlocking tests, etc.
Some high intensity shots to check the consistency with the nominal beam intensity.
Ans Pardons
Readiness 2011
IEFC Workshop Mar. 22, 2011
18
Dismantling 99% finished Beamline 90% installed, remaining part planned for week 13 Beam dump will be completed in week 19 Ventilation system will be ready for first user. Installation before
week 20 unsure. Discussion on-going to allow limited amount of test pulses/protons without ventilation.
Experimental area test tables designed & tested, production under way, will be ready for first user
Cabling for test tables remains to be done during the next technical stops (weeks 13, 19&25). Installation sequence will be done such that the needs for 2011 will be met before installation first user.
Remaining work
Ans Pardons
Irradiation area layout
IEFC Workshop Mar. 22, 2011
19
3 possible focal points for beam 3 positions for test stand Geometry & services available to users on test stand:
Volume ~1.5x0.7x0.7 m³, weight up to 4 tons Cooling circuit, electricity, neutral gas available Signal connectors (e.g. for camera, motorization, beam instrumentation,
vibration measurement, … ) ~25m upstream: Patch panel to test signals/services before beam ~100m downstream: cool-down storage area for test objects
Layout & conceptRadiation Measurement
Beam Loss MonitorsBeam Focal Points:
Ans Pardons
Irradiation area layout
IEFC Workshop Mar. 22, 2011
20
Test stand : base table in TNC and mobile table with test object (remote handling) comes from surface
Interface between tables : remote / automatic plug-in connectors (water, power, signal)
Check user system (motors, camera, laser, ...) before beam in TJ7, during beam only from surface control room
Design
Large object, e.g.LHC Collimator
Small object, e.g. material sample
Ans Pardons
Operation
IEFC Workshop Mar. 22, 2011
21
Guidelines (up to) 10 users/year, (up to) 1015 protons/user This quota includes several pilot pulses during setup
Pilot pulses can be done in an almost transparent way to present operations
High-intensity pulses will be done in dedicated HiRadMat cycles impact on other SPS physics users
User selection panel will: (panel with experts from: radiation protection, safety, beam, physics goals, engineering, PS&SPS operation as well as external experts) Review the beam requests, establish criteria for acceptance/rejection
(e.g. scientific value, beam feasibility, safety concerns, impact to the facility,…) Establish priority list of experiments with respect to the available beam time Distribute beam time and schedule experiments
Ans Pardons
Operation22 Operating procedure: first ideas
A HiRadMat “brochure” will show what HiRadMat offers in services, signal, alignment, control room, observation equipment, beam type, ...
Approval of user’s proposal by user selection panel Preparation of interface parts (windows, containers, observation equipment,
motorised tables etc.) in collaboration with area engineers & designers Arrival at CERN of users ~2 weeks before beam: mounting test object on
mobile table, alignment and test connectors in surface lab and control room During the week before beam (LHC technical stop): remote installation,
remote test of signals, motorization, observation equipment, etc. Beam start. Observation and data taking from control room on surface. After beam tests: remote moving of mobile test table to cool-down area Later, possibly only during end-of-year shut-down: bringing test object back
to surface (RP lab)
IEFC Workshop Mar. 22, 2011Ans Pardons
A detailed and official “operating procedure” document will be written & released by the project team in due time
Operation
IEFC Workshop Mar. 22, 2011
23 Activation dose rate after 1 user test – Fluka calculation results
After 1 hour: <50000µSv/h(*)avg. at 40cm, detailed results available
After 1 week: <5000µSv/h(*)avg. at 40cm, detailed results available
27070 1000 40002051.40.4 µSv/h15E3 50E3
Assumption: Short SPS cycle, 1.98E12 p/s for 504 s (1e15 protons) The beam hits the carbon jaw of a typical collimator
Activation dose near(*) test object after 1 hour/1 week cool-down
Beam dumpTest object To TJ7
Ans Pardons
Operation
IEFC Workshop Mar. 22, 2011
24
Assumption: 1016 protons over 1 year on a 15cm long copper test object, followed by removal of test object
Background dose rate in TNC after 1 day / 1 month
Background dose rate after a full year of operation – test object removed
After 1 day: <100µSv/h
After 1 month: <25µSv/h
205 50 10020.60.20.1 µSv/h
During annual shut-down: possible to intervene near test stands for repair or upgrade
Ans Pardons
Summary
IEFC Workshop Mar. 22, 2011
25
Work done in 2010 and early 2011: WANF dismounted Primary beamline installed
Readiness for 2011: Remaining works for week 13 & 19 well defined,
prepared & planned Ready for dry run week 14, commissioning week 20 Ready for scheduled users from week 26 on
Planning for 2011: aim for 3 users w26, w32, w39 “Operating procedure” document under way
95%
Ans Pardons
HiRadMat knocking at the door
IEFC Workshop Mar. 22, 2011
26
Thank you for listening – Any questions?
Ans Pardons
Extra: Introduction
IEFC Workshop Mar. 22, 2011
27
Protons Heavy ions
Beam parametersBeam extracted from SPS (450GeV/c): provides 1011 protons per bunch, 300 bunches per pulse, 100 pulses per user and beam spot 0.5-2mm² at impact.
Extra: Dismantling - transformation
IEFC Workshop Mar. 22, 2011
28 TED Geometry & materials
Extra: Dismantling
IEFC Workshop Mar. 22, 2011
29
Design new equipment with remote handling & waste disposal in mind Collaboration with RP during design Write future dismantling procedures now Update technical drawings “as-built”
Largest dismantling dose from cables, cleaning, etc. Use specialised company & invest in tools Install new cables, trays, lights etc. with dismantling in
mind
lessons learnt from dismantling
Extra: Dismantling
IEFC Workshop Mar. 22, 2011
30
Lesson learnt: also install services with easy future dismantling in mind! (largest doses are not taken on the most complex/radioactive objects)
origin of dose during dismantling WANF
Add dismantling T9 in Jan. 2011: ~1200 µSv)
31 T1 removal
September 2009 January 2011
February 2011
IEFC Workshop Mar. 22, 2011
Example: Dismantling T1 target station & MTR magnets31
Extra: Dismantling
Extra: Irradiation area
IEFC Workshop Mar. 22, 2011
32
Repeatability test of alignment & automatic connectors successful design approved
In 2011: Need 1 base table and 3 mobile tables Installation base table planned week 19, mobile tables
under construction, ready for first user
Prototypes & Tests
Signals connector
Base table with alignment plug-ins
Alignment plug-ins Waterconnector
Ans Pardons
Extra: Operation
IEFC Workshop Mar. 22, 2011
33 Activation dose rate after 1 user test
Ans Pardons
Extra: Operation
IEFC Workshop Mar. 22, 2011
34 Users
Parameter ValueExperiments in 2011 ~3Maximum intensity per experiment
1×1015 protons<30 full intensity pulses
Waiting time after experiment for de-installation
≥ 2 weeks
Access during experiment (except urgent interventions)
no
Control of experiment and data taking
remote
Maximum intensity per year <<1×1016 protons
Warning! Non-contractual test object
images. Pictures may differ from actual
product(a lot).
• First: short cool-down period before dismounting
• Then: taken out to surface or moved to underground downstream cool-down area
Extra: Operation35 Measures because of radiation dose rates
Alignment at surface on pre-aligned base table Remote handling of test stand, crane operator in TJ7 Access to TJ7 before beam, rack for tests of signals,
services, motorisation, observation equipment No access to TNC (exception only with RP approval) Cool-down area for equipment downstream TNC Re-use of mobile tables only if negligible dose rate
TJ7TNC
Bef
ore
beam
Afte
r bea
mE
nd-o
f-yea
r sh
ut-d
own Possible (RP approval) to
intervene in TNC for “upgrade” of user’s services, limited repair works, ...
Ans Pardons
Extra: Operation
IEFC Workshop Mar. 22, 2011
36 Future users
Future users already interested in using HiRadMat Collimator phase 2 (prototyping work) LHC beam dump entrance window robustness Studies of protection devices and windows (TE-ABT) Vacuum chamber coatings for electron cloud mitigation R2E teams - irradiation facility – radiation damage BLM developments LARP Rotatable Collimator Robustness Test (SLAC) Radiation tolerance tests (EN-STI) ISOLDE – Target and Ion Source Development
Extra beamline
IEFC Workshop Mar. 22, 2011
37
Christoph Hessler
Beam
25 m
Experimental area
TI 2
TT60
TT66
Christoph Hessler38
22.03.2011
Beam Line Status (March 2011)Beam
25 m
Experimental area
TI 2
TT60
TT66
TT60 upstream chicane:
• All magnets installed and aligned.• Vacuum system installed and under
vacuum.• TT60 back in operation.
Christoph Hessler39
22.03.2011
Beam Line Status (March 2011)Beam
25 m
Experimental area
TI 2
TT60
TT66
TI 2:• TBSE and additional BPMs installed.• Re-installation completed and under vacuum.• TI 2 back in operation.
Christoph Hessler40
22.03.2011
Beam Line Status (March 2011)Beam
25 m
Experimental area
TI 2
TT60
TT66TT66 in TCC6:
Installation completed in TCC6:• Magnets/BI/vacuum system installed. • Cables pulled and connected.• Vacuum: Leak tested up to
QTLF.660300 at the end of TCC6.
Christoph Hessler41
22.03.2011
Beam Line Status (March 2011)Beam
25 m
Experimental area
TI 2
TT60
TT66
Christoph Hessler42
22.03.2011
Beam Line Status (March 2011)Beam
25 m
Experimental area
TI 2
TT60
TT66
TT66 in TJ7/TNC:• All magnets and most BI installed
(only last BTV and BPKG missing).• Alignment work
almost completed.• Installation of
vacuum system on-going.
• To be under vacuum at end of next TS.