seattle.gov home - th avenue swmarch 2015 design alternatives review meetings june 2015 final...

46
35 th Avenue SW Road Safety Corridor Design Alternative Review Meetings Project Manager Jim Curtin March 10 and 12, 2015

Upload: others

Post on 23-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

35th Avenue SW

Road Safety Corridor

Design Alternative Review Meetings

Project Manager Jim Curtin

March 10 and 12, 2015

Page 2: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Our mission, vision, and core values

Committed to 5 core values to create a city that is:

• Safe

• Interconnected

• Affordable

• Vibrant

• Innovative

Mission: deliver a high-quality

transportation system for Seattle

Vision: connected people,

places, and products

Page 3: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

• Meeting purpose

• Project background

• Design process and

alternatives

• General Q & A

• Feedback session

3

Presentation overview

Page 4: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Background

• Safety improvements

requested by local

community on several

occasions

• Issue Identification

Meetings, October

2014

4

Page 5: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

• Reduce speeds

• Reduce collisions and

injuries

• Improve conditions for

vulnerable users

• Maintain acceptable

vehicular travel times

Project goals

5

Make 35th Avenue SW safer for everyone

Page 6: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Vision Zero Seattle’s plan to eliminate

traffic deaths and

serious injuries

• Street designs that

prioritize safety

• Public education and

engagement

• Targeted enforcement

patrols

6

www.seattle.gov/visionzero

Page 7: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Project area

7

35th Avenue SW between

SW Avalon Way and SW Roxbury Street

Page 8: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Current street design

35th Avenue SW • Principal arterial

• 4 to 5 lane street

• 55 feet wide

• Served by multiple transit routes

• Emergency response route

8

Page 9: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Volumes

0

5000

10000

15000

20000

25000

30000

SW Alaska St SW Brandon St SW Morgan St SW Myrtle St SW Holden St SW Thistle St SW Barton St SW Roxbury St

• 16,500 AWDT at Roxbury; 24,600 AWDT at Alaska

• Significant pedestrian use

• Transit: 21, 21X, Rapid Ride C Line

Page 10: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Along the corridor

• 488 parcels • 73% single family residential

(359)

• 11% apartment, condo, townhouse (55)

• 10% commercial/industrial (48)

• 4 churches or religious service centers

• 3 schools within two blocks

• 2 libraries, parks and community centers

• 2 daycare centers

• Retirement/nursing homes, medical services

10

Page 11: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Recent speed studies

Posted speed limit 35 mph

• 38.5 mph at SW Brandon St

• 40.9 mph at SW Willow St

• 36.5 at SW Roxbury St

11

Page 12: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Why speed matters

12

Drivers’ field of vision

15 mph

Drivers’ field of vision

30 mph – 40 mph

Page 13: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Why speed matters

13

Note that the chance of injury is nearly 100 percent when

pedestrians or people on bicycles are involved in a collision

Page 14: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Collision data

Last 3 plus years

• 294 total collisions

• 128 injuries

• 2 fatalities

Last 10 years

• 1065 total collisions

• 412 injuries

• 5 fatalities

14

Page 15: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Collision data Pedestrian and bicycle collisions

last 3 plus years

• 15 pedestrian-vehicle

• 1 bicycle-vehicle

Pedestrian and bicycle collisions

last 10 years

• 40 pedestrian-vehicle

• 8 bicycle-vehicle

• 4 of 5 fatalities were pedestrians or bicyclists

15

Page 16: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Collision data

16

15

1

49

33

59

31 26

20

0

10

20

30

40

50

60

70

Collision Types

Page 17: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Behavioral issues and enforcement

• Distraction top

contributing cause of

crashes on 35th

• Other issues

– Speeding

– Impairment

– Failure to grant ROW

17

Page 18: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Design process

18

Design options developed to:

• Balance the need to move people and goods with the

function of the nearby land uses

• Reduce collisions

Performance monitoring

• Collect baseline data and update traffic data regularly on

35th and nearby streets

Page 19: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Design process

19

Enforcement • Grant funds secured for

extra patrols

• Data-driven deployment

• Pedestrian safety emphasis

Page 20: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Design process

20

Modeling

• Synchro 8 and

SimTraffic 8

• Full report and

traffic analysis at

Spring meeting

Page 21: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Implementation

• Summer 2015

through 2016

Design process

21

Page 22: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Lower speed limit

• 35 mph 30 mph

• New speed limit to be

implemented with other

roadway modifications

Design alternatives

22

Page 23: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Design alternatives

23

• Signal improvements

– Turn signals at some

locations

– Signal optimization

– Reflective materials for

most signals

• Lane line markers

(buttons) throughout the

corridor

Page 24: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Bicycle facilities

• Protected bicycle lanes

envisioned long-term for 35th

– 2014 Bicycle Master Plan

• Public comment suggested we

focus on other routes

• Neighborhood Greenway

study

• 2017 implementation

Design alternatives

24

Page 25: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Design alternative A

25

SW Roxbury St to SW Edmunds St

Rechannelization

• 4 lanes 3 lanes

• 2 general purpose lanes

• Center left turn lane

Page 26: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Design alternative A

26

Key features

• Reduces top collision types

• Lower vehicle speeds

• Better conditions for people walking

• Opportunities for new crossings

• Improved efficiency

• Easier turning movements

Limitations

• Initial modeling shows vehicle delays of

3 to 4 minutes (peak hours only)

• *Additional delays possible*

Page 27: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Design alternative B

27

SW Roxbury St to SW Raymond St

• Rechannelization

SW Raymond St to SW Edmunds St

• Peak hour parking restrictions

– Allows for one additional lane for

vehicular traffic

• AM – northbound

• PM - southbound

Page 28: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Design alternative B

28

Key features

• Maintains extra travel lane during

peak

• Same benefits as Alternative A south

of SW Raymond Street

• May consider extending/reducing

rechannelization extents

Limitations

• Initial modeling shows vehicle delays

of 3 minutes

(peak hours only)

• Partial pedestrian safety benefits

during peak hours

Page 29: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

• Improves efficiency

• Reduces vehicular speed

• Easier turns

• More space for parking

Design alternatives

29

Left turning vehicles

out of the

flow of traffic

Easier turning movements to and from 35th

More space for parking

Page 30: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Existing conditions:

35th between Henderson and Barton

Design alternatives

30

SW HENDERSON ST

35

TH A

VE S

W

Southwest

Library

7-11

Super

Deli Mart

Rapid Ride C Line must make

3 lane changes between

Roxbury and Barton

Route 21 must make

3 lane changes in

one block (350 feet)

Insufficient capacity

in turn pockets

Tony’s

Market

SW BARTON ST

Page 31: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Proposed: 35th between Henderson and Barton

• Improves efficiency

Design alternatives

31

SW HENDERSON ST

35

TH A

VE S

W

Southwest

Library

7-11

Route 21 makes 2 lane

changes in one block (350 feet)

between Henderson and Barton

Maximum capacity in turn pockets Tony’s

Market

SW BARTON ST

Rapid Ride C Line benefits

from this configuration

Page 32: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Existing conditions: 35th and Barton

• 20 total collisions

• 13 injuries

• C line and 21/21X transit stops

• Turn pocket capacity issues

Design alternatives

32

0

5

10

Other Angles Ped Left turn

Collision types

Page 33: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Proposed: 35th and Barton

• Reduces left turn collisions

• May reduce angle collisions

• Improves pedestrian conditions

Design alternatives

33

SW BARTON ST

35

TH A

VE S

W

Tony’s Market

7-11

Super

Deli Mart

Longer left turn pockets

• Easier movements for buses

New right turn pockets

• Possible bus and turn lanes

Buses pull out of the flow of traffic

Page 34: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Proposed: 35th and Holden

• Offset intersection

• Models show peak hour delays

with new channelization

• Reduces left turn collisions

– 7 crashes during study period

– 5 related to left turns

Design alternatives

34

SW HOLDEN ST

SW HOLDEN ST

35

TH A

VE S

W

New left turn pockets

New right turn pockets

• Possible bus and turn lanes

Page 35: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Proposed: 35th and Webster

• Reduces left turn collisions

– 9 collisions during study period

– 8 left turn crashes

• Reduces exposure for pedestrians

Design alternatives

35

SW WEBSTER ST

35

TH A

VE S

W

New left turn pockets

Fewer lanes of traffic to cross

Page 36: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

• Improves efficiency

• Provides more structured

roadway channelization

Design alternatives

36

SW MORGAN ST

35

TH A

VE S

W

Right turn pockets

Potential bus and turn lanes

Page 37: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Proposed: 35th and Juneau

• Reducing left turn collisions

• Reducing pedestrian exposure

Design alternative A

37

SW JUNEAU ST

35

TH A

VE S

W

Center turn lane

Fewer lanes of traffic to cross

Page 38: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Longer-term: 35th and Juneau

• Monitor left turn and angle crashes

• Potential crossing with turn

restrictions (design for discussion

only)

• Similar conditions at SW Graham St

Design alternative A

38

SW JUNEAU ST

35

TH A

VE S

W

0

2

4

6

Angles Rear end Left turn

Collision types

Page 39: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Proposed: 35th and Juneau

• Reduces left turn collisions

• Does not reduce the number of

lanes pedestrian must cross

• Crossing may require traffic signal

• May consider extending

rechannelization to Juneau

Design alternative B

39

SW JUNEAU ST

35

TH A

VE S

W

Center turn lane

Page 40: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Proposed: 35th and Dawson

• Entrance to Camp Long

• Long-standing community request

for crossing

• Reduces exposure for pedestrians

• Opportunity for new crossing

Design alternative A

40

Camp

Long

SW DAWSON ST

35

TH A

VE S

W

Page 41: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Longer-term: 35th and Dawson

• Low cost treatments

– Signs

– Pavement markings

– Flashing beacons

– Potential refuge island

Design alternative A

41

Camp

Long

SW DAWSON ST

35

TH A

VE S

W

Page 42: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Proposed: 35th and Dawson

• Peak hour parking restrictions

create a 3-lane roadway

• 3-lane configuration in effect for

4 hours on weekdays only

• Signal may be required for new

crossing

Design alternative B

42

Camp

Long

SW DAWSON ST

35

TH A

VE S

W

Page 43: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

North of Edmunds

• Volumes near or above 25,000 ADT

• Existing channelization to remain

• Signal optimization

Design alternatives

43

Page 44: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Design alternatives

44

Safety benefits of rechannelization

• Lower speeds, less severe crashes

• Less exposure for vulnerable users

• Reduction in crash frequency

• Easier turning movements

Street Collisions 85% speed 10+ mph

speeders

Volume

change

Nickerson St -23% -21% -94% -1%

Fauntleroy Way

SW

-31% -1% -13% +0.3%

NE 125th St -10% -8% -69% +4%

NE 75th St -50% -13% -76% to 90% +0.3%

Page 45: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Next steps

October 28

3:30 PM to 5 PM

Issue Identification Meeting 2

Southwest Library

November through

January

Outreach and conceptual

designs

March 2015 Design Alternatives Review

Meetings

June 2015 Final determination and

outreach meeting

Late Summer 2015 Implementation begins 45

Page 46: Seattle.gov Home - th Avenue SWMarch 2015 Design Alternatives Review Meetings June 2015 Final determination and outreach meeting Late Summer 2015 Implementation begins 45 Questions?

Questions?

[email protected] | (206) 684-8874

http://www.seattle.gov/transportation/35thSW.htm

http://www.seattle.gov/transportation