Hoobrook Link Phase 2-

Transport Assessment

Traffic Modelling Report

Prepared for Worcestershire County Council

September 2013

 Red Hill House 227 London Road 

Worcester, WR5 2JG GB 

+44 (0) 1905 361 361 +44 (0) 1905 361 362 

 

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] III

Contents Section  Page 

Acronyms and Abbreviations ...................................................................................................................... v 

  Introduction ............................................................................................................................... 1‐1 1.1  Introduction ........................................................................................................................... 1‐1 1.2  Report Structure .................................................................................................................... 1‐2 

  Assessment Methodology ........................................................................................................... 2‐1 2.1  Introduction ........................................................................................................................... 2‐1 2.2  Model Specification ............................................................................................................... 2‐2 2.3  Model Scenarios .................................................................................................................... 2‐2 2.4  Do‐Minimum Network ........................................................................................................... 2‐4 2.5  Do‐Something Network ......................................................................................................... 2‐5 2.6  Generalised Costs .................................................................................................................. 2‐5 2.7  Forecast Matrices .................................................................................................................. 2‐7 2.8  Variable Demand Model ........................................................................................................ 2‐8 

  Model Results ............................................................................................................................. 3‐1 3.1  Introduction ........................................................................................................................... 3‐1 3.2  Network Statistics .................................................................................................................. 3‐1 3.3  Link Flow ................................................................................................................................ 3‐2 3.4  Link Flow Differences ............................................................................................................. 3‐4 3.5  Junction Turn Flows and performance .................................................................................. 3‐7 

  Conclusions ................................................................................................................................ 4‐1 4.1  Conclusions ............................................................................................................................ 4‐1 

 

Tables 

Table 2‐1 Planning assumptions for Wyre Forest District ............................................................................... 2‐3 TABLE 2‐2 Development Trips .......................................................................................................................... 2‐7 TABLE 2‐3 Growth factors for LGV and HGV .................................................................................................... 2‐7 TABLE 2‐4 Reference Case Matrices Totals ...................................................................................................... 2‐8 TABLE 2‐5 Illustrative Parameter Values for Destination Choice..................................................................... 2‐8 TABLE 2‐6 Demand Supply Convergence Gap ................................................................................................. 2‐9 TABLE 3‐1 Network Summary Statistics Comparison‐ AM Peak Hour ............................................................. 3‐1 TABLE 3‐2 Network Summary Statistics Comparison‐ Avg. IP Hour ................................................................ 3‐2 TABLE 3‐3 Network Summary Statistics Comparison‐ PM Peak Hour ............................................................. 3‐2 TABLE 3‐4 Forecast traffic on HBL .................................................................................................................... 3‐3 TABLE 3‐5 Two‐ Way flow on A442 and A451 adjacent to HBL ‐ 2016 ............................................................ 3‐4 TABLE 3‐6 Two‐Way flow on A442 and A451 adjacent to HBL ‐ 2031 ............................................................. 3‐4 TABLE 3‐7 A442/HBL Junction Turn Flows (vehicles) ‐ 2016 DM and DS ......................................................... 3‐8 TABLE 3‐8 A442/HBL Junction Turn Flows (vehicles) ‐ 2031 DM and DS ......................................................... 3‐8 TABLE 3‐9 A451/HBL Junction Turn Flows (vehicles) ‐ 2016 DM and DS ......................................................... 3‐8 TABLE 3‐10 A451/HBL Junction Turn Flows (vehicles) ‐ 2031 DM and DS ....................................................... 3‐9 TABLE 3‐11 Performance of junctions (V/C ratio) around scheme ‐ 2016 DM and DS .................................... 3‐9 TABLE 3‐12 Performance of junctions (V/C ratio) around scheme ‐ 2031 DM and DS .................................. 3‐10 

CONTENTS, CONTINUED

 

Section  Page 

IV HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA]

Figures  FIGURE 1‐1 Proposed HBL Alignment ............................................................................................................... 1‐1 FIGURE 2‐1 Model Study Area .......................................................................................................................... 2‐1 FIGURE 2‐2 Sites for Committed Developments .............................................................................................. 2‐3 FIGURE 2‐3 DM network Changes .................................................................................................................... 2‐4 FIGURE 2‐4 Do‐Something Network Changes .................................................................................................. 2‐5 FIGURE 3‐1 2016AM ‐ Link Flows (DS) .............................................................................................................. 3‐3 FIGURE 3‐2 2016 AM‐ Link Flow Difference (DS‐DM) ...................................................................................... 3‐5 FIGURE 3‐3 2016PM ‐ Link Flow Difference (DS‐DM) ....................................................................................... 3‐5 FIGURE 3‐4 2031AM ‐ Link Flow Difference (DS‐DM) ...................................................................................... 3‐6 FIGURE 3‐5 2031PM ‐ Link Flow Difference (DS‐DM) ....................................................................................... 3‐7   

 

 

     

 

 

 

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] V

Acronyms and Abbreviations  

Avg.  Average 

Hrs  Hours 

DM  Do minimum 

DS  Do something 

HGV  Heavy goods vehicle 

Kms  Kilometres 

Kph  Kilometres per hour 

LGV  Light goods vehicle 

Min  Minute 

Pass‐hrs  Passenger hours 

Pass‐km  Passenger kilometres 

s  Seconds 

Sqm  Square metres 

Veh‐hrs  Vehicle hours 

Veh‐kms  Vehicle kilometres 

Vs  versus 

WCC  Worcestershire County Council 

WFDC  Wyre Forest District Council 

WFTM  Wyre Forest Transport Model    

 

 

SECTION 1 

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] 1-1

Introduction 1.1 Introduction CH2M Hill has been commissioned by Worcestershire County Council (WCC) to undertake a transport assessment of developing Phase 2 of the Hoobrook Link (HBL) Road in Kidderminster, Wyre Forest District.  The HBL aims to connect the A442 Worcester Road and A451 Stourport Road across the River Stour and through the former British Sugar site providing better connectivity to the employment centres in Kidderminster and Stourport. 

The HBL is proposed to be developed in two phases. The development of the 1st phase is part of the redevelopment of the British Sugar site into a mixed use development, accessed from A451 Stourport Road. Phase 2 of the HBL completes the link between A442 in the east and A451 in the west. The alignment of HBL is illustrated in FIGURE 1‐1.  

This report sets out the transport modelling assessments undertaken to appraise the development of HBL phase 2 (‘the scheme’) via use of the Wyre Forest Transport Model. 

FIGURE 1‐1  Proposed HBL Alignment 

 

 

 

SECTION 1 INTRODUCTION

1-2 HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA]

 

1.2 Report Structure This report is structured as follows: 

Chapter 2 describes the methodology adopted to assess the  scheme and modelling undertaken; 

Chapter 3 describes the results of the various models comparing the Do‐Something scenario with the Do‐Minimum scenario; and 

Chapter 4 draws conclusions on the results presented. 

SECTION 2 

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] 2-1

2 Assessment Methodology 2.1 Introduction The transport implications of building the HBL have been assessed using the Wyre Forest Transport Model (WFTM). The WFTM is a multi‐modal model comprising a highway assignment model, public transport model and a variable demand model. The WFTM model area is illustrated in FIGURE 2‐1. The WFTM has been developed using VISUM (version 12.52) and has been calibrated and validated in accordance with WebTAG guidelines.  This section of the report discusses the WFTM which was used to assess the impact of the scheme. 

FIGURE 2‐1  Model Study Area 

 

SECTION 2 ASSESSMENT METHODOLOGY

2-2 HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA]

2.2 Model Specification The highway and public transport models are validated to a 2011 base year and comprise an AM peak hour (08:00‐09:00) model, an average IP hour model and a PM peak hour (17:00‐18:00) model. The models were calibrated and validated to and meet the acceptability guidelines contained within WebTag and  DMRB.  Forecast models were developed for the opening year 2016 of the scheme and 2031, a design year period 15 years after the scheme opening year. These forecast models were used to assess the transport implications of HBL phase 2.  An incremental variable demand model was developed to predict the demand responses due to change in generalised costs without the scheme and with the scheme.  The variable demand model adopts a hierarchical model structure and incorporates trip frequency, mode choice, distribution choice and route choice with the least responsive (trip frequency) being at the top of the hierarchy.  The model forms used for these choices are multinomial or nested logit models.  These model forms have proved to be satisfactory for use to represent mode and destination choice in a number of previous important studies.  The models represent the attractiveness of competing mode and destination alternatives through a ‘utility’ (or generalised cost) measure.    For mode split an incremental logit model formulation was used which assessed the changes in costs by alternative modes across the time periods by purpose. So for example for commuting trips the assessment takes into account cost changes in the peak hours.  Similarly for distribution modelling a logit model formulation was used which assessed the change in generalised costs from each zone to all other zones and identified whether there are any changes in destination choice.  Again this was undertaken by purpose.  For school and commuting trips this process was doubly constrained as it reflects a defined number of attractions. For 'other' purposes the constraint was only applied at the origin end of the journey.  The trip frequency response represents the change in number of (typically short distance) trips due to change in travel costs. The WFTM models both highway and public transport trips but not active modes. As the choice between highway and public transport is realistically represented, the effect of trip frequency is likely to be negligible. WebTAG does not recommend any parameters for trip frequency and suggests this response would generally apply to Home‐based other trips.   The demand models were run iteratively until the output matrices satisfied WebTAG convergence criteria. These output matrices were then assigned to the forecast networks to assess the implications of HBL phase 2.  

2.3 Model Scenarios Two scenarios have been developed to assess the transport implications of the scheme, a Do‐Minimum (DM) and Do‐Something (DS) scenario. Currently the Wyre Forest District is required to accommodate new dwellings and employment as part of the overall strategy for Worcestershire as indicated in Table 2‐1. A number of sites have been identified in Kidderminster, Bewdley and Stourport and also some additional sites on Greenfield land.  

SECTION 2 ASSESSMENT METHODOLOGY

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] 2-3

TABLE 2‐1  Planning assumptions for Wyre Forest District 

Location  Residential  Employment 

Kidderminster  1840  19ha 

Stourport on Severn  1049  ‐ 

Bewdley & Rural areas  398  2ha 

Total  3287  21ha 

 

The DM scenario includes all committed developments identified in the Transport position statement for Wyre Forest District Council and the associated transport network improvements. The spread of committed developments are shown in FIGURE 2‐2 and as indicated in Table 2‐1 above are concentrated in Kidderminster and Stourport.   The DS scenario has the same extent of developments as in the DM scenario. Only network changes are considered in the DS scenario.  

FIGURE 2‐2  Sites for Committed Developments 

 

 

SECTION 2 ASSESSMENT METHODOLOGY

2-4 HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA]

2.4 Do-Minimum Network The Do‐Minimum network includes transport schemes identified as part of various committed developments after the base year (2011) conditions. The schemes are illustrated in FIGURE 2‐3 and include the following:  

Network changes on St.Marys Ringway, Blackwell street and Horse Fair lane as part of the Churchfields development; 

Network changes on Kidderminster Ringway, Bromsgrove Street and Prospect Hill around the proposed Eastern Gateway development; 

Parsons Chain Link Road in Stourport and its access junction; 

Resolution Way, Severn Road and Mitton Street in Stourport;  

HBL phase 1 in the British Sugar Site and its junction with A451 as a priority junction; and 

New signalised junctions at St. Marys Ringway/Blackwell street junction, Churchfields, The Ringway/Eastern Gateway Access Road and Mitton Road/Severn Road junction. 

 

FIGURE 2‐3  DM network Changes 

 

 

SECTION 2 ASSESSMENT METHODOLOGY

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] 2-5

2.5 Do-Something Network The Do‐Something network comprises the HBL phase 2 scheme and its associated network changes. The HBL on completion is proposed to be a single carriageway with its junction with A442 and with A451 signalised.  The speed limit of the HBL is assumed to be 40mph. The Do‐Something network is illustrated in FIGURE 2‐4.  FIGURE 2‐4  Do‐Something Network Changes 

  

2.6 Generalised Costs The calculations in the variable demand model are driven by changes in Generalised Costs (GCs).  Public Transport GCs are calculated for each purpose, differing only in respect of the value of time. They are derived as follows:  Cij(pt.p) = f.Dij/v(pt) + Iij + w.Wij + x.Xij + a.Aij  Where:  

Cij(pt.p) = generalised cost by public transport between i and j for purpose segment (p); f = fare per kilometre in pence; D = travel distance in km; v(pt) = value of time for segment p in pence per minute; 

SECTION 2 ASSESSMENT METHODOLOGY

2-6 HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA]

I = in‐vehicle time in min; w = wait time weight; W = wait time in min;   x = transfer penalty in min; X = number of transfers; a = access and egress time weight; and A = access and egress time in min. 

 Private vehicle GCs are calculated for each purpose, differing in respect of the value of time and the treatment of non‐fuel costs:  Cij(car.p) = a.Aij + Iij + (VOC.Dij +Pj)/v(p)   Where: 

Cij (car.p) = generalised cost by car between i and j, for segment p; a = access and egress time weight; and A = access and egress time in min. I = in‐vehicle time in min; VOC = Vehicle Operating Cost; D = highway distance in km; P = parking charge in pence (taken as half per trip); v(p) = value of time for segment p in pence per minute.  

The parameters for calculation of generalised costs are sourced from Transport Analysis Guidance (TAG) Unit 3.5.6.   The weights applied for walking, waiting are as follows: 

Walk = 2.0 

Wait = 2.0 

Non fuel costs are also derived using WebTAG values. These are only applied to Working time journeys in line with the guidance which states that drivers on non‐working time journeys (commuting and other journeys) do not perceive non‐fuel vehicle operating costs.  The travel times are taken from the public transport and highway assignments.  The changes in generalised cost that drive the calculations in the mode choice model are calculated as follows:  

Cijm(p) = (Cijm(p)’‐Cijm(p)), where: 

Cijm(p) = change in generalised cost for mode m for segment p; Cijm(p)’ = test cost for mode m for segment p; and Cijm(p) = base cost for mode m for segment p. 

 Forecast VOT and VOC are based on WebTAG values. Bus fares and parking charge increases are assumed to be in line with RPI and Rail fares are assumed to increase by RPI+1%. All forecasts costs are in 2011 prices.   

SECTION 2 ASSESSMENT METHODOLOGY

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] 2-7

2.7 Forecast Matrices Forecast year reference case matrices for 2016 and 2031 incorporate growth in background trips due to income and car ownership changes and trips attributed to committed developments in the model area, the totals constrained to TEMPRO at the Wyre Forest District level.   Growth in background trips were developed using 24‐hr PA growth factors from TEMPRO (v6.2) for car trips (driver and passenger) and bus trips split by journey purpose which were applied to the base year 24‐hr PA matrices. Growth in rail trips were based on factors derived from the Passenger Forecast Demand Handbook v5. The background forecast matrices were converted to peak hour OD matrices using generation and attraction factors.  As mentioned earlier, all committed developments identified in the Transport position statement for Wyre Forest District Council were made available to the CH2M Hill. Trips for committed developments were taken from various transport assessments where available and trip rates from the TRICS database applied for the rest. The development trips were distributed based on gravity model parameters developed for the base year model. The total car trips related to the various committed developments identified in the Transport Position statement including those at Churchfields, Eastern Gateway, Parsons Chain and British Sugar Phase 1 for the years 2016 and 2031 are given in TABLE 2‐2. 

 TABLE 2‐2  Development Trips 

Time Period  2016 2031

Arrivals Departures Arrivals Departures 

AM Peak Hr  815  976  967  1396 

Average IP hr  787  789  938  928 

PM  1065  1054  1306  1217 

24 Hr  9918  9954  11825  11874 

 

The forecast background matrices were combined with the distributed development trips to form the forecast year reference case matrices for various purposes and by modes and their totals constrained to TEMPRO forecasts.   Forecasts for LGV and HGV vehicles were taken from Road Transport Forecasts 2011, based on DfT’s National Transport Model (NTM) and growth factors derived for the model forecast years. The LGV and HGV forecast growth factors are given in TABLE 2‐3. The forecast matrices totals are given in TABLE 2‐4. 

 

TABLE 2‐3  Growth factors for LGV and HGV 

  Year Growth factors 

LGV 2016  1.13 

2031  1.65 

HGV 2016  1.07 

2031  1.34 

 

SECTION 2 ASSESSMENT METHODOLOGY

2-8 HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA]

TABLE 2‐4  Reference Case Matrices Totals 

User Class 2016  2031 

AM  IP  PM  AM  IP  PM 

Car_HBW  49338  12412  57507  54434  13828  62806 

Car_HEB  3786  2328  5656  4432  2552  6139 

Car_HBO  32944  53534  43511  39378  63932  51135 

Car_HED  14358  6422  6996  17238  7715  8170 

Car_NHB  5342  16360  6805  5808  17788  7398 

Car_NHO  32166  42248  30400  38576  50737  35761 

LGV  3165  1857  2164  4614  2707  3155 

HGV  729  726  445  905  902  553 

 

A similar approach was applied to forecast the public transport trip matrices. Only the non‐captive (car available) proportions for public transport users were used in the demand model. 

 

2.8 Variable Demand Model VISUM has a nested demand add‐in module that incorporates the variable demand modelling approach recommended in WebTAG 3.10.    Various tests were undertaken on the WebTAG recommended demand model parameter values to assess their suitability for the Wyre Forest Transport Model. Details of the tests are described in the WFTM Demand Model report. The recommended parameters values that satisfy the WebTAG criteria are minimum lambda values with cost damping applied at a 25km cut‐off.  The minimum parameter values outlined in WebTAG 3.10.3 for destination choice responses are shown in TABLE 2‐5. For the purpose of trip frequency, a minimal parameter value of 0.01 was applied as this is the least sensitive response. 

 

TABLE 2‐5  Illustrative Parameter Values for Destination Choice 

Mode  Trip Purpose  Minimum 

Car 

Home‐based work  0.054 

Home‐based employers business  0.038 

Home based others  0.074 

Non‐home‐based employers business  0.069 

Non‐home‐based others  0.073 

PT 

Home‐based work  0.023 

Home‐based employers business  0.030 

Home based others  0.033 

Non‐home‐based employers business  0.038 

Non‐home‐based others  0.032 

 

The demand model is an incremental model pivoting off the base year. Only the car and public transport matrices were run through the demand model. Freight demand forecasts were considered as fixed demand. 

SECTION 2 ASSESSMENT METHODOLOGY

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] 2-9

The matrices were input into the demand model developed and assigned separately to the DM and DS networks through an iterative loop till they satisfied the WebTAG convergence criteria. WebTAG recommends a demand‐supply convergence gap of at least 0.2%. The best convergence gap achieved for the various models are shown in TABLE 2‐6. The matrices from the iteration run that achieved the best convergence were finally assigned to the forecast network to obtain the final assignment results.  

TABLE 2‐6  Demand Supply Convergence Gap 

Best Convergence Gap (%)  Scenario  AM  IP  PM 

2016 DM  0.09  0.08  0.07 

DS  0.08  0.09  0.07 

2031 DM  0.11  0.07  0.11 

DS  0.11  0.05  0.11 

 

 

 

 

SECTION 3 

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] 3-1

3 Model Results 3.1 Introduction The forecast model assignments results provide an indication of the changes attributed to developing the Hoobrook link (DS option) between the A442 and A451 by comparing it the DM option. This chapter compares the various traffic attribute results between the DS and DM options.   

3.2 Network Statistics The network summary statistics for Wyre Forest district comparing the DM and DS options from the various models are given in TABLE 3‐1 to TABLE 3‐3. The tables provide the overall performance of trips made by public transport and private transport.   The tables show that public transport performance statistics such as passenger‐kms and passenger‐hrs exhibit insignificant change between DM and DS options in both peaks and scenarios.   The vehicle‐kms figures show that with the scheme in place, they increase by less than 1% in both peak hours.  In the DS option, the vehicle‐hrs spent on the network decrease by around 2% in the peak hours in 2016. In 2031 however, it decreases by around 2% in the PM peak hour only whilst marginally increasing by 1.3% in the AM peak. An interrogation of the model shows that with the scheme, the variable demand model results in redistribution of trips around Kidderminster town centre resulting in increased congestion around Crossley Retail Park and A451 Stourbridge Road due to redistribution of other purpose trips. These are in addition to the delays brought about by the introduction of signals on A451 and A442 at their junctions with the scheme. The average vehicle speeds increase in all DS scenarios except 2031AM due to reasons mentioned above.  

TABLE 3‐1  Network Summary Statistics Comparison‐ AM Peak Hour Wyre Forest Summary Statistics  AM 

2016 DM  2016 DS  % change  2031 DM  2031 DS  % change 

Public Transport 

Passengers Boarding  1265  1262  ‐0.2%  1215  1208  ‐0.5% 

Passengers Alighting  1090  1087  ‐0.2%  1018  1012  ‐0.6% 

Transfer Passengers  628  619  ‐1.4%  412  406  ‐1.4% 

Pass‐km  9227  9144  ‐0.9%  8224  8189  ‐0.4% 

Pass‐Hrs  259  257  ‐1.0%  231  231  ‐0.1% 

Avg. Travel dist (km)/pass  7  7  ‐0.7%  7  7  0.1% 

Avg. Travel time (min) /pass  12  12  ‐0.8%  11  11  0.4% 

Private Transport 

Veh‐Km  142979  143248  0.2%  167112  168079  0.6% 

Veh‐Hrs  3911  3840  ‐1.8%  5166  5230  1.3% 

Avg. Speed (kph)  37  37  2.0%  32  32  ‐0.7% 

Total delay time (Hrs)  12  12  ‐1.5%  16  16  2.0% 

 

SECTION 3 MODEL RESULTS

3-2 HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA]

TABLE 3‐2  Network Summary Statistics Comparison‐ Avg. IP Hour Wyre Forest Summary Statistics  IP 

2016 DM  2016 DS  % change  2031 DM  2031 DS  % change 

Public Transport 

Passengers Boarding  898  820  ‐8.7%  968  885  ‐8.6% 

Passengers Alighting  893  824  ‐7.7%  956  883  ‐7.6% 

Transfer Passengers  379  268  ‐29.2%  432  296  ‐31.5% 

Pass‐km  5218  4710  ‐9.7%  5591  5060  ‐9.5% 

Pass‐Hrs  169  150  ‐11.2%  184  166  ‐9.9% 

Avg. Travel dist (km)/pass  6  6  ‐1.1%  6  6  ‐1.0% 

Avg. Travel time (min) /pass  11  11  ‐2.7%  11  11  ‐1.4% 

Private Transport 

Veh‐Km  117283  118201  0.8%  139919  135070  ‐3.5% 

Veh‐Hrs  2865  2919  1.9%  3821  3766  ‐1.4% 

Avg. Speed (kph)  41  40  ‐1.1%  37  36  ‐2.1% 

Total delay time (Hrs)  8  8  0.4%  11  11  ‐3.4% 

 TABLE 3‐3  Network Summary Statistics Comparison‐ PM Peak Hour Wyre Forest Summary Statistics  PM 

2016 DM  2016 DS  % change  2031 DM  2031 DS  % change 

Public Transport 

Passengers Boarding  986  987  0.1%  1050  1057  0.6% 

Passengers Alighting  1100  1101  0.1%  1152  1163  1.0% 

Transfer Passengers  329  330  0.4%  402  392  ‐2.4% 

Pass‐km  6875  6868  ‐0.1%  7582  7629  0.6% 

Pass‐Hrs  193  194  0.6%  224  228  1.8% 

Avg. Travel dist (km)/pass  7  7  ‐0.2%  7  7  0.0% 

Avg. Travel time (min) /pass  12  12  0.5%  13  13  1.1% 

Private Transport 

Veh‐Km  147897  149204  0.9%  163643  164814  0.7% 

Veh‐Hrs  4329  4230  ‐2.3%  5647  5551  ‐1.7% 

Avg. Speed (kph)  34  35  3.2%  29  30  2.5% 

Total delay time (Hrs)  11  11  0.1%  16  16  1.2% 

  

3.3 Link Flow Link flow plots and link flow difference plots between the DS and DM options were generated for all three time model time periods and the two forecast years. A typical link flow diagram is illustrated in FIGURE 3‐1. 

The two‐way flow on the Hoobrook link in the opening year 2016 is forecast to be over 900 vehicles in the AM peak hour and over 800 vehicles in the PM peak hour. The Annual Average Daily Traffic (AADT) on the link is forecast to be 10500 vehicles in the opening year.  The forecast AADT on HBL for 2031 is expected to be around 12600 vehicles per day. The forecast traffic for the peak hours are given in TABLE 3‐4. 

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] 3-3

FIGURE 3‐1  2016AM ‐ Link Flows (DS) 

 

  

TABLE 3‐4  Forecast traffic on HBL 

Hoobrook Link 2016  2031 

LV  HV  Total  LV  HV  Total 

AM Peak Hour  1034  6  1040  1168  11  1179 

IP Hour  703  6  709  894  10  904 

PM Peak Hour  888  3  891  982  5  987 

 TABLE 3‐5 and TABLE 3‐6 show the peak hour two‐way flows (all vehicles) on links adjacent to the HBL in 2016 and 2031 under both the DM and DS scenarios.  The DS figures in the table are colour coded with green indicating a flow reduction and red a flow increase when compared to the DM flows. The tables show that under the DS scenario, in all time periods and forecast years, flow on the A451 south of HBL as well as on the A442 south of HBL increases whilst they reduce on other arms adjacent to HBL.      

SECTION 3 MODEL RESULTS

3-4 HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA]

TABLE 3‐5  Two‐ Way flow on A442 and A451 adjacent to HBL ‐ 2016 

2‐way Total Flow 2016 DM  2016 DS 

AM  IP  PM  AM  IP  PM 

A451‐North of HBL  2164  1905  2206  1956  1757  1979 

A451‐South of HBL  2188  1904  2233  2484  2078  2501 

A442‐North of HBL  2127  1897  2148  1692  1474  1911 

A442‐South of HBL  2199  1945  2147  2353  1729  2373 

  

TABLE 3‐6  Two‐Way flow on A442 and A451 adjacent to HBL ‐ 2031 

2‐way Total Flow 2031 DM  2031 DS 

AM  IP  PM  AM  IP  PM 

A451‐North of HBL  2330  2047  2261  1897  1961  2010 

A451‐South of HBL  2379  2052  2308  2473  2305  2492 

A442‐North of HBL  2393  2266  2192  1874  1691  2050 

A442‐South of HBL  2468  2321  2205  2643  2126  2582 

  

3.4 Link Flow Differences Flow difference plots between the DS and DM scenarios for 2016 peak hours are given in FIGURE 3‐2 and FIGURE 3‐3. The figures show with the scheme in place, traffic reassigns itself to access the employment centres along the A451 between Kidderminster and Stourport.  The scheme helps reduce traffic flow on the A442 Worcester Road, A451 section between The Ringway junction and HBL junction, Wilden Lane and in Stourport town centre. Traffic flow however increases on the A451 between Stourport town centre and HBL junction. The patterns are similar in other time periods as well as in 2031 forecasts.  

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] 3-5

FIGURE 3‐2  2016 AM‐ Link Flow Difference (DS‐DM) 

 FIGURE 3‐3  2016PM ‐ Link Flow Difference (DS‐DM) 

 

SECTION 3 MODEL RESULTS

3-6 HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA]

Other links expected to be affected due to traffic reassignment are the Spennells Valley Road in the AM peak hour and A449 Chester Road South in the PM peak hour. The peak hour link flow difference plots between DS and DM for 2031 are shown in FIGURE 3‐4 and FIGURE 3‐5.   As is expected, the scale of impacts are more pronounced in 2016 than 2031 as the increase in demand during the intervening period results in the network capacity being well utilised. 

 FIGURE 3‐4  2031AM ‐ Link Flow Difference (DS‐DM) 

  

 

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] 3-7

FIGURE 3‐5  2031PM ‐ Link Flow Difference (DS‐DM) 

 

  

3.5 Junction Turn Flows and performance The HBL phase 2 scheme introduces a new link between the A442 and A451. It introduces two new signalised junctions to the network, one each on the A442 and A451. These junctions in the DM scenario operate as priority junctions serving the Hoobrook industrial estate along the A442 and British Sugar Site along the A451.   The turn flows at these junctions for 2016 and 2031 under both the DM and DS scenarios are given in TABLE 3‐7 to TABLE 3‐10.  The tables show that under the DS option, major movements at the junction are between the A442 arms accounting for around 60% of the total junction volume. This is followed by movements between A442 south and HBL that account for 27‐34% of the total junction volume. The A442 north‐ HBL movements only account for 10% of the total junction volume. The turning proportions are very similar in both 2016 and 2031. This shows that HBL attracts trips primarily from south of Kidderminster.      

SECTION 3 MODEL RESULTS

3-8 HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA]

 

TABLE 3‐7  A442/HBL Junction Turn Flows (vehicles) ‐ 2016 DM and DS 

Turning Movement 

2016 

DM  DS 

AM  IP  PM  AM  IP  PM 

A442(N)‐HBL  8  8  6  83  105  103 

A442(N)‐A442(S)  1042  862  932  805  651  827 

A442(S)‐A442(N)  1017  949  1109  667  563  827 

A442(S)‐HBL  132  125  94  449  261  357 

HBL‐A442(S)  10  9  11  432  271  362 

HBL‐A442(N)  53  65  91  137  164  154 

 

TABLE 3‐8  A442/HBL Junction Turn Flows (vehicles) ‐ 2031 DM and DS 

Turning Movement 

2031 

DM  DS 

AM  IP  PM  AM  IP  PM 

A442(N)‐HBL  6  5  5  88  106  91 

A442(N)‐A442(S)  1175  1018  948  895  754  886 

A442(S)‐A442(N)  1136  1154  1140  733  651  889 

A442(S)‐HBL  143  138  91  558  342  429 

HBL‐A442(S)  13  11  14  457  378  378 

HBL‐A442(N)  66  76  102  158  178  184 

 

The tables show that at the A451/HBL junction, under the DS option, major movements at the junction are between the A451 arms accounting for around 70% of the total junction volume. This is followed by movements between A451 south and HBL that account for around 25% of the total junction volume. The A451 north‐ HBL movements only account for 3%‐6%% of the total junction volume. The turning proportions are very similar in both 2016 and 2031. This again shows that HBL attracts trips primarily from south of Kidderminster  The interaction between A451 north – HBL are significantly lower than HBL‐A451 north due to the presence of a secondary access to the British Sugar site that draws most of the demand for left turning movements from A451 north.  

TABLE 3‐9  A451/HBL Junction Turn Flows (vehicles) ‐ 2016 DM and DS 

Turning Movement 

2016 

DM  DS 

AM  IP  PM  AM  IP  PM 

A451(N)‐A451(S)  1115  975  1024  900  803  944 

A451(N)‐HBL  15  21  24  49  0  8 

HBL‐A451(N)  0  0  0  103  69  79 

HBL‐A451(S)  14  9  13  363  215  335 

A451(S)‐HBL  25  11  38  334  184  302 

A451(S)‐A451(N)  1035  909  1158  904  878  948 

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] 3-9

 

TABLE 3‐10  A451/HBL Junction Turn Flows (vehicles) ‐ 2031 DM and DS 

Turning Movement 

2031 

DM  DS 

AM  IP  PM  AM  IP  PM 

A451(N)‐A451(S)  1168  997  1053  889  869  924 

A451(N)‐HBL  16  21  24  8  34  68 

HBL‐A451(N)  0  0  0  111  94  84 

HBL‐A451(S)  15  11  12  381  273  350 

A451(S)‐HBL  50  15  49  341  199  313 

A451(S)‐A451(N)  1145  1029  1193  890  964  934 

 Junction performances were assessed using the Intersection Capacity Analysis (ICA) tool within Visum. The ICA adopts the US Highway Capacity Manual (HCM) 2010 methodology for junction performance assessment. For roundabouts, Visum offers both the HCM approach and TRL/Kimberly approach widely used in the UK. The latter approach was used for assessing roundabouts in the model.  The Volume/Capacity (V/C) ratios as used in HCM or Ratio of Flow to Capacity (RFC) (UK nomenclature) for various junctions around the scheme are given in TABLE 3‐11and TABLE 3‐12. For signalised junctions, the table provides the overall junction V/C ratio output by Visum whilst for roundabouts and priority junctions; they provide the maximum V/C for any junction approach arm. For signalised junctions, the approach arms V/C ratio could differ from the overall junction V/C ratio and is dependent on the signal settings.  UK standards suggest priority junctions and roundabouts operate satisfactorily at RFC levels below 0.85 whilst signalised junctions operate satisfactorily at RFC levels below 0.90. When these are exceeded, random delays increase and flow breakdown can occur.   The tables show that the introduction of signals at the A442/HBL and A451/HBL junctions will result in delays to all movements but the overall performance of the junctions are well within the  0.9 threshold. For the remaining junctions, introduction of the scheme improves the junction performance when compared with the DM scenario.  

 

TABLE 3‐11  Performance of junctions (V/C ratio) around scheme ‐ 2016 DM and DS 

Name of Junction  Type of Junction 

2016 

DM  DS 

AM  IP  PM  AM  IP  PM 

A451/HBL Priority (DM)/ Signalised (DS) 

0.06  0.03  0.05  0.55  0.58  0.55 

A442/HBL Priority (DM)/ Signalised (DS) 

0.06  0.07  0.1  0.47  0.51  0.43 

A451/A4535Sutton Rd  Signalised  0.76  0.65  0.72  0.64  0.54  0.6 

Ringway Junction  Roundabout  0.77  0.65  0.77  0.63  0.55  0.69 

A442 /A449/Wilden Lane  Roundabout  0.71  0.53  0.85  0.71  0.49  0.69 

A451 Stourport Rd/B4549 Sutton Park Rd 

Priority  0.23  0.19  0.23  0.23  0.17  0.23 

SECTION 3 MODEL RESULTS

3-10 HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA]

Wilden lane/B4193 Hartlebury Rd  Priority  0.04  0.32  0.02  0.04  0.28  0.02 

A449/A4025 Stourport Road  Roundabout  0.48  0.39  0.56  0.48  0.38  0.56 

 

 TABLE 3‐12  Performance of junctions (V/C ratio) around scheme ‐ 2031 DM and DS 

Name of Junction  Type of Junction 

2031 

DM  DS 

AM  IP  PM  AM  IP  PM 

A451/HBL Priority (DM)/ Signalised (DS) 

0.07  0.04  0.05  0.55  0.67  0.55 

A442/HBL Priority (DM)/ Signalised (DS) 

0.07  0.08  0.11  0.51  0.63  0.46 

A451/A4535Sutton Rd  Signalised  0.8  0.72  0.74  0.64  0.6  0.63 

Ringway Junction  Roundabout  0.85  0.78  0.81  0.69  0.65  0.75 

A442 /A449/Wilden Lane  Roundabout  0.93  0.84  0.99  0.87  0.66  0.93 

A451 Stourport Rd/B4549 Sutton Park Rd 

Priority  0.23  0.21  0.23  0.26  0.20  0.24 

Wilden lane/B4193 Hartlebury Rd  Priority  0.05  0.41  0.02  0.05  0.37  0.02 

A449/A4025 Stourport Road  Roundabout  0.57  0.46  0.61  0.57  0.45  0.61 

 The above tables demonstrate that the scheme will improve the performance of most junctions around it. However, there is a possibility that due to the increase in traffic on both A442 and A451 south of HBL, junctions along them could experience deteriorating performance. The tables above include the A442/A449/Wilden Lane junction (south of the A442/HBL junction) that shows an improvement in performance primarily due to traffic re‐routeing away from Wilden Lane to HBL. Junctions on the A451 south of HBL leading to the A451/B4195 junction could experience additional delays as a result of increasing traffic.         

HBL-PH2TA .DOCX/[WORCS-FS-01\\CTWALY WCC FRAMEWORK 2011\500 WYRE FOREST TM SPECIFICATION AND BUILDING\62.0 REPORTS\HBL-PH2TA] 4-1

4 Conclusions 4.1 Conclusions This report describes the traffic modelling work undertaken to assess the impact of the proposed Hoobrook link phase 2 scheme that will provide a direct connection between the employment centres along the A442 and A451.  The modelling adopts a variable demand approach using the Wyre Forest Transport Model developed using Visum 12.5. Models were developed for the opening year 2016 and a design year 2031 for three time periods and two scenarios, a Do‐Minimum and Do‐Something scenario. The DM scenario includes all committed developments and those identified in the Transport Position Statement of the Wyre Forest District Council. The DS scenario includes the proposed scheme and its associated improvements. The modelling undertaken shows that the demand‐supply loops converge quite well satisfying WebTAG requirements.  The models show that the scheme will benefit the A442 Worcester Road, A451 section between The Ringway junction and HBL junction, Wilden Lane and in Stourport town centre. Junctions along these routes too will benefit from the scheme, bringing about travel time savings in most scenarios as a result of the scheme.