Data-link Services (DLS) implementation
2017 CEF Transport Calls for proposals
Brussels, 17th November 2017
EC Workshop on DLS
Copyright SESAR Deployment Manager 2
Agenda
➢ Overview
➢ SDM activities for Path I and Path II
➢ Path I - implementation status
➢ Path II - main findings
➢ 2017 CEF Transport Calls for Proposals
➢ SDM working in progress – main items
From ELSA study to DLS Recovery Plan
Implementation of a Transitional Solution (Model B or Model C with Multi-
frequency (MF) by 2018 to meet the EU (IR) 2015/310
Implementation of Model D as the target solution by 2022, through the
implementation of ELSA recommendations to grant the required performance
needed to achieve full AF6 implementation
ELSA study: “VDL Mode 2 Measurement, Analysis
and Simulation Campaign”
Recommends WHAT technical
needs to be implemented in Europe
Urges to establish a “pan-European
air/ground datalink implementing
function” to organize the activities
DLS Recovery Plan developed by SDM and
approved by EC
Defines the activities to be
undertaken to achieve the full
DLS implementation in Europe,
avoiding inappropriate
investments
Based on the outcomes of ELSA
study, it is a realistic recovery
plan to bridge between current
status and PCP/AF6
From DLS Recovery Plan to DLS Cluster
5
Following the EC mandate, the SDM has started to act as the
DLS Implementation Project Manager
As Data-Link Services (DLS) has been identified as priority for the 2016 CEF Transport Calls, a
dedicated DLS cluster has been identified by SDM in order to ensure a synchronized DLS
implementation in Europe.
According to EC mandate, “the SDM should now assume the role of DLS
implementation project manager responsible for organizing, implementing
and monitoring the activities identified in the recovery plan as necessary for
the implementation of the DLS transitional solution and the preparatory
actions for the full achievement of the European target solution, Model D,
in order to achieve the implementation of AF6 in accordance with the
deadlines defined in the PCP Regulation.
This role shall include managing the overall set-up, steering and coordination of
the technical approach through:
- Identification of homogenous service areas starting from the analysis of
the current situation in EU Member States;
- Definition of target ground architecture per service area in cooperation with
the local stakeholders;
- Interconnection of sub-networks within each service area to achieve a
European distributed network and a European common approach;
- Updated CBA and expected contribution to SES performance objectives.
SDM – as DLS project manager – shall facilitate the involvement of relevant
stakeholders to ensure a coordinated submission of DLS IPs to the CEF
Transport Calls for proposals, also enabling projects to stimulate
establishment of a single European DLS governance”
EC mandate to SDM – 18/10/2016
Copyright SESAR Deployment Manager 8
Agenda
➢ Overview
➢ SDM activities for Path I and Path II
➢ Path I - implementation status
➢ Path II - main findings
➢ 2017 CEF Transport Calls for Proposals
➢ SDM working in progress – main items
Copyright SESAR Deployment Manager 10
SDM as DLS Project Manager
According to EC mandate, the SDM is the DLS implementation project manager
responsible for organizing, implementing and monitoring the activities identified in the
DLS Recovery plan.
Path I: SDM monitors the implementation of DLS transitional solutions
(Model B or Model C (MF) for the ground segment and best in class
avionics for the airborne segment), with reference both to EU co-
funded projects and any other initiative.
Path II: SDM performs preparatory activities needed to achieve the
target solution (Model D).
SDM role
and
activities
Other required activites: SDM establishs mechanisms of
cooperation with all those Bodies having to perform complementary
activities essential to a successful DLS deployment.
Copyright SESAR Deployment Manager 11
DLS Implementation: joint effort and results
ANSPs CSPsRelevant EU
Bodies
➢ Implementation of DLS Transitional Solutions
➢ Preliminary definition of Service Areas and Overall
Technical architecture for the target solution
➢ Establishment of the DLS Performance Monitoring
Function
➢ Shared definition of “best-in-class” avionics
➢ Setting up of regulation review
AUs
Copyright SESAR Deployment Manager 12
Agenda
➢ Overview
➢ SDM activities for Path I and Path II
➢ Path I - implementation status
➢ Path II - main findings
➢ 2017 CEF Transport Calls for Proposals
➢ SDM working in progress – main items
Copyright SESAR Deployment Manager 14
Path I implementation status - monitoring exercise
➢ A Monitoring Exercise has been launched by SDM late March 2017 to
provide the implementation status of DP Family 6.1.3 building on the data
provided by the involved stakeholders by 28th April 2017.
➢ Considering that data reflect the state of the art as of May 2017 and
taking also into account the ongoing activities related to SDM DLS
Recovery Plan on Path I, as well as the Regulation EU (No) 2015/310, a
more detailed monitoring session has been performed in October
2017.
➢ Specifically, a dedicated questionnaire has been submitted to the
ANSPs and CSPs with the aim of collecting more updated
information about the implementation status at country level.
Copyright SESAR Deployment Manager 15
Path I - ARINC MF coverage : planned status (February 2018) RF Network
Copyright SESAR Deployment Manager 16
Path I - SITA MF coverage : planned status (February 2018) RF Network
Copyright SESAR Deployment Manager 17
Path I - DLS implementation: current status (October 2017)
NOTES:
• France: DLS
operation is
partial with
regard to
functional
scope: 3 DLS out
of 4 (DLIC, ACM,
AMC) are in
operation in the
five ACCs above
FL 195, for all
aircraft
(ARINC/SITA/Unc
ontracted). ACL
service is not in
operation.• Portugal: Lisbon
ACC provides
DLIC-LOGON
customers
Data-link service
Copyright SESAR Deployment Manager 18
DLS implementation: planned status (February 2018) Data-link service
NOTES:
• Bulgaria: Only
SITA customers:
Initial Operating
Capab. (DLIC,
ACM, AMC);
• France: In
February 2018,
no change
compared to
October 2017
status;
• Italy: Padova by
February 2018;
Milan by April
2018; Rome by
May 2018;
• Latvia: Expected
date: end of
2018
• Norway:
Expected date:
Q2 2021• Portugal: Only
DLIC-LOGON for
SITA and ARINC
customers.
• Spain: Madrid by
May 2018
Copyright SESAR Deployment Manager 19
DLS implementation: planned status (May 2018) Data-link service
NOTES:
• DLS Provided in
Full Italy and
Spain
Copyright SESAR Deployment Manager 20
DLS implementation: planned status (December 2018) Data-link service
NOTES:
• DLS Provided in
Latvia
• France: DLS fully
provided in Brest
and Bordeaux
ACCs
Copyright SESAR Deployment Manager 21
5 AIRBORNE-RELATED INITIATIVES
3 from Civil
Airspace Users
2 from Military
Stakeholders
AIRBORNE domain
IP Reference
NumberIP Title Project Leader A/C Model
# of A/C planned to
be upgraded as per IP
Template
CIVIL AIRSPACE USERS
2016_061_AF6Deployment of ATN B1 capability
within TAP GroupTAP Portugal
A320 Family 43
E195 36
2016_164_AF6Ryanair Upgrade to ATN B1 to
"best in class”Ryanair B737-800 140
2016_165_AF6
Lufthansa Group & Air France
Group Datalink upgrade to "best in
class" avionics
Lufthansa
LUFTHANSA GROUP A/Cs
LH - A380-800 14
LH - B747-8 19
LH - B777F 5
LH - CRJ900 35
LH - A320
Family36
LH - E195 17
AIR FRANCE GROUP A/Cs
AF - A320
Family118
AF - CRJ1000 14
AF - E195 25
MILITARY STAKEHOLDERS
2016_125_AF6Airbus A310 ATN VDL2
Compliance
Spanish Air
ForceA310 2
2016_126_AF6FALCON 900 compliance with Air
Ground ATN VDL2 Data Link
Spanish Air
ForceFALCON 900 2
Path I - Airborne Domain: IPs submitted within 2016 CEF Transport Calls
Copyright SESAR Deployment Manager 22
Path I – airborne domain: monitoring exercise
A dedicated questionnaire has been submitted to the Airspace Users, to collect updated information
about the status of the adoption and installation of the “Best-in-Class” avionics. Moreover, the questionnaire
has been submitted to other partners not involved in the 2016 CEF Transport Calls.
Main results
Overall IP statuso Lufthansa Cargo, Lufthansa CityLine, Air France and Spanish AF have all started equipping their aircrafts to
varying degrees.
o Ryanair has started planning and finalizing vendor selection.
o TAP were awaiting the SGA to be signed before formalizing supplier contracts.
o Lufthansa Passenger and Austrian Airlines have a slight delay at starting the upgrade.
Proposed number of Aircraft equipped by Mid 2018 (Against IP Number)o Air France has stated that the retrofit will be completed.
o Lufthansa Cargo & Lufthansa CityLine have both stated as in line with what declared in the IPs.
o Ryanair stated the planned number could be up to 75 aircraft.
Fully Operational by 2020o All
Copyright SESAR Deployment Manager 23
Agenda
➢ Overview
➢ SDM activities for Path I and Path II
➢ Path I - implementation status
➢ Path II - main findings
➢ 2017 CEF Transport Calls for Proposals
➢ SDM working in progress – main items
Copyright SESAR Deployment Manager 25
Path II tasks
2.3 - Elaboration of a Business Case
for the target solution
2.2 - European technical architecture
definition
According to EC mandate, these tasks are performed by SDM in close coordination with the
Path II Project “Preparatory activities towards target solution (Path II)” and further consulted
with stakeholders.
2.1 - Requirements collection &
Service area definition
2.4 - Transitional activities towards
target solution
2.5 – Ensuring consistency of
activities related to DLS Governance
definition
Completed
Work in
Progress
Work in
Progress
Work in
Progress
Completed
Copyright SESAR Deployment Manager 26
Path II - Main Findings (1/3)
➢ “2.1 – Requirements collection and Service Areas definition ” activities are completed. The Service
Areas Proposal has been included in the Report on Service Areas and DLS Overall
Architecture deliverable submitted to EC the 29/09.
➢ In this document, the SDM has proposed to implement a scenario with a single Service Area
as the optimal one.
➢ Nevertheless, considering the tight timeframe envisaged in the PCP regulation and outlined in the
DLS Recovery Plan, the SDM has proposed a two steps approach
First Step
Two Service Areas implementation of Model D
Final Step
Single Service Area implementation of
Model D
Copyright SESAR Deployment Manager 27
Path II - Main Findings (2/3)
➢ “2.2 - European technical architecture definition” activities are completed. In
particular, two possible technical architectures have been identified
Architecture Proposal 1 Architecture Proposal 2
Each proposal is characterized by several technical and non-technical open points, whose solution
is necessary to clearly define the overall DLS architecture.
Copyright SESAR Deployment Manager 28
Path II - Main Findings (3/3)
“2.3 - Elaboration of a Business Case for the target solution” activities are in progress considering the
Service Areas and the architecture outcomes; specifically the SDM is preparing a preliminary version of the D3.1
–Business Case Report, which will be released by the end of December 2017.
“2.4 - Transitional activities towards target solution” activities are in progress considering the Service Areas
and the architecture outcomes.
“2.5 – Ensuring consistency of activities related to DLS Governance definition”: Activities are on-going in
accordance to the schedule, however SDM is recommending to accelerate the main deliverables.
Copyright SESAR Deployment Manager 29
Agenda
➢ Overview
➢ SDM activities for Path I and Path II
➢ Path I - implementation status
➢ Path II - main findings
➢ 2017 CEF Transport Calls for Proposals
➢ SDM working in progress – main items
Copyright SESAR Deployment Manager 31
2017 CEF Transport Calls for Proposals - Call text
2017 CEF
Transport Calls
Objectives and
Priorities
“[…] the Commission aims at continuing the implementation of the
Datalink (DLS) Recovery Plan developed by the SESAR Deployment
Manager. Consequently, priority will
be given to implementation projects aiming to
implement datalink capability in support to AF6 Initial Trajectory
Information Sharing. These projects shall be implemented in
accordance with the DLS Recovery Plan
Air/Ground and Ground/Ground Multi-Frequency
Datalink Network in defined European Service Areas
Considering the provisions in the Reg. (EU) No 310/2015, in particular the deadline
for ground implementation by February 5th, 2018, the priority is to finalize the
definition and initiate the implementation of the Model D.
Consequently, proposals for implementation projects aiming at implementing
Model B or Model C Multi-Frequency will NOT be eligible under the present call
for proposals.
Furthermore, applicants are invited to join their efforts within a limited number of
implementation projects.
6.1.3
ATN B1 capability in MF environment in aircraft domain
Under this Family, priority will be given to implementation projects aiming to fit or
retrofit aircraft with DLS avionics, as identified in the DLS recovery plan.
6.1.4
Copyright SESAR Deployment Manager 32
SDM proposal for the 2017 CEF Transport Calls for ProposalsG
rou
nd
Do
ma
in
According to the priorities set on DLS in
CEF Calls 2017 and considering the
progress achieved by Path I and Path II
projects, 3 new Implementation
Projects are strongly recommended by
the SDM to be submitted as proposals.
The aim of these new IPs is to definitively
solve the open points identified within
the aforementioned projects.
Objective DLS European target solution
assessment
Model D pre-implementation
Design for a common European ATN
Ground Network
Current Implementation Projects
dedicated to the avionics upgrade shows
remarkable results, nevertheless the
percentage of equipped aircrafts
required by IR (EU) regulation still has
to be reached
Objective
Continuously support avionics upgrade
Proposed approach
• Path II project extension (including a capacity
analysis)
• Model D performance evaluation
• Pre-implementation activities for ATN G/G
network
2
3
1
Air
bo
rne
Do
ma
in
Copyright SESAR Deployment Manager 33
SDM Guidelines for the 2017 CEF Transport Calls for Proposals
The SDM considers fundamental to guide stakeholders towards the
most appropriate deployment approach and connect at same time to
the co-funding opportunities expected for the 2017 CEF Transport
Calls for Proposals.
For this reason, SDM has elaborated dedicated guidelines “DLS
Guidelines for the 2017 CEF Transport Calls” for a coordinated
submission of implementation projects for the 2017 CEF Transport
Calls for Proposals.
In these guidelines, according to the DLS Recovery plan and the
outcomes of the Path II project execution, the SDM strongly encourages
the submission of the before mentioned projects.
Copyright SESAR Deployment Manager 34
DLS IPs submission roadmap
Interested stakeholders are requested to provide IPs proposal from 15th November to 28th
November, by using the dedicated space on STAR Tool
Copyright SESAR Deployment Manager 35
Agenda
➢ Overview
➢ SDM activities for Path I and Path II
➢ Path I - implementation status
➢ Path II - main findings
➢ 2017 CEF Transport Call for Proposals
➢ SDM working in progress – main items
Copyright SESAR Deployment Manager 37
SDM Work in progress - main items (1/3)
“Best in Class” and the need for a working forum.
• SDM is supporting EUROCAE in the definition of ED92C in coordination with EASA. The ED92C is
expected to characterize the standardization of Best-in-Class.
• At the same time, SDM is working on the requirements identification for the establishment of a DLS
dedicated working forum for the problem reporting, investigation and resolution, including day-to-day
topics. Roles and responsibilities of this forum will be discussed with other relevant Bodies.
➢ Current progress
Critical activities that need to be completed by February 2018.
• The most critical activity to be performed by February 2018 is the completion of the service provision at
EU level, as required by the IR (EU) No 310/2015; this activity is in charge of ANSPs and CSPs,
coordinated by SDM.
Need for consensus on future capacity needs
• SDM is promoting a capacity assessment of Model B and Model D through simulations in portions of
European Airspace (including high traffic levels area), considering as baseline the current situation.
• The study could be useful also to understand the future capacity needs.
Copyright SESAR Deployment Manager 38
➢ ATS & AOC
Prioritisation of ATS traffic over AOC
• SDM is promoting a proposal where it will be taken into account the analysis of the introduction of the
priorisation of ATS over AOC (considering also the availability of real implementations worldwide).
SDM Work in progress - main items (2/3)
Target Architecture work – main items
➢ Performance: SDM is promoting within the 2017 CEF Transport Calls:
• A capacity assessment of Model B and Model D through simulations in portions of European
Airspace (including high traffic levels area), considering as baseline the current situation.
Moreover, the SDM is
• A performance trade-off analysis of Models B and D RF Layers, on the basis of real data
coming from Model B (already implemented) and data gathered within the Model D already pre-
implemented in a limited portion of the European Airspace.
➢ Business Case: SDM is working on the Business Case elaboration and at the same time is promoting
a proposal for the 2017 CEF Transport Calls with the aim of supporting SDM in its activity.
➢ Path I & Path II alignment: SDM is coordinating the Path I & Path II projects, ensuring the alignment
of the main outcomes in the ground domain, where applicable. Path I has to be considered as part of
the baseline for Path II activities. For the airborne domain, the AUs are expected to follow the
indications included in the DLS Recovery Plan.
➢ Target architecture (1/2)
Copyright SESAR Deployment Manager 39
Target Architecture work – main items
➢ Target architecture (2/2)
➢ Path II & ELSA recommendations alignment: Path II activities are based on the ELSA
recommendations. With regard to the target dates SDM has the need to take into consideration also
the deadlines of PCP Regulation for AF 6.
➢ Evolution from Current model to the target architecture: SDM is working on the elaboration of a
transitional plan towards the target architecture. These activities are in the Path II project WP4 scope
.
➢ Service Governance: SDM is supporting and monitoring the stakeholders of the Path II project WP5
that are working on the DLS Governance definition.
SDM Work in progress - main items (3/3)
w. www.sesardeploymentmanager.eu
t. +32 (0) 2 793 07 57
follow us on Twitter @SESAR_DM follow us on LinkedIn
CONTACT US