Hot Dry / Mixed Dry Prototypes Wathen Castanos Hybrid Homes, Inc. Duncan Prahl, RA Sr. Research Associate, IBACOS Inc. DOE Quarterly Meeting, Denver, CO July 21, 2010

Upload: vudan

Post on 12-May-2019

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Hot Dry / Mixed Dry Prototypes

Wathen –Castanos Hybrid Homes, Inc.

Duncan Prahl, RA

Sr. Research Associate, IBACOS Inc.

DOE Quarterly Meeting, Denver, CO

July 21, 2010

Page 2: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Wathen Castanos Hybrid Homes, Inc.

• Company Profile:

• ~180 Homes per year in Clovis / Fresno CA

• First-time, Move-up and Empty-nester buyers

• House sizes from 1100 to 2700 square feet

• Started high performance homes in 2006

• Current standard practice ~ 48% WRT BA Benchmark

• Currently 36 employees

Page 3: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Initial Evaluation - Mapping and Gap Analysis

2 days- mapped operational activities in 5 areas:

– Planning and Development, Product Design and Purchasing,

Home Sales and Marketing, Construction, and Customer

Care

– Identified key strengths and gaps as a builder of high

performance homes

– Strong corporate culture, trade relationships, brand

awareness, and reputation

– Integrated Design Process

From this activity 6 work improvement

groups were identified

Page 4: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Work Improvement Groups (WIG’s)

• Company had to invent a new operational

model

– Company reduced staff by 2/3 from 2007 - 2009

• Developed cross functional teams to

address highest value gaps

• Training was provided to company and

trades on Building Science, Quality

Management, and Quality Tools

– DMAIC (Define, Measure, Analyze, Improve,

Control) process for WIG’s

• Applied for National Housing Quality Award

in 2010, received site visit by judging panel.

Page 5: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Initial Evaluation - Technical

IBACOS Quality Assessment Results

• Two days of site evaluations.

• Overall score 3.2 (scale of 0 to 4)

– “Low Risk” Category

Page 6: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Initial Evaluation - Technical

Best Practices Observed:

– Excellent HVAC duct installation.

– High efficiency equipment

– 92 AFUE furnace

– 14 SEER air conditioner

– Zoned distribution

– Rinnai tankless, gas fired water

heaters

Page 7: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Initial Evaluation - Technical

Best Practices Observed:

– Grade I fiberglass batt installations.

– R-13 cavity + R-4 continuous exterior

insulating sheathing.

– Good air sealing of the enclosure.

Page 8: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Initial Evaluation - Technical

Energy Performance of Existing Practices (Jan 2010):

– 48% above Building America Benchmark.

– Participating in Builder’s Challenge, California Build it Green,

& ENERGY STAR.

– 30% beyond 2008 CA Title.

– Average duct leakage <5%.

– Average building tightness < 3.5 ACH50.

– Taking advantage of every tax incentive and energy rebate

available to offset all energy upgrades.

– Homes marketed competitively at $/sq. ft. for region.

Page 9: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Prototype – Design Strategies

Wathen Castanos Hybrid Homes Inc. wanted to roll out a

fresh product offering for a community development,

“Loma Vista”.

• Plan #200 is a 2000 square foot, 3 bedroom ranch

style home.

– IBACOS encourage the builder to consider moving the HVAC

system and ducts to inside conditioned space.

– The cost to do a conditioned attic proved too high for the

builder’s price point.

– Very concerned about marketability of 8’ ceilings in areas of

the house.

Page 10: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Plan 200

Page 11: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Prototype – Specification Package

The point deficiency to get

from 48% to 50% beyond

BAB would have to be made

up in system efficiency and

an enhanced building

enclosure.

Net positive cash flow to the

consumer of ~$935 / year

Rating for this design

package:

RESNET HERS Index - 53

CA HERS I – 46

CA HERS II – 68

(see barriers…)

Component 2010 Base Package Prototype

Concrete Slab Uninsulated Uninsulated

Exterior Walls

2x4 16" o.c. R-13 + R-4 cont. sheathing (R19 knee walls)

2x4 16" o.c. R-15+ R-4 cont. sheathing (R19 knee walls)

Roof

Attic floor - R-38 + Radiant Barrier

Attic floor - R-49 + Radiant Barrier

Exterior Doors R-4 R-4

Windows U-.34, SHGC-.25 U-.32, SHGC-.25

Building Air Tightness 3.5 ACH50 2.7 ACH50

Mechanical Ventilation Exhaust with pressure relief Exhaust with pressure relief

Heating 92 AFUE 94.7 AFUE

Cooling 16 SEER 18 SEER

Ductwork R-8 in unconditioned R-8 in unconditioned

Water Heater Tankless, gas .82 EF Tankless, gas .98 EF

Appliances All Energy Star All Energy Star

Fluorescent Lighting 100% 100%

Photovoltaic System variable 3.7 kW

% Better than Building

America Benchmark48.4% 52.6% & 70% w/PV

Page 12: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Prototype – Design Strategies

• This demonstrates their

commitment to taking

this specification

package to community

scale production

• Wathen Castanos Hybrid Homes has been adamant

that the resulting prototype product would still fit into a

price point that would be competitive in their market.

Page 13: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Prototype – Design Strategies

• Strategies to achieve a tighter building envelope (to get

from 3.5 to below 3.0)

– Addition of seal sill that layer up under stucco weep screed.

– Glued drywall to top and bottom plates & around openings.

Page 14: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Prototype – Design Strategies

• Builder was already:– Sealing all penetrations through plates and enclosure.

– Sealing all window and doors between R.O.s and frames.

– Sealing all penetrations through the drywall.

• Actual blower door test results indicate a total leakage rate of 2.7 ACH50. Not amazing, but not bad for California, open frame construction.

Page 15: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Prototype – Design Strategies

• Additional wall R value was achieved by using Johns

Manville Spider® blown in fiberglass.

Page 16: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Prototype – Design Strategies

• Though attic insulation was increased to R-49 (from R-38) raised heel trusses were priced but not included.

• Some designs require raised heels for aesthetics

Page 17: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Design Challenges & Barriers

System Sizing

• Initial modeling indicated that a 2 ton AC was sufficient.

– Total cooling load was 20,888 Btuh

• The builder wanted to use the Bryant Evolution system.

• The 2 ton was discontinued and a 2 ½ ton wasn’t

available.

• Therefore a 3 ton system was installed.

• Again, the industry is faced with manufacturing split AC

systems that are high efficiency and small enough for

low load, high performance homes.

Page 18: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Challenges and Barriers

• Bringing Ducts inside conditioned space– Aesthetic concerns

– Footprint of the HVAC unit

– Noise concerns

• How much is enough?– 50% package is possible, but incremental step above 48%

builder standard practice is marginal.

– Even if we “threw everything at it” we’d only be getting in the mid 50% savings

• CA HERS I, II & RESNET Ratings– T-24 vs. 2006 IECC reference homes

– States rights vs. national uniformity

Page 19: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Buyer response

• Since the opening of this home, WCHH has offered a PV package as an included upgrade. Buyers can opt for any other options instead. The majority are taking the other options.

• “The home is efficient enough, I’ll take the granite countertops.” is the common response to this offering.

• The 3.7 kW photovoltaic system cost $13,940 with a

rebate of $7709 for a final cost to the builder of $6231

to the builder.

Page 20: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Next Steps

• Implement a model Quality Management System

within the organization

– Way to document and standardize procedures for HP

homebuilding

– Identify operational best practices for translation to other

building companies

– Track operational metrics to demonstrate benefits of making

HP a basic operational strategy

• Evaluate Prototype

– Are incremental strategies enough to maintain market

leadership?

– Re-evaluate systems strategies

Page 21: Hot Dry / Mixed Dry Prototypes, Wathen – Castanos Hybrid ... · –DMAIC (Define, Measure, Analyze, Improve, Control) process for WIG’s ... BAB would have to be made up in system

Building America Team Meeting

Questions?

Duncan Prahl