How to Develop a Permit— T he Process and Implementation. Gila River Indian Community By Will Antone III, Air Quality Specialist. Summary of Presentation. Community Background Air Quality Management Plan Permit Process Review Technical Support Document Overview of Permit - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: How to Develop a Permit— T he Process and Implementation

1

How to Develop a Permit—The Process and Implementation

Gila River Indian CommunityBy Will Antone III, Air Quality Specialist

Page 2: How to Develop a Permit— T he Process and Implementation

2

Summary of PresentationCommunity BackgroundAir Quality Management PlanPermit ProcessReview Technical Support DocumentOverview of PermitEnforcement Case Study

Page 3: How to Develop a Permit— T he Process and Implementation

3

Gila River Indian Community Background

Established in 1859 by Executive OrderConsists of two (2) tribes

Akimel O’odham (Pimas) – Districts 1 thru 5Pii-Pash (Maricopas) – Districts 6 & 7

Landbase374,000 Acres

Population On reservation 15,000Off reservation 5,000

Page 4: How to Develop a Permit— T he Process and Implementation

4

Page 5: How to Develop a Permit— T he Process and Implementation

5

Monitoring Stations

Gila River Indian Community

Industrial ParksSand & Gravel

Page 6: How to Develop a Permit— T he Process and Implementation

6

Industry BackgroundTwo industrial parks, 50 businesses &

industriesPacific Scientific, Triumph, Local Motors,

Superlite Block, Pimalco, Champion Homes, etc.Other GRIC-Area Sources

40,000 agricultural acresAcreage will increase to 146,000 over next 10

yearsInterstate 10 bisects Community

(largest source of air pollution)

Page 7: How to Develop a Permit— T he Process and Implementation

7

Air Quality Management PlanPart I. General ProvisionsPart II. Permit RequirementsPart III. Enforcement OrdinancesPart IV. Administrative AppealsPart V. Area Source Emission Limits

Open BurningFugitive Dust

Page 8: How to Develop a Permit— T he Process and Implementation

8

Air Quality Mgmt. Plan (cont.)Part VI. General Requirements

Visible EmissionsVOC Usage, Storage, HandlingDegreasing, Solvent Metal Cleaning

Part VII. Source/Category Specific Emission LimitsSecondary Aluminum ProcessingAerospace Manufacturing and Rework

OperationsNon-Metallic Mineral Mining and Processing

Page 9: How to Develop a Permit— T he Process and Implementation

9

AQMP Background

2006 GRIC Enacts

Complete AQMP

2007 GRIC Submits AQMP to

USEPA for Federal

Enforceability

2009 GRIC Submits AQMP

supplemental packet to

USEPA

2011 USEPA

approves AQMP

2002 GRIC Enacts Part I of AQMP

Page 10: How to Develop a Permit— T he Process and Implementation

10

Page 11: How to Develop a Permit— T he Process and Implementation

11

Permit ProcessMail permit packet to facility

Application, O&M Guidelines, Dust Control Plan, offer to meet

Permit meetingBackground informationAQMP overviewApplication reviewTimeframeContact information

Page 12: How to Develop a Permit— T he Process and Implementation

12

Permit Process (cont.)Completeness check

Request additional informationAdditional on-site meeting, if necessary

Draft PermitResearch GRIC regulations, federal

regulations, and emission factorsTechnical Support Document Emission calculations

Page 13: How to Develop a Permit— T he Process and Implementation

13

Permit Process (cont.)Mail final permit to facility 2 weeks prior

to 30-day public comment periodPermit invoice

30-day public comment periodNotice publish in local paper (Gila River

Indian News)Respond to comments, if necessaryHold public hearing, if necessary

Issue air quality operating permit

Page 14: How to Develop a Permit— T he Process and Implementation

14

Page 15: How to Develop a Permit— T he Process and Implementation

15

Page 16: How to Develop a Permit— T he Process and Implementation

16

CEMEX Enforcement ActionAQP observed emissions from Asphalt PlantConducted an inspection on San Tan Plant

Lead to inspection of Maricopa PlantObserved visible emissionsConducted visible emissions readings (U.S. EPA

Method 9) on baghouse, passive baghouses and asphalt silo

Exceeded emission limitations 7% Opacity limitations for storage silo20% Opacity limitations for baghouse

Page 17: How to Develop a Permit— T he Process and Implementation

17

Page 18: How to Develop a Permit— T he Process and Implementation

18

U.S. EPA Method 9 Visible Emissions Observations

Page 19: How to Develop a Permit— T he Process and Implementation

19

Page 20: How to Develop a Permit— T he Process and Implementation

20

CEMEX Enforcement Action (cont.)Completed inspection reportInternal meetings discussing enforcement

actionResearch regulating authoritiesResearch facility background and track recordDecision on enforcement route in accordance

with AQMPIssued three (3) NOVs

Offered an opportunity to meet to discuss corrective actions

Page 21: How to Develop a Permit— T he Process and Implementation

21

Page 22: How to Develop a Permit— T he Process and Implementation

22

CEMEX Enforcement Action (cont.)Received “NO” response from CEMEXProceeded with a Compliance Order and

issued a $15K administrative penalties$5K per violation per day

Issued letter to CEO of CEMEXWebsite claimed CEMEX

environmentally conscious company

Page 23: How to Develop a Permit— T he Process and Implementation

23

CEMEX Enforcement Action (cont.)CEMEX Environmental personnel arranged

meetingCEMEX signed order and paid $15K penalty

CEMEX submitted a Corrective Action Plan

Page 24: How to Develop a Permit— T he Process and Implementation

24

Page 25: How to Develop a Permit— T he Process and Implementation

25

Page 26: How to Develop a Permit— T he Process and Implementation

26

Page 27: How to Develop a Permit— T he Process and Implementation

27

HighlightsConducted enforcement actions using

tribes inherent sovereign authorityOther jurisdictions all had

enforcement actions against CEMEX, sought advice from Air Quality Program on compliance strategies

Achieved compliance and working relationship with CEMEX

Page 28: How to Develop a Permit— T he Process and Implementation

28

Questions?

Gila River Indian CommunityDept. of Environmental Quality

Will Antone III, Air Quality Specialist(520) 562-2234