Howells Roof Light Systems Howells Roof Light Systems Step By Step Installation Guide Double Hipped Roofs Double Hipped Roofs DEC 2011 Howells Roof Light Systems Tel. 01384 820060 Fax. 01384 860150 Tel. 01384 820060 Fax. 01384 860150 Email [email protected]

Upload: others

Post on 01-Feb-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • Howells Roof Light SystemsHowells Roof Light Systems

    Step By Step Installation GuideDouble Hipped RoofsDouble Hipped Roofs

    DEC 2011

    Howells Roof Light SystemsTel. 01384 820060 Fax. 01384 860150Tel. 01384 820060 Fax. 01384 860150

    Email [email protected]

  • Index

    Good working practice & delivery method........................... Page 3

    Typical kerb detail................................................................

    Eaves beam assembly.........................................................

    Corner assembly..................................................................

    Preparation of kerb..............................................................

    Installing hip bars................................................................

    Ridge assembly...................................................................

    Centre glazing bar eaves....................................................

    Centre glazing bars to ridge................................................

    Ridge assembly detail.........................................................

    Jack bars to hip...................................................................

    Final stage before glazing...................................................

    Installation of glass..............................................................

    Eaves beam foil taping........................................................

    Ridge capping......................................................................

    External beading..................................................................

    Silicone sealing....................................................................

    Outer capping......................................................................

    Ridge gasket........................................................................

    Roof vent installation (ridge to eaves)................................

    Roof vent installation (with transum)...................................

    Tie wire................................................................................

    Component List - Profiles....................................................

    Component List - Accessories/Parts....................................

    Page 4

    Page 5

    Page 6

    Page 7

    Page 8

    Page 9

    Page 10

    Page 11

    Page 12

    Page 13

    Page 14

    Page 15

    Page 16

    Page 17

    Page 18

    Page 19

    Page 20

    Page 21

    Page 22

    Page 23

    Page 24

    Page 25

    Page 26

    2

  • Thank you for purchasing your Howells Glazing Roof Light System, which has beenprefabricated by our team of our skilled craftsmen prior to delivery.

    The following instructions will ensure an efficient and easy installation of yourroof light . These instructions cover both delivery in flat-pack and assembled form

    A little time spent looking through the instructions prior to commencement will help togive an understanding of the structure and the processes involved and will help to avoidcomplications during assembly

    Tools Required

    For your safety when installing yourroof light you should observethe following points:

    • Always use relevant ‘Personal ProtectiveEquipment’ (i.e. gloves, helmet, goggles,safety shoes etc.) when erecting theconservatory.

    • All power tools used outdoors should be 110 volt and connected through a transformer.

    • Window frames supporting therooflight roof should be installedstrictly in accordance with the systemmanufacturer’s instructions.

    • The use of a stable working platform(scaffold or trestles) is highlyrecommended for any conservatoryinstallation.

    • Do not rely upon incomplete structures to support your weight (either directly or via ladders).

    • Only use ‘Low Modulus, Neutral Cure’Silicone for sealing aluminium to brickwork,concrete or Lead

    • Check tightness of all fixings prior toglazing roof or frames.

    • Building sites (whether large or small) are dangerous places. As such, thegeneral public (particularly children)should be kept away until the installationis complete.

    • Remove all debris from the site uponcompletion.

    GOOD WORKING PRACTICE DELIVERY METHOD

    01384 820060

    Tech SupportAny Technical Questions?

    Picture above shows how a ‘flat-pack’ roof would arrive, double glazed units would beloose on a glass stillage.

    Please insure that there is sufficient bodies to assist driver to unload.

    Roof lights with dimensionsunder 3000mm x x 2000mm are general delivered in an assembled form(unless you have access issues)

    • Non-markable rubber mallet• Battery Drill• Silicone gun• Pozi Head screw driver• 3mm & 4mm Allen Key• 13mm Spanner

    3

  • TYPICAL KERB DETAILP A D LTY IC L KERB ETAI

    4

  • 3. Offer eaves beam together and insert c/sunk M6 16mm screws & tighten (4mm allen key required)

    4. Apply expandable foam tape to underside of eaves

    EAVES BEAM ASSEMBLYA A YEAVES BE M SSEMBL

    5

  • PREPARATION OF KERBR KPREPA ATION OF ERB

    6

  • INTERNAL CORNERIN ERNAL C RN RT O E

    7

  • INSTALLING HIP BARSINSTALLING HIP BARS

    Eaves BeamEaves Beam

    1. Slide hip bar onto corner bracket. 2. Line up holes and use c/sunk M6 16mm Boltsand tighten with 4mm allen key .

    3. Repeat to all four corners

    8

  • Eaves BeamEaves Beam

    RIDGE ASSEMBLEYRIDGE ASSEMBLEY

    Eaves BeamEaves Beam

    1. Ridge assembly requires two people. Whilst holding ridge in position insert ridge bracket into topof hip bar.

    2. Line up holes and use c/sunk M6 16mm Bolts and tighten with 4mm allen key .

    3. Repeat to all hip bars.

    9

  • INSTALLING CENTRE BARS

    Eaves BeamEaves Beam

    INSTALLING CENTRE BARS

    Eaves BeamEaves Beam

    1. Line up holes and use c/sunk M6 16mm Bolts and tighten with 4mm allen key .

    (TO EAVES)

    ACVT-002

    Associated Parts

    VT060 - Ring Beam Adaptor Variable Bracket for Eaves & Ridge

    10

  • INSTALLING CENTRE BARS

    Eaves BeamEaves Beam

    INSTALLING CENTRE BARS

    Eaves BeamEaves Beam

    (TO RIDGE)

    Associated Parts

    VT061 - Ridge Adaptor Variable Bracket for Eaves & Ridge

    ACVT-002

    1. Snap VT061 Ridge Adaptor into ridge profile

    2. Clip in variable bracket [ACVT002] and tighten.

    3. Depress bracket and using M6 16mm Bolts secure, repeat on all centre bars.

    11

  • A

    A

    12

  • INSTALLING JACK BARS

    Eaves BeamEaves Beam

    INSTALLING JACK BARS

    Eaves BeamEaves Beam

    2. Jack bar bracket will be pre-fixed. Offer bar to bracket and secure with small tek fittings asprovided. When fixing jack bar, ensure that it is held firmly against the hip bar to avoid gaps occurring.

    [ACVT009]

    Eaves BeamEaves Beam1. Line up holes and use c/sunk M6 16mm Bolts and tighten with 4mm allen key . (ALL AS CENTRE BARS)

    Jack BracketHIP

    BAR

    JA

    CK

    BA

    R

    JA

    CK

    BA

    R

    HIP

    BAR

    ACVT-009

    Jack Bar Plate

    13

  • Eaves BeamEaves Beam

    FINAL STAGE BEFORE BEFORE GLAZINGFINAL STAGE BEFORE BEFORE GLAZING

    Eaves BeamEaves Beam

    Eaves BeamEaves Beam

    1. Using a rubber mallet, knock on White PVC Glass carrier [VR514] ensuring it’s fully snapped in.Repeat to all bars on roof.

    1. Snap in ‘front raise profile’ [VR-565] ensuring it’s fully snapped in.

    VR-514 - GLASS CARRIER

    VR-565 - FRONT RAISE PROFILE

    VR565 - RAISE PROFILE

    14

  • INSTALLING GLASSINSTALLING GLASS

    Eaves BeamEaves Beam

    1. Glazing :- Dependant on size of D/G Unitsinstallation could be a ‘two man’ job.

    The glass would normally have two labels.One to show the size and specification theother to show which surface faces theinterior of the build.

    2. Place the glass onto the gasket at the ridge, lower bottom of glass unit onto the glass carrier.

    3. Repeat until fully glazed

    ** IMPORTANT NOTE **

    TIE WIRES (IF REQUIRED) MUST BE INSTALLED PRIOR TO GLAZING

    15

  • EAVES BEAM FOILINGEAVES BEAM FOILING

    Eaves Beam

    1. Width Foil tape (30mm) to be applied as to the entire eaves beam to glass perimeter once DG units have been placed in situ

    DIAGRAM 1

    2. Foil tape (i.e smaller strips) to hips and centre bars.....

    DIAGRAM 1

    16

  • RIDGE CAPPINGRIDGE CAPPING

    Eaves Beam

    1. The internal ridge will have white spacers attached to itsecured with self tappers, these are for the externalridge to fixed to.

    2. Line ridge up with end spacers and knock downridge outer capping firmly into place.

    3. Place the foam bung where glass units come together.(both ends)

    4. There are self adhesive foil tapes provided, use at topof hip..

    6. Also apply to bottom on hip bar

    5. At the top of the hip bar cover the foil tape stripes &foam bung with the foil fan ( as shown in Fig 5)

    7. The end spigot are now fitted. Apply siliconeseal to the top of the ridge capping and push downspigot against the ridge capping.

    8. Secure spigot to ridge with self tappers (provided)Please note that a self-adhesive pad painted thethe same colour as the roof is supplied to hidescrew fixings.

    END SPIGOT SELF ADHESIVE FOIL FAN

    17

  • EXTERNAL BEADING AND CAPPINGEXTERNAL BEADING AND CAPPING

    Eaves Beam

    Hold hold bottom external beading in place and fix down hip cap to secure . Dependent of roo flight dimensions , external bead comes in 1 or 2 length per side.

    Silicon hip bars against outer hood, the install black pressure using clamping plates provided. Any black pressure intercepting hip bars require silicone sealant

    SNAP ON - All outer aluminium outer capping (HIP BARS FIRST) and attached glass stops

    A

    HIP

    BR

    IPH B

    AR

    OUTER HOOD

    GLASS STOP

    SQUARE R TE LAS S P DE EN N P ROF OR O NA G S TOS P DANT O CAP ING P ILE

    PVC P

    RESS

    URE P

    LATE

    40mm x82mm

    TE IORE NT N P ATEL

    HIP PRESSURE PLATE

    PVC PRESSURE PLATE

    18

  • SILICON SEALING REQUIRED SILICON SEALING REQUIRED

    Eaves Beam

    SNAP ON - All outer aluminium outer capping (HIP BARS FIRST) and attached glass stops

    HIP PRESSURE PLATE

    PVC PRESSURE PLATE

    19

  • OUTER CAPPINGSOUTER CAPPINGS

    1. Firstly starting with Hip Outer Cap . Knock on all outer cappings with a ‘non-markable’ rubber mallet.

    2. Glass stops to Hip caps may now we pushed on. Although they’re a tight fit, we recommend a dab of silcione.

    20

  • RIDGE GASKETRIDGE GASKET

    1. nsert ridge gasket into grove on side of ridge .. ooflight is now complete..Insert flipper gasket into groove ridge capping

    21

  • ROOF VENTsROOF ENTSV

    Detail for FULL HEIGHT roof vet i.e glazed into ridge and eaves

    Ridge Detail Eaves Detail

    FULL HEIGHT RIDGE TO EAVES

    22

  • ROOF VENTsROOF ENTSV

    Detail for FULL HEIGHT roof vet i.e glazed into ridge and eaves

    Ridge Detail Transum H Came Detail

    RIDGE TO H CAME TRANSUM

    23

  • Itemised Parts List

    PROFILES

    HGVR111N

    HGVT111

    73mm SQUARE BAR RAFTER

    70mm ORNATE BAR RAFTER

    HGVR011N

    HGVT011

    105mm SQUARE BAR RAFTER

    95mm ORNATE BAR RAFTER

    VR2011N

    VT511

    125mm SQUARE BAR RAFTER

    130mm ORNATE BAR RAFTER

    VR511 MC152

    VR611

    150mm SQUARE BAR RAFTER ALUM HIP PRESSURE PLATE

    190mm ORNATE BAR RAFTER

    HG DK052N

    PVC PRESSURE PLATE

    25mm x 25mm ANGLE

    OUTER RIDGE CAPPING

    HG-VT240

    INTERNAL RIDGE MEMBER EAVES OUTER TRIM

    HG-VT140CLIP IN COVER

    EAVES INNER TRIM

    HG910- 30 DEG

    STANDARD EAVES BEAM

    VT910

    75mm EAVES BEAM

    VT110

    64mm EAVES BEAM

    VT010

    51mm EAVES BEAM

    LAN 910

    LANTERN EAVES BEAM

    VT 092

    0-30 DEG RAISE PROFILE

    VT091

    30-45 DEGREE RAISE PROFILE

    VT060

    RING BEAM ADAPTOR

    VT061

    RIDGE ADAPTOR

    VR565

    RAISE PROFILE WEATHER BAR

    HGDK052N

    16mm SQUARE CAP

    HGDK053

    21mm SQUARE CAP

    VT052

    31mm ORNATE CAP

    MC050 ETC157

    30mm ROUNDED CAP 150mm CILL

    MC050

    30mm ROUNDED CAP

    24

  • ACVT-005

    HG-ACVR-202

    30mm (w) x 0.8mm (Thick)

    HG-ACVT-0032

    HG-ACVT-0017

    ACVR313 EXPANDABLE FOAM TAPE

    HG-ACVT-0082HG - ACDK-066

    AMC019

    CORNER BRACKET JOINING FOR EAVES

    RIDGE FLIPPER GASKET

    FOIL BACKED FLASHBAND TAPE

    HIP BOX 180 DEGREE - (3 rafters)HOOD SPIGOT 180 Deg - (3 rafters)GLASS RETENTION PLATE

    HIP OUTER CAP GASKET

    Itemised Parts List

    BRACKET FOR HIP BOX

    HIP INNER/ RIDGE BAR GASKET

    ORNATE GLASS STOP

    ACVT 0004

    HG-ACVT011

    HG-COWL ORNATE

    ACVT-001 HG-ACVT-009HG-ACVT-008 ACVT-002 HG - ACVT-002

    VARIABLE BRACKET FOR HIPS JACK BAR HIP PLATE)90 DEG CORNER BRACKETVARIABLE BRACKET FOR EAVES FIXED BRACKET FOR EAVES

    GLAZING BAR / EAVES GASKET

    SQUARE GLASS STOPWEEP HOLE DRAINAGE COVER

    EAVES GASKET

    SPECIAL GASKET FOR LOW PITCH ROOFS UNDERSIDE OF EAVES BEAM

    HG-ACMC016

    HG-COWL SQUAREHG-WEEP

    50mm (w) x 0.8mm (Thick)

    FOIL BACKED FLASHBAND TAPE

    Itemised Parts List

    ACCESSORIES

    HG ELEC VENT

    ELECTRICAL ROOF VENT

    HG MAN VENT

    MANUAL ROOF VENT

    HG-CRANK

    MANUAL OPERATING POLE

    SWITCH

    ON/OFF SWITCH

    CONTROL

    DIGITAL CONTROL PANEL

    GASKETS & TAPES

    ROOF VENTS

    25

  • The main components of the Tiewire are the coil of wire and the bracket box.

    Refer to the conservatory roof plan supplied to show the position of the Tiewire.

    The bracket box will contain a pair of brackets, the tensioner and the dome nuts and washers for fixing the brackets to the rafters.The design of the brackets and tensioner may vary depending on the roof system.

    The Synseal (Global) roof uses 2 security bolts (84mm apart).Ensure these are tightened with an Allen key.Note: it is usual practice for the roof fabrication company topre-fit the two bolts in each rafter. Please refer to the seperatebracket position drawing for drilling and fixing should the bolts be supplied loose.

    Other roof systems use 4 bolts through the rafter drainage channel. Seal over the heads of the screws in the rafter drainage channel to reduce risk of leaks through the bolt holes.Note: it is usual practice for the roof fabrication company topre-drill the four bolt holes in each rafter. Please refer to the seperate bracket position drawing for drilling these holes should it not be done.

    Uncoil the wire from the box, note the different terminal at each end. One end should have a locknut fitted.

    Take the end without the locknut fitted and thread it into the pin through the slot in the bracket.

    Ensure the thread on this terminal goes all the way through the pin.

    Take bracket and attached wire to the rafter and fasten the bracket to the rafter bolts using the dome nuts and washers provided. Let wire hang down until you have fitted the opposing bracket.

    Fasten the other bracket (the one with the threaded stud pre-fitted) onto the opposing rafter on the other side of the conservatory roof. Use the dome nuts and washers provided.

    Take the tensioner and thread it onto the threaded stud 1 turn only (clockwise using end of tensionerwith red spot as shown in photo).

    Take the other end of the wire (the one with the lock nut fitted) andbring it across the roof to meet the tensioner.

    Insert the wire fitting into the tensioner and turn the tensioner clock-wise until the tensioner tightens equally onto both the wire fitting and the threaded stud.

    Keep tightening the tensioner until the slack is removed from the wire.Use the spanner flats on the wire fitting (to stop the wire rotating) until the wire becomes taught and the window frames are plumb.

    Pull down on the wire to relieve any ‘lock-up’ check the tension andtighten the two locknuts against the tensioner.

    Each Tiewire is made to measure. Should the wire length appear too long or short, check the internal width of the conservatory and the length of the wire against the sizes shown on the label (back of box). The wire length is measured between the spanner flats on each fitting.

    I N S T A L L A T I O N I N S T R U C T I O N S

    These instructions are provided for guidance only and Tiewire cannot be held responsible for theway in which the information in this instruction is interpreted.

    We reserve the right to alter specifications and descriptions without prior notice as part of ourpolicy of continual development.

    September 2009

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    26

  • Woods Lane, Cradley Heath. Warley. West Midlands. B64 7AS. Tel. 01384 820060 Fax. 01384 860150. Web. www.howellsglazing.co.uk

    Please could we have photo’s of your completed projects

    Email them to :- [email protected]