1 Hunts Point Interstate Access Improvement Project Contract 2 PIN X731.64, Contract No. D900051 Utility Information Meeting August 27, 2020

Upload: others

Post on 05-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

1

Hunts Point Interstate Access Improvement ProjectContract 2PIN X731.64, Contract No. D900051

Utility Information MeetingAugust 27, 2020

Page 2: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

2

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

Department’s Designated Representative for this Procurement is:

Chris NebralAttn: Hunts Point Interstate Access Improvement-Contract 2

Contract Management BureauNew York State Department of Transportation

50 Wolf Road, 6th FloorAlbany, New York 12232, USA

email: [email protected]

Page 3: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

3

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

Agenda

Project Overview

Utility Accommodation NYCDEP Water

NYCDEP Sanitary, Storm, and Combined Sewer

Questions and Answers

Page 4: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

4

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

Project Overview

New connection to

Concrete Plant Park

Page 5: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

5

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

General Scope of Work – Bruckner Viaduct Widening of the Bruckner Expressway Construction of 2 new ramp structures connecting Bruckner Expressway

WB to Leggett Ave. Structural strengthening Replacement of concrete bridge deck Concrete and Steel repairs Replacement of concrete bridge barrier Replacement of bearings and pedestals Structural Steel painting Concrete substructure sealing Removal of existing Ramp RE including superstructure, piers, abutment

and retaining walls

Page 6: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

6

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

General Scope of Work

Pavement rehabilitation including reconstruction and resurfacing Sidewalk and curb replacement Redesign of 15 local street intersections Installation of new traffic and pedestrian crossing signals Construction of a shared-use path Drainage Improvements Repairs to concrete retaining wall Stabilization of existing slopes

Page 7: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

7

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

Utility Contractual RequirementsThe Utility Contractual Requirements are located in the following Parts and

Sections of the Contract Documents:

Part 2 – DB Section 100

DB 101-02 Definitions of Terms: Utility terms are defined

DB 102-02 C. Subsurface Utility Quality Level

DB 104-04 B. Changes Applicable to Utility Relocations

DB 105-06 Cooperation with Utilities and other Contractors

Part 3 – Project Requirements

Section 12: Utilities

Section 21: Drainage

Part 4 – Utility Requirements

Part 7 – Engineering Data

Page 8: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

8

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

Utility Coordination – Existing UtilitiesIn accordance with Part 4 – Utility Requirements, the Design-Builder is responsible for:

Verifying utility facility locations

Identifying and resolving any conflicts not yet documented

Coordinating with utility owners for utility relocations

Providing stakeout and final layout of utility relocations

Protecting existing utilities

Cost to repair damages to utilities caused by the Design-Builder

Informing the Department of all meetings and correspondence with utility owners

Page 9: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

9

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

Utility Coordination Manager (Part 4 - Section 4.2.2)

Page 10: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

10

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

Existing Utility Info NYCDEP Water

Page 11: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

11

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

Existing Utility Info NYCDEP WaterDesign Builder Scope of Work (see HC-140 and plans for details)

• Coordinate with NYCDEP for final water main design in accordance with Design-Builder’s Design Solution

• Relocate designated water mains within the following areas: • 12” water main at the intersection of Bruckner Boulevard and East 149th Street• 20” water main at the Intersection of Bruckner Boulevard and Longwood Avenue

• Avoid damage and support and protect as necessary for all other facilities within the project area

• Adjust manhole castings at designated locations and as needed

• Relocate Hydrants, valves, and connections at designated locations

• All water main replacements shall follow NYCDEP restraint length requirements

Page 12: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

12

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

Existing Utility Info NYCDEP Sewer Relocation - 74”

x 75” Combined

Sewer

Page 13: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

13

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

Existing Utility Info NYCDEP SewerDesign Builder Scope of Work (see HC-140, Part 3 Section 12 and 21, and plans for details)

• Coordinate with NYCDEP for final drainage and sewer design in accordance with Design-Builder’s Design Solution

• Relocate existing 74”x75” NYCDEP away from the proposed Ramp BL.

• Avoid damage and support and protect as necessary for all other facilities within the project area

• Adjust manhole castings at designated locations and as needed

• Replace all existing frames and grates within the Boulevard limits of work

• The NYSDOT Contractor shall permanently provide supplemental storm sewer facilities as required for proposed roadway/bridge work and in accordance with the New York State Department of Transportation Highway Design Manual (NYSDOT HDM) Chapter 8 and New York State Department of Environmental Conservation (NYSDEC). The alignment of the New York City Department of Environmental Protection facilities shall be coordinated with New York City Department of Environmental Protection and constructed in accordance to all applicable New York City Department of Environmental Protection standards by the NYSDOT Contractor.

Page 14: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

14

Page 15: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

15

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

Anticipated Procurement Schedule

Page 16: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

16

RFP Documents: Instructions to Proposers Part 1: D-B Agreement Part 2: General Provisions, Section DB 100 and Appendices Part 3: Project Requirements (Scope of Work) Part 4: Utility Requirements Part 5: Special Provisions Part 6: RFP Plans (Directive and Indicative) Part 7: Engineering Data Part 8: Special Specifications (Including New DB Specifications) Part 9: The Design-Builder’s Proposal Part 10: RFP Addenda (If Any)

Reference Documents: On Department’s website (Not Part of the Contract Documents)

Hunts Point Interstate Access PIN X731.64, Contract No. D900051Request For Proposals (RFP) Documents

Page 17: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water

17

Responses to Proposer Questions will be posted on the Department’s Project Web Site.

Reference Documents are Posted on the Department’s Project Web Site:

https://www.dot.ny.gov/main/business-center/designbuildproject51

Hunts Point Interstate Access PIN X731.64, Contract No. D900051

Additional Information

Project Draft EIS Report;

Record Plans;

Boring Logs;

Utility Plates;

As-Built Utility Plans;

Potentially others (To be Determined)

Page 18: Hunts Point Interstate Access Improvement Project Contract ......Aug 27, 2020  · • 12” water main at the intersection of Bruckner Boulevard and East 149th Street • 20” water