hydro pump storage pp in estonia
DESCRIPTION
Energia salv. Hydro pump storage PP in Estonia. Energy sources in Baltics. Content. Content. Three distinctive modes of electricity generation represented on a large scale. Overview. Primary energy sources in Baltics (2009). - PowerPoint PPT PresentationTRANSCRIPT
Hydro pump storage PP in Estonia
Energiasalv
Energy sources in Baltics
Content Content
2
Overview Primary energy sources in Baltics (2009)
Oil shale91%
Natural gas7%
Other2%
Other3%Natural
gas20%
Imports30%
Hydro47%
Other3%
Hydro3%
Natural gas15%
Nuclear79%
Baltic electricity markets inherited powerful North-West Russian electricity system and are still largely isolated power markets from the rest of the EU
The trading in the Baltic electricity market is carried out by bilateral contracts between large utilities, not via spot-market, wholesale market practically non-existent
Estonian oil-shale based electricity production, albeit with relatively low energy efficiency, is a dominating energy source
Due to its environmental risks, lower competitiveness and limited amount1, the key issue is to reduce its consumption at the expense of renewable energy alternatives
By virtue of the electricity full liberalisation market program announced in 2007, 35% of Estonian energy market was set to be opened from 1 January 2009 and full opening is scheduled for 1 January 20132
Cost-based electricity pricing will be converted into market-based pricing
In Latvia electricity is generated mostly by three Daugava hydro power plants
Lithuanian energy production is substantially dependent on decommissioning of Ignalina nuclear power plant (INPP)
After the decommissioning of INPP Lithuania to rely heavily on local gas PP and electricity import, this is further exacerbated by lack of viable interconnections with Poland, Sweden and Finland
According to the EU directive, the remaining INPP unit 2 has to be decommissioned by the end of 2009
Source: Freenergy, Eesti Energia1) At the current extraction level of 40-50 million tonnes per year, it is estimated to last about the next 50-60 years2) Latvian and Lithuanian electricity markets are opened from 1.07.2007
Three distinctive modes of electricity generation represented on a large scale
Baltic electricity market
Primary origin of energy sources: Estonia – local oil-shale, Latvia – local hydro, imported energy and natural gas, Lithuania – nuclear and imported
Total annual gross power consumption amounts to around 29 TWh/year:
Estonia – 9 TWh/year
Latvia – 8 TWh/year
Lithuania – 12 TWh/year
Due to environmental reasons and physical amortization there will be shutdowns of several major power plants in Baltics
Lithuania to shut down Ignalina nuclear plant in 2009
Estonia to shut down ca 41% of capacity of oil shale power plants by 2016 (4x250 MW + 2x200 MW remains out of existing 2,380 MW)
Agreement on the construction of flue gas desulfurization installations on 4 Eesti Power Plant’s units was signed in March 2009
Although the new plants are planned to be developed, these will require large-scale investments and will not be probably completed before 2016
It is estimated that there will be a substantial gap between production and consumption capacities in Baltic states amounting to as high as 2,500 MW by 2017
In addition, 1,500 MW of capacities will be based on natural gas imported from Russia, being therefore with limited reliability and having upwards price pressure
Importance of the issues of “energy security” and “energy independence” is increasing
3
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
MW
Peak demand Installed capacity
Overview Energy production capacities and future imbalance, 2007-2015
Shutdown of Elektrenai Lithuanian Power Plant, 2007
Shutdown of Ignalina Nuclear Power Plant, 2009
Shutdown of old energy blocks in Narva Power Plants, 20151
Gap tp be filled
Source: Freenergy1) All old pulverised combustion boilers have to be closed by the end of 2015 according to EU Directive on the limitation
of emissions into the air from large combustion plants
Peak load is foreseen to grow at 4% per annum
Estonian electricity market full liberalisation, 2013
Production capacity shortage in the wake of worn-out infrastructure
Energiasalv
Interconnections in the Baltics
Content Content
Estonia
Latvia
Lithuania
Russia
Finland
Sweden
Belarus
Poland
Russia
4
Overview Grid connection in the Baltic states and actual power flow in 2007
650 MW350 MW
800 MW
400 MW
1,000 MW
1,000 MW
2,000 MW
2,000 MW
1,000 MW
700 MW
1,000 MW
Electricity system of all three Baltic countries is connected only to the IPS/UPS interconnection based on agreements with eastern neighbours Russia and Belarus, with the exception of Estlink (350MW), which is the only interconnection with EU network
Estlink 2 (650 MW) is planned to be built by 2013
Governments of the three Baltic States decided to work on the integration of the Baltic electricity market into CEE regional electricity market, UCTE
After decommissioning of Ignalina in 2009, the trading and thus, the usage of pan-Baltic electricity connections is expected to increase considerably
Baltic transmission capacity is limited to around 900-2,200 MW, implying 300-750 MW import capacity per country from third countries
From 2010 the grid capacity becomes insufficient if no new power plants will be built. Such a situation might lead to disruptions in electricity supply and limitation on power imports within the Baltic countries
In order to adjust to the changing environment, especially the closure of Ignalina, besides the new links to neighbouring countries, additional links are considered
Planned new interconnections:2010 Fennoscan 2: Finland-Sweden 500/800 MW2011-2013 Estlink-2, 650 MW2013-2016 Lithuania-Poland, 1000 MW2015-2016 Lithuania-Sweden, 700MW Possibly additional Latvia-Sweden and/or Estonia-Sweden links will be built
Existing grid connection
Planned grid connection
Exported: 707 GW
Imported: 442 GW
Net export: 265 GW
Exported: 3 GW
Imported: 478 GW
Net export: -475 GW
Exported: 2,016 GW
Imported: 19 GW
Net export: 1,997 GW
Exported: 1,524 GW
Imported: 195 GW
Net export: 1,329 GW
Exported: 376 GW
Imported: 200 GW
Net export: 176 GW
Exported: 2,001 GW
Imported: 3,603 GW
Net export: -1,602 GW
Exported: 1,392 GW
Imported: 3,239 GW
Net export: -1,847 GW
Exported: 1,978 GW
Imported: 852 GW
Net export: 1,126 GW
Source: Baltso
Transmission capacity to outside Baltics is limited
Energiasalv
Balancing capacities needed
National Electricity Development Strategy sets the target of wind energy installed capacity of 900 MW by 2018
Significant share of wind energy in the country’s electricity balance leads to the eminent need for wind farms’ balancing capacities
The Strategy envisages building up 1 800 MW of reserve and wind parks’ balancing capacities by 2018
Wind balancing: 900 MW
Peak-load reserve: 300 MW
Emergency reserve: 600 MW
Possibilities to balance wind energy with other countries’ electricity systems are limited due to insufficient grid connections
Need for internal solution for balancing and maintaining the reserve capacities
5
Overview Need for reserve and balancing capacities in Estonia
1 700 MW of reserve and balancing capacities to be built
MW
Energiasalv
Balancing electricity prices
Significant fluctuations in Estonian balancing electricity prices
Average price of the most expensive 1 000 hours in 2009 was EUR 59/MWh, while the average price of the cheaperst 1 000 hours was EUR 15/MWh, meaning the spread of 44 EUR/MWh
As wind energy will play more importnat role in country’s electricity generation, the respective spread is projected to increase due to fluctuating nature of wind energy production
Limited interconnection capacity of the Baltics with UCTE and the start of free trading with electricity should contribute to the increase in the spread
Large and even increasing in the future spreads in electricity prices would support the business model of hydro pump storage power plant that would sell electricity when prices are high and buy it when prices are low, thus generating profits on the price spread
6
Balance electricity price fluctuations in Estonia (2009)
Source: Elering
Average price of the most expensive 1 000 hours EUR 59/MWh
Average price of the cheapest 1 000 hours EUR 15/MWh
Spread EUR 44 /MWh
Electricity price spread to increase in the upcoming years
Energiasalv
Hydro pump storage power plant
7
Hydro pump storage power station – most efficient way for balancing wind farms
Projected 500 MW installed capacity
Upper reservoir is the Baltic sea, while the lower reservoir is a granite mine
Synergy created with granite mining
The power plant is projected to be commissioned by 2017
Geological studies, EIA and preliminary design
To set up a granite cluster in cooperation with Estonian Road Administration
Need to agree the subsidy scheme with the government
ǺF carried out pre-feasibility study
LOI signed with the Port of Tallinn regarding the land plot
Efficient logistic site for granite realisation
Upper reservoir would be Gulf of Finland
Port territory is industrial land according to the detail plan
Seawater intake scheme design completed
Ideal solution for provision of balancing power to wind energy
Pump storage sells electricity at high prices
Hours in a year
Sp
rea
d
Distribution of electricity pricesProject snapshot
Activities so far
Next steps
Pump Storage power plant design
Pump storage buys electricity at low prices
Energiasalv
Hydro pump storage power plant
Need for wind energy balancing capacities in the region
Ideal solution for balancing of wind farms and as a reserve capacity station due to short start-up times
Low investment per MW due to low cost of reservoirs
Synergy arising from granite mining
No reliance on imported resources, no gas
Strong project with positive impact on the environment
Strong bussiness concept Positive impact on the environment
Realisation of the hydro pump storage would allow reducing production of energy from oil shale, meaning significant reduction of CO2 emissions
Expected CO2 reduction per annum: 1,5 MT of CO2
Hydro pump storage with contemplated capacity of 500 MW would allow1,5 TWh production of wind energy per annum
No CO2 emissions and no related expenses
Preliminary design
Upper reservoir
Lower reservoir
Maintenance tunnelHigh pressure pipe
Low pressure pipe
Turbines
Electrical grid tunnel Lift
Management centre
Sub-station Entrance to maintenance tunnel
Energiasalv
Hydro pump storage power plant
9
Planned location of the station is Muuga Port
Good grid connections in the planned location
Preliminary land agreement with Port of Tallinn signed
Contemplated location
Location on the Baltic sea coast with good grid infrastructure
Energiasalv
Project developer: Energiasalv
10
Vardar Eurus
35% EBRD
65% Estonian private investors
70% Vardar A/S
30% NEFCO
Freenergy
25% 25%
Inve
stor
s
Management of 4E50%
4 Energia is focused on developing renewable energy projects and operating wind parks
Vardar Eurus AS, a company registered in Norway, is 70% owned by Vardar, a Norwegian power company, and 30% by NEFCO, the Nordic Environment Finance Corporation
NEFCO is an international finance institution established by 5 Nordic countries with operations in CEE countries, Russia, Belarus and Ukraine, its portfolio comprises nearly 300 small and medium-sized projects in different sectors
Organizational structure
Energiasalv
Hydro pump storage project Developer
Voolu Energia
Competence in granite miningCompetence in development and management of renewable energy
projects
Energiasalv
Experienced project development team
11
Martin Kruus(CEO of 4 Energia)
Education: Tallinn Technical University - Thermal Engineering
Previous employment:Eesti Energia, Director of Business Unit of Renewable Energy. Main responsibility was to establish and run
power plants using renewable energy sources – wind, hydro, biomassMinistry of Economic Affairs, Department of Management of State CompaniesEstonian Privatization Agency, Project Manager for IPO’s
Main accomplishments: Renovation of Estonian biggest hydro power plant – Linnamäe HPP Building of Estonian first wind park – Virtsu wind parkSeveral feasibility studies and project management about CHPs
Lembit ValiEnergiasalv CEO
Kalle Kiigske(CFO of 4 Energia)
Education: Estonian Business School – Banking and Financial Management
Previous employment:United Partners Group, Pan-Baltic investment bank, Partner, responsible for merchant banking and investmentsAS Hansa Capital – leading asset-based finance company in the Baltics, Russia and Ukraine with total assets over EUR 1,7 billion, Hansa Capital is the industry’s largest company in Eastern Europe and among top 50 in Europe, Member of Board and Head of Factoring and Trade Finance Several positions in Factor Chain International (Amsterdam, the Netherlands) - Member of the Communication Committee, Member of the Internal Audit
Education: Tallinn Technical University – Electrical Engineering
Previous employment:Elering, Estonian national grid company – CEOEstonian Energy – Technical Director, a member of the management boardNarva Elektrijaamad (Narva Power Plants) - CEO
Main accomplishments: Extenstive experience in power industry since 1973Worked on top management positions in energy sector for 18 years
foto
foto
foto
Hands-on experience in renewable energy and granite mining
Peep SiitamVoolu Energia CEO
Education: Tallinn Technical University- M.Sc. in civil engineering Estonian Business School - MBA
Previous employment:Vool - Co-founder of of the company having majority shareholding in Maardu Granite MineMerko Mines - Chairman of the management boardEstonian Energy Technology Program - Program Manager
Main accomplishments: Chartered Engineer since 1998Substantial experience as a member of top management in the Baltic leading construction companies
foto
Energiasalv