hywind scotland - assembly and logistics presented by hege … stavanger... · 2016-04-08 · role...
TRANSCRIPT
Hywind Scotland - Assembly and logistics Presented by Hege Eskild NorSea Group
Role in Hywind Scotland Pilot Park
• My name is Hege Eskild, operation engineer in the NorSea Group
project organization
• NorSea Group awarded the base contract for Hywind Scotland
• AS Stordbase will be the used
• NorSea Dusavik was involved with the installation of Hywind Demo
Contents of this presentation
• About the Floating Wind Turbine
• Why assemble onshore
• Scope of work at Stordbase
• Challenges
Size of the Floating Wind Turbine
The Floating Wind Turbine
The FWT consist of
Spar substructure
4 Tower sections
3 Blades
Hub
• Tower section 83 m high, total weight of 668 tonnes
• Blade diameter of 154 m, total weight of 90 tonnes
• Nacelle weight 235 tonnes
• Hub weight 95 tonnes
Why assembly onshore?
• Too large movements on for assembly offshore
• Hywind Demo assembled inshore with barge
and crane
• Size Hywind Pilot Park making inshore
assembly challenging and expensive
Assembly at Stordbase
Location of Stordbase
Scope of work at Stordbase
• Providing a “tool box” for Statoil and other subcontractors
• Quay for offloading parts and equipment
• Storage and transport of all equipment
• Offices and accommodation
• 5 Erection stand for tower and turbine
assembly
• Crane for heavy lifting
• Transport routes on base
• Security
Technical challenges - Erection Stand • For assembly of tower and turbine
sections • Ground investigated will be required
for this construction • 100 year wind requirements • Holes necessary for bottom tower
section guiding pins • Area and placements requirements due
to idling and yaw motions
Technical challenges - The guiding system
• Two guiding pins on bottom tower section
• Guiding pins used for mating lift onto
substructure
• The erection stand must be designed for
these pins, and possible movements of pins
during lift of
• Challenges with this lift:
1. The weight of the turbine
2. Center of gravity if placed forward,
meaning the turbine will tip when lifted
3. Small unforeseen movements can damage
the guide system making the mating
impossible
• All parts transported by vessel
• Ro-Ro and crane offloading
• Main crane necessary for all lifting of
parts
• Use of Self-Propelled Modular
Transport (SPMT)
• Offloading parts at storage without
use of main crane
Technical challenges - Transport and Storage
Technical challenges – Storage and assembly sequence
• Logistics challenges with storage plan and
assembly sequence
• Central storage area close to assembly site
• Assembly sequence in accordance with
assembly sequence
• Area requirements for blade and hub
assembly
• Other considerations: Crane and SPMT
usage, offloading method, transport routes,
etc.
• One big puzzle
• Tower section assembled one by one
• Blades and hub assembled before lift
• Final lift approximately 100 meters high
• Crane cannot crawl during lift
Technical challenges - Tower and turbine erection
And the things you didn’t think of beforehand
• How to install a lightning rod on a 160 meters wind turbine?
• What will happen to the sewage pipes when 300 tonnes crane drives
over them?
• Different operators at the same area, what if someone plans too
construct a building at the same area you plan to use?
• What do you do when the Ministry of Foreign Affairs has reserved all
available floatels due to the current refugee crises?
Questions?