iaea conference-31-05-2010 1 management of radioactive waste and spent fuel in germany ulrich alter,...

47
IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety Bonn, Germany

Upload: josephine-peters

Post on 01-Apr-2015

214 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 1

Management of Radioactive Waste and Spent Fuel in

Germany

Ulrich Alter, Federal Ministry for the Environment

and Nuclear Safety Bonn, Germany

Page 2: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 2

Content

Inventory of Spent Fuel Balance of Reprocessing vitrified high active waste from

reprocessing on–site storage facilities Reuse of Plutonium as MOX – fuel

Page 3: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 3

Amounts of Spent Fuel (December 2009)

Since the commissioning of the first nuclear power reactor in 1960 until the end of 2009 a total of about

13,000 tonnes of spent fuel has been produced in Germany.

Page 4: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 4

Annual unloading per reactor: 15 to 30 tHM/a Total annual production in Germany: 50 … 400 tHM/a Produced by end 2009: 13,097 tHM Storage (December 2009): 6,427 tHM Reprocessing 6,670 tHM Expected quantity produced by 2025: ~ 17,200 tHM

Production of Spent Fuel

Page 5: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 5

Amounts of Spent Fuel (December 2009)

The major part of the fuel has been shipped to Cap de la Hague, Sellafield and Mayak for reprocessing, a total of 6,670 tonnes of spent fuel.

At the end of the year 2009, roughly 6,430 tonnes of spent fuel were stored in domestic wet or dry storage facilities. 3,420 tonnes (53 % of the quantity) were stored in wet storage pools, particularly in the reactor buildings.

Page 6: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 6

Amounts of Spent Fuel (December 2009)

The remaining 3,010 tonnes (47 % of the quantity) were stored in casks at dry storage facilities

Ahaus, Gorleben and Lubmin 12 on-site storage facilities

Page 7: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 7

Balance of Reprocessing

Page 8: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 8

Balance of Reprocessing

The shipments to the reprocessing facilities were based on contracts that had been concluded in 1979 and once more in 1989 by the German utilities with COGEMA and BNFL covering the reprocessing of spent fuel assemblies from German nuclear power plants.

Page 9: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 9

Balance of Reprocessing

The contracts contained obligations to take back radioactive wastes and the separated Plutonium.

A relatively small amount of spent fuel (nearly 200 tonnes) had been reprocessed between 1971 and 1990 in the domestic pilot reprocessing plant at Karlsruhe.

Page 10: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 10

Shipments of Spent Fuel

The very first shipment to the reprocessing facilities La Hague in France and Sellafield in United Kingdom started in 1973.

The final delivery of spent fuel assemblies was terminated on July 1st, 2005.

Page 11: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 11

Shipments of spent fuel to AREVA NC

t SM pro Jahr

0

50

100

150

200

250

300

350

400

1976 1977 1978 1979 1980 1981 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007

Page 12: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 12

Balance of Reprocessing

With regard to the quantities of spent fuel contracted for reprocessing between the German utilities and the reprocessing plants

of Cogema (5,400 tonnes) and BNFL (850 tonnes), most of the separated plutonium will

arise in France

Page 13: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 13

Balance of Reprocessing

From nuclear power plants in the eastern part of Germany

a total amount of

293 tonnes of spent fuel was sent to the reprocessing facility in

Mayak.

Page 14: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 14

Vitrified high active waste from reprocessing facilities

Page 15: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 15

Vitrified high active waste from the reprocessing

The radioactive waste streams that will return to Germany started in 1996.

The largest part of waste comes from France. Roughly 80 % of the vitrified high active waste from the reprocessing of spent fuel from German nuclear power plants in France was shipped during the last years - from 1996 to 2008 - to the interim storage facility in Gorleben

(86 casks with 2408 canisters).

Page 16: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 16

Vitrified high active waste from the reprocessing

It is planned to ship the residual vitrified waste from France back to Germany until 2011 - exactly 11 casks in 2010 and the last 11 casks up to the end of the year 2011.

Shipments from the UK are expected to start in 2014 / 2015.

Page 17: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 17

Shipment of 12 CASTOR-HAW-Casks, TBL Gorleben in 2006

Page 18: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 18

Returning Reprocessing Wastes

Gorleben interim storage facility, the storage facility for vitrified waste from reprocessing

Page 19: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 19

Page 20: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 20

on-site storage facilities

Page 21: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 21

on-site storage facilities

Since 1983 nuclear licences had been granted for GORLEBEN and AHAUS,

central storage facilities for spent fuel assemblies.

The first shipment with CASTOR-casks started in 1993 to AHAUS and in 1995 to GORLEBEN.

Page 22: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 22

on-site storage facilities

By the end of 2003, nuclear licences had been granted for on-site storage facilities for spent fuel assemblies at twelve nuclear power plant sites. They are designed as dry storage facilities in which transport and storage containers loaded with spent fuel assemblies are emplaced.

Page 23: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 23

on-site storage facilities

Starting in 2007, all on-site storage facilities went into operation.

In 2005, the operator of the Obrigheim nuclear power plant applied for a licence for dry on-site storage of a small number of 15 casks.

Page 24: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 24

on-site storage facilities

The Federal Office for Radiation Protection is the competent authority for the licensing of spent fuel storage facilities. According to Section 6 para. 2 no. 4 Atomic Energy Act, it has to be proven that necessary protection against external events exists.

Page 25: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 25

on-site storage facilities

This includes the crash of a large aircraft onto the spent fuel storage facility.

Expert calculations – carried out as a reaction to the events of September 11th, 2001 – proved that in case of the crash of a large aircraft safety can be guaranteed.

Page 26: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 26

on-site storage facilities

The capacities of the storage facilities are different.

Limitations exist for the duration of storage, the number and type of fuel casks, the thermal capacity and the total activity.

Page 27: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 27

Power Plant Mass [Mg] No. of casks

Biblis 1400 135

Brokdorf 1000 100

Brunsbüttel 450 80

Grafenrheinfeld 800 88

Grohnde 1000 100

Gundremmingen 1850 192

Isar 1500 152

Krümmel 775 80

Lingen 1250 130

Neckarwestheim 1600 151

Philippsburg 1600 152

Unterweser 800 80

14;025 1;440

Page 28: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 28

on-site storage facilities

Page 29: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 29

on-site storage facilities

Two different design concepts for the storage building, the WTI and the STEAG concept, are applied for the storage of spent fuel in Germany.

The two concepts are not fundamentally different but represent alternatives of the same basic concept.

Page 30: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 30

on-site storage facilities

The use of either the STEAG concept or the WTI concept was the decision of the applicants. Both concepts fulfil the requirements for the safe storage according to the Atomic Energy Act.

Page 31: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 31

on-site storage facilities

The transport and storage casks guarantee that the main safety criteria are met. The main function of the storage hall is to provide protection against weather conditions and to assure heat removal.

Page 32: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 32

on-site storage facilities

It should be mentioned that beside the STEAG and WTI concepts an individual tunnel concept is being used at Neckarwestheim.

This special underground solution was developed to accommodate the specific site situation of the nuclear power plant.

Page 33: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 33

on-site storage facilities

The licensing requirements for the storage facility of spent fuel from VVER-440 reactors in the eastern part of Germany were the same as for spent fuel from other reactors.

The transport and storage casks for VVER-440 spent fuel assemblies are licensed or approved according to the German transport regulations which are fully consistent with the IAEA transport regulations TS-R-1.

Page 34: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 34

on-site storage facilities

The last spent fuel assemblies from the wet storage facility

(Central Waste Storage Nuclear Fuel, ZLN) in Greifswald / Lubmin

were transferred to the ZLN dry storage facility at the same site on 15-06-2006.

Page 35: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 35

Storage Facilities (1/4)

Interim Storage Facility Emsland, STEAG

Page 36: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 36

Storage Facilities (2/4)

Interim Storage Facility Emsland

Page 37: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 37

WTI, Gundremmingen (3/4)

Page 38: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 38

Tunnel – concept, GKN (4/4)

Page 39: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 39

wet storage facility, ZAB

dry storage, Z L N

Page 40: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 40

Plutonium as MOX - Fuel

Page 41: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 41

Reuse of Plutonium as MOX - fuel

This will ensure that during the remaining operation time of the German nuclear power plants the recovered Plutonium will be in total processed into mixed-oxide (MOX) fuel assemblies and subsequently irradiated in the existing nuclear power plants.

Page 42: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 42

Reuse of Plutonium as MOX - fuel

About 40 tonnes of fissile plutonium will be separated by reprocessing of German spent fuel. About 965 tHM of fresh MOX fuel are already or will be fabricated from these 40 tHM of fissile Plutonium. After reuse in nuclear power plants in Germany, which have a license to use MOX, the spent MOX fuel will be stored until final disposal.

Page 43: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 43

Reuse of Plutonium as MOX - fuel

The reuse of Plutonium as MOX fuel in the past and in the future is the basis for a step by step reduction of the German Plutonium inventory.

Page 44: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 44

… use of MOX – Fuel, 1986 to 2016

Page 45: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 45

0

5000

10000

15000

20000

25000

Pro

per

ty o

f P

u-f

iss

[kg

]Reduction of Pu-fiss Stock by Use of MOX Fuel

Page 46: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 46

Ongoing Reuse of Separated Plutonium

Sufficient capacity in German Nuclear Power Plants for reuse

Possible delay only if problems in MOX Fuel Facilities arise

Transfer of all separated Plutonium in MOX fuel elements expected until 2014

All spent MOX fuel elements in fuel pools expected until 2017/2018

Page 47: IAEA Conference-31-05-2010 1 Management of Radioactive Waste and Spent Fuel in Germany Ulrich Alter, Federal Ministry for the Environment and Nuclear Safety

IAEA Conference-31-05-2010 47

Thank you very much

for your attention