Waterview Connection -The Final Drive to completion
Annual Australian Tunnelling Conference – Sydney 2016
Iain Simmons – Alliance Project Manager, Well-Connected Alliance
David Taylor – M&E Construction Manager, Well-Connected Alliance
11th October 2016
![Page 2: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/2.jpg)
Waterview Connection –The Final Drive to Completion
1. (Re)Introduction to the project
2. Recap on tunnel facts
3. TBM final breakthrough
4. TBM de-mobilization
5. Status across the three distinct project zones
6. Cross passage completion
7. M&E fit-out to the tunnels and ventilation buildings
8. Timeline for completion
9. Community legacy
10. Questions
Contents
![Page 3: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/3.jpg)
Key Auckland transport links- Less than 2km wide isthmus
- Traffic running through congested central corridor
- Overly dependent on central, single north-south spine
- Network “ladder” model adopted
Western Ring Route- One of the NZ Governments seven roads of
national significance (RONS)
- Waterview Connection is the missing link between SH 20 and SH 16
- Completes 48km motorway ring route for the NZ Transport Agency
- Links major population and industrial centres
Waterview Connection- 5km of new motorway
- 2.4km of which comprises two three lane tunnels
Project Costs- NZ $1.4 Billion – the country’s biggest roading
project
(Re)Introduction to the Project
![Page 4: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/4.jpg)
![Page 5: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/5.jpg)
Tunnel Section – Connecting State Highway 16 with State Highway 20
Tunnel Facts
• Southbound length 2398m
• Northbound length 2410m
• Internal dia. 13.1m
• 3 traffic lanes each direction
• Max. vertical grade 5%, curve min. radius 1,500m
• 18 Cross-passages linking both main tunnels together, spaced every 150m
![Page 6: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/6.jpg)
Tunnel LayoutCross Section
M&E
Traffic Envelope
Lining
Pavement
Stage 2 Backfill
Stage 1 Backfill
Service Culvert
![Page 7: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/7.jpg)
Tunnel during excavation
![Page 8: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/8.jpg)
Completing the Northbound TunnelTBM Breakthrough
![Page 9: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/9.jpg)
De-commissioning the TBM
Completing the Northbound Tunnel
![Page 10: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/10.jpg)
Completing the Northbound TunnelDe-commissioning the TBM
![Page 11: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/11.jpg)
Completing the Northbound TunnelDe-commissioning the TBM
![Page 12: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/12.jpg)
Completing the Northbound TunnelDe-mobilisation of the TBM
![Page 13: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/13.jpg)
Great North Road Interchange (GNRI)
• 4 new Highway Bridges linking with State Highway 16
![Page 14: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/14.jpg)
GNRI Current Status
![Page 15: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/15.jpg)
Southern SectionAerial view looking South
![Page 16: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/16.jpg)
Finishing the Southern Approach PortalSouthern civils entering final stages
![Page 17: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/17.jpg)
Cross PassagesLogistical challenge of 16 cross passages
![Page 18: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/18.jpg)
Cross PassagesExcavation – monitoring load transfer
![Page 19: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/19.jpg)
Cross PassagesShotcrete primary support
![Page 20: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/20.jpg)
Cross PassagesWaterproof lining
![Page 21: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/21.jpg)
Cross PassagesInvert Formwork
![Page 22: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/22.jpg)
Cross PassagesCross PassagesCollar Reinforcement
![Page 23: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/23.jpg)
Collar Formwork
Cross Passages
![Page 24: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/24.jpg)
Completed cross passage ready to hand over to the M&E team
Cross Passages
![Page 25: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/25.jpg)
Completing the paving
What’s happening underground right now?
![Page 26: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/26.jpg)
Completing the M&E Installation
What’s happening underground right now?
![Page 27: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/27.jpg)
M&E Fit-out
• Main challenges and lessons learnt
• Ngarara - The drilling gantry
• M&E fit-out Scope of works
![Page 28: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/28.jpg)
Black roof 86,000m2
Tunnel Painting
White walls 48,000m2
![Page 29: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/29.jpg)
• Tunnel Anchors (Approximately 36,000 post installed mechanical anchors in bored tunnel)
• Supports (Approximately 8,600 supports in bored tunnel)
• Typically support groups located (longitudinally) in the centre of every ring, skipping every third ring, e.g. 2m, 2m, 4m spacing
Tunnel Supports
![Page 30: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/30.jpg)
• Tunnel lighting (4000)
• PA Speakers
• Radio Rebroadcast (RRB)
• Dynamic signage
Tunnel Systems
• Speed Cameras
• CCTV
• Overhead detection and barrier gates
![Page 31: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/31.jpg)
• Fire deluge and hydrants (175 sprinkler zones, 109 double hydrant outlets)
• Jet Fans (62)
• Sliding egress doors (36)
• LHD Cable (10km)
Fire Life Safety
![Page 32: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/32.jpg)
• Tunnel and culvert cable support system (50km cable tray)
• HV, LV, data and comms cabling (270T, 400km)
• 8 Transformers, 4 x 22kv Switchgear Panels, 8 x LV 690V/415V MSB, 4 x UPS Units, 500 Batteries, 64 x XP DB’s, 40 x RIO’s
Electrical Distribution
![Page 33: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/33.jpg)
• Exhaust Fans (8)
• Maintenance Hoists (17)
• HVAC
• Fire alarm, gaseous suppression and foam suppression systems
• 3 drainage sumps (13 pumps)
• Fire water storage tanks (5)
• Fire water pumps (5)
Vent Building Systems
![Page 34: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/34.jpg)
Challenges and Lessons Learnt
Design
• Subcontractor design
• Inter disciplinary coordination
Procurement
• Procurement packages
• Overseas supply and lead times
• Seismic compliance
Construction
• Planning & coordination amongst teams
• Storage & site facilities
Commissioning
• FAT
• Systems completion and handover
• Programme
![Page 35: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/35.jpg)
Challenges and Lessons LearntDesign
• Subcontractor design
• Inter disciplinary coordination
• Construction and stakeholder review
Procurement
• Procurement packages
• Overseas supply and lead times
• Post award Subcontractor submittals
• Seismic compliance
Construction
• Resourcing
• Construction area handover
• Planning & coordination amongst teams
• Storage & site facilities
Commissioning
• FAT
• Systems completion and handover
• Programme
![Page 36: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/36.jpg)
Ngarara – The Drilling Gantry
![Page 37: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/37.jpg)
Ngarara – The Drilling Gantry
![Page 38: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/38.jpg)
Ngarara – The Drilling Gantry
![Page 39: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/39.jpg)
Overall Project Programme
October
2016
![Page 40: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/40.jpg)
Waterview Playground
Community Benefits – already in use
![Page 41: Iain Simmons & David Taylor - Well Connected Alliance](https://reader031.vdocument.in/reader031/viewer/2022022203/5873bc521a28abbc788b5927/html5/thumbnails/41.jpg)
Boardwalks, Shared paths, Skate parks, BMX tracks
Community Benefits – more to come