implementing ims for project management
TRANSCRIPT
Instructional Management System Implementation
Project Plan
Prepared By:
Sachin Bajracharya
Paul Michalek
Ruben Shrestha
Laikun Tang
Instructional Management System Implementation Project
TABLE OF CONTENTS
Executive Summary......................................................3
Statement of problem/ opportunity................................5
Goal statement.............................................................7
Definition of objectives..................................................9
Task descriptions........................................................11
Project Hierarchy (WBS)..............................................16
Project priorities.........................................................18
Risk Assessment.........................................................22
Task assignments including the responsibility matrix.....29
Resources..................................................................31
Scheduling.................................................................33
Illustration and explanation of Gant Charts and Network 35
Budgeting, including Earned Value Analysis...................39
Simulation..................................................................42
Probability of project completion within the deadline............
47
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 2
Instructional Management System Implementation Project
Instructional Management System Conversion
Executive Summary
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 3
Instructional Management System Implementation Project
EXECUTIVE SUMMARY
In 1999, Minnesota State Colleges and Universities (MnSCU) campuses and the Office of the
Chancellor completed an RFP evaluation process to select an instructional management
system (IMS). Though a single statewide IMS platform was preferred at that time, the
decision was made to contract with three vendors (Anlon, Blackboard, and WebCT).
As the three system contracts were nearing expiration, an IMS of the Future Task Force was
established. Three years ago, multiple choices were given because there did not seem to be
any product that was a leader. As the result of the RFP process, the Evaluation Team and the
Academic Software/Systems Committee recommended Desire2Learn (D2L) as the e-
Learning platform for the single IMS platform to be hosted and supported by the Office of the
Chancellor. The Leadership Council endorsed these recommendations and October 13, 2003,
a software License Agreement was signed with Desire2Learn.
Metropolitan State University has chosen to be at the forefront of the MnSCU institutions
that are moving to the D2L platform. This purpose of this project is to rollout the successful
delivery of D2L at Metropolitan State University to meet the Web-based learning needs of
the students system-wide. The goal is to have a fully developed and tested D2L learning
platform available by the start of fall term 2004.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 4
Instructional Management System Implementation Project
Instructional Management System Implementation
Statement of Opportunity
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 5
Instructional Management System Implementation Project
STATEMENT OF PROBLEM/OPPORTUNITY
After a careful and lengthy evaluation of various instructional management systems (IMS)
Metropolitan State University’s parent institution (Minnesota State Colleges and Universities,
MnSCU) has selected new IMS platform called Desire2Learn (D2L). This platform has been
determined to be the best solution to address the fast growing demand for universities to
offer better quality instruction and more courses via the internet.
The new IMS needs to be implemented at Metropolitan State University in a relatively short
timeframe and must address the following areas of concern:
Migrate existing courses from old IMS and create new course into the new IMS
Integrate various relevant technologies into the new IMS structure
Train existing faculty, student and staff on how to use the new IMS effectively
Setup a defined structure for campus-wide support and services
Define processes and procedures to ensure effective use by various user groups
such as faculty, students and staff.
Successful implementation of D2L will put Metropolitan State in a position to be competitive
with the best higher-education institutions in its online course offerings nation-wide. This will
in turn allow Metropolitan State more effectively meet its institutional missions of providing
accessible high quality education to its students.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 6
Instructional Management System Implementation Project
Instructional Management System Implementation
Goal Statement
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 7
Instructional Management System Implementation Project
GOAL STATEMENT
Achieve successful implementation new IMS Desire2Learn at
Metropolitan State University by August 1st, 2004 within a budget
of $100,000.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 8
Instructional Management System Implementation Project
Instructional Management System Implementation
Definition of Objectives
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 9
Instructional Management System Implementation Project
PROJECT OBJECTIVES
1. Complete project to specifications by August 1st, 2004.
2. Complete project to specifications within total budget of $100,000.
3. Migrate all existing courses from old IMS and create new courses into new IMS.
4. Train faculty student and support staff how to effectively use tools within the
structure of the new IMS.
5. Develop dependable and proactive support structure to assist in migration,
communication, on-going training and maintenance of new IMS once it has been
implemented.
6. Develop processes for both faculty and student end-users to effectively use the
IMS.
7. Create a fully-integrated seamless system with stable and secure system
environment.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 10
Instructional Management System Implementation Project
Instructional Management System Implementation
Task Descriptions
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 11
Instructional Management System Implementation Project
TASK DESCRIPTIONS
Objective 1:
o Complete project to specifications by August 15th, 2004
Objective 2:
o Complete project to specifications within total budget of $100,000
Objective 3:
1) Create Courses
o Create naming convention for courses that closely matches course schedule
and is most useful (includes as much information as needed).
o Create hierarchy for courses in order to keep track of courses in Colleges,
Schools and Departments.
o Enable the tools necessary for University use and disable tools that are not
going to be used.
o Produce and label different access rights to different layers of users.
o Produce template for University portal level and use Cascading Style Sheet
(CSS) for general formatting (i.e. Text, layout, and media).
o Produce templates for each level of organization (i.e. Department, College
etc.). Use CSS to enhance the different designs for each level.
o Produce useful widgets such as RSS feeds for University and organization level
(e.g. Widgets for campus-wide news, weather-related news, and content-
related material).
2) Course Content Migration
o Set up process to migrate content after deciding how to approach transfer of
content from WebCT to D2L. The options available were to use special IMS
export tools or use regular proprietary IMS tools.
o Train Graduate Assistants (GA) to migrate content.
o Track and document GA workload and course migration.
o Track type of courses (i.e. New courses, Master courses, courses in live in
WebCT, courses archived in WebCT), course categories, instructors and
migration status.
o Crosscheck courses and their content after migration is complete.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 12
Instructional Management System Implementation Project
o Get material from faculty for new courses and enter into courses.
3) Migrate Other Tools (Quiz/ Exam) specific materials
o Select migration tool for most efficient and effective transfer of quiz content
from previous IMS to new.
o Transfer questions per course.
o Crosscheck content after migration is complete.
4) Integrated Student Registration System Integration with D2L system.
o Receive final product for Course Schedule offered by University. (This is a
task conducted by the respective college departments in University)
o Set up screen to migrate course Integration so that necessary courses in ISRS
are integrated with D2L courses automatically.
o Run automated process for course shell.
o Run system integration automated process for courses.
o Populate students through automated process making sure they are in the
correct access right.
Objective 4:
5) Create Demo Course
o Create a course and include the main tools for demonstration.
o Prepare the Navigation and D2L environment for demonstration.
o Create Content for demonstration.
6) Conduct Demo
o Set up Demonstrations by education departments.
o Prepare feedback form.
o Get feedback from faculty for the D2L demo and D2L use in general. Material
from the feedback can be used for FAQ.
o Prepare worksheet forms for faculty to fill out.
o Get worksheet per faculty per course.
7) User Guide
o Create user guide/ reference for faculty.
o Create user guide/ reference for Staff.
o Create user guide/ reference for Students.
o Include in website.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 13
Instructional Management System Implementation Project
8) Student Training
o Conduct D2L Overview training.
o Conduct Tools training.
o Handout user guide including registration process.
9) Faculty Training
o Conduct D2L Overview training.
o Conduct Tools training.
o Conduct advanced training
o Handout user guide including registration process.
10) Train Support staff
o Create user accounts with specific rights.
o Train basic D2L and FAQ.
o Give support documentations (guide, FAQ, and website URLs).
11) Rich Media Training
o Get general consensus for rich media demand and style.
o Choose format for delivering rich media (i.e. Flash, Shockwave, videos,
screenshots, photos, screenshots)
o Create and conduct Demos (For each method chosen).
o Create a process for requesting and a request Form. Include in website.
Objective 5:
12) Set up FAQ
o Collect Question and divide into topics from demo and training sessions.
Answer questions and refer (link) to user guide.
o Set up user accounts FAQ.
o Set up Metropolitan State Policy for Use of IMS FAQ.
13) Create Website
o Information and Layout Design
o Build the website as a part of the existing Center For Online Learning website.
Include necessary forms.
o Include support, training, and user guide material.
o Test development for functionality, usability and accessibility.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 14
Instructional Management System Implementation Project
Objective 6:
14) Create Faculty/ Student User Process
o Create a process for course account. This process will allow a d2l domain for
valid courses.
o Create a process for faculty account. This process will allow a faculty member
to use d2l domain with proper access for valid courses.
o Create a process for student user account. This process will allow students to
be registered for valid courses offered online.
o Create Instructions for the above user process.
Objective 7:
15) Outsource/Contract IT Tasks
o House D2L applications
o Setup Windows server
o Configure network
o Configure systems
o Integrate other utilities
o Integrate email client
o Portal integration
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 15
Instructional Management System Implementation Project
Instructional Management System Implementation
Project Hierarchy(Work Breakdown
Structure)
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 16
Instructional Management System Implementation Project
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 17
Instructional Management System Implementation Project
Instructional Management System Implementation
Project Priorities
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 18
Instructional Management System Implementation Project
PROJECT PRIORITIES
Comparative Prioritization of Tasks and Objectives
Objectives Priorities Chart
The objectives defined above are prioritized with a number from 1 through 5 corresponding to
increasing priority. The objectives are prioritized for the main goal as defined in goal
statement. The objectives summarized are as follows:
Objective 1: Complete project by August 15th, 2004.
Objective 2: Complete project within total budget of $100,000.
Objective 3: Migrate existing courses and create new ones.
Objective 4: Train faculty, student and support staff.
Objective 5: Develop support structure for Campus-wide needs.
Objective 6: Create user processes.
Objective 7: Create a fully integrated seamless system.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 19
Instructional Management System Implementation Project
Project Tasks Priorities Chart
The project tasks defined above are prioritized with a number from 1 through 5 corresponding
to increasing priority. The objectives are prioritized for each objectives defined above. The
tasks descriptions are labeled in the following graphical representations:
Project Priorities Form
Project Priorities
Objectives Obj 1 Obj 2 Obj 3 Obj 4 Obj 5 Obj 6 Obj 7
Priorities 5 3 2 4 4 3 3
Task
#
Task Description Task
Priority
Obj 1
Task
Priority
Obj 2
Task
Priority
Obj 3
Task
Priority
Obj 4
Task
Priority
Obj 5
Task
Priority
Obj 6
Task
Priority
Obj 7
Overall
Task
Priority
Relativ
e
Task
Priority
%
1 Create courses 5 2 5 3 1 0 0 57 9
2 Course content
migration
4 3 5 2 1 0 0 51 8
3 Migrate other
tools
3 2 3 1 2 0 0 39 6
4 ISRS/D2L 1 2 3 2 2 5 5 48 7
5 Create demo
course
3 2 1 4 2 1 0 50 7
6 Demo 3 3 2 5 4 1 0 67 10
7 User guide 4 3 1 5 4 2 0 73 11
8 Student training 2 1 0 3 1 1 0 32 5
9 Faculty training 4 3 2 5 3 1 0 68 10
10 Train support
staff
3 2 1 4 5 2 0 65 10
11 Rich media
training
1 2 0 2 2 0 0 27 4
12 Setup FAQ 2 1 3 3 2 1 0 42 6
13 Create website 3 2 2 2 3 1 0 48 7
14 Create
faculty/student
user process
2 2 0 2 3 0 5 36 5
Project Priorities Cont.
The project priorities table does not include technical outsourcing since it is assumed that
the contract has begun prior to the implementation. Therefore, the task prioritization is DSCI 620: Project Management (Nezhad), Spring 2003 Page: 20
Instructional Management System Implementation Project
focused on the tasks implemented by the Metropolitan State University D2L implementation
team.
Overall Relevancy of Tasks with Objectives
The training and timeline being the highest priority objectives in the project, relevancy of
the tasks per objective are illustrated above. Highest relevancy of the training is seen with
the training tasks and other tasks that relate with training.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 21
Instructional Management System Implementation Project
Instructional Management System Implementation
Risk Assessment
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 22
Instructional Management System Implementation Project
RISK ASSESSMENT
The following data is our analysis of the primary risks involved with the project.
1. Unexpected decrease in personnel resources.
Likely Causes and Consequences:The project may find itself lacking in personnel resources due to various unforeseen circumstances such as sickness, employee turnover and/or changes within the university. Although this risk is potential throughout the project tasks, it is a bigger threat to project tasks in the critical path.
Tasks: All
Preventive Action:Identify key personnel and critical task to discuss availability of the resource through the project. Assign backup resources to critical tasks. Keep resumes ready for new hire.
Contingent Action:Hire new personnel or shift resources from other tasks.
Trigger:Any member of the project team leaves the project.
2. Technical difficulties lead to incomplete/delayed tasks.
Likely Causes and Consequences:Most tasks in the project that use technological resources are open to technical problems. They can be caused by equipment failure, disruptions in the campus-wide computer network, incompatible systems and/or inadequate technical knowledge.
Tasks: 2, 3, 4, 5, 7, 16
Preventive Actions:Plan for adequate technical training, ensure maximum possible redundancy of the critical technological equipment, conduct compatibility tests and keep technical support staff on the standby.
Contingent Actions:Call technical support. Purchase new equipment.
Trigger:Task progress decreases due to technological malfunctions
Risks cont.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 23
Instructional Management System Implementation Project
3. Courses incompletely/incorrectly populated.
Likely Causes and Consequences:This can be caused by an error in the automated ISRS-D2L integration process. The probability of this risk factor increases with the number of courses and students in the system.
Tasks: 5
Preventive Actions:Test automated process several times. Check populated courses thoroughly.
Contingent Actions:Manually populate courses
Trigger:Student or Faculty reports discrepancies in the converted courses.
4. Course complexity, lack of material or instructor co-operation leads to delayed course conversion
Likely Causes and Consequences:Although all the resources are available and there are no technical difficulties, the project may still face some course conversion setbacks. This could be attributed to several reasons including unforeseen course complexity, lack of material or simple unavailability of the instructors to discuss the problem with.
Tasks: 3
Preventive Actions:Setup a general meeting with all the instructors to discuss their courses prior to the start of the conversion task, thus identifying potentially risky courses. Get the instructor’s tentative schedule and their commitment.
Contingent Action:Add additional resource (such as more GAs working on the conversion) or leave the course in WebCT until the problem is taken are of.
Trigger:Assigned GA reports conversion difficulty with a course.
Risks cont.
5. Insufficient Faculty/Staff training resulting in delayed/inaccurate course sites
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 24
Instructional Management System Implementation Project
Likely Causes and Consequences:Even with the training sessions completed, we may find that the training was not sufficient for some of the instructors. This could be due to poorly planned training session, complexity in some of the courses or in D2L itself, the absence of the instructor in the sessions or even their retention capacity for technical trainings. This could lead to the instructors facing difficulty in modifying/maintaining their courses in D2L, resulting in inaccurate course sites.
Task: 10, 11, 12
Preventive Actions:Identify training requirements early on and establish an accurate feedback system after the training session. Ensure attendance in the training sessions. Provide an option for repeated training sessions. Plan for providing a one-on-one help support.
Contingent Actions:Assign a GA to the faculty/staff for a one-on-one support.
Trigger:Faculty/Staff expresses difficulty in modifying/maintaining courses
6. Lack of co-operation from the existing IMS (WebCT) in the transition process.
Likely Causes and Consequences:The availability and co-operation of WebCT is important in the project. However, as WebCT is losing a customer, it may not be their priority to facilitate the transition. This could result in difficulties when a situation arises that requires their participation.
Tasks: 3, 4
Preventive Actions:Review their contract terms carefully and explicitly state their roles and responsibilities in the process. Establish a contact point on both sides. Keep lawyer standby incase enforcing contract terms become necessary.
Contingent Actions:Legally enforce contract terms and liability issues.
Risks cont.
7. Outsourced/contracted work delivered not to specification.DSCI 620: Project Management (Nezhad), Spring 2003 Page: 25
Instructional Management System Implementation Project
Likely Causes and Consequences:There is a chance that tasks that are outsourced to external agents (D2L, MnSCU, IT department) are not delivered up to the required specification. This can be caused by inaccuracy in laying out requirements, misunderstanding of the expectations, and even the incompetence of the external agents. This could seriously jeopardize the project as a lot the tasks are dependent on these outsourced tasks.
Tasks: Objective 7
Preventive Actions:Thoroughly examine requirements and lay out the expectations explicitly in writing. Establish influential contact points on both sides. Incorporate insurance terms into the contract with the IMS vendor transferring part of the risk to the external agent.
Contingent Action:Take legal action to recuperate the loss. Extend project timeline and switch vendors if possible.
Trigger:Discrepancy found when examining the specification of the delivered products against the requirements.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 26
Instructional Management System Implementation Project
Risk Assessment Probability Table
Project Risk AssessmentRisk Factor Probabilit
y%
Impact Overall
Impact
Relative
Impact %
Tasks Affected by the
Risk Factor
Risk Response
Unexpected decrease in personnel resources
25 4 100 14 All Hire or shift
resourcesTechnical difficulties lead to incomplete/delayed tasks
75 2 150 21 2, 3, 4, 5, 7, 16
Seek technical
support or purchase
equipmentCourses incompletely/incorrectly populated
20 4 80 11 5 Manually populate courses
Delay in some courses due to course complexity, lack of material or instructor co-operation
45 2 90 13 3 Add additional resources (Graduate Assistants)
Faculty/Staff training is insufficient resulting in delayed/inaccurate course sites
45 4 180 25 10, 11, 12
One-on-one
support
Lack of co-operation from old IMS (WebCT) in the transition to new IMS
12 3 36 5 3, 4 Legally enforce contract terms
Outsourced/contracted work delivered incomplete or not to specification or late
15 5 75 11 15 Legal action to
recuperate loss
Risk Factors Graph
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 27
Instructional Management System Implementation Project
Priorities of Risk Factors
0102030
Un
exp
ecte
dd
ecre
ase
inp
erso
nn
el
Co
urs
esin
com
ple
tely
/inco
rre
ctly
po
pu
late
d
Fac
ult
y/S
taff
tra
inin
gis
insu
ffic
ien
tre
sult
ing
in
Ou
tso
urc
ed/c
on
trac
ted
wo
rk d
eliv
ered
inco
mp
lete
or
no
t toPri
ori
ties
(%
)
Faculty training is recognized as the largest risk as illustrated above. Variances of tasks
relating to this objective is high. Some faculty may need more time to get used to the new
system environment due to retention capacity or insufficient training.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 28
Instructional Management System Implementation Project
Instructional Management System Implementation
Task Assignments
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 29
Instructional Management System Implementation Project
PROJECT RESPONSIBILITIES
The below matrix includes task implementers for the project and their hourly rate for implementation as human resources costs. It also includes other costs produced by the other resources (described below in other resources section). The total task costs is the sum of Human resources and Other Costs.
Responsibility MatrixTask Implementers Task Costs
Task #
Task Description
Proj. Mgr.
P S S Hour per
Task
HR Budget $
Other Cost $
Total Budget $
1 Create courses
PM IMSA DA ASPREG
40 2950.00 781.00 3731.00
2 Course content
migration
PM IMSA GA 240 9300.00 4687.00 13987.00
3 Migrate tools
materials
PM IMSA GA 40 1550.00 781.00 2331.00
4 ISRS/D2L integration
PM DA IMSA 40 2350.00 781.00 3131.00
5 Create demo course
PM ID 40 1150.00 781.00 1931.00
6 Demo PM ID GA 40 1550.00 781.00 2331.007 User guide PM ID GA 80 3100.00 1562.00 4662.008 Student
trainingPM GA ID 16 592.00 312.00 904.00
9 Faculty training
PM ID GA 120 4650.00 2344.00 6994.00
10 Train support
staff
PM ID GA 80 2960.00 1562.00 4522.00
11 Rich media training
PM ID GA 80 2960.00 1562.00 4522.00
12 Setup FAQ PM ID GA 80 3100.00 1562.00 4662.0013 Update
websitePM WM GA ID 24 1290.00 469.00 1759.00
14 Create user processes
PM IMSA DA REG 24 1770.00 469.00 2239.00
15 Outsource IT tasks
PM ASP 41300.00
Total Project Budget: $99008.00
P = Primary Responsibility (Task Leader) S = Secondary Responsibility (Task Member)
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 30
Instructional Management System Implementation Project
Instructional Management System Implementation
Resources
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 31
Instructional Management System Implementation Project
PROJECT RESOURCES
The principal resources required for this project are of human resources based. These
personnel will include managerial, IT professionals and administrative staff. The positions
are described as follow:
Human Resources
TITLE
Project Manager
Web Master
Application Service Provider
Registrars
Database Administrator
IMS Administrator
Instructional Developer/Trainer
Graduate Assistant
Other Resources
Hardware
Computers (15)
Standard Software
Adobe Acrobat Reader 6.0
Adobe FrameMaker 6
Adobe Photoshop 7
Conversion Tool (Respondus)
Decide 2000
Macromedia Dreamweaver MX
Macromedia Flash MX
Microsoft Access XP
Microsoft Excel XP
Microsoft Front Page 2000
Microsoft Powerpoint XP
Microsoft Project XP
Microsoft Publisher 2002
Microsoft SQL
Microsoft Visio 2002
Microsoft Word XP
Office Supplies
Xerox Services
Facsimile Services
Phone Services
Internet Services
Stationery Supplies
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 32
Instructional Management System Implementation Project
Instructional Management System Implementation
Scheduling
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 33
Instructional Management System Implementation Project
PROJECT SCHEDULING
Task Scheduling/Duration
Task Duration Formula:
Duration=(Optimistic Duration + 4*Expected Duration + Pessimistic Duration)/6
Task Duration
Task
ID
Task Name (O)
Unit
(P)
Unit
(E)
Unit
Derive
d
Unit
Varianc
e
SD Slack Variance
of
Critical
Task
1 Create Course 32 60 40 42.00 21.78 4.67 0.00 21.78
2 Course content
migration
192 360 240 252.00 784.00 28.00 0.00 784.00
3 Migrate tools
materials
32 60 40 42.00 21.78 4.67 0.00 21.78
4 ISRS/D2L integration 32 60 40 42.00 21.78 4.67 0.00 21.78
5 Create demo course 32 60 40 42.00 21.78 4.67 0.00 21.78
6 Demo 32 60 40 42.00 21.78 4.67 0.00 21.78
7 User guide 64 120 80 84.00 87.11 9.33 0.00 87.11
8 Student training 13 24 16 16.80 3.36 1.83 0.00 3.36
9 Faculty training 96 180 120 126.00 196.00 14.00 0.00 196.00
10 Train support staff 64 20 80 84.00 87.11 9.33 0.00 87.11
11 Rich media training 64 120 80 84.00 87.11 9.33 0.00 87.11
12 Setup FAQ 64 120 80 84.00 87.11 9.33 0.00 87.11
13 Update website 19 36 24 25.20 8.03 2.83 0.00 8.03
14 Create user
processes
19 36 24 25.20 8.03 2.83 0.00 8.03
15 Outsource IT tasks
ΣVc 1456.75
бT 38.17
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 34
Instructional Management System Implementation Project
Critical Task Table
Critical Task
Task
ID
Task Name Duration
Unit
Immediat
e
Predecess
or
ES EF LS LF Slac
k
Critical
T/F?
1 Create Course 42.00 3-1-04 3-8-04 3-5-04 3-12-
04
0.00 True
2 Course content
migration
252.00 1 3-8-04 4-20-
04
3-12-
04
4-26-04
0.00 True
3 Migrate tools
materials
42.00 1 3-8-04 3-15-
04
5-14-
04
5-21-04
0.00 True
4 ISRS/D2L
integration
42.00 1 3-8-04 3-15-
04
5-11-
04
5-18-04
0.00 True
5 Create demo
course
42.00 3-1-04 3-8-04 3-1-04 3-8-04 0.00 True
6 Demo 42.00 5 3-8-04 3-15-
04
3-8-04 3-15-04
0.00 True
7 User guide 84.00 6 3-15-04 3-29-
04
3-15-
04
3-29-04
0.00 True
8 Student training 16.80 7 3-30-04 4-1-04 5-14-
04
5-18-04
0.00 True
9 Faculty training 126.00 2,7 4-20-04 5-12-
04
4-26-
04
5-18-04
0.00 True
10 Train support
staff
84.00 7 3-30-04 4-15-
04
5-7-04 5-21-04
0.00 True
11 Rich media
training
84.00 7 3-30-04 5-21-
04
4-15-
04
5-21-04
0.00 True
12 Setup FAQ 84.00 7 3-30-04 4-13-
04
5-7-04 5-21-04
0.00 True
13 Update website 25.20 7 3-30-04 4-6-04 5-18-
04
5-21-04
0.00 True
14 Create user
processes
25.20 4,8,9 5-12-04 5-17-
04
5-18-
04
5-21-04
0.00 True
15 Outsource IT
tasks
3-1-04 4-27-
04
3-24-
04
5-21-
04
0.00 True
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 35
Instructional Management System Implementation Project
Instructional Management System Implementation
Gantt Chart/Network
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 36
Instructional Management System Implementation Project
GRANTT CHART/NETWORK DIAGRAM
Project start date is on March 1st, 2004 and project completion on May 21st,2004. Critical
path reflects on only the sequence of tasks in relation to predecessors but also the resource
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 37
Instructional Management System Implementation Project
allocated to various tasks in that some tasks can not begin until a resource is freed from
another class.
Network Diagram
The network diagram illustrates the sequence of tasks in relation to one another. Some
tasks start at the same time as others where as other tasks are interpedently related.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 38
Instructional Management System Implementation Project
Instructional Management System Implementation
Budgeting
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 39
Instructional Management System Implementation Project
PROJECT BUDGET
Position Salary Per Hour or Per Piece
Human Resources
Project Manager 35.00
Web Master 15.00
Application Service Outsource
Registrars 15.00
Database Administrator 30.00
IMS Administrator 20.00
Instructional Developer 20.00
Instructional Technology Trainer 20.00
Graduate Assistant (8) 10.00
Other Resources
Computers (15) @ $500.00 7500.00
Adobe Acrobat Reader 6.0 400.00
Adobe FrameMaker 6 640.00
Adobe Photoshop 7 1200.00
Respondus – Conversion Tool 800.00
Decide 2000 800.00
Macromedia Dreamweaver MX 400.00
Macromedia Flash MX 400.00
Microsoft Access XP 796.00
Microsoft Excel XP 796.00
Microsoft Front Page 2000 396.00
Microsoft Powerpoint XP 796.00
Microsoft Project XP 796.00
Microsoft Publisher 2002 396.00
Microsoft SQL 280.00
Microsoft Visio 2002 280.00
Microsoft Word XP 760.00
Office Supplies 1000.00
Sub Total $18,436.00
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 40
Instructional Management System Implementation Project
Budget-Task Table
BudgetTask Implementers Task Costs
Task #
Task Descriptio
n
Proj. Mgr.
P S S Hour per
Task
HR Budget $
Other Cost $
Total Budget $
1 Create courses
PM IMSA DA ASPREG
40 2950.00 781.00 3731.00
2 Course content
migration
PM IMSA GA 240 9300.00 4687.00 13987.00
3 Migrate tools
materials
PM IMSA GA 40 1550.00 781.00 2331.00
4 ISRS/D2L integration
PM DA IMSA 40 2350.00 781.00 3131.00
5 Create demo course
PM ID 40 1150.00 781.00 1931.00
6 Demo PM ID GA 40 1550.00 781.00 2331.007 User guide PM ID GA 80 3100.00 1562.00 4662.008 Student
trainingPM GA ID 16 592.00 312.00 904.00
9 Faculty training
PM ID GA 120 4650.00 2344.00 6994.00
10 Train support
staff
PM ID GA 80 2960.00 1562.00 4522.00
11 Rich media training
PM ID GA 80 2960.00 1562.00 4522.00
12 Setup FAQ PM ID GA 80 3100.00 1562.00 4662.0013 Update
websitePM WM GA ID 24 1290.00 469.00 1759.00
14 Create user
processes
PM IMSA DA REG 24 1770.00 469.00 2239.00
15 Outsource IT tasks
PM ASP 41300.00
Subtotals: 39272.00 40216.00 99008.00Total Project Budget: $99,008.00
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 41
Instructional Management System Implementation Project
Instructional Management System Implementation
Simulation
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 42
Instructional Management System Implementation Project
PROJECT SIMULATION
For our simulation we selected our two most probably risks and realized those risks. The
risks, what caused the risk to be realized and the results are listed in the table below.
RISK CAUSE RESULT
Unexpected decrease in
personnel resources.
Instructional designer (ID)
raised hourly rate.
The cost of this resource
increased from $20/hr to
$30/hr which increased
the overall cost of the
project by $11,708.30.
Technical difficulties lead
to incomplete/delayed
tasks.
Task number 6, ISRS
integration takes longer
than planned.
The duration of this tasks
is increased from 1 week
to 3 weeks.
Insufficient Faculty/Staff
training resulting in
delayed/inaccurate course
sites
Task number 12, training
faculty member took
longer than planned.
The duration of this task is
increased from 3 weeks,
day 1 to 5 weeks. This
task is in the critical path.
The overall effect of these risks being realized were a cost increase of $11,708.30 and total
project duration increase of 14 days.
The graphics on the following page illustrate the effects of the simulation on the project.
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 43
Instructional Management System Implementation Project
Tracking Gantt
The simulation was run on April 1st which is aprox. one third of the way from the projected
completion date. The project completion date of the simulation was pushed out to June 4th
from May 21st.
Earned Value Table
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 44
Instructional Management System Implementation Project
Earned Value Report
Earned Value Graph
Analysis of the simulation data illustrates our conclusion that the project is over budget and
on schedule (BCWS < BCWP < ACWP).
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 45
Instructional Management System Implementation Project
Instructional Management System Implementation
Probability of Completion on Time
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 46
Instructional Management System Implementation Project
PROJECT COMPLETION PROBABILITY
We can calculate the probability of project completion using formula Z=(LF-EF)/T and
reference of Z-values, which can be found in Successful Project Management by Gido &
Clemens. For the LF value we chose to use the project deadline date.
Z = (5/21 – 7/31)/5.7393 = 1.8602
Using the table for Z-value we determined that probability of the project accomplishment
between EF and LF is 0.3668. By adding 50% to this value we calculated the probability of
the project completion on time: 0.3668 + 0.5 = 0.96875
Overall Probability 97%
DSCI 620: Project Management (Nezhad), Spring 2003 Page: 47