importance of energy planning - international atomic … development plan 2013 – 2028, by uetcl...
TRANSCRIPT
BY
GERALD BANAGA-BAI NGI
AND
EM M ANUEL WAM ALA
M I NI S TRY O F ENERGY AND M I NERAL DEVELO P M ENT UGANDA
UGANDA: IMPORTANCE OF ENERGY PLANNING
Technical Meeting on Topical Issues in the development of Nuclear Power Infrastructure, 2-5 February, 2016, IAEA Headquarters, Vienna, Austria.
Presentation Layout
Country Profile
Estimated Power Potentials
Uganda Vision 2040
Key Events
Energy Planning Studies
Other Developments
Conclusions and Recommendations
Country profile
Location: East Africa
Total Area: 241,038 km2
Area covered by water: 36,330 km2
Capital: Kampala
GDP Growth Rate at Constant (2009)
Market Prices : 5.0%
Population (2014 Census): 34.9million
Total Installed Capacity: 867.0 MW
Electricity consumption: 150 kwh/capita
Access to national electric grid: 15%
Sources: UBOS, 2014 World Bank, Uganda Vision 2040, Rural Electrification Survey , 2014
Shares of Fuels
Energy Source Contribution (%)
Traditional Biomass 88.8%
Fossil Fuel 9.5%
Electricity 1.7%
Source: MEMD 2014
Electricity coverage 16% and only 7% in rural areas. Electricity demand growth at 10% Need to increase access to clean energy and reduce poverty
Energy Sector Objectives
To increase electricity generation capacity
To expand the transmission and distribution networks
To increase access to modern energy services through rural electrification and renewable energy development.
“clean energy including Nuclear Energy sits in the middle of our clean low carbon growth strategy”
Estimated Power potentials
Energy Source Potential (MW)
Hydro 4,500
Biomass Co-generation 1,650
Geothermal 450
Peat 800
Total 7,400
Source: NDP 1
Some of the Vision 2040 Targets
Development Indicator 2010 2040
Per capita income $506 $9500
%population with access to electricity 11 80
Electricity consumption per capita (kwh)
75
3,668
% level of urbanisation 13 60
Source: Vision 2040
1700 Km Electrified Standard Gauge Railway (SGR) Network being developed to connect major urban centres and neighbouring
countries.
Vision 2040: Transport Infrastructure 8
Energy Planning Studies
Studies so far include:
Project for Masterplan Study for Hydropower Development, 2011 initiated by Directorate of Energy Resources Development and conducted by JICA
Power Sector Investment Plan 2010 – 2030, initiated by Directorate of Energy Resources Development
Grid Development Plan 2013 – 2028, by UETCL Energy Demand and Supply Analysis initiated by
Directorate of Energy Resources Development and supported by IAEA.
Study on Integrating Nuclear Power into the Generation Capacity Plan 2015 – 2040, initiated by Directorate of Energy Resources Development.
Nuclear Energy Key Events
2010 – Nuclear energy was identified in Uganda Vision 2040 as a key source for meeting future energy needs.
1 July 2014, Ministry of Energy and Mineral Development restructured into three Directorates and 11 Departments. Nuclear Energy Unit made a stand alone reporting directly to Director of Energy Resources Development
22 April 2015 – Cabinet approved the Nuclear Power Roadmap Development Strategy 2014 – 2015 and constitutes a Standing Cabinet Committee on Nuclear Energy Development
May 2015, Dr. Kwaku Aning, the Deputy Director General (DDG) and Head TC at IAEA visited Uganda to further enhance the partnership on nuclear power development, Cancer management, and Management of zoonotic diseases such as Ebola.
Key Events
The Minister of State for Mineral Development, Hon Peter Lokeris and Dr. Kwaku Aning, the Deputy Director General (DDG) TC during his visit to the country focusing on nuclear power development.
Energy Demand and Supply Analysis Study
Siting and Technology Deployment Working Group (TDWG) comprising of experts from relevant MDAs was constituted.
IAEA Inception Mission on UGA2001: Supporting Pre Feasibility Studies for Launching the First Nuclear Power Plant
Energy Demand and Supply Analysis Study
National Training Course on MAED was from conducted in Kampala from 18 – 22 August 2014 with support from IAEA
National Training Course on MESSAGE was conducted at Munyonyo, Kampala from 17 – 21 November 2014 with support from IAEA.
Over 10 staff in the Ministry of Energy and Mineral Development, ERA, UEGCL, UETCL and National Planning Authority were trained.
A scientific visit on Nuclear Technology, 1 – 5 June 2015 was conducted in Republic of Korea.
Energy Demand and Supply Analysis Study
Members of Working Groups during IAEA Inception Mission on UGA2001: Supporting Pre Feasibility Studies for Launching the First Nuclear Power Plant
Energy Demand and Supply Analysis Study
Selected Members of STDWG during a scientific visit to Republic of Korea on Nuclear Technology, 1 – 5 June 2015. Courtesy of Korea Nuclear Association
Energy Demand and Supply Analysis Study
Relevant input Data for MAED and MESSAGE was collected by expert and national models developed.
A Scientific visit to IAEA Headquarters, Vienna on nuclear power infrastructure development focusing on energy planning was conducted by five (5) members of STDWG.
The aim of the scientific visit was to review national models with IAEA experts
Study on Integrating Nuclear Power into the Generation Capacity Plan 2015 - 2040
Overall Objectives :
To Conduct a study which would translate into a series of carefully cost-planned and actionable nuclear power projects or activities over a period of up to 25 years.
Study on Integrating Nuclear Power into the Generation Capacity Plan 2015 - 2040
Specific Objectives:
(i) To update the electricity demand forecast for 2015 – 2040;
(ii) To update the generation capacity expansion plan; and
(iii) To analyse the financial viability of the envisaged nuclear power development programme
Scope of the Study
Seven Tasks
Task 1: Review of the available documentation
Task 2: Review and update of the demand forecast
Task 3: Review and update of the generation plan
Task 4: Nuclear fuel cycle assessment
Task 5: Investment and financial planning report
Task 6: Training and capacity building
Task 7: Consultation of Stakeholders
Organization of the Study
The study was conducted by an international consultant under the supervision of the Technology Deployment Working Group (TDWG).
The TDWG comprise of members from relevant government MDAs.
IAEA provided training to members of TDWG on the use of computer based models for energy demand and supply analysis.
TDWG were also trained by consultant so as to be to maintain the models.
Methodology
Electricity demand forecasts were reviewed and updated using an econometric modelling of key economic drivers i.e. GDP, Population, load shedding, electrification rates, export sales, system losses and Per Capita Consumption.
Five scenarios were considered: the Base Case, High Case, Low Case, Grid Development Plan 2013 - 2028 Case and Uganda Vision 2040 Case.
Methodology
ORDENA plus ® model was used by the consultant to optimize the generation requirements for the five demand forecast scenarios outlined above.
Ten candidate technologies were considered for the supply capacity expansion.
These included were hydro, nuclear, solid waste, peat, Oil, natural gas, HFO, bagasse, geothermal and solar PV.
Methodology
A nuclear fuel cycle assessment was conducted to identity suitable nuclear reactor technologies to be deployed, options for nuclear fuel supply and radioactive waste management.
Ten (10) Generation III & III+ reactor types on market were considered.
An investment and financing plan was prepared by undertaking an economic simulation using the ORDENA plus ® model, specifically for the nuclear capacity required based on the results of the optimisation process.
While developing a nuclear power generation investment and financing plan, options for the reactor technologies, options for nuclear fuel supply and waste management were considered.
Generation Capacity Expansion Plan 2015 - 2040
Base Case Generation Capacity Expansion Plan (MW). Source: Study report
Generation Capacity Expansion Plan 2015 - 2040
Vision 2040 Case Generation Capacity Expansion Plan (MW). Source: Study report
Nuclear Fuel Supply Option
Utilizing international suppliers of nuclear fuel and their nuclear fuel cycle services was found to be the most cost effective approach for the first nuclear power project.
Continue with exploration and evaluation of Domestic resources which will become financially attractive as nuclear generation programme grows.
Benefits
Project Name Capacity (MW) Status
Karuma Hydropower Project 600 Construction
Isimba Hydropower Project 183 Construction
Ayago Hydropower Project 840 Feasibility studies completed and Government signed MoU signed with a developer
Achwa Hydropower Project 83 Feasibility studies completed, negotiating PPA and Implementation Agreements with Govt
Muzizi Hydropower Project 44 Procurement of Contractor
Small Hydropower Projects 64 Feasibility studies completed
Total 1,814
Challenges
Some models such as MAED have huge data reqquirements.
Limited capacity for energy planning in the country
Since the sector involves many stakeholders coordination of planning is still a challenge.
Other Developments
Nuclear Power Infrastructure Development Project
Approved by Government with the following objectives:
To establish basic infrastructure required by Government and other stakeholders to launch the first nuclear power plant.
To strengthen the capacity of Nuclear Energy Unit for planning and managing nuclear power projects.
To enhance stakeholders involvement in nuclear power infrastructure development.
Conclusions and Recommendations
Energy plans are dynamic and regular update.
Studies so far conducted show that electricity demand will continue to grow and current sources are inadequate to meet all future needs.
Nuclear power will therefore play an important role in the future energy mix.
Appropriate infrastructure development planning is critical for nuclear energy dev’t
Infrastructure and investment requirements varies with the size of the nuclear power programme.