Improving Project Performance 1 How PDRI can improve your project performance This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written permission. Benefits of PDRI What is PDRI? Value Who uses it? How is PDRI being used? What we offer This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written permission.

Upload: others

Post on 25-Dec-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Improving Project Performance

Improving Project Performance

1

How PDRI can improve your project performance

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

•  Benefits of PDRI •  What is PDRI? •  Value •  Who uses it? •  How is PDRI being used? •  What we offer

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Page 2: Improving Project Performance

Improving Project Performance

2

Benefits of PDRI

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

•  Higher probability of meeting cost and schedule •  Lower percentage of change orders •  Better team alignment and communication

–  Contractor / owner communications •  Improved risk assessment •  Ability to make “trade-off” decisions •  Can be used in developing project portfolio

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Page 3: Improving Project Performance

Improving Project Performance

3

•  Higher probability of meeting cost and schedule •  Standardized scope package •  Ability to measure scope definition •  Avenue to communicate and reconcile differences •  Monitor progress in planning phase •  Minimize design rework

–  Fewer change orders

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

What Is PDRI?

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Page 4: Improving Project Performance

Improving Project Performance

4

•  An Acronym –  Project Definition Rating Index

•  An Index –  Score along a continuum representing the level of

scope definition •  A Risk Management Tool

–  Identifies and measures risks related to project scope definition

•  Developed by Construction Industry Institute –  Affiliated with University of Texas, US

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Page 5: Improving Project Performance

Improving Project Performance

5

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

 Industrial      Buildings Sec%ons:  3    3  

Categories:      15  11  

Elements:                                              70      64  

Score    Low:                                        70                                                                                64  

Score:  High                                    1000                                                                  1000  

Page 6: Improving Project Performance

Improving Project Performance

6

Elements: 70 for industrial and 64 for buildings

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

A1.  Reliability  Philosophy  

A  list  of  the  general  design  principles  to  be  considered  to  achieve  dependable  opera%ng  performance  from  the  unit.  Evalua%on  criteria  should  include:  

  Jus%fica%on  of  spare  equipment  

  Control,  alarm,  and  safety  systems  redundancy  

  Extent  of  providing  surge  and  intermediate  storage  capacity  to  permit  independent  shutdown  of  por%ons  of  the  plant  

  Mechanical  /  structural  integrity  of  components  (metallurgy,  seals,  types  of  couplings,  bearing  selec%on,  etc.)  

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Page 7: Improving Project Performance

Improving Project Performance

7

Note: Score is weighted per criteria – weighting not shown here

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Value

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Page 8: Improving Project Performance

Improving Project Performance

8

1000  Points  

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

N = number of projects

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Page 9: Improving Project Performance

Improving Project Performance

9

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Page 10: Improving Project Performance

Improving Project Performance

10

•  A score –  Represents a continuum –  Relative to timing –  Only as valid as effort/seriousness

•  Accuracy (the real score) can be improved with facilitation

•  Perhaps is not the most important output of the assessment –  Working towards improvement of score

provides benefit This copyrighted material is the property of Project Auditors,

LLC, and may not be reproduced without written permission.

Who uses it?

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Page 11: Improving Project Performance

Improving Project Performance

11

PDRI TYPE PDRI USAGE

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

•  Saudi Aramco / Aramco Services, Chevron, Conoco Phillips

•  NASA, Smithsonian •  Jacobs Engineering, Bechtel, ABB Lumus, Black

& Veatch, Cargill, KBR

Page 12: Improving Project Performance

Improving Project Performance

12

How is PDRI Being Used?

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

•  As a checklist in early project development (81%)

•  As a “gate” check before moving to the next project phase (72%)

•  In conjunction with other front end planning measurement methods (72%)

•  As a means of measuring or benchmarking front-end planning process performance (70%)

•  More than once on most projects (42%)

Source: CII, Gibson, 2007

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Page 13: Improving Project Performance

Improving Project Performance

13

•  Other usage of PDRI:

–  As an audit tool (42%)

–  In a modified form for small or unusual projects (33%)

–  To help capture lessons-learned (28%)

Source: CII, Gibson, 2007

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

What We Offer

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Page 14: Improving Project Performance

Improving Project Performance

14

•  Can be performed during pre-planning –  Chevron does multiple

times during front-end planning for larger projects, once for smaller ones

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

•  Management discussions (variable) •  Time to provide explanation of PDRI

and value: half hour •  Two-and-a-half to four hours initially

per package •  Report time is additional •  Management briefing •  Risk mitigation is additional

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Page 15: Improving Project Performance

Improving Project Performance

15

•  One day course •  Agenda

–  Value of process –  History –  Case study –  Explanation of building and

industrial PDRIs –  Role play exercise –  Personal action plan

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Summary

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

Page 16: Improving Project Performance

Improving Project Performance

16

•  PDRI is a tool that works

•  PDRI should be used with care

•  “Score” is good

– Process of getting there provides additional value

•  How will your organization be using this leading practice in the future?

This copyrighted material is the property of Project Auditors, LLC, and may not be reproduced without written

permission.

For more information, contact us