index page no 5. present scenario of swd in cmc 16 · underground drainage system health and...
TRANSCRIPT
1
INDEX
Page No
1. Introduction 2
2. Profile of Chitradurga 3
3. Existing Services Status 5
4. Planning Aspects 9
5. Present Scenario of SWD in CMC 16
6. Citizen Engagement 23
7. Prioritize Projects 23
8. Condi tonalities 23
9. Resilience 23
10. Financial Plan 24
11. Estimate and Plan 31
12. SAAP 32
Salient Features of Chitradurga CMC:
Location: 200 Kms, North East of Bangalore & center of Deccan plateau
14° 15’ North latitude and 76
Altitude: 735m above MSL
Connectivity: Railhead – Chitradurga on Miraj Bangalore Railway line.
Connected by NH4
Sholapur & SH
Geology: Red earth on Western and North Western Parts, Black clay on
Eastern & Northern part. Impervious granite strata at 10 to 15m
depths.
Climate: Moderate –Ranges from
Touist attraction: Chitradurga F
Bruhanmatta, Chandravalli Garden.
Population: 2011 Census 145853 souls
Annual Rainfall (average): 688mm
2
INTRODUCTION
Salient Features of Chitradurga CMC:
200 Kms, North East of Bangalore & center of Deccan plateau
15’ North latitude and 76° 25’ East longitude.
Chitradurga on Miraj Bangalore Railway line.
Connected by NH4 (Bangalore – Pune), NH13 Chitradurga
Sholapur & SH-48 (Pavagada – Bhadravathi)
Red earth on Western and North Western Parts, Black clay on
Eastern & Northern part. Impervious granite strata at 10 to 15m
Ranges from 12°C to 35°C
Chitradurga Fort, Obavvana Kindi, Murugharajendra
Bruhanmatta, Chandravalli Garden.
2011 Census 145853 souls
688mm
200 Kms, North East of Bangalore & center of Deccan plateau
Chitradurga on Miraj Bangalore Railway line.
Pune), NH13 Chitradurga
Red earth on Western and North Western Parts, Black clay on
Eastern & Northern part. Impervious granite strata at 10 to 15m
ort, Obavvana Kindi, Murugharajendra
3
Profile of Chitradurga.
The Municipal area is declared as planning area under Karnataka
town and Country planning Act (KTCP act), and a separate planning
authority called Chitradurga Urban Development authority is constituted
For the town. While CMC is in-charge of providing infrastructure
facilities and other developmental activities the planning authority exercises
the power of urban planning and regulation of development activities and
also implementation of development plan proposals.
The Government of Karnataka constituted Chitradurga town
municipal council in November 1964 and it was upgraded to Chitradurga
city Municipal council in year 1983, The Administrative boundaries of the
town cover an area of 21.57 Sq. Km is divided into 35 Municipal wards and
is governed by the city Municipal council (CMC). Out of total land 76.5%
area is developed, whereas 7 percent is vacant land and 16.5 percent
area is covered by conservation area of chitradurga fort and cholaguddu
hillock
Climate:
Chitradurga town has a moderate climate with temperature varying
12° C in winter to 35° C in summer.
Geology:
There are two types of soil predominantly present in Chitradurga town
are, black cotton soil and red soil, the soil on the eastern and northern part
of the town is of black cotton type whereas it is red gravelly on the western
and north – western part of the town. Locally available building material is
kattya and is widely used for construction purpose
4
Economic Base:
Chitradurga is a multi functional town. The economic base of the town
depends on agriculture, trade and commerce, industries and tourism sector
sheep rearing activity is predominantly found in the town along with small
scale industries like oil mills, leathers, welding units, cotton mills, etc Dry
agriculture is main occupation in the hinterland of the town. Chitradurga is
lagging behind industrially but trade and commerce is gaining an upper
hand Davangere and Harihar have retained their industrial characters,
which are surrounding towns of Chitradurga
5
EXISTING SERVICES STATUS
INTRODUCTION
The existing status of various services or infrastructure in Chitradurga ULB. The services covered are:
Water Supply
Storm Water Drainage System
Solid Waste Management
Roads
Underground Drainage System
Health and Hygiene
WATERSUPPLY
Chitradurga town has Water Supply System with surface water as source
provided in the year 1973. The source is Vedavathi River with pickup weir across it
near Hiriyur which is 42 Km away from Chitradurga. The capacity of system is 9.08 MLD.
Chitradurga town has water supply system with surface water has source is
Shanthisagara lake with pickup with Bhadra river near Shanthisagara which is 65
Km away from Chitradurga. The capacity of system is 16MLD provided in year
2008
In addition to these there are 175 bore wells within the town area to
tap ground water. Out of total bore wells. 150 bore wells are fitted with
power pumps. About 150 out of 175 bore wells, which are fitted with power
pumps are yielding and are supplementing to the present water supply to
the town. Identification of dependable water source is essential for
Chitradurga.
Flow meters are not available at pumping stations to assess the utilization of the installed capacity. The daily water requirement for 160,000 souls (2016) at 135 lpcd will be 21.60 MLD and for projected population of 35,000 by the year 2021 I at
6
135 lpcd will be 26.32 MLD. The present per capita water available from surface source is 124 lpcd in normal water is met Auth by tapping ground water. The situation gets worsened in peak summer; when there is water scarcity even to provide regular quantity of water. CMC, under such circumstances arrange through tankers to most of the areas.
The water availability against the requirement is as given in Table-l
TABLE-1
Status of water availability in Chitradurga
Sl.No. Source Capacity (MLD) Remarks Fair
season Summer
1 Vedavathi river near Hiriyur
5.5 5.0
2 Ground water from bore wells (150 no’s of at 20000 liters per day )
2.4 2.0
3 Shanthi Sagara Lake Project
12.00 10.00
Total 19.9 17.0
STORM WATER D R AI N
For drainage of storm water during rainy season and avoiding the flooding ot’
low lying areas and water stagnation it is necessary to provide the drainage
pathway for proper disposal of storm water from the developed area. The storm
water drainage system in Chitradutga is predominantly open The major storm water
drainage network comprises of the primary drain from Kanaka Circle to Holalkere Road
(NH4) which runs for 2. 725 Km length in North ward direction inside the town. Road
side drains from different parts of the town join this main drain.
Some portions of the drain needs desilting to facilitate smooth flow during rains. The
main drain passes through the built up area of the city and is filled up with debris
and encroached in some stretches. This results in water stagnation during rains
7
leading to mosquito and contamination of under ground water sources which makes
it more necessary to provide storm water drains from hygienic point of view.
Therefore, it is proposed to provide storm water drain of about 10 km length to cover all proper
drainage.
SOLID WASTE MANAGEMENT SYSTEM
Chitradurga has an obligatory function of managing solid waste of the town. The ULB
has been covered under Nirmala Nagara Scheme and some components had been implemented. The CMC has provided a site for Solid Waste
disposal in Dhyamoavvanahalli for an extent of 34.79 acres situated at a distance of 7 Km from the city
on Challakere road. The site has been protected with pucca compound walls and interior service
roads are of gravel riding surface.
Managing solid waste is collecting waste within the town, transporting the same and
disposing it off in the dumping site. Solid waste management can be done by CMC or it can be
outsourced to private operator.
• The primary collection of waste is through community bin system. One RCC
bin is located per point; (uncovered) with 60 to 80kgs carrying capacity; at
every 100 m in highly populated areas and 300 in in medium and low
populated areas.
• Few roads are swept 3 times a week and few are not swept even once a
week.
• The waste will be overflowing from the bins in highly populated wards like
ward No.7, 8, 12, 19, 20, 21 and 22.
• Only in ward No. partly official area 23 and 26, door-to-door waste collection is taking
place, initiated by the RWA of that area.
ROADS
The major roads passing through the Chitradurga city is the stretch betwéen
Shankar tallies and Union tallies is situated in the commercial area. The width of
carriageway gets narrowed as it leads to Santhapet Circle due encroachments.
Medehally road from Santhapet Circle up to the regulated market experiences
heavy volume of mixed traffic like lorries, bullock carts, buses, vans and other
8
transport vehicles. The commercial activity along the major road by hawkers on road
sides and foot paths create tralEc congestion.The through traffic along the National
Highways mainly pass through the NH, byepass and the regional traffic for the town
with lorries and other commercial vehicles pass through the heart of the town
generating heavy volume of traffic.
The existing pattern of the roads in the town shows that the area in the North -
South-Eastern portion of the town have a relatively better road net work compared
to the other parts of the town. Hence, it is essential to the roads by strengthening,
widening and up grading the riding surface wherever found necessary.
Apart from these other internal roads are maintained by city municipality.
The carriage way width varies from 3.0 m to 5.5 m throughout the town. Total road
length of the city is 284.95
Disposal OF DEAD
The existing burial (grave yards) and burning ghats are not having basic
amenities. Some of these places are mostly open and not provided with compound
wall. Other facilities like mourner’s room bathing & toilet facilities are not available.
Approach roads, electrification, water supply facilities to timse places are essential.
Moreover the modern method of burning the dead with silicon vessels and chimney
system with building to house the components are not available.
Hence there is a need for Provision of Silicon Vessel, Compound wall, Electrification & Access
paths for major Hindu & Muslim grave yards.
9
PLANNING ASPECTS
PROPOSED SERVICE AREA
At present storm water drains carry waste water from about 6O% of the town because of
non existence or non performance of underground drainage system in some of the
areas of the town. Remaining 40% of the city area is not covered by storm water
drains.
Three major open drains are discharging their waste in Baragere kere, which carries
sullage and sewage from the households polluting the tank. In order to prevent the pollution of
fresh water in the tank and also ground water, it is necessary provide suitable storm water
drains to avoid the sewage entering into the tank. The CMC has desired that following drains
be constructed. The details are given in Table-2.
TABLE-2
Details of drains to be constructed as part of the project
Sl.no Description Length (M) Width (M) Depth (M) 1 Construction of storm
water drain at Babu
Jagajeevan Ram Nagara
Ramakrishna ashrama
Housing board colony
through IUDP
Sarswathipuram 1st
cross
4000 5 to 7 1.5 to 3.0
4.2 SURVEYS AND INVESTIGATIONS
Topographie Surveys
Topographic survey was carried out by electronic total station and auto level
equipment. Temporary bench mark was fixed using the total station instrument for the Storm
Water Drain. Later the Temporary bench mark was connected with GTS bench mark. Total
station survey reveals both the horizontal and vertical alignment of the drain to facilitate
improvements. The details of existing cross-sectional drawings for the drain work with the
levels at sill, top ofthe road surface with cross section details ofthe drains/streams have been
carried out.
10
Geo Technical Survey
Geo Technical Investigation involving trial pits were carried out to ascertain the soil
met with along the proposed Storm Water Drain. The details of quarries have been collected with lead details including suitability sufficiency of yield etc. for the construction materials. The approved lists of quarries with quarry maps and lead chart from the PWD have been obtained.
Design and Office Work
The survey data and drawings were taken for rehabilitation of the drains and the
details of the existing drain with longitudinal and cross sectional corrections were
provided to design the proposed storm water drain.
DESIGN METHODOLOGY
Storm Water run-off is a portion of precipitation which drains over the ground
Estimation of such runoff reaching the storm water drains is dependent on the intensity, duration
of rainfall, characteristics of tributary area and the time required for the flow to reach the drain.
The storm water drains have to be designed to carry the maximum rain runoff.
Planning and Design Criteria:
I. Formula adopted: Tire formulas adopted for estimating the design
discb.argue for the Storm Water Drains
a) Empirical method:
Design standards to be adopted for drains
F= 2i 2i131212
( 1+ 1/t)
F = Total rainfall fromStorm in cm. i = Max. Intensity of rainfall cm/hr. i = Duration of storm in hours.
(i = l0cm to 12.5 cm for areas of intense & prolonged rainfall and 5 cm to 7.5 cm for other areas in india (assumed)
mw11 city water sheds, the following formula is used:
Q = CAR(S/A) 1/2 455
Q = Runoff in cumecs
C = Coefficient or Impermeability factor
0.50 in rural areas
11
0.90 in suburban areas
0.75 average
A = Area in hectares
R — Maximum rainfall intensity (25-75 mm/hr)
S = Slope (1 in 1000)
Recommended runoff for Empirical desistn of storm water drains in towns.
Average annual rainfall
Upto 500mm
500 to 1000mm
1000 to 2000mm
2000 to 3000 mm
Over 3000mm
Run off per hour
3mm 6 mm 12 mm 18 mm 25 mm
Maximum Rainfall: 1.5 times average rainfall of 35 years (appx)
Appx. Flood runoff available from total precipitation:
a) Coastal Zones: 66 — 55 %
b) Interior transit Zones: 55 — 30 %
c) Dry Zones: 30 — 15 %
Rainfall lost in:
a) Evaporation and absorption by vegetation : 30 — 15 ° »
b) Percolation :15 — 25 %
Available as surface runoff : 25 — 55 %
b) Rational Method
Q = 10 CiA where
Q — Runoffm'/hour
i = Intensity of rainfall in mm/hr
C = Runoff coefficient depending on the ground slope and land use (varies from
0.10 to 0.90)
12
Run off coefficients
Type of land use Coefficient
Commercial and industrial 0.70 to 0.90
Residential
i) High density ii) Low density
0.60 to 0.75
0.35 to 0.60
Park and undeveloped areas 0.10 to 0.20
Max:- values for small districts having steep slopes and minimum values for large and flat
districts)
Coefficient for large drainage basin with varying land use over different
portions is to be
C = C1.A1 + C2. A2+ C3.A3 + …….
A1+A2+A3………….
Where
CI,C2,C3. . . .= Run off coefficients of the respective areas
A1,A2,A3. . . .= Areas drained in hectares in the sections under consideration
3. Critical Intensity
I = 2i 2I
(1 + t)
Where
I = Critical intensity of rainfall in cm/hr
i = Max. Intensity of rainfall in cm/hr
T = Time of concentration in hours (depends on ground slope, distance of travel
and nature of soil)
13
4.Storm Frequency:
a) Residential areas i) Peripheral area : Twice a year
ii) Central and comparatively high priced areas : Once a year
b) Commercial and high priced areas: Once in 2 Years.
5. Intensity of Precipitation
Intensity – Duration for a given frequency of storm is obtained from past records over a
period of years of the observed data on the rainfall of the area.
Intensity – Duration relationship is given by
I=a/tn
And I=a/t+b
Where i= intensity of rainfall (mm/hr)
t-duration of storm (minutes) and a,b and n are constants. By plotting the available data of i and
t on an arithmetic graph paper, the values of intensity (i) can be determined for any given time of
concentration (tc)
6.Time of Concentration:
Time of Concentration (tc)
Tc = Inlet time + time of flow
Intel time 3 minutes in highly developed areas 5-30 minutes for other areas depending on
shape, distance to inlet, topography, and character of area.
Time of flow= Distance of flow/Velocity
7. Formula for design of open channels and circular conduits:
For open channel, Manning’s formula may be used:
V=1 r2/3 S1/2/n
For circular conditions:
=1 3.968x10-3xd2/3xS1/2
V= Velocity in mps
R=Hydraulic mean depth in m
14
D=Dia. Of pipe in mm
S=Slope of hydraulic gradient
n=Manning’s coefficient of Roughness (varies from 0.011 to 0.015)
8. Velocity in Storm Water Drains:
a. Minimum Velocity :0.75 – 0.90 m/sec
b. Maximum Velocity :1.40 – 4.00 m/sec
Components of the proposed Storm Water Drain
1. The side walls of the Storm Water drain will be provided with reinforced cement
concrete using M20 mix with 20mm and down size granite jelly.
2. The cross sectional profile of the walls has been provided to withstand the earth
pressure, surcharge from traffic and water pressure during rains.
3. Foundation will be 15 cm thick plain cement concrete M20 mix over PCC 1:4:8 below
the side walls and for the bed.
4. RCC cover slabs with M20 mix (suitably reinforced) will be provided over the drains in
the built up area wherever necessary.
5. M20 mix with 20mm down size granite jelly is proposed for retaining walls.
The drains will be designed to carry the maximum discharge during rains, based on the
formulae shown. Two types of sidewalls will be provided for the drains as described in the
following paragraphs.
Culverts across the Storm Water Drains: Necessary provisions for culverts across
the drains have been provided wherever necessary. The slab of the culverts is designed
to carry motorized traffic of 40 tones.
ASSESSMENT OF MATERIAL AVAILABILITY
The details of material availability are given as below:
Cement : Chitradurga
TMT Steel : Chitradurga and Bangalore
HYSD bars : Chitradurga and Bangalore
Bitumen : Bangalore
Metal and Stone : Katheral Village
Sand : Chitradurga (Parasurampur river side Challakere)
15
PROPOSED TECHNOLOGY FOR CONSTRUCTION
Before taking of the original work, entire drain will be desilted by manual laborer and
jungle will be cleared all along the drain and some internal templates will be marked and
constructed in RCC M20 mix. Bed concrete 1:4:8 below RCC 1:1.5:3 is laid using
concrete mixers to the true line and groove. Finally 1:1.5:3 RCC with concrete mixer is
laid to the required longitudinal gradient.
Wherever pitching is proposed for sites, the area is excavated to the required side
slopes and stone pitching over filter media (sand and metal) is laid and pointed in CM
1:3 by manual laborer i.e skilled mason.
CLEARANCES REQUIRED FROM OTHER AGENCIES
This project involves the Rehabilitation of the Existing drains which runs along the side of the
existing roads. Hence there is no any land acquisition. But in order to shift the electric power
lines the involvement of BESCOM authorities is necessary.
NEED FOR INSTALLING GENERATORS
Generators are not necessary because the equipments used for the construction of drains are
fuel operated. Hence it is not necessary to install any generators.
LAND REQUIREMENT
The storm water drains proposed as a part of the project for Chitradurga CMC shall be aligned
over Government land. No private land will be required for the project. Hence, issues related to
resettlement and rehabilitation is not envisaged in the proposed project.
16
Present Scenario of Storm Water Drain in Chitradurga City Municipal Council,
Chitradurga city municipal council having total 10 no.s of storm water drain.
Out of 10 storm water drain 2 no.s of storm water drain is developed by KUIDFC
under the project of KMRP.
1) Kanaka circle to NH-4 by pass Length of this drain is 2.73 Kms. This drain is
constructed by size stone masonry under the project of KMRP.
2) Ravi nursing home to Subamma galli. Length of this drain is 0.83 Kms. This
drain is constructed by size stone masonry under the project of KMRP.
3) From LIC office via Sarswathi law college, Turuvanoor road near hero Honda
show room via JCR extension to NH-4 approximately 2.5 Kms length is
constructed.
4) From Holalkere road Devi marble shop via Mallapanahatti road to kanaka
circle. This SWD length is 1.5Kms. This drain is constructed by earthen
drain. This drain is has to be developed.
5) The from Krishna Yadava Mahasastana temple behind SJM college via
Holalkere road to Devi marbal shop.Length of this drain is 1.00 Kms. This
drain is constructed by earthen drain. This drain is has to be developed.
6) Construction of storm water drain at Babu Jagajeevan Ram Nagara
Ramakrishna Ashrama Housing board colony through IUDP
Sarswathipuram 1st cross Length of this drain is 4 Kms. This drain is
constructed partly earthen drain and partly size stone masonry. Length
of the size stone masonry is 200mtrs. Balance length of drain is
constructed under the project of AMRUT.
7) Construction of storm water drain at K.S.R.T.C Layout through Teachers
Colony Onake Onake Obavva. Circle length of drain is 3.00Kms. This
drain is constructed under the project of AMRUT.
8) Construction of storm water drain at Back side of regional school to
Kothwal Nagara 4th Cross. length of drain is 2.00Kms. This drain is
constructed under the project of AMRUT.
17
9) Construction of storm water drain at KMRP Fish Babanna house to NH-4
length of drain is 1.0 Kms. This drain is constructed under the project of
AMRUT.
10) From Malapanahatti circle to infront of Muruga Rajendra temple lake
length of drain is 6.44Kms. This drain is constructed by earthen drain.
Total storm water drain length is 25kms. 2.29kms storm water drain is
developed by KUIDFC under the project of KMRP. 3.50Kms SWD is
developed under the other schemes. Total length constructed SWD is
5.79Kms. Remaining 19.21Kms. Is to be developed.
The gap is 19.2Kms .
Under the AMRUTH scheme 10.0Kms Storm water drain is developed.
The Four major storm water drain’s are developed under the scheme of AMRUTH.
Total cost of this project is 10.00Crore.
The city is covered by 7 rock hills. During rainy season the rain water is
collected at the bottom of hills. The storage water is flowing through 12 SWD.
In summer season only residential waste water is flowing through storm water
drain.
These SWD are inter connected by small lateral drains.
At the end the storm water drain is connected to Mallapura lake and infront of
Muruga Rajendra lake.
Presently the waste water of SWD is not treated. The old STP plant is situated at
the pillekarana halli village. The waste water is sedimented and then flowing to
mallapura lake. 95% of the waste water is reached to Mallapura lake only 5% of
waste water is reached to infront of Muruga Rajendra lake.
The Karnataka urban water sanitary and drainage board is constructing the new
STP at Pillekaranahalli village site. The work is under progress. The expected STP work
completion is by December -2016.
18
UGD work under progress by KUWS & DB. Total 283Kms. UGD work estimate cost of
70.7crores work is completed by December -2016.
Table1.1: Status of Storm Water Level service levels
Sl..
No. Indicators
Sustainable
standards
Black (Caution for
improvement)
Red(Immediate
action for
improvement)
Present
Status
1 Coverage of Storm water
drainage network
100% <75% <50% 17.30%
2 Incidence of sewerage mixing in
the drains
0 <25% <50% 25
3 Incidence of water logging 0 <25% <50% 10
Table 1.2. In case of mixed drainage how it works in peak rainy days?
Sl.
No. Location
Merging with which
sewer Reason
1 Near LIC office of bang lore
and Davanagere road.
Secondary drain to storm
motor drain
Linking secondary drain is
connected to storm water
drain
2 Behind Prasanna talkies road Secondary drain to storm
motor drain
Linking secondary drain is
connected to storm water
drain
3 Venkateshwaara talkies road Secondary drain to storm
motor drain
Linking secondary drain is
connected to storm water
drain
4 Burujinahatti circle Secondary drain to storm
motor drain
Linking secondary drain is
connected to storm water
drain
5 Chandravalli to via Holalkere
main road housing board colony
storm water drain storm
motor drain
Linking SWD to SWD
6 In Thuruvanoor road Beside of
hero honda show room
Secondary drain to storm
motor drain
Linking secondary drain is
connected to storm water
drain
19
Sl.
No. Location
Merging with which
sewer Reason
7 From Sarswathi law collage
near C K pura
Secondary drain to storm
motor drain
Linking secondary drain is
connected to storm water
drain
8 Gopalpura road behind Ramdas
compound
Secondary drain to storm
motor drain
Linking secondary drain is
connected to storm water
drain
9 Maruthi nagara Secondary drain to storm
motor drain
Secondary drain to storm
motor drain
10 In Buddhanagara near stadium
road
Secondary drain to storm
motor drain
Secondary drain to storm
motor drain
Table: Flood prone points in the city
Sr.
No. Area No of points
No of times water logging reported in a
year ( stagnant water for more than four
hours of a depth more than 6” )
1 Key road intersection 10 10 to15 times
2 Along roads ( 50 mtrs
length or more)
6 5 to 10 times
3 Locality (affecting 50 HH
or more)
6 6 to 8 times
Table 1.2: Detail of Locations prone to chocking of drains due to solid waste
Sr.
No. Location
Stretch Length
Affected Reason
1 Ward no.18 Idgamohalla 1st cross
drain
50mtr Due to dumping of solid waste.
2 Ward no.27 near Airoplane building 50mtr Due to dumping of solid waste.
3 Ward no.15 Bhovi colony 50mtr Due to dumping of solid waste.
20
Sr.
No. Location
Stretch Length
Affected Reason
4 Ward no.1 opp Nagarakatte 100mtr Due to dumping of solid waste.
5 Ward no.33 opp Christian burial
ground
60mtr Due to dumping of solid waste.
6 Ward no.19 opp Majed NH-4 100mtr Due to dumping of solid waste.
7 Ward no.18 Medehally road
Bomboo bazar
100mtr Due to dumping of solid waste.
8 Ward no.18 M H road APMC 2nd
gate
60mtr Due to dumping of solid waste.
Planning and Design
Construction/
Implementation O&M
ULB Chitradurga ULB and appointing Project
Management Consultancy
(PMC)
O & M by ULB
Table: Status of Ongoing/ Sanctioned Project
Sl.No. Name of Project Scheme Name
Cost in
Rs
Corer Month of Completion
Status (as on dd
mm 2015)
1 Nil Nil Nil Nil Nil
21
Table:1.5 Demand Gap Assessment for Storm Water Drainage Sector
COMPONENT
2015 2021
PRESENT
ONGOING
PROJECTS TOTAL DEMAND GAP
Major drains(new
construction)
5 0 5 25 kms 20 kms
Network requirement to
provide proper drainage
to all identified water
stagnant point flodding
points up to the end
discharge point in(kms)
2.5 0 2.5 25 kms 22.50kms
Network length where
households discharging
waste water directly in to
the drains
10 0 10 kms 20 kms 10 kms
Rejuvenation of existing
primary drains and
primary drains including
covering and installation
of filter
0 0 0 3 kms 3 kms
22
Table: Alternative Activities To Meet Objectives
Sr.
No. Objective Activities Financing Source
1 Construction of Storm
Water Drain to avoid
flooding and water logging
due to heavy rains
Identifying the water logging points,
chocking of drains, surveying. Data
collection, DPR preparation, DPR
approval, tendering process,
implementation and execution and
completion.
GOI(AMRUT
Scheme), State
Government and
ULB
23
Citizen Engagement:
ULB Organized and conducted city level citizen consultation with
35 Councilors, Publics and NGOs. And discussed construction of
Strom motor drain in the City. Feedback received from
Councilors, Publics and NGOs are that boundaries of SWD to be
fixed, awareness to be given by capable persons to Publics and
SWD work will carried out without any problem to publics. And
maximum safety measures to be taken. All SWD works to be
taken up in the city. Preference should be given where water
flooding and water logging area are located there to avoid the
flooding and water logging the SWD project is proposed first.
Prioritize Projects:
Main source of funding is Governament of India and State
Governament and ULB to cover universal coverage.
Conditionalities:
Availability of land no issues. Financial commitment by GOI/state government /ULB. Approved and permission is needed for implementation as per AMRUT Guidelines. Environmental obligation No issues in SWD only rain water and waste water from residential area will be received in this drain industrial waste is not included. NOC is not required.
Resilience:
The Proposed SWD is surveyed and designed to with stand earth pressure and water pressure. The Construction of SWD including quality materials and quality of work is maintained.
24
Financial Plan:
The project implemented by central /state government /ULB
funding scheme. Construction of SWD to avoid water logging and
water flooding.
Financial plan is sharing basis. Government of India is sharing 50% and
State Government is 20% and ULB 30% sharing pattern of the total
approval project cost.
Table 1.7: Master Plan of storm water drainage Projects for Mission Period
(As per Table 2.1 of AMRUT guidelines
Sl.No. Project Name
Priority
number
Year in which to be implemented
Year in which proposed to be
completed
Estimated Cost
1 Construction of storm
water drain at Babu
Jagajeevan Ram Nagara
Ramakrishna ashrama
Housing board colony
through IUDP
Sarswathipuram 1st cross
1 2016 2017 4.0
2 Construction of storm
water drain at K.S.R.T.C
Layout through Teachers
Colony Onakeonake
obavva Circle
2 2017 2017 3.0
3 Construction of storm
water drain at Back side of
regional school to Kothwal
Nagara 4th Cross
3 2018 2018 2.0
4
Construction of storm
water drain at KMRP Fish
Babanna house to NH-4
4 2019 2019 1.0
Grand - Total 10.00
25
TABLE 1.8: MASTER SERVICE LEVELS IMPROVREMENTS DURING MISSION PERIOD
(As per Table 2.2 of AMRUT guidelines)
(Amount in Rs. Cr)
Sl.
No.
Project Name
Physical Components
Change in Service Levels Estimated
Cost
Indicator Existing
(As-ls)
After
(To-be)
1 Construction of storm
water drain at Babu
Jagajeevan Ram Nagara
Ramakrishna Ashrama
Housing board colony
through IUDP
Sarswathipuram 1st cross
RCC SWD side drain
wall, bed wall with
covering slabs
100% 17.30% 18.38% 4.00
2 Construction of storm
water drain at K.S.R.T.C
Layout through Teachers
Colony Onake obavva
Circle
RCC SWD side drain
wall, bed wall with
covering slabs
100% 18.38% 19.75% 3.00
3 Construction of storm
water drain at Back side
of regional school to
Kothwal Nagara 4th
Cross
RCC SWD side drain
wall, bed wall with
covering slabs
100% 19.75% 20.41% 2.00
4 Construction of storm
water drain at KMRP
Fish Babanna house to
NH-4
RCC SWD side drain
wall, bed wall with
covering slabs
100% 20.41 20.76% 1.00
26
TABLE 1.9: ANNUAL FUND SHARING PATTERN FOR STORM WATER
PROJECTS
(As per Table 2.3.1 of AMRUT guidelines)
(Amount in Rs. Cr)
Sl. No.
Name of Project
Total Project
Cost
Share
GOI State ULB Others Total
1 Construction of storm
water drain at Babu
Jagajeevan Ram Nagara
Ramakrishna ashrama
4.0 2.0 0.8 1.2 0 4.0
2 Construction of storm
water drain at K.S.R.T.C
Layout through Teachers
Colony
3.0 1.5 0.6 0.9 0 3.0
3 Construction of storm
water drain at Back side of
regional school to
KothwalNagara 4th Cross
2.0 1 0.4 0.6 0 2
4 Construction of storm
water drain at KMRP Fish
Babanna house to NH-4
1.0 0.5 0.2 0.3 0 1
27
1.10 ANNUAL FUND SHARING BREAK-UP FOR STORM WATER
PROJECTS
(As per Table 2.3.2 of AMRUT guidelines)
Sr.
No.
Project
GOI
State ULB Convergence
others
Total
14th
FC
Others Total 14th
FC
Others Total
1 Construction of
storm water drain
at Babu
Jagajeevan Ram
Nagara
Ramakrishna
ashrama Housing
board colony
through IUDP
Sarswathipuram
1st cross
2.0 0 0.4 0.4 0 1.6 1.6 0 0 4.0
2 Construction of
storm water drain
at K.S.R.T.C
Layout through
Teachers Colony
Onake obavva
Circle
1.5 0 0.6 0.6 0 0.9 0.9 0 0 3.0
3
Construction of
storm water drain
at Back side of
regional school
to Kothwal
Nagara 4th Cross
1.0 0 0.2 0.2 0 0.8 0.8 0 0 2
28
Sr.
No.
Project
GOI
State ULB Convergence
others
Total
14th
FC
Others Total 14th
FC
Others Total
4 Construction of
storm water drain
at KMRP Fish
Babanna house
to NH-4
0.5 0 0.2 0.2 0 0.3 0.3 0 0 1.0
TABLE 1.11: YEAR WISE PLAN FOR SERVICE LEVELS IMPROVEMENTS
(As per Table 2.5 of AMRUT guidelines)
Sr
No.
Proposed
Projects
Project
Cost Indicator Baseline
Annual Targets
(Increment from the Baseline Value)
FY 2016 FY
2017
FY
2018
FY
2019
FY
2020 H1 H2
1 Construction of
storm water
drain at Babu
Jagajeevan
Ram Nagara
Ramakrishna
ashrama
Housing board
colony through
IUDP
Sarswathipuram
1st cross
4.0 100% 17.30% 18.38%
2 Construction of
storm water
drain at
K.S.R.T.C
Layout through
Teachers
Colony Onake
obavva Circle
3.0 100% 18.38% 19.75%
29
Sr
No.
Proposed
Projects
Project
Cost Indicator Baseline
Annual Targets
(Increment from the Baseline Value)
FY 2016 FY
2017
FY
2018
FY
2019
FY
2020 H1 H2
3 Construction of
storm water
drain at Back
side of regional
school to
Kothwal
Nagara 4th
Cross
2.0 100% 19.75% 20.41%
4 Construction of
storm water
drain at KMRP
Fish Babanna
house to NH-4
1.0 100% 20.41% 20.76%
30
Design of Storm Water Drain
Total length of SWD is 1860mtrs
Length of Constructed SWD is 200mtrs
Difference in Levels 775.466 – 717.406=58.06mtrs
Depth of SWD is
Minimum depth is 2.0mtrs
Maximum depth is 4.0mtrs
Thickness SWD is
H/10 or H/15
Thickness of SWD side wall = 2300/10=230mm=0.23mtr
Thickness of the SWD side at Maximum depth = 4000/10=400mm=0.4mtr
Adopting slop 1 in 200
Velocity is 0.6mtr/sec to 0.75mtr/sec
SBC of Soil is 135KN/m2 to 140KN/m2