india: accelerating infrastructure investment facility in india ......the state of west bengal and...
TRANSCRIPT
Environmental and Social Due Diligence Report
Project Number: 47083-004 December 2019
INDIA: Accelerating Infrastructure Investment
Facility in India – Tranche 3 Ashoka Ranastalam Anandapuram Road Limited (Part 1 of 4)
Prepared by India Infrastructure Finance Company Limited for the India Infrastructure Finance
Company Limited and the Asian Development Bank.
This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 1
Due Diligence Report on Environment and Social Safeguards
By
India Infrastructure Finance Company Limited (IIFCL)
(A Govt. of India Enterprise)
Sub-Project: Six-laning of NH-16 from Ranastalam to Anandapuram
(Vishakhapatnam) (from km 634.000 to km 681.000) in the State of Andhra
Pradesh under NHDP Phase-V on Hybrid Annuity Mode (Package II)
June 2019
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 2
SUB PROJECT: Six-laning of NH-16 from Ranastalam to Anandapuram
(Vishakhapatnam) (from km 634.000 to km 681.000) in the State of Andhra
Pradesh under NHDP Phase-V on Hybrid Annuity Mode (Package II)
Ashoka Ranastalam Anandapuram Road Limited (ARARL)
Environment and Social Safeguards Due Diligence Report
(ESDDR)
Prepared by Dr. Rashmi Kadian
Assistant General Manager
(Environmental Specialist)
ESMU, IIFCL
Mr. Krupasindhu Guru
Assistant General Manager
(Social Specialist)
ESMU, IIFCL
Reviewed and Approved by Dr. S. S. Garg
Head, ESMU
IIFCL
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 3
CONTENTS
PROJECT BACKGROUND ....................................................................................................... 5
1. PURPOSE OF THE REPORT ........................................................................................... 6
2. SUB-PROJECT TITLE ..................................................................................................... 6
3. SUB-PROJECT BACKGROUND ...................................................................................... 6
4. SUB-PROJECT LOCATION & DESCRIPTION ................................................................ 6
5. CONCESSIONAIRE ......................................................................................................... 9
6. EPC CONTRACTORS ...................................................................................................... 9
7. INDEPENDENT ENGINEER ............................................................................................ 9
8. IIFCL FUNDING .............................................................................................................. 9
9. STATUS OF PROJECT IMPLEMENTATION .................................................................. 9
DUE DILIGENCE ON ENVIRONMENTAL SAFEGUARDS .................................................... 10
10. ENVIRONMENT SAFEGUARDS COMPLIANCE REVIEW .......................................... 11
11. APPLICABILITY OF ENVIRONMENTAL IMPACT ASSESSMENT NOTIFICATION .. 11
12. APPROACH TO THE ENVIRONMENT SAFEGUARDS DUE DILIGENCE REPORT: .. 11
13. COMPLIANCE OF THE SUB PROJECT TO THE ESSF OF IIFCL: .............................. 12
14. POLICY, LEGAL AND REGULATORY REQUIREMENT: ............................................ 12
15. IMPACT ASSESSMENT OF SUB-PROJECT .................................................................. 15
16. IMPLEMENTATION OF ENVIRONMENTAL MANAGEMENT PLANS ....................... 16
17. HEALTH AND SAFETY ................................................................................................. 20
18. GRIEVANCE REDRESSAL MECHANISM .................................................................... 20
19. ENVIRONMENTAL SENSITIVITY ................................................................................ 21
20. PROJECT AGAINST THE PROHIBITED INVESTMENT ACTIVITIES LIST ............... 21
21. CATEGORIZATION OF SUB-PROJECT ....................................................................... 21
22. SITE VISIT OBSERVATIONS ........................................................................................ 22
23. CONCLUSIONS AND RECOMMENDATIONS .............................................................. 25
DUE DILIGENCE ON SOCIAL SAFEGUARDS ....................................................................... 27
24. PURPOSE OF THE SOCIAL SAFEGUARDS DUE DILIGENCE .................................... 28
25. PROJECT AGAINST THE PROHIBITED INVESTMENT ACTIVITIES LIST ............... 28
26. OBJECTIVE OF SOCIAL SAFEGUARDS DUE DILIGENCE ......................................... 28
27. APPROACH AND METHODOLOGY ............................................................................. 28
28. SOCIAL IMPACT OF THE PROJECT ........................................................................... 29
27.1 LAND ACQUISITION IN THE PROJECT ...................................................................... 29
27.2 IMPACT ON STRUCTURE ............................................................................................ 30
27.3 REHABILITATION AND RESETTLEMENT IMPACT IN THE SUB-PROJECT ............ 30
27.4 IMPACT ON INDIGENOUS PEOPLE ............................................................................ 30
29. GREIVANCE REDRESSAL MECHANISM FOR THE SUB-PROJECT .......................... 30
30. EMPLOYMENT GENERATION .................................................................................... 31
31. THE COMMUNITY ENGAGEMENT ACTIVITIES ....................................................... 31
32. LABOUR LICENSE OBTAINED BY THE SUBPROJECT DEVELOPER ....................... 32
33. DISCLOSURE ................................................................................................................ 32
34. SITE VISIT OBSERVATION .......................................................................................... 32
LIST OF FIGURES
Figure 1: Project Location on Map………..……..……………………………………………………7
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 4
LIST OF TABLES
Table 1: Salient Features of Ashoka Ranastalam Anandapuram Road Limited…………………….8
Table 2: Status of Regulatory Permits/ Clearances Obtained related to Environmental Safeguards…12
Table 3: Status of EMP Implementation at ARARL…………………………………………………….16
ANNEXURES
Annexure I Environment Management Plan of ARARL
Annexure II Tree Cutting Permission Srikakulum
Annexure III Tree Cutting Permission Vizianagaram
Annexure IV Tree Cutting Valuation Vishakhapatnam
Annexure V Consent to Establish
Annexure VI Consent to Operate
Annexure VII Borrow Area Permissions from Mining Deptt.
Annexure VIII Borrow Area Permissions from Irrigation Deptt.
Annexure IX Labour License
Annexure X Labour Insurance
Annexure XI Borewell Permissions
Annexure XII Environmental, Safety and Social Management System Manual
Annexure XIII Avenue & Median Plantation Scheme
Annexure XIV Emergency Response Plan
Annexure XV Environmental Monitoring Reports
Annexure XVI Traffic Safety Management Plan
Annexure XVII Organizational Chart of ARARL for EHS
Annexure XVIII Grievance Redressal Mechanism Guidelines
Annexure XIX RoW Handover Letter
Annexure XX Local employment details
Annexure XXI Community Development Activities
PHOTOPLATE
Photoplate I : Site Visit Photographs
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 5
PROJECT BACKGROUND
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 6
1. PURPOSE OF THE REPORT
1. This Environmental and Social Due Diligence Report (ESDDR) has been carried out by India
Infrastructure Finance Company Limited (IIFCL) in consultation with the Concessionaire,
Ashoka Ranastalam Anandapuram Road Limited (ARARL) to assess the adequacy of the
project with the applicable national, IIFCL’s ESSF and ADB’s safeguard compliance. The
report has been prepared as per the documents/information received from the Concessionaire
and on the basis of site visit observations.
2. SUB-PROJECT TITLE
2. The sub-project includes - Six-laning of NH-16 from Ranastalam to Anandpuram
(Visakhapatnam) (from km 634.000 to km 681.000) in the state of Andhra Pradesh under NHDP
Phase-V on Hybrid Annuity Mode (Package II).
3. SUB-PROJECT BACKGROUND
3. National Highways Authority of India (NHAI), during January 2017, invited proposals from
various bidders for construction, operation and maintenance of the 6 laning of NH16 from
Ranastalam to Anandapuram (Visakhapatnam) from km 634.000 to km 681.000 (approx. 47
Kms) in the State of Andhra Pradesh under NHDP Phase V (Package II) on Design, Build,
Operate and Transfer (Hybrid Annuity) basis. NHAI awarded the Project to Ashoka
Concessions Limited (ACL) and established Ashoka Ranastalam Anandapuram Road Limited
(ARARL) for development of the Project. ARARL is a special purpose vehicle (SPV) formed as
a 100% subsidiary of Ashoka Concessions Ltd (ACL), a holding company of road assets of
Ashoka Buildcon Limited (ABL).
4. The site of the existing four-lane divided project highway is situated from Km 634.000 to Km
681.000 of Ranastalam to Anandapuram section of NH-16 in the state of Andhra Pradesh.
4. SUB-PROJECT LOCATION & DESCRIPTION
5. The sub-project road is part of NH-16. NH-16 is a part of golden quadrilateral, connects Kolkata in
the state of West Bengal and Chennai in the state of Tamilnadu. Under the present project, the
existing 4 lane section of NH-16 from Ranastalam at Km 634.000 (design chainage Km 634.000) to
Anandapuram at Km 681.000 (design chainage Km 681.000) is being upgraded to 6-lane divided
highway. The entire sub-project stretch falls in Srikakulum, Vizianagaram and Vishakhapatnam
districts in the state of Andhra Pradesh. This section of NH-16 is passing through plain terrain. The
proposed scheme is being developed keeping in view the six lane cross section along with additional
facilities to be developed in such a manner that the improvements are accommodated to the
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 7
maximum extent within the proposed right of way. Existing raised median of 4.5M is retained in the
entire reach and widening is proposed on outer side for both the carriage ways.
6. ARARL has entered into a Concession Agreement (CA) with the Authority on 2nd May 2017 for
construction, operation and maintenance of the Project. The CA sets out the scope, rights and
obligations of all the parties, overall framework for the development, operation and maintenance of
the Project. The Bid project cost of the project is Rs 1,187 Cr. The concession period is for 17.5 years
including construction period of 2.5 years. The Project is expected to achieve SCOD on May 15,
2020 based on 910 days of construction period from the Appointed Date i.e. November 16, 2017.
NHAI shall fund the 40% of the Bid Project Cost adjusted for Price Index Multiple, during the
construction period in the form of grant. The grant shall be disbursed in 5 equal installments of 8%
each. Annuity payments shall be made half yearly basis, which would consist of annuity payments
(60% of bid cost adjusted for price index multiple); interest payments (RBI Bank Rate plus 3%) and
O&M cost adjusted for price index multiple to be paid semiannually till the tenor of concession
agreement.
7. The alignment will pass through settlements of Ranastalam, Pusapatirega, Pydi Bheemavaram,
Boghapuram and Anandapuram. Additional land shall be acquired for Toll plazas, interchanges, rest
areas and truck parking. In view of future growth one new interchange is proposed at access road to
Bhogapuram International Airport. There are 2 major bridges on the project corridor. These bridges
are proposed to be retained and are to be repaired/strengthened/widened as per the concession
agreement. One toll plaza is proposed at Natavalsa at chainage Km 656.700 (Design chainage
656.700 Km). The subproject location is given in Figure 1
Figure 1: Project Location on Map
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 8
8. The sub-project will provide the widening and strengthening of existing 4 lanes Section of NH-16
and its Operation and Maintenance (O & M). The work also includes the widening of existing
bridges, culverts and construction of new bridges/culverts for new carriageway. The Salient features
of the sub-project are given in Table 1.
Table 1: Salient Features of Ashoka Ranastalam Anandapuram Road Limited
Particulars Features
Project Road NH -16 Section from Ranstalam (km 634.000) to
Anandapuram (km 681.000)
State Andhra Pradesh
District Srikakulum, Vizianagaram and Vishakhapatnam
Concessioning Authority National Highways Authority of India (NHAI)
Concessionaire M/s Ashoka Ranastalam Anandapuram Road Limited
Terrain Plain
Important Town Ranastalam, Pusapatirega, Pydi Bheemavaram,
Boghapuram and Anandapuram
Project Length 47 km
Junctions Major Junction – 2
Minor Junction – 52
Bypass Nil
Toll Plaza 1 at Natavalasa
Flyover (Nos.) 1 at Km 641.230
Interchange 1 at Km 665.640
Service & Slip Road Service road – 32.304 Km (LHS - 15.560 Km; RHS -
16.744 Km)
Slip Road – 43.960 Km (LHS – 21.290 Km; RHS – 21.290
Km)
Total – 76.264 Km (LHS – 37.540 Km; RHS – 38.724
Km)
Vehicular Under Pass (Nos.) 7
Lower Vehicular Underpass (New) 13
Major Bridges 2 at Champavati & Gostani rivers
Minor Bridges on main carriageway (Nos.) 2
Minor Bridges on Service Road (Nos.) 8
Cross Drainage works 137
Major Intersections (Nos.) 2
Minor Intersections (Nos.) 52
Rest Area (Nos.) 1
Truck Lay bye (Nos.) 1
Bus Bay with Bus Shelter (Nos.) 36
Helipad 1
Source: Independent Engineer Report, January 2019 & as per information provided by Developer.
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 9
5. CONCESSIONAIRE
9. NHAI has appointed M/s. Ashoka Ranastalam Anandapuram Road Limited (ARARL) as the
concessionaire for this sub-project. ARARL is a Special Purpose Vehicle (SPV) company
promoted by Ashoka Buildcon Limited (ABL). ARARL has entered CA with NHAI on
2.05.2017 for a concession period of 17.5 years from the Appointed Date including construction
period of 910 days.
6. EPC CONTRACTORS
10. Ashoka Buildcon Limited (ABL), Nashik is the turnkey EPC and O&M contractor for the sub-
project. EPC agreement has been signed between ABL and ARARL on 30.9.2017.
7. INDEPENDENT ENGINEER
11. The contract agreement between NHAI and M/s MSV International Inc. in association with
ARMENGE Engineering and Management has been signed to monitor the sub-project as
Independent Engineer (IE).
8. IIFCL FUNDING
12. The total project cost of ARARL is ₹ 1187.10 crores. The project is financed by IIFCL under
Direct Finance Scheme. IIFCL has sanctioned an amount of ₹ 194 crore towards ARARL and IIFCL
has disbursed ₹ 86.00 crores as on 30.4.2019.
9. STATUS OF PROJECT IMPLEMENTATION
13. The sub-project is under construction and the Scheduled Commercial Operations Date (SCOD) is
expected to be May 15, 2020 based on 910 days from the Appointed Date of November 16, 2017. As
per IE report of January 2019, 39.20% physical progress has been achieved at ARARL. At the time
of site visit during 9th-10
th April, 2019, ARARL staff has informed that approximately 47% physical
progress has been achieved.
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 10
DUE DILIGENCE ON ENVIRONMENTAL SAFEGUARDS
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 11
10. ENVIRONMENT SAFEGUARDS COMPLIANCE REVIEW
14. The environmental due diligence (EDD) report focuses on the status and review of the applicable
environmental regulatory requirements, compliance to the regulatory requirements, review of the
environment related sub-project documents, implementation to the Environmental Management
Plans (EMPs), institutional arrangements for implementation and monitoring of environmental
mitigation measures, EMP planned for operation phase, environment, health & safety (EHS) related
clauses in agreements, health and work safety measures, status of plantations, safety and emergency
preparedness plan. The EDD also reviews the environment & social management system of the sub-
project developer.
11. APPLICABILITY OF ENVIRONMENTAL IMPACT ASSESSMENT NOTIFICATION
15. It is required that the project meets the applicable national guidelines / regulations relating to the
environment, occupational health and safety and social issues. The project should have necessary
clearances as well as permits and approvals for project implementation and suitable environmental
management plans.
16. National Highway projects up to 100 Kms involving additional right of way or land acquisition upto
40 meters on existing alignments and 60 meters on re-alignments or by-passes are exempted from
the preview of the Environmental Impact Assessment Notification, 2006 of Government of India.
The total length of the sub-projects is approximately 47 Kms, therefore, ARARL does not require
environmental clearance and is not required to conduct an Environmental and Social Impact
Assessment (ESIA) as a statutory requirement. A detailed Environmental Management Plan (EMP)
is prepared for the sub-project, based on the impacts envisaged by the sub-projects and the EMP is
being implemented at the sub-project.
12. APPROACH TO THE ENVIRONMENT SAFEGUARDS DUE DILIGENCE REPORT:
17. The Environmental Due Diligence Report (EDDR) reviews the available documents and assesses the
compliance of the sub-project with the respect to environmental safeguards; regulatory clearances;
environmental impacts and management measures; EMP implementation; Health, Safety and
Environment (HSE) measures; and categorization of sub-project on the basis of above review.
18. The following documents were referred in order to prepare Environmental Safeguards Due-
Diligence Report:
Project Information Memorandum (PIM)
Concession Agreement
Environment Management Plan (EMP) and its implementation
Feasibility Study of ARARL
Independent Engineer’s (IE) Report
Lender’s Independent Engineer (LIE) Reports
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 12
Project Statutory Approvals/Permits
Project HSE Documents
Labour License & insurance
Contract Documents
Environment, Safety and Social Management System Manual
Emergency Response Plan
Grievance Redressal Mechanism
19. The environmental safeguard due-diligence study was carried out for the sub-project on the basis of
site visit observations and understanding project scope based on information and documents
provided by Concessionaire. A detailed discussion on the environmental and social safeguards
related issues was also carried out with the team of the sub-project at site.
13. COMPLIANCE OF THE SUB PROJECT TO THE ESSF OF IIFCL:
20. The Environmental and Social Safeguard Framework (ESSF) provides the enabling mechanism to
IIFCL to deliver its policy objectives and applies to projects funded by IIFCL throughout the project
cycle. The ESSF defines procedures, roles, and responsibilities, at various project milestones for
managing the adverse environmental impacts. The environmental due diligence for ARARL has
been done as per requirements of direct lending scheme of IIFCL. The environmental safeguard risks
during construction phase have been assessed and risks during operational phase have been
evaluated. ARARL is under construction. There does not seem to be any significant risk for either
IIFCL or DFI involved. The environmental measures being implemented at the sub as per EMP. It
can be concluded that ARARL is compliant to the requirements of IIFCL’s ESSF under direct lending scheme and has adequate EMP implementation on site.
14. POLICY, LEGAL AND REGULATORY REQUIREMENT:
21. ARARL does not fall under the schedule of EIA Notification, 2006 that lists projects or activities
requiring prior environmental clearance and hence these are exempt from obtaining environmental
clearance. ARARL is required to comply with the applicable guidelines relating to the environment,
occupational health and safety in addition to complying with local pollution control board
regulations. The statutory permits/clearances related to environmental aspects obtained/to be
obtained from regulatory authorities as part of ARARL development were assessed and current
status of availability of such permits/clearances are given in Table 2 below:
Table 2: Status of Regulatory Permits/ Clearances Obtained related to Environmental Safeguards
S.No. Permits/Clearances Statutory Authority Current Status
1. Environmental
Clearance
Ministry of
Environment, Forests &
Climate Change
(MoEF&CC), New
Not Applicable. As the sub-project length is below
100 kms (~47 Kms), this is exempted from
obtaining environmental clearance and conducting
EIA. An EMP has been prepared for ARARL
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 13
Delhi which is being implemented at the sub-project
(Annexure I). The status of EMP is reported in
the subsequent sections of the ESDDR.
2. Forest Clearance MoEF&CC and State
Forest Department
The sub-project does not involve any forest land.
3. Wildlife Clearance MoEF&CC The Project area does not lie within an
ecologically sensitive area and is not located close
to any National Park/Wildlife Sanctuary. The
location of Project does not contravene any
international biodiversity or ecosystem
conservation conventions. Therefore, it does not
require wildlife clearance or permission.
4. Tree cutting
permissions
State Forest
Department, Andhra
Pradesh
Sub-project involves cutting of trees during
highway expansion. Tree cutting permissions have
been taken from three district forest authorities
viz., Srikakulum Forest Department letter dated
7.7.2017 for 3439 no. of trees (Annexure II);
Vizianagaram Forest Department letter dated
2.8.2017 for 3399 no. of trees (Annexure III) and
Vishakhapatnam Forest Department for 3440 no.
of trees (Valuation report dated 18.8.2017 attached
as Annexure IV).
5. Consent to Establish
Andhra Pradesh
Pollution Control Board
(APPCB), Andhra
Pradesh State
Consent to Establish under section 25 of Water
(Prevention & Control of Pollution) Act, 1974 and
under section 21 of Air (Prevention & Control of
Pollution) Act 1981 was obtained from Andhra
Pradesh Pollution Control Board on 27.9.2017
(Annexure V).
6. Consent to Operate Andhra Pradesh
Pollution Control Board
(APPCB), Andhra
Pradesh State
Consent to Operate under section 25/26 of the
Water (Prevention & Control of Pollution) Act,
1974 and under section 21 of Air (Prevention &
Control of Pollution) Act 1981 and amendments
thereof and Authorization under Rule 6 of the
Hazardous and other Wastes (Management and
Transboundary Movement) Rules, 2016 is taken
on 5.2.2018 for all units (Annexure VI).
7. Borrow Area
Permissions
Mining and Geology
Department,
Government of Andhra
Pradesh; Irrigation
Department,
Government of Andhra
Pradesh
ARARL has borrow areas utilized/in use at the
sub-project. Borrow earth permissions have been
granted in favour of Ashoka Buildcon Limited for
and in favour of J. Kishore for one borrow area to
be utilized for NH-16, Ashoka Ranastalam
Anandapuram – six laning road project by
Department of Mines & Geology, Government of
Andhra Pradesh. As per Andhra Pradesh Minor
Mineral Concession Rules-1966, under clause 9 of
sub-clause (iii), the Competent Authority (Deputy
Director/Assistant Director for Department of
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 14
Mines & Geology) is authorized to issue
permission on temporary basis i.e. “Temporary Permit” to operate the borrow earth quarry on payment of royalty fee in advance for the works to
meet the timely or immediately requirements. The
temporary permits are issued for the project period
and/or less than project period. The excavated
borrow earth is to be utilized only for the project
and not for sale or any other commercial use. The
developer has confirmed from the Authorities that
for such temporary permits environmental
clearance is not mandatory and hence the
department concerned is allowing temporary
permit holder for excavation and transportation of
earth to the works area.
Government of India, Ministry of Road Transport
& Highways has issued a Notification vide
reference RW/NH-34066/09/2017-s&r(b) dated
31.08.2017 w.r.t. utilization of Borrow earth from
irrigation ponds on free of cost by NHAI & other
projects only. Accordingly, Government of
Andhra Pradesh, Water Resources (CADA)
Department has also issued a Notification vide
reference G.O.Ms.No.40 dated 21.05.2018,
wherein referred under Clause 7 of III that a
security deposit of Rs l per cubic meter of silt is to
be remitted and the cost of material is free of
charges under Clause 7 of IV. With reference to
the Central and State Government notifications,
Executive Engineer, Vijayanagaram has issued
letters to the Project Director, NHAI (PIU),
Visakhapatnam with a remittance of caution
deposit (refundable) @ Rs l per cubic meter of the
quantity to be lifted and operate the excavation &
transportation from the pond. Sample copies of
permissions are attached as Annexure VII &
VIII.
8. Labour License &
Insurance
Licensing Officer &
Assistant
Commissioner of
Labour, Government of
Andhra Pradesh
ARARL has taken Labour License under the
Contract Labour (Regulation and Abolition) Act,
1970 (Annexure IX).
The establishment has valid labour insurance
which is enclosed as Annexure X.
9. Borewell Permissions Ground Water and
Water Audit
Department,
Government of Andhra
Pradesh
ARARL and its sub-contractors have taken
permissions for digging borewells for drawing
water for construction purpose sample copies are
attached as Annexure XI.
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 15
15. IMPACT ASSESSMENT OF SUB-PROJECT
22. EIA study was not conducted for the sub-project due to explanation provided in Section 11 of the
EDDR. An EMP is prepared for ARARL (Annexure I). EMP outlines the impacts of the sub-
project. The main impacts envisaged due to various activities at the sub-project are summarised in
the paragraphs below:
23. Impact on Land Environment: The sub-project involves strengthening and widening of the
existing four lanes to six lane highway. During construction phase the topography at sub-project
location will change due to excavation of borrow areas, cuts and fills for project road and
construction of project related structures. The impacts are temporary and are manageable with
mitigation measures which are given in Section 15.
24. Impact on Water Resources: Along the sub-project stretch, 54 water resources are present
including wells, hand-pumps, tanks and over-head tanks. These are the mainly sources of potable
water. Three rivers viz., Kandivalasagadda, Champavathi and Gosthani are present along the sub-
project section with few water bodies. Two bridges on river Chamapvathi and Gostani are part of the
sub-project. As per the design no partial / complete loss of water body will take place. Hence no loss
in volumetric capacity of water resources is envisaged. Adverse impact on surface and ground water
resources is envisaged during construction phase due to increased sedimentation load because of
construction activities, waste water discharge from labour camps, fuel/oil from construction vehicles
etc. During the operation stage the leakage or spillage from vehicles damaged, overturned or just
badly maintained may also lead to contamination of water bodies. EMP has been proposed to
manage these impacts.
25. Impact on Air Quality: The setting up of camp including hot mix plant, crusher & ready mix
concrete plant, and up-gradation works at sub-project stretch shall involve generation of dust and
release of other pollutants leading to the localised degradation of air quality. The plants are
environment friendly with attachment of bag house to hot mix plant. All the belt conveyors are
covered with canopy to control the dust pollution, ready mix concrete plant is well equipped with
the cartage filters. All aggregate stock yards are provided with water sprinkling system.
Mitigation measures are in place to manage these not very significant and temporary impacts.
26. Impact on Noise Environment: Impact on noise environment is envisaged during both
construction and operation phases. The baseline noise levels are below the prescribed limits. In
construction phase, all DG Sets having acoustic attachments to control noise at source. ARARL
has proactive plant and machinery maintenance schedule to control noise and air pollution.
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 16
27. Impact on Biological Environment: No National Park or Wildlife Sanctuary is located within
close proximity of the project road and there is no notified animal corridor/migration route is
present in the project area. No Protected / Reserve Forest are located along the project road. About
10,278 trees are likely to be affected in upgradation of NH-16 for which permissions from the
Forest Department have been obtained. No significant impacts on fauna are anticipated at the sub-
project. The repair and up gradation of minor bridges will cause some contamination of the river /
canal water due to spillage of construction material, sediment loading & increased turbidity
downstream of the bridge location. This may impact aquatic flora and fauna temporarily.
Necessary mitigation measures have been recommended at locations of structure where
construction/maintenance is proposed.
16. IMPLEMENTATION OF ENVIRONMENTAL MANAGEMENT PLANS
28. The status of EMP implementation is elaborated in the subsequent paragraphs on the basis of
information received from the developer and on confirmation of the same by site visit. EMP is
being implemented at ARARL and the status of implementation is being maintained at site and
communicated to ARARL corporate level on quarterly basis.
29. ARARL has a separate EMP budget including that for health and safety related issues. Budgetary
provision for HSE for the year 2019-20 is ₹ 1.99 crores.
30. Ashoka Group has its own Environmental, Safety and Social Management System Manual,
which is applicable at its projects (Annexure XII).
31. The EMP implementation status on the basis of documents/information shared by developer and
confirmations at the time of site visit is given in Table 3.
Table 3: Status of EMP Implementation at ARARL
Issues EMP Status of EMP Implementation
Avenue tree cutting and
Plantation
10278 no. of trees are to be cut according to
Forest Department permissions at the sub-
project. Then avenue plants proposed
along the project stretches are as per IRC-
SP-21:2011. The avenue plants proposed to
be planted in the sub-project are about
42,157 on either side of the road in two
rows.
Tree felling permissions have been obtained
from Forest department. Sub-project
developer has informed that Avenue
plantation began from monsoon of the year
2019. Typical plan for avenue plantation is
attached as Annexure XIII.
Tree translocation Approximately 700 nos. of trees to be
translocated at the sub-projects
700 nos. of trees were translocated at the sub-
project.
Median Plantation Median plantation to be done as per IRC.
Approximately 667plants will be planted
Median plantation has begun in May 2019.
Typical plan for median plantation is attached
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 17
every km. as Annexure XIII.
Borrow pits and Quarry
sites
Borrow of Earth shall be carried out
up to depth of 2.0m in non-cultivable
& elevated lands, 0.45 m in
productive lands etc. with a slope of
not steeper than 1 vertical to 4
horizontal.
Borrow areas shall be 15 m away
from the water bodies identified
along the project corridor.
The borrow areas shall be located at
least 800 m away from the
villages/towns.
All the conditions of location are being met at
all borrow areas. Resurfacing and landscaping
of the borrow pits utilized in the project will
not be needed as the borrow earth is removed
from either hill or ponds.
Site for storage and
construction camp
Storage of HSD, Bitumen will be
expected as per the stipulated
guidelines.
Besides these, emergency response
plan will be in place towards meeting
unforeseen emergencies.
Trained personnel will be handling
such materials and care will be taken
so that spills are abated and in case of
spills, immediately they are
contained.
Storage is done at designated areas, with
markings and signboards.
Emergency response plan is in place for
ARARL (Annexure XIV).
Trainings are imparted to labour and
staff and forms part of the HSE
performance indicators.
Sewerage and solid waste
disposal.
For sewerage disposal, septic tanks
with soak pits will be provided at
campsites. Proper sanitation facilities
at the construction workers camp to
be provided.
Salvage material/ demolition wastes
will be reused to the possible extent
in embankments, shoulders, slopes,
approach roads and temporary
campsites.
It is envisaged that approximate 300-
500 Kg of domestic solid waste (300-
500 gm/person) per day will be
generated from the workers camps
which will be disposed of to the
nearest solid waste disposal sites.
Septic tanks with soak pits are provided
at site. Proper toilets and bathrooms are
provided at labour camps.
Camp haul roads and Borrow area haul
roads are maintained with salvage
material / demolition wastes.
Proper solid waste management with
different colour dust bins is being done
at the camp site. Waste disposal from
camp site is being done in association
with Municipal department of
Bhogapuram (Near Base camp)
panchayat.
Traffic management Secure assistance from local police
for traffic control during construction
Safety measures to be undertaken by
installing road signs and markings for
safe and smooth movement of traffic.
Secure assistance was provided from
local Police Department for traffic
control at construction zones.
Road signs, solar blinkers and
barricades for construction zone as per
IRC standards.
All traffic diversions are approved from
IE and Local Traffic Police.
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 18
Sufficient light arrangement has been
done at construction zone and diverted
areas
Noise level Stationary equipment shall be
placed as far as possible from
residential areas to minimize noise
impacts on the near inhabitants.
Construction activities will be
strictly prohibited between 10.00
PM to 6.00 AM near habitation.
Provision of ear plugs to workers
exposed to high noise levels in the
project who work in batch mix
plants, hot mix plants, quarries etc.
This is ensured at site.
Site work timings are 8 AM to 8 PM.
Workers are provided with personal
protective equipment (PPE).
Noise monitoring is done on quarterly
basis and results are found to be
within prescribed limits of Pollution
Control Board (Annexure XV).
Air Quality Trucks will carry construction
material for which emission of air
pollutants will increase. All the
vehicles deployed for construction
of the project will have to keep
“Pollution under Control” (PUC)
certificates.
DG sets will also emit air
pollutants in the area during
construction period. The emission
generated during construction will
be temporary and localized in
nature.
Vehicles carrying construction
material shall be covered to avoid
spilling.
Mixing equipment shall be sealed
and equipped with dust removal
device.
Water will be sprinkled in morning
and evening hours at the
construction yards and the unpaved
sections of the road.
PUC certificate is checked for all
construction vehicles.
Air quality monitoring is done at sites
on quarterly intervals.
Vehicles are covered to avoid spilling of
construction material.
Mixing equipment is sealed to control
dust.
Water sprinkling is done at site to
control dust.
Maintenance schedule is in place to
control further environmental damage in
case of break-down
All belt conveyors are covered with
canopy to control the dust pollution
Air Quality is being monitored at site
on quarterly basis and results are
found to be within prescribed limits of
Pollution Control Board (Annexure
XV).
Water Quality Water to be sourced from valid
sources
During construction it will be
ensured that contractor does not
dispose off debris in water bodies.
The majority of the project stretch
is plane & horizontal land which
will be act as water logging areas
during the rainy seasons and may
cause the breeding of the vectors in
the area.
Uncontrolled digging of approved
Borrow pits in the areas will be
avoided to prevent water
accumulation which results in
breeding of disease causing vectors
Borewell permissions have been taken
at all sites by the sub-project
developer.
All debris and other unsuitable
material are being reused in haul road
making purpose.
The entire project stretch was almost
covered by RCC drain which will be
allows free water flow without
obstructions.
No uncontrolled digging was allowed
in borrow areas.
Water Quality is being monitored at
site on quarterly basis and results are
found to be within prescribed limits of
Pollution Control Board (Annexure
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 19
in the area. XV).
Occupational Health and
Safety Labourers shall be equipped with
proper safety gears like helmets,
gloves and gum boots.
Periodic health check-up of
construction workers.
Training of workers to be ensured
All workers and labourers are
equipped with all PPE’s like helmets, gloves and gum boots.
Periodical health check-up will be
conducted as per prescribed schedule
of health check-up calendar.
HSE induction trainings are organized
for labour and staff.
ARARL has come out with innovative
idea of showing a short film on HSE
issues and training staff on the same.
Fuel for labourers Adequate supply of fuel
(LPG/Kerosene) shall be provided
to the labourers to avoid felling of
trees for cooking and other
domestic chores.
Community kitchen/canteen is being
run the site for labour and other staff.
LPG is supplied for cooking purpose.
Prevention of erosion
and scouring Stabilizing the embankment with
appropriate technique immediately
after placing.
Embankment work is in progress
Drainage system Adequate care to be taken for the
purpose of free flow of flood
discharge in the design stage itself.
There are 2 major and 17 minor
bridges proposed along the project
corridor to allow free flow of the
natural drainage water in the area.
Highway Construction works is in
progress
Construction of toe drain along the
road on both the sides is proposed for
76 km (except in areas where service
road is proposed). 67 km out of the
proposed drain is completed till April
2019.
Rain Water Harvesting
(RWH) About 188 nos. of RWH Pits are
proposed on either side of the road
at an interval of 500m. The
proposed RWHs are having
diameter of 1.5 m with a depth of
3.8 m.
Highway construction works is in
progress and RWH pits work has not
yet started.
Utilization of Fly Ash Thermal power plants are located
within 500 km of the sub-project.
Fly ash to be used at ARARL.
Fly ash is being used from Simhadri
Super Thermal Power Station of
NTPC Ltd located on the out skirts of
Vishakhapatnam and Vizag Thermal
Power Station, Palavalasa village in
Vishakhapatnam.
Till April 2019, approximately
10,50,000 MT of fly ash has been
used at the sub-project from
19,35,015 MT proposed.
Fly ash is being used at ARARL,
thereby reducing the requirement of
earth for dyke height. Ash has better
compacting factor than earth.
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 20
17. HEALTH AND SAFETY
32. ARARL has a Traffic Safety Management Plan (Annexure XVI), which elaborates the
organizational structure of ARARl; roles and responsibilities of HSE staff; traffic safety and
management practices; work place safety etc.
33. ARARL follows the safety guidelines and conducts safety training programmes as defined in the
procedures and records for the same are maintained at the sub-project site. The HSE performance
indicators are mentioned in Figure 2.
34. First aid boxes and fire fighting systems are maintained at sub-project camp sites.
35. ARARL has adequate institutional arrangement to look after HSE related aspects. There are seven
HSE staff at ARARL (including one from Contractor side). The organizational chart for HSE is
given as Annexure XVII.
Figure 2: HSE Performance Indicators for 2018-19 at ARARL
18. GRIEVANCE REDRESSAL MECHANISM
36. Ashoka Group has devised guideline for Grievance Redressal Mechanism (GRM) for its
SPVs (Annexure XVIII).
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 21
37. The guidance manual for GRM outlines mechanism to handle and manage grievances raised
by road users, project affected persons and employees/workers including those of sub-
contractors.
38. Record of any grievance or demand received from locals is maintained at the site office.
19. ENVIRONMENTAL SENSITIVITY
39. The environmental sensitivity of ARARL has been assessed by reviewing various documents,
supplemented by field visit and consultation with the developer.
40. The environmental sensitivity assessment is given below:
The sub-project is being developed on the existing right of way. At certain places
(intersections and lay byes) additional land is required. Developer has informed that this
additional land is private land and it was confirmed during site visit that this is waste
land.
The sub-project sites are not located in any protected area like wildlife sanctuary /
national park or in close proximity of any eco-sensitive area.
During site visit and as per discussions with the sub-project staff, it was informed that no
wild animals are sighted in and around the sub-project area.
No forest area is getting affected due to the sub-project.
Approximately 10,278 trees are cut at the sub-project and tree cutting permissions were
taken from Forest Department.
As informed by the concessionaire, no important cultural or heritage sites are getting
affected due to the sub-project.
The sub-project has the necessary approvals and permits from regulatory authorities.
The impacts of the sub-project are temporary in nature and are manageable with EMPs.
20. PROJECT AGAINST THE PROHIBITED INVESTMENT ACTIVITIES LIST
41. The sub - project does not involve any prohibited activity as per the Prohibited Investment
Activities List (PIAL) of ADB.
21. CATEGORIZATION OF SUB-PROJECT
42. The sub-project can be classified as Category B based upon ADB’s EA requirements as per their Safeguard Policy Statement (2009). This classification is based on the review of the
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 22
available documents and site visit with respect to the environmental sensitivity due to project
activities.
22. SITE VISIT OBSERVATIONS
43. A site visit was undertaken by IIFCL’s Environmental and Social Safeguard Specialists on 9th -
10th April 2019. The site visit was undertaken to review the implementation of the project’s
environmental and social safeguards. During the site visit, following staff were mainly consulted
regarding environmental safeguards related measures implemented at the project site:
(a) Mr. Mohit Kar, VP
(b) Mr Anil Kumar Shimpi, AGM-HSE, Corporate Office ABL
(c) Mr. Ganesh Kumar, Additional GM
(d) Mr. Himanshu Jodhani, DH – Accounts
(e) Mr. Pattnaik, DH-HR
(f) Mr. Pavan Rao, Senior Officer, HSE
(g) Mr. Vibu Datt, DH-Store
(h) Mr. Fenandra, DH-QC
(i) Mr Avadhut Deshpande, Senior Manager HR & Admin HO
44. The sub-project is under construction, more than 47% works are completed at the time of site
visit. Based on the discussions with above mentioned officials and visit, the site observations are
given below:
The sub-project has obtained necessary clearances/permits from the State Pollution
Control Board and other regulatory organizations and is complying to the reporting /
monitoring requirements.
The sub-project is involves strengthening and widening of highway in the existing
ROW.
Tree cutting is complete at site. Avenue and median plantation began during monsoon
of 2019. During site visit it was informed that approximately 60% of plantations will
be done during the year 2019. Developer has been informed to keep a record of
plantations and survival rate.
Utility shifting at site is complete.
98.75% of land is already available for highway up-gradation. Balance additional land
acquisition is in progress for construction of wayside amenities and new interchange.
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 23
The workers and staff at the site were seen wearing personal protective equipment
such as helmets, jackets, boots, gloves etc.
Regulatory signs, warning signs and direction signs were available at all relevant
places at site. ABL has devised innovative ways for signages for diversion. Life size
dummy with red flag can be seen at sites where diversions signages were required.
Fly ash is being used to create dykes for flyovers and other purpose instead of earth
filling.
Developer informed during site visit that during road diversion, HSE Officers and
local traffic police is doing consultation and conveying the update related to road
construction and risk to locals in concerned area.
There are three camp sites at the sub-project. Camp 1 at Ch 662.000 is the main camp
which has stone crusher, HMP, WMM, block casting yard, office, laboratory, labour
camp etc. Camp 2 at Ch 639.000 is the sub-contractor (Arvind Techno) camp storage
yard and third camp is located at Ch 640.000 which houses casting yard.
Labour camp is located at Camp 1 site. The labour camp has dormitories for labour
which are well-maintained and hygienic conditions. Approximately 250 labour are
residing at the camp. The dormitories were having fans and coolers. Good standards of
health and hygiene were maintained at camp. Dust bins were placed at different
locations. Toilets were available at the camp site for labour with continuous water
supply. Good housekeeping was maintained at the site.
Kitchen/mess is being run at the camp site where food is prepared and served to all
labour and staff. LPG is being used in the kitchen for cooking purpose.
All waste water being generated at the sub-project premises is disposed in septic
tanks/soak pits.
RO water purifier of large capacity is available at labour camp for drinking water
purpose.
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 24
Milling machines are used at sub-project for recycling material. There are 4 nos. of
vehicles with recycling units available at ARARL. Recycling is saving aggregate and
bitumen. Total reclaimable quantity at the sub-project is 3,78,661 ton material, out of
which 1,51,769 is already recycled till 10th April 2019.
Adequate EHS staff was present at the site and understood their commitments.
On discussions with the site staff, it was observed that tool box talk, safety induction
trainings are done for labour as well as staff.
Vehicle movement in the administrative premises was very limited and control by
Security at entrance of camp.
No oil spillage was observed at the site. At the sub-contractor camp diesel was stored
in barrels on impervious (cemented) surface. The sub-contractor was advised to keep
the oil barrels on an elevated surface.
Concrete waste generated from demolished structure has been kept at secured and
identified location and is being utilized for low laying area development and leveling
purpose by local community.
Tested waste cube generated from QC Lab is utilized for garden development
boundary.
The permits and NOCs required for the project are in place.
The concessionaire has undertaken the implementation of safety management system
by adopting safety policy for the sub-project.
Fire extinguishers and first aid kits were available at camp site.
Emergency contact numbers have been displayed at appropriate locations.
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 25
Records of safety trainings, mock drills and various inspections/audits are maintained
at site office.
The sub-project has a proper grievance handling mechanism and records are
maintained at site.
45. The site visit photographs are given in Photoplate - I.
23. CONCLUSIONS AND RECOMMENDATIONS
46. It is concluded on the basis of review of the available information, reconnaissance site visit and
interaction with sub-project staff it can be concluded that the concessionaire ARARL is complying
with the statutory requirements as per the national and state guidelines and regulations. ARARL is
committed to protection of the environment while performing its activities. The 47 km road
strengthening and widening project in the State of Andhra Pradesh is unlikely to pose any adverse
environmental risks given the nature of the activities.
47. There are no legally protected areas, cultural heritage sites and forest land located within and/or in
close proximity to the sub-project. However, the sub-project activities have reversible environmental
impacts which have been managed.
48. Based upon the available documents and site visit, it is concluded that the concessionaire has
undertaken adequate environmental safeguard measures. The conclusions for the sub-project are
given below:
The sub-project has been planned as per the National and State Government requirement and
not in anticipation to ADB operation.
The project site is not located in an ecologically sensitive area.
The sub-project is being developed in the existing ROW and some additional land is
being acquired for interchange and lay byes, which is waste land.
The project does not involve diversion of forest land. However, approximately 10,278
trees have been cut for widening and the concessionaire has developed an elaborate
plantation scheme to compensate for the tree cutting.
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 26
Concessionaire has confirmed continuous compliance with the terms and conditions stipulated
while according statutory clearances /approvals /consents. Concessionaire has been informed
to implement the EMP and maintain a record of status of implementation.
The institutional arrangement available for the implementation of environment, health &
safety appears to be adequate.
The concessionaire is maintaining safety at the site as per the management plans. The
EMPs are undertaken to minimize any significant negative impact on environment.
During site visit and discussion with the project developer, the implementation of EMP was
found to be adequate.
After approval from ADB the ESDDR will be uploaded on website for public disclosure.
49. Based on the site visit and due diligence findings, it can be deduced that the sub-project has no
significant environmental safeguard issues. The sub-project, therefore, does not appear to involve
any kind of reputational risk to ADB funding on environmental safeguards.
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 27
DUE DILIGENCE ON SOCIAL SAFEGUARDS
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 28
24. PURPOSE OF THE SOCIAL SAFEGUARDS DUE DILIGENCE
50. The Social Safeguards Due Diligence Report (SSDDR) has been carried out by India Infrastructure
Finance Company Limited (IIFCL) in consultation with the Concessionaire, Ashoka Ranastalam
Anandapuram Road Ltd. (ARARL) to assess the Social safeguards compliances of the project with
the applicable National Policies. The report has been prepared as per the documents/information
received from the concessionaire and subsequent to the site visit organized during 9th and 10th of
April 2019. The information given in the SSDDR is agreed and confirmed by the Concessionaire.
25. PROJECT AGAINST THE PROHIBITED INVESTMENT ACTIVITIES LIST
51. The sub project JUWML does not involve any prohibited activity as per the Prohibited
Investment Activities List (PIAL) of ADB.
26. OBJECTIVE OF SOCIAL SAFEGUARDS DUE DILIGENCE
52. Social Safeguards due diligence study is carried out to assess the social safeguards monitoring
compliance status of the project as per the applicable National policies/procedures as observed
during the site visit as well as the information received. The main objective of this Social
Safeguard Due Diligence Report (SSDDR) is:
To assess the likely social impacts and its minimization/mitigation majors adopted
for the project with respect to land acquisition, compensation , Indigenous people
affected, involuntary resettlement and common properties resources affected, if any,
in terms of displacement, loss of incomes, and community links:
To ascertain, in case of any adverse impact, if appropriate mitigation measures have
been taken during the project planning, designing and frameworks established for
carrying out safeguard measures during the construction stage to minimize and
mitigate such if any adverse impacts;
27. APPROACH AND METHODOLOGY
53. The Social safeguard due diligence study for ARARL has been carried out after reviewing the
documents made available by the subproject developer. On site visit to the project location by the
Environmental and Social Safeguards Specialist, discussion with the project developer and
various permits and approvals relating to the project to understand the salient features of the
project and social concerns. The following documents/Reports/Licenses/permits and notifications
were referred in order to prepare the Social Safeguard Due Diligence Report:
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 29
Project Information Memorandum (PIM);
Feasibility Study Report;
Right of Way (RoW) handover letter
Concession Agreement
Independent Engineer’s (IE) Report Lender’s Independent Engineer (LIE) Reports (January 2019)
Labour License & insurance
Guide line for Grievance Redressal Mechanism
28. SOCIAL IMPACT OF THE PROJECT
27.1 Land Acquisition in the Project
54. Land acquisition is not in the scope of the project developer and it is under the purview of the
Concessioning Authority, National Highway Authority of India (NHAI). Land acquisition for the
project ARARL for 6-laning of section NH-16 from Km 634.000 to Km. 681.000 is in the state of
Andhra Pradesh (Approx.47 Km. of length) has been completed by NHAI as per NH Act 1956.
During the discussion it was informed that the land acquisition to the extent of 60m Right of Way
(RoW) for 6-laning of this project was completed during 2 to 4-laning of project in the year 2002. As
per the RoW hand over letter, the 98.75% of land was made available to the project developer. The
detail of RoW hand over letter is attached as Annexure XIX. The detail of Land is given in Table-3:
Table: 3: Status of Land available at ARARL
Sl. No. Description Status of Land available
with the Concessionaire
Present status of Land as on 31st
March 2019
Required Area to be
made available as per
agreement
Area in
Hectare
In
Percentage
Area in
Hectare
In Percentage
1 Required Area to be
made available as per
agreement
282.00 100% 282.00 100%
2 Available Area at Site 278.47 98.75% 278.47 98.75%
3 Area for RoW to be
made available
3.53 1.25% 3.53 1.25%
55. Land acquisition process was initiated prior to IIFCL’s involvement and not in anticipation of ADB
financing and that IIFCL was not involved in the rehabilitation and resettlement activities of project
if any.
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 30
27.2 Impact on Structure
56. The sub-project stretch falls in Srikakulum, Vizianagaram and Vishakhapatnam districts in the state
of Andhra Pradesh. The entire section of project road is passing through plain terrain. As informed
by the concessionaire and noted during the site visit, that no structure is getting affected due to the
project.
27.3 Rehabilitation and Resettlement impact in the sub-project
57. Land acquisition to the extent of 60m Right of Way (RoW) for 6-laning of this project was
completed during 2 to 4-laning of project in the year 2002. During the site visit it was informed that
there was no involuntary resettlement because of land acquisition in the year 2002. Further during the
site visit it was observed that there was no rehabilitation and resettlement impact in the project.
27.4 Impact on Indigenous people
58. As information provided by the concessionaire the project does not disturb indigenous people in the
project and does not have adverse impact or create any threat to the survival of any indigenous
community along the alignment, hence no indigenous people affected in this sub-project.
29. GREIVANCE REDRESSAL MECHANISM FOR THE SUB-PROJECT
59. During the site visit it was observed that the project authority has formed their own institutional
arrangements to deal with any issues/concerns in the site. Grievance Redressal Mechanism with the
help of project site official has in place which comprises of the following members:
Project Head;
EHS Head
Manager (Administration)
60. The Grievance Redressal Committee (GRC) was formed at the project site to ensure that any
affected person’s grievances are adequately addressed and to facilitate timely project implementation. At project level the GRC is headed by the Project Head.
61. As informed by the developer during the site visit, whenever any complaints receives in writing from
any project affected person, at first the complaint is being registered in the Grievance
Registered/complain Register. At first the issues /concerns are taken care by the Deputy Manager
(Administration) at the project level and forwarded to Project Head. If the Project Head is unable to
resolve the issue then the matter is forwarded to the Vice President and subsequently to the COO.
During the site visit it was observed that the sub project developer is maintaining a Grievance
register. However, during the discussion it was informed that no grievance was received at site.
62. The organization chart for handling grievances is given below:
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 31
30. EMPLOYMENT GENERATION
63. As informed by the concessionaire, the project land acquisition was completed during 2 to 4-laning
of project in the year 2002, so the project does not impact the livelihood of the local people. It has
been confirmed by the concessionaire that employment opportunities are being provided to the local
people for various unskilled and semi-skilled activities like security guards and office assistants,
drivers.
64. As informed by the concessionaire they have given job opportunity to more than 80 local labours.
Based on the available skill and qualification requirements, employment preference has been given.
Labour employed in the project from the local area is given in Annexure XX.
31. THE COMMUNITY ENGAGEMENT ACTIVITIES
65. As information provided by the concessionaire, to reach the local people, ARARL has under taken
few of community development activates to reach the local people during the construction stage of
the project. The subproject developer celebrated its road safety week, blood donation camp, free
medical check-up camp, health and hygiene awareness camps has also been under taken under
community development initiatives. The details of work done by the subproject developer were
given in Annexure XXI.
66. The concessionaire has carried out community development activities based on the demands made
by the local community / nearby village/Panchayats as below:
Provide drinking water facilities at Bogapuram, Akkivaram village
Construction and maintenance of village temples.
Vice President
Project Head
EHS Head
Deputy Manager (Administration)
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 32
Construction and maintenance of village road in the project affected villages as per the
requirement of the villagers.
32. LABOUR LICENSE OBTAINED BY THE SUBPROJECT DEVELOPER
67. The subproject developer ARAPL has received the Labour license from the Licensing Officer and
Regional Labour Commissioner, (Central), Visakhapatnam, Govt. of India, Ministry of Labour &
Employment for doing the work of Six laning of Ranasthalam to Anandapuram section of NH-16
under Section 12(1) of the Contract Labour (Regulation & Abokition) Act, 1970. As per the labour
licenses the subproject developer can employed as contract labour in the establishment will not on
any day exceed 400 Nos. The detail of labour license is attached as Annexure VII.
68. The subproject developer has taken insurance policy for the project Ashoka Ranastalam
Anandapuram Project including contractors & sub-contractors workers are covered under policy.
The developer has covered 400 number of workers. The detail of accident insurance is given in
Annexure IX.
33. DISCLOSURE
69. On approval from ADB, the report will be uploaded for public disclosure in IIFCL’s and ADB’s website.
34. SITE VISIT OBSERVATION
70. A site visit was undertaken by IIFCL’s Environmental and Social Safeguard Specialists during 9th -
10th April, 2019. The site visit was undertaken to review the implementation of the project’s
environmental and social safeguards parameters at the project site. The sub-project at the time of site
visit was in the initial stage of construction.
71. During the site visit and discussions with subproject developer it was observed/noted that :
The sub-project has been prepared by NHAI as per its own funding requirement and not
anticipation to ADB operation;
Land acquisition process was initiated prior to IIFCL’s involvement and not in anticipation of
ADB financing.
Land acquisition was completed during the 2 to 4-laning of project in the year 2002;
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 33
Land acquisition has been done by NHAI under NH Act-1956 and the compensation for land
acquisition was paid to the affected families before handing over the land to the
concessionaire;
There is no Rehabilitation and Resettlement in the project.
The subproject do not have any indigenous people in the project;
Local people’s view have been given due consideration during the project planning and
designing of the project;
Construction workers are provided with ready access to on- or off-site health care check-up
facilities and are being provided with first aid facilities for minor injuries;
As informed during the site visit it was confirmed that no fatal accident happened in the
project till date.
Emergency contact numbers have been displayed at the prominent places in project site.
During the site visit it was observed that, workers and staffs at the site were seen wearing
personal protective equipment such as helmets, jackets, boots, gloves etc.
As informed by the project developer, after discussions with the local people, the affected
cultural properties are being relocated by the concessionaire;
Local labours are being engaged in the construction activities for skilled as well as unskilled
activities;
Concessionaire has undertaken various community development activities to benefit the local
people;
It seems that the sub-project does not appear to involve reputational risk to Asian
Development Bank funding on social safeguards and recommended for funding under the
proposed project.
Employment opportunities have been provided to the local people
Environment and Social Due Diligence Report Ashoka Ranastalam Anandapuram Road Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/112/V3 34
Concessionaire has undertaken community development activities based on the demands
raised by the local people.
72. Based on the site visits observations and desk review, it appears that the sub-project have no negative
significant social safeguard issue.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 1 of 68
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 2 of 68
INDEX
NO. CHAPTER Page No
1 QHSE POLICY 5
1 (A) BRIEF INTRODUCTION OF PROJECT 6-17
2 STATUTORY AND REGULATORY REQUIREMENTS 18-19
3 INSTITUTIONAL ARRANGEMENT 20-28
4 ENVIRONMENTAL MANAGEMENT PLAN AND REVIEW FRAMEWORK 29-41
4 (A) ENVIRONMENTAL MITIGATION AND ENHANCEMENT & GRIEVANCE REDRESSAL MECHANISM 42-44
5 ENVIRONMENTAL MANAGEMENT SYSTEM 45-50
5(A) APPLICABLE LAWS AND ACTS 51
6 ENVIRONMENTAL STIPULATION FROM THE COMPETENT AUTHORITY SEIAA, MOEFCC, SPCB,
FOREST DEPARTMENT AND CHECK LISTS OF ENVIRONMENTAL REMIDIAL MEASURES 52
7 ENVIRONMENT MONITORING PLAN 53-54
8 HEALTH AND SAFETY 55-59
9 ENVIRONMENTAL REPORTING AND FREQUENCY 60-98
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 3 of 68
Glossary Abbreviations
NHAI - National Highways Authority of India
CPCB - Central Pollution Control Board
PPP - Public-Private Participation
EHS - Environment, Health and Safety
CPR - Common Property Resources
COI - Corridor of Impact
ROW - Right of Way
APSPCB - Andhra Pradesh State Pollution Control Board
MOEFCC- Ministry of Environment Forest and Climate Change
SEIAA - State Environmental Impact Assessment Authority
IE - Independent Engineer
CA - Concession Agreement
PAP/Fs - Project affected peoples / Families
EIA - Environment Impact Assessment
Definitions of Terms
Term Definition
Corrective Action Action to eliminate cause of a detected nonconformity
Environment Surroundings in which an organization operates, including air, water, land, natural resources, flora, fauna, and their interrelation
Environmental Aspect Element of an organization activities or products or services that can interact with the environment.
Environmental Impact
Any change to the environment, weather adverse or beneficial, wholly or partially resulting from an organization aspects
Hazard Source, situation, or act with a potential for harm in terms of human injury or ill health, or combination of these
Hazard identification The process of recognizing a hazard in existence and defining its characteristics
Incident Work-related events in which an injury or ill health or fatality occurred or could have occurred
Interested Parties Person or group, inside or outside the workplace, concerned with or affected by the Integrated management system of an organization
Non conformance Non-fulfillment of a requirement as per IMS standards, Applicable Rules & Regulations & Client requirements
Ill Health Identifiable, adverse physical or mental condition arising from and/or made worse by a work activity and/or work-related situation
Risk Combination of the likelihood of an occurrence of a hazardous event or exposures and the severity of injury or ill health that can be caused by the event or exposures
Risk Assessment The process of evaluating the risks arising from a hazards, taking into account the adequacy of any existing controls, and deciding whether or not the risks is acceptable
Occupational health and Safety
The condition and factors that affect or could affect the health and safety of employees or other workers (including temporary workers and contractor personnel), visitors or any person in the workplace
Preventive Action The action to eliminate the cause of a potential nonconformity or other undesirable potential situation
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 4 of 68
1. QHSE Policy.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 5 of 68
CHAPTER – 1(A)
BRIEF INTRODUCTION OF PROJECT
The Concessionaire has prepared the report of Environmental Management Plan for effective
implementation of remedial, compensation and mitigation measures during the project cycle of Pre –
construction, Construction and Maintenance phase. The report addressed about the measures required to be
taken for implementation of project in environmental friendly manner along the entire timelines and
development period. The report covered the entire features, check-list for remedial actions and person(s)
responsible for each covering links headed by the senior person.
The report confirm the fulfilment of all the requirements of conditions for environmental management
covering the WP OP 4.01, principle guideline so as Environmental Protection, Regulation, Acts, Policies
applicable to sustainability and Environmental Protection, Guidelines and Norms related to road
construction by Indian Road Congress that help for environmental protection include, IRC: 104-1988,
IRC: 36-1974, IRC: 10-1961, IRC: 36-1970, IRC: 43-1972, IRC: 72-1978, IRC: 33-1982.
1.0 INTRODUCTION
1.1 Project Background
The National Highways Authority of India (NHAI) has been entrusted with the development, maintenance
and management of such of the National Highways as entrusted to it by the Government. Under NHDP
Phase –V Programme, the Government has been decided to convert some of the existing four lane
highways into Six lane highways. These projects are to be executed by private entrepreneurs as Hybrid
Annuity Projects.
The existing road is of Four lane carriageway. The project corridor from Ranastalam to Anandapuram is
presently a 4-lane highway with service roads in major villages / habitations. While 4-laning the corridor
as a part of NHDP, all the new structures have been constructed to accommodate 3-lane carriage way.
However, on the existing carriageway, some of the bridges have been retained with 2-lane carriageway.
There are Grade Separators / Underpasses at some locations. There are bus bays and truck lay byes at
many places on either side of the corridor. To achieve the objectives of the project and the guidelines given
in the six laning manual, the following up-gradation is proposed. The existing road is of Four lane
carriageway except at Toll Plazas. Carriageway width was measured at every 100m interval along the
entire project corridor. Width of median at the centre of the road and width of shoulders on either side
were measured separately along with carriageway measurements. The existing carriageway width is 7.0m
with paved shoulders of 1.50m width on either side of the road. Median width varies from 2.0m in builtup
to 5.0m in rural areas including kerb shyness.
1.2 Project Description
The Site of the Project comprises the section of National Highway NH–16 (OldNH-05) commencing from Km Chainage at 634+000 (near Ranastalam) to Km Chainage at 681+000 (near Anandapuram) section in the State of Andhra Pradesh.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 6 of 68
1.2.1 Short Description of the Works I. Road Work: Six-Laning of Ranastalam - Anandapuram section of NH-16 from km 634.000 to km 681.000 in the State of Andhra Pradesh under NHDP Phase- V on Hybrid Annuity Mode Annuity Basis. II. Lateral and vertical clearances at underpasses/flyovers :- (NEW) 21 Nos, Repair & Rehabilitation of Existing Underpasses 2 Nos. III. Culverts to be reconstructed / widened / new construction: - Widening of Box/Slab Culverts 6 Nos , Widening of HPC 87 Nos, Reconstruction of Box/Slab Culverts 24 Nos, Reconstruction of Pipe Culverts 1 no, New Construction of Box / Slab Culverts 1 no, Retain of Box/Slab Culverts 1 Nos, Reconstruction of Box/Slab Culverts for Median Drain 1 Nos, Widening of Median Drain Pipe Culverts 18 Nos, Widening of Median Drain Pipe Culverts 18 Nos IV. Details of Bridges to be Reconstructed / Widened / New Construction: Rehabilitation & Repair of Existing Major Bridges and Construction of new Major Bridges 3 Nos, Rehabilitation & Repair of Existing Minor Bridges and Construction of new Minor Bridges: 6 Nos,
1.2.2 Proposed Road Futures
1.2.2.1 Highway Design
This Section of the National Highway No 16 is passing through the plain terrain. The median width has
been proposed as 4.5m for the entire project stretch. Facilities in the form of service road, under / over
passes and grade separators will be considered at the reasonable intervals for local traffic including
pedestrians.
1.2.2.2 Alignment
The existing road is developed into six lane road by widening, utilizing the existing road as far as possible.
Existing raised median of 4.5M is retained in the entire reach and widening is proposed on outer side for
both the carriage ways.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 7 of 68
Fig 1.1: Road Project Map
1.2.2.3 Pavement
Pavement design is carried out in accordance with IRC 37:2012 for Granular base and sub-base layers. The
design standards as given in plate-7 of IRC: 37-2012, specifies the minimum thickness and specifications
of various component layers for the given traffic in terms of cumulative standard axles and the subgrade
CBR. The required pavement composition for the project corridor according to IRC: 37-2012 is as given
below.
Homogenous Section MSA CBR(%)
Crust Composition in mm
Bitumen
Grade BC DBM WMM GSB Total
HS - 03 130 10 VG -40 50 120 250 200 620
HS - 04 150 10 VG -40 50 125 250 200 625
1.2.2.4 Geometric Design Aspects
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 8 of 68
This has been decided to convert the existing four lane highway into Six lane highway. Right of Way
(ROW) is 60 mtr, Design Speed for existing is 60-80 Km/H and proposed was 100 Km/H.
It is observed that the project highway has a straight and curved alignment and traverses through plain and
rolling terrain. Some part of the stretch is passing through rolling locations in section A. All the horizontal
curves confirm to acceptable geometric standards in terms of super elevation. The vertical gradients are not
so gentle and the required sight distances are not available in the stretch as per the design standards. The
project stretch has horizontal and vertical curves at various locations in the stretch and the same will be
addressed in the current up gradation proposal.
1.3. ACTIVITIES INVOLVED IN THE PROJECT
1.3.1 Pre-Construction Stage
Pre-construction activities
The Concessionaire shall take responsible for Pre-construction stage involves mobilization of the project
requirement, planning of logistics and site preparation necessary for commencing construction activities.
The activities include:
Joint field verification of EMP with the Environment Specialist IE and of the ARARL
Environmental Officer
Identification and selection of material sources (quarry and borrow material, water, sand etc.).
Procurement of construction equipment / machinery such as hot mix plants, batching plants and
other construction equipment and machinery.
Selection, design and layout of construction areas, hot mix and batching plants, labour camps etc.
Apply for and obtain all the necessary clearances from the agencies concerned.
Planning traffic diversions and detours including arrangements for temporary land if required.
Monitoring environmental conditions (Baseline data) through approved monitoring agency
1.3. 2 Construction Stage
1.3.2.1 Construction activities by the ARARL
The Concessionaire is responsible during the Construction stage is the most crucial stage in terms of
activities that require careful management to avoid environmental impacts. Environmental impact
mitigation measures as per CA will be taken to control the impact on environment. There are several other
environmental issues that have been addressed as part of good engineering practices by ARARL. They
include providing roadside drainage provision of cross drainage structures and Toe wall etc.
1.3.3 Operational Stage
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 9 of 68
The Concessionaire commit to regular monitoring of environment conditions (Air, Water, Noise & Soil
etc) will be carried out through an approved pollution monitoring agency.
1.4 BASELINE & ENVIRONMENTAL IMPACT SUMMARY
The EIA preparation led to identification of potential environmental impacts and their feasible remedial
measures (including avoidance, mitigation and enhancements). Public consultations were conducted for
both the Environmental and Social aspects and are reported in the EIA and SIA Report.
In the four to six lane project construction works are to be confined within the proposed ROW varies from
60 m depending on the typical road cross-section applied. However, in toll plaza locations it goes up to 90
m (approx.). In isolated instances where the embankment heights are significant, a wider ROW to
accommodate the full width of embankment is necessary. Hence, the environmental impacts would be
observed during the construction period. Thus in depth of analysis for this scope of work is limited and no
significant adverse impacts are anticipated except in some areas in the project road. The various
environmental impacts envisaged during the proposed widening works are summarized in Table 4.7.
1.4.1 Physical Environment
The project corridor traverses mainly through plain terrain of land. The entire stretch runs through fertile
agriculture land and plantation along the project road. The abutting land uses along the project road are
agricultural, barren revenue and settlement lands.
1.4.1.1 Land
The project involves widening of the existing Four lane Highway. During the construction of the proposed
project, the topography will change due to excavation of borrow areas, cuts and fills for project road and
construction of project related structures etc.
Provision of construction yard for material handling will also alter the existing topography.
Loss of productive lands in the direct impact zone;
Erosion of the soil from the embankment land;
Inappropriate disposal of wastes from the site;
Indirect impacts at quarry and borrow area locations during and after the period of construction;
Loss of road side Avenue Plantation
1.4.1.2 Water
Water Resources
Ground Water resources can be categorised on basis of their occurrence as shallow aquifers such as wells,
hand pumps and deep aquifers such as tube wells or bore wells. The location of these resources is the
prime determinant of the impacts. Along the project road section 10 wells, 18 hand-pumps, 17 tanks and 9
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 10 of 68
over head tanks are located. These are the mainly sources of potable water. Out of these water utilities 23
utilities likely to affected by the project.
3 Rivers a) River Kandivalasagadda, b) River Champavathi and c) River Gosthani and 14 water bodies are
present along the project road section. However, as per the design no partial / complete loss of water body
will take place. Hence no loss in volumetric capacity of water resources is envisaged. Impact on surface &
ground water resources has been tabulated in table 4.1 & 4.2.
Table 1.4.1: Surface Water Resources along the Road
Sl. No Chainage (Km) Feature
Name Side
Volumetric
Capacity Loss
1 643+083 Kandivalasa
gedda river NO
2 655+726 Champavthi
river NO
3 675+296 Gostani
river NO
4 642.700 – 643.000 Water Body Both Sides NO
5 651.400 – 651.600 Water Body Both Sides NO
6 655.000 – 655.500 Water Body Both Sides NO
7 656.500 – 656.600 Water Body Both Sides NO
8 666.300 – 666.400 Water Body Both Sides NO
9 669.200 – 669.300 Water Body Both Sides NO
10 669.800 – 669.900 Water Body Both Sides NO
11 674.700 – 675.400 Water Body Both Sides NO
12 656.700 – 657.000 Water Body LHS NO
13 657.700 – 658.300 Water Body LHS NO
14 664.500 – 664.600 Water Body LHS NO
15 668.700 – 669.200 Water Body LHS NO
16 669.600 – 669.800 Water Body LHS NO
17 636.900 – 637.000 Water Body RHS NO
Table 1.4.2: Ground/ Drinking Water Resources
Road Number Affected features Nos
NH-16 Drinking and Ground water sources 17
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 11 of 68
Water Quality
Water sources including flowing and stagnant water sources are likely to be contaminated due to activities
such as setting up workers camp near water sources or transportation of construction material such as sand,
borrow material etc. without covering it. Contamination of groundwater is another likely impact of road
construction and allied activities. The groundwater recharge areas may be reduced due to an increase in
impervious layers due to the construction. The contamination of the groundwater resources due to the
project is likely at the following locations:
Along construction sites, camps involving moving of construction equipment‟s- and machinery.
At the various community water bodies and sources of water supply such as hand pumps etc
Along the entire length of the corridor especially around urban areas and productive lands.
The impacts on water quality will be of greater concern during the construction stage. Increased sediment
load during preparation of the site is the most likely adverse impact. The contamination by fuel and oil
from construction vehicles or bitumen from hot-mix plants is less likely and in any case expected to be
localised. Discharge from labour camps and vehicle parking areas may contaminate watercourses if
discharged untreated. During the operation stage the leakage or spillage from vehicles damaged,
overturned or just badly maintained may also lead to contamination of water bodies.
1.4.1.3 Air Quality
There will be rise in PM levels during the construction activities, which shall again be within prescribed
limit after the construction activities are over. All of the pollutants are well under stipulated standard of
CPCB. The setting up of camp including hot mix plant, up-gradation works etc. shall involve generation of
dust and release of other pollutants leading to the degradation of air quality, which shall be localised and
mitigation measures to reduce such pollutions shall be adopted therefore, air quality impacts are not very
significant. Measures required for avoiding the air quality impacts are presented in the Table 4.1:
Environmental Management Plan.
1.4.1.4 Noise
The baseline noise levels monitored at various locations along the project road indicates the baseline levels
are within the permissible limits of CPCB. Thus, noise is not a major concern in this area. However, a
number of sensitive receptors (schools, colleges and hospitals) have been identified to be quite close to the
road. The impacts on noise due to the project will be of significance in both the construction as well as the
operation stages.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 12 of 68
Noise Standards
The Central Pollution Control Board has specified ambient noise levels for different land use for day and
night times. Importance was given to the timing of exposure and areas designated as sensitive. The
National ambient noise level standards are given below.
Area Code category Limits in Decibels (dB(A))
Day Time Night time
A Industrial 75 70
B Commercial 65 55
C Residential 55 45
D Silence Zones 50 40
Day Time is recorded in between 6 a.m. and 9 p.m. and Night time is recorded in between 9 p.m. to 6 a.m.
Silence zone is defined as areas upto 100 meters around such premises as hospitals, educational institutions
and courts. The silence zones are to be declared by the Competent Authority.
Use of vehicular horns, loudspeakers and bursting of crackers shall be banned in these zones.
Mixed categories of areas should be declared as one of the four above mentioned categories by the
Competent Authority and the corresponding standards shall apply.
Source: EPA Notification [G.S.R. 1063 (E) dt. 26.12.1989 published in the Gazette No. 643 dt.
26.12.1989].
1.4.2 BIOLOGICAL ENVIRONMENT
1.4.2.1 National Park / Sanctuary / Biosphere Reserve / Notified Animal Corridor.
No National Park or Wildlife Sanctuary is located within 1.0 km aerial distance from the project road.
Also, there is no notified animal corridor/migration route is present in the project area.
1.4.2.2 Forest Areas
No Protected / Reserve Forest are located along the project road.
1.4.2.3 Flora
The main species are Ficus species, Tamarind, Babul (Prosopsis juliflora), Neem (Azardirachta indica,
Gulmohar (Delonix regia), Ipomea sp., Acacia nilotica, Mango (Magnifera indica), Eucalyptus, Pongomia
pinnata & Tamarind are the major floral species noticed along the project road. Roadside plantations
including the above mentioned species will need to be cleared for the project. Chainage wise details of the
trees that are affected shall be provided in Form B. About 1162 Trees are likely to be getting affected in
this road section. Felling shall start only after obtaining all the necessary clearances & permissions from
the Forest Dept.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 13 of 68
1.4.2.4 Fauna
No impacts on fauna are anticipated for the project except loss of habitats where the trees are felled or
trimmed.
1.4.2.5 Aquatic Ecology
The repair and up gradation of minor bridges will cause some contamination of the river / canal water due
to spillage of construction material, sediment loading & increased turbidity downstream of the bridge
location. This change shall have some impact on the flora and fauna species and change the nature of the
substratum resulting in decline in the number and diversity of plants and thus the food web. However, at
different locations of structure where construction/maintenance is proposed, necessary mitigation measures
have been recommended in Table 4.1.
1.4.3 SOCIAL IMPACTS
Since the construction activities involves widening of the project road, some private and or community
asset will be impacted during the execution of the project. Care shall be taken that activities are carried out
in such a way so that no community or private assets or structures are impacted accidentally. The traffic
movement will be within the constricted width available and the traffic shall be managed as per the Traffic
management Plan. All public utilities like electricity lines, telephone lines, hand pumps or water pipelines
which are likely to be impacted shall be replaced before the start of work. SIA Report furnishes the extent
of Loss of properties and details of Project Affected Families.
1.4.3.1 Places of historical importance /Archaeological Sites/Places of Tourist Interest
There are no other historical places and protected monuments or sanctuaries in the project region.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 14 of 68
1.4.4 KEY ENVIRONMENTAL FEATURES
The entire link roads under this package Road No. 7, NHAI are passing through the flat rolling terrain to gently undulating terrain with residual
hills.
The identified significant impacts due to project are summarized in following impacts due to project are summarized in the impacts matrix
given in Table – 1.4.1 Table 4.5: Environmental Impact Matrix for Road Project
Sl.
No. Activity Magnitude Reversible Irreversible
Nature
Positive Negative Direct Indirect Long
Term
Short
Term
Pre-Construction Phase 1 Land Acquisition Low √ √ √ √
2 Relocation of Common Utilities and Common Property Resources Medium √ √ √ √
3 Construction Camps and Storage Areas Medium √ √ √ √
4 Disposal Locations Medium √ √ √ √
5 Borrow Areas Medium √ √ √ √
6 Quarries Medium √ √ √ √
7 Hot Mix / Cement Batching Plant Medium √ √ √ √
8 Temporary arrangement of land for construction purpose Low √ √ √ √ √ √
9 Arrangement for Construction Water Low √ √ √ √ √
10 Arrangement of Labour Medium √ √ √ √
Construction Phase
1 Clearing of Site Low √ √ √ √ √ √ √
2 Felling of Trees High √ √ √ √ √
3 Disposal of Debris Low √ √ √ √
4 Stripping , Stacking and Preservation of Top Soil Low √ √ √
5 Borrow Areas operation Medium √ √ √ √
6 Quarry Area Operation Medium √ √ √
7 Traffic Management During Construction Medium √ √ √
8 Operation of Hot Mix Plant/ Cement Batching Plant Medium √ √ √ √
9 Labour Camp Medium √ √ √ √ √
10 Construction of Road Low √ √ √ √ √ √ √
11 Maintenance of Cross Drainage and Longitudinal Drains Low √ √ √
12 Use of Construction Water Low √ √ √ √
13 Rehabilitation of Borrow Areas/ Quarry/ Disposal location Medium √ √ √ √
14 Clean up Operation, Restoration and Rehabilitation of Sites Medium √ √ √ √
15 Plantation Medium √ √ √ √
Note: Categorizing of Low / Medium / High has been done on recommendation of EIA Report
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 15 of 68
Table 4.6: Aspect Impact Matrix For project activities is as follows
Sr.
No.
Activity Environmental aspect Environment impact
Pre-Construction Phase 1. Tree Cutting Tree Cutting / Generation of waste Depletion of Natural Resources
2. Relocation of Communities (Utilities) Generation of waste Land Pollution
3. Usage of electricity Wastage of electrical power Resource depletion
4. Setting of Plants / Relocation Disturbance to land pattern Land Contamination / Soil Pollution
5. Transportation of vehicle/ material mobilization Use of Diesel
Depletion of Natural Resources/Air
Pollution
Construction Phase
6. Disposal of debris/ waste from dismantling
structure & excavation of existing road Generation of debris Land contamination
7. Borrow Area operation Top soil wastage, generation of dust Air Pollution , Soil contamination
8. Material Transportation at construction Site Generation noise & dust Noise and Air pollution
9. Drilling /Cutting Air, Sound pollution Noise Pollution
10. Welding, Gas Cutting Generation of Fumes/UV Radiations Air pollution
11. Preventive maintenance Usage of oil, diesel Land contamination
12. Running of RMC plant : loading of aggregate to
feeding point by dozers Generation of dust and noise Noise and Air pollution
13. Crusher Plant operation Generation of noise and dust Noise and Air pollution
14. WMM Plant operation Generation of noise and dust Noise and Air pollution
15. HMP Plant Operation Generation of noise and dust Noise and Air pollution
16. Running of conveyor belt Generation of dust Air pollution
17. Recycling plant Generation of cement slurry Land pollution
18. Plant & skip area gate open Dust generation Air pollution
19. Consumption of Water for Drinking Purpose
(drivers &helpers) Water leakage Water pollution/Contamination
20. Concrete pump (installed diff. Type silencer) Generation of noise Noise pollution
21. Sampling of concrete Generation of waste concrete Land pollution
22. Curing water for concrete cubes Generation of (waste water) fungus, algae Water pollution
23. Cement & silica Water consumption , co2 emission Air& water pollution prevention
24. Foam sprinkler on aggregates Water consumption Control air pollution
25. Natural sand (Consumption of Usage) Reduced natural recourses consumption natural resource
26. Wasted food, clothe & tobacco in surrounding labor
room Infection/ disease Air & land contamination/pollution
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 16 of 68
Sr.
No.
Activity Environmental aspect Environment impact
27. Handling of admixture usage Generation of spillage Land contamination/pollution
28. Cleaning of curing tank during discharge water Generation of logging water Water pollution
29. Testing of cube Generation of waste cube which are tested Land pollution
30. Storage of chemicals Leakages, spillages Land contamination
31. Transportation Use of natural resource Depletion of Natural Resources
32. Storage of diesel Spillage of diesel Air, land contamination
33. Cement loading/unloading Cement Air, land contamination
34. Diesel distribution Leakages, spillages Land contamination
35. Storage of LPG cylinders Cylinder explosion Air pollution
36. Diesel storage Diesel spillage and improper storage Land contamination
37. Usage of paper Improper & unplanned paper consumption/Wastage Resource depletion
38. Electricity consumption Usage of power Resource depletion
39. Usage of Diesel Generator (DG) Wastage of electrical power Resource depletion
40. Operating matching change oil Waste oil spillage Air, land contamination
41. Connection of bulker rubber pipe while feeding cement
or fly ash
Dust generation (high amount of fly ash or cement can
be leak) Air pollution
42. Admitter drum area below conveyer belt Admixture leakage spillage land contamination
43. Aggregates 10mm,20mm &sand Wastage of aggregates & dust generation Land pollution
44. Manufacturing of RMC - transportation of aggregate by
dumper & conveyor Generation of dust Air pollution
45. Use of admixtures Generation of empty barrels of admixture Land contamination
46. Use of cement bags Generation of waste cement bags Land contamination
47. Manufacturing of RMC - washing of RMC plant Generation of waste water Water pollution
48. Labour camp management Generation of waste Land Contamination
49. Quarry Operation Generation of Dust Air Pollution / Land Contamination
Operation & Maintenance Phase
50. Maintenance work
Wastage of after the maintenance such as oil soak cotton
waste, engine oil container Land contamination
51. Maintenance work Waste oil generation Land contamination
52. Patrolling Work Usage of Diesel Depletion of Natural Resources
53. Repair Work Generation of Debris Land Contamination
54. Use of Machinery / Vehicles Generation of Noise Noise Pollution
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 17 of 68
CHAPTER:2
STATUTORY AND REGULATORY REQUIREMENTS
2.1 Legal Compliance
The M/s. Ashoka Ranastalam Anandapuram Road Ltd commits to attend all the environmental stipulated
conditions over which obtained permission, NOC and license for compliance of legal and statutory
requirements from the concerned authority for the execution of project, Package II, ARARL. We shall conduct
our operations in such a manner so that we protect the property, health of public and prevent damage to natural
ecosystem and environment at the entire location on and off the project sites.
This will be achieved by the incorporation of following:
1. Organization set-up for responsibility of EHS management System
2. Sound Management planning in execution of works
3. Strong Commitment for remedial actions on Environmental Management Plan
4. High degree Commitments on Pollution Prevention and Abatement
5. Prompt actions for the safeguards of natural ecosystem and environment
6. Commitment for continuous monitoring and reporting on environmental aspects
7. Occupational, Health and Safety for staffs and workers
8. Prompt actions on the safety for road –users and Personnel safety for workers
9. Addressing grievances redress and approach
10. Training and participation
Further, M/s. Ashoka Ranastalam Anandapuram Road Ltd commits that not contravene any legislation and
obtain all licenses, NOC, Permits as per legal and statutory requirements under the laws and acts governed in
India for this Contract package, on or before the appointed date.
The details are given in the following head
2.2 Applicable Permits
2.2.1 The Concessionaire shall obtain, as required under the applicable laws, the following Applicable
Permits on or before the Appointed Date, save and except to the extent of a waiver granted by the
Authority in accordance with Clause 4.1.3 of the Agreement:
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 18 of 68
a) Permission for new quarries from Department of Mines and Geology, State Pollution Control
Board, land conversion from State Revenue Department and District Administration. If mining area
comes under forest land, permission from State Forest Department;
b) Permission of Village Panchayat and Pollution Control Board for and installation of crushers (as per
the recent guidelines from Supreme Court);
c) License for use of explosive from the office of Explosives controller;
d) Permission for drawing water from bore well / pond / river from village Panchayat / Irrigation
Department as applicable;
e) License from Inspector of factories or other competent authority for setting up Batching Plant;
f) Consent for Establishment and Operation of Asphalt Plant, WMM Plant and Concrete Batching
Plant from State Pollution Control Board;
g) Borrow Earth:
i) Permission required from Village Panchayat and owner of the land in case of private land;
ii) Permission from Local Municipalities and Development Authorities;
h) Permission of State Forest Department for cutting of trees, if any;
i) Ministry of Finance / RBI:
i) Approval for foreign investment and foreign loans, if required;
ii) Approval for import of equipment and machinery for construction and operation, if required;
iii) Exemption of Excise Duty on construction materials, if required;
j) Department of Telecommunication:
i) Permission / clearance for setting up of wireless system, if required;
ii) Clearance / permission for the use of optical fiber cables of Department of Telecommunication,
if required;
k) Electricity:
i) Permission required from State Electricity Board (SEB) and Consent from State Pollution
Control Board for installation of Diesel Generator (DG);
ii) Permission for electrical connection, if power source is available;
l) Sewage Lines and Water Mains:
i) Permission from local Municipalities and Development Authorities; and
m) Any other permits or clearances required under Applicable Laws
As per the clause 32.4 Concessionaire will take out and maintain the following insurance policies in the
specified sums and with the specified deductibles as set out below:
(a) Cargo Insurance During Transport: Equipment/ Machinery Invoice value.
(b) Installation All Risks Insurance: Total Project Cost
(c) Third Party Liability Insurance: Minimum Rs 20,00,000/- per occurrence, with the number of
occurrences unlimited.
(d) Professional Liability Insurance: Minimum Rs 10 Crores per occurrence, with the number of
occurrences unlimited.
(e) Automobile Liability Insurance: Value at market rates of vehicles
(f) Worker‟s Compensation: In accordance with the requirements of the Applicable Law of India
(g) Authority‟s Liability: In accordance with the requirements of the Applicable Law of India
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 19 of 68
CHAPTER – 03
INSTITUTIONAL ARRANGEMENT
3.0 INSTITUTIONAL ARRANGMENT
3.1 Project Site Arrangements
The responsibility of implementation of the Environmental Safety Social Management Plan rests with the
following personnel involved in the implementation of the project.
3.1.1 Chief Operating officer (COO) / Project Director
The COO/ Project Director are responsible for the overall implementation of the project. In the present
case, the ABL contractors are also members of the ABL, VHPL, and hence the Project Director is
responsible for undertaking the engineering, procurement and construction of the project.
o Guiding the formation of Policy & its Approval
o Giving the guideline for the Budget & its Approval
o Review of the safety & Environment Procedure & its Approval
o To provide guideline for all legal aspect of project & comply all environment legal rules & regulation.
o To provide guidance for the implementation of OHSAS & EMS System
3.1.2 Project In-Charge / Vice President
The Project In charge / Vice president are responsible for the overall implementation of the project. The
Project In charge / VP are responsible for undertaking the engineering, procurement and construction of the
project. The VP shall oversee the implementation of the EMP by assigning the necessary resources and
periodically review the effective use of the EMP on site.
3.1.3 Resident Engineer (RE) – Road and Bridge Works
The Project Engineer - Road Works shall be responsible for implementation of the EMP during the
construction of the road works. He being responsible for day to day operations with regards to road works
shall supervise and oversee construction activities such as site clearances, stripping of top soil, excavations.
Filling and laying material etc. which necessitates the operation of construction equipment and machinery
at the site.
These activities would have environmental effects in terms of impairment to noise and air quality, tree
cutting and severances and hence shall be responsible for implementing the EMP in the day to day
activities of road construction. The Project Engineer – Bridge Works shall be responsible for
implementation of the EMP during the construction of bridge works. These activities would necessitate
diversion of roads, cutting of trees and diversion to natural drainage paths which would have a bearing on
the environmental quality of the area. The RE (bridge works) shall be responsible for implementation of
EMP with respect to environmental aspects during bridge construction.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 20 of 68
3.1.4 Environmental Officer
For effective implementation and management of the EMP, the Concessionaire has established a Safety,
Health and Environment (SHE) Cell headed by an Environment Officer to deal with the environmental
issues of the project. This officer shall interact with the EPC Contractor, NHAI, IE and other line
departments to ensure that the mitigation and enhancement measures mentioned in the EMP are adhered.
The Environmental officer of the Concessionaire shall be the interface between the Environmental
Specialist of IE and the Environmental Officer of the contractor. His prime responsibility shall be to
apprise the Sr. Environmental Specialist of the IE about the ground conditions. He shall also procure the
requisite clearances and the NOCs for the project and shall also strictly supervise that the Contractor
adheres to the EMP. The environmental officer can also look after the additional charges of safety and
health.
Roles & Responsibilities
He / She shall be reporting directly to the Chief Project Manager of the Concessionaire.
Primarily responsible for implementation of the EMP on site and ensuing that the environmental
quality is meeting the standards laid down by Central Pollution Control Board and other related
authority.
The EO shall implement the EMP by assigning the necessary resources (manpower, money and
machinery) and attend such meetings as are required for the effective implementation of the EMP on
site.
He shall maintain a “Complain Register” to record any grievances from public. He shall maintain a register of all road side trees planted and present within ROW.
The EO shall be the interface of the Concessionaire with the client and the IE.
3.1.5 Site Engineers / Supervisors
The site engineers/supervisors report to the RE and are responsible for day to day operations of
construction works in their respective areas. They supervise and oversee the construction activities and
hence shall be made responsible for ground the EMP and minimize the impacts during construction. Some
of the key aspects that shall be taken up by the site engineers/ supervisors shall include periodic sprinkling
of water in inhabited areas during transportation of material and operation of construction machinery.
3.1.6 Contractors / Subcontractors
Execution of works will be the responsibility of the EPC Contractor.
The Concessionaire may himself be the executioner of the project or might decide to outsource or hire
contractor for highways and structures, who may in turn sublet some part of their work to petty contractors.
In case the Concessionaire decides to execute the work by himself then the responsibilities of the EO as
given in Box 6.1 shall also be performed by the EO of the Concessionaire. The contractor shall be
responsible for both the jobs done by the petty contactor (if Sublet) as well by him. In both the cases the
Concessionaire will implement the environmental measures (either through the contractors or themselves).
This has been done with a view to ensure that road construction and environmental management goes
together.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 21 of 68
Roles & Responsibilities
The Environmental Officer shall report directly to the Resident Construction Manager / Project
Manager so that the pertinent environmental issues that he raises are promptly dealt with.
He shall also have a direct interaction with the Environmental Specialist and the Environmental
Officer of the IE and the Concessionaire respectively.
Monitor / implement measures laid out in the EMP and or as directed by the IE for the work
executed both by petty contractors and the contractor.
Provide key inputs in the development of the Contractors‟ implementation plan for all construction activities, including haulage of material to site, adhering to the requirements of the EMP and getting
approval of concessionaire and the IE on the same before start of works.
Ensure that the regulatory permissions required for the construction equipment, vehicles and
machinery (given in the EMP) have been obtained and are valid at all times during the execution of
the project.
Prepare / fill up the environmental and safety related compliances monthly/Qtr. given in the EMP
Prepare Safety Plans, Emergency Response Plans and Quarry Management and other safety, health
and environment related Plans for approval of the IE and the Concessionaire.
Identify locations for sitting construction camps and other plants, machinery, vehicles and
equipment, as well as locations for storage and disposal of wastes, both from the construction
camps and from the site and obtain approval for the same from the concessionaire and the IE.
Detail out site-specific environmental mitigation and enhancement measures and obtain approval of
concessionaire and the IE for the same
Carry out the measurements of environmental mitigation and / or enhancement works and prepares
bills for the same for approval and payment through the Concessionaire‟s Environmental Officer Ensure that the safety of the workers and other site users is not compromised during construction
Ensure that adequate monitoring facilities are available for collecting samples of all discharges
from the Contractor‟s plants, equipment and camps
Verify the extent of environmental compliance at sites from where the Contractor is procuring the
material – Borrow Area, Quarries, Crushers or even sand and suggest appropriate mitigation
measures, if required
Responsible for implementation of safety and health regulations if also acting as safety officer
The environmental officer shall have a small environmental, health and safety team to help him in
implementing the EMP. These team members may / may not report to him / her directly but shall
apprise him of all the incidents and mark a formal report of any incident having an impact on the
Health, Environment and Safety issues.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 22 of 68
3.2 Training Programs:-
HSE induction training and job specific training needs will identified by EPC /SPV and training will be
imparted to EPC project personnel, SPVS and sub-contractor engaged for the project activities. Specific
training will be imparted to undertake the required ESMP management actions and monitoring activities.
The project will ensure that all concerned team members assigned for implementation of EMP and project
specific ESMP understand the following aspects through the training programme :-
Purpose and Importance of EMP & ESMP for Various project activities ;
Requirements of the mitigation measures under the management plan and specific action plans ;
Understanding of the sensitive environmental and social features within and surrounding the project
area ;
Aware of the potential risks from the project activities.
Table.3.1 Suggested training module matrix for EPC, SPV and Sub-contractor for better
implementing is as below
Sr.
no Training Topic
Designation Project
Management
(GM, DGM, Sr.
Manager and
Manager)
Engineers /
Departmental
Heads
Supervisor Operators Driver Labour
/Workers Frequency
1 E S & S Induction √ √ √ √ √ Six Monthly
2 Emergency Preparedness
and Response Plan √ √ √ √ √
Quarterly
3 Environment & Social
Management Plan √ √ √ √
Quarterly
4 General Safety Rule √ √ √ √ √ Six Monthly
5 Fire Fighting √ √ √ Six Monthly
6 Hazardous Material
(MSDS) √ √ √
√
Six Monthly
7 Road Safety & Road
Barricading
√ √ √ √
Quarterly
8 First Aid Box & its use √ √ √ √ √ √ Monthly
10 Working at Height √ √ √ √ Quarterly
11 Material Handling √ √ √ √ Quarterly
12 Electrical Safety √ √ √ √ √ Quarterly
13 Defensive Driving √ √ √ √ √ √ Quarterly
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 23 of 68
3.2(A) Project Site HSE Organization Chart:
3.3 REPORTING SYSTEM
Reporting system provides necessary feedback for project management to ensure quality of the works and
that the program is on schedule. The rationale for a reporting system is based on accountability to ensure
that the measures proposed as part of the Environmental Management Plan get implemented in the project.
Reporting system for the suggested monitoring program operates at two levels as:
Reporting for environmental condition indicators and environmental management indicators
Reporting for operational performance indicators at the Chief operation officer to site level.
The reporting system will operate linearly – contractor who is at the lowest rung of the implementation
system reporting to the Concessionaire, who in turn shall report to IE and the NHAI. All reporting by the
Concessionaire shall be on a monthly/Quarterly basis, while the reporting time of the contractor shall be
decided upon by the Concessionaire.
Chief Operating Officer
ARARL
Vice President
ARARL
Dy. Manager
ARARL
Sr. HSE Officer
ARARL
Environmental Officer
ARARL
Safety officer
ARARL
HSE Supervisor
ARARL
Asst.Project Manager
(ARARL)
Joint General Manager
(ARARL)
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 24 of 68
3.4 RELEVANT ENVIRONMENTAL LEGISLATIONS
The Central and State Level Environmental Laws and Regulations pertaining to the Project that has been
framed by the Government of India or State Government of Andhra Pradesh are provided in Table 3-1. Table 3.1.1: Relevant Environmental Laws & Regulations
Sl.N
o
Law/Regulation/Guidel
ines Relevance
Applic
able
Yes/N
o
Reason for
Application
Implementing
Responsible
Agency
1
The Environmental
(Protection) Act. 1986,
and the Environmental
(Protection) Rules,
1987-2002 (Various
amendments)
Umbrella Act Protection and
improvement of the
environment. Establishes the
standards for emission of noise
in the atmosphere.
Yes
All environmental
notifications, rules
and schedules are
issued under the act
MOEFCC, State
Department of
Environment &
Forest, CPCB and
SPCB
2
The EIA Notification,
14th September 2006 &
amendments
All new National Highway
projects & NH expansion
projects in hilly terrain (above
1000 MSL) and or ecological
sensitive areas (item 7 (f) of
schedule) as one of the
projects requiring prior
environmental clearance.
No
Project road is
neither a new state
highway nor a SH
expansion projects
in hilly terrain
(above 1000 MSL)
or in ecological
sensitive areas
Opening of Borrow Area (if
required) No
Opening of new
Borrow Area
3
Notification for use of
Fly ash, 3rd November
2009
Reuse fly ash discharged from
Thermal Power Station to
minimise land use for disposal
and minimise borrow area
material. The onus shall lie
with the implementing
authority to use fly ash unless
it is not feasible as per IRC
Yes Fly ash utilizing as
per the notification. MOEFCC, SPCB
4
The Water (Prevention
and Control of
Pollution) Act,1974
Central and State Pollution
Control Board to
establish/enforce water quality
and effulent standards, monitor
water quality, prosecute
offenders, and issue licenses
for construction/operation of
certain facilities
Yes
Consent required
for not polluting
ground and surface
water during
construction
State Pollution
Control Board
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 25 of 68
Sl.N
o
Law/Regulation/Guidel
ines Relevance
Applic
able
Yes/N
o
Reason for
Application
Implementing
Responsible
Agency
5
The Air (Prevention and
Control of Pollution)
Act. 1981
Empowers SPCB to set and
monitor air quality standards
and to prosecute offenders,
excluding vehicular air and
noise emission
Yes
Consent required
for establishing and
operation of plants
State Pollution
Control Board
6
Noise Pollution
(Regulation And
Control) Act. 1981
Standards for noise emission
for various land uses Yes
Construction
machineries and
vehicles to conform
to the standards for
construction
State Pollution
Control Board
7 Forest (Conservation)
Act. 1991
Conservation and definition of
forest areas. Diversion of forest
land follows the process as laid
by the act
No No Forest land
involved
8 Coastal Regulatory Zone
Notification, 1991
Protect and manage coastal
areas No
The project area is
not within
designated coastal
zone
9 Wild Life Protection
Act. 1972
Protection of wild life in
sanctuaries and National Park
(Protected Area)
No
No Wildlife
sanctuary/National
Park/Biosphere
Reserve is located
within 1.0 km from
the project road
10
Ancient Monuments and
Archaeological sites and
Remains Act. 1958
To protect and conserve
cultural sanctuaries and
National Park (Protected Area)
No
No Archaeological
monument along
the project road
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 26 of 68
Sl.N
o
Law/Regulation/Guidel
ines Relevance
Applic
able
Yes/N
o
Reason for
Application
Implementing
Responsible
Agency
11 The Motor Vehicle Act.
1988
Empower State Transport
Authority to enforce standards
for vehicular pollution. From
August 1997 the "Pollution
Under Control Certificate is
issued to reduce vehicular
emissions
Yes
All vehicles used
for construction
will need to comply
with the provisions
of this act
State Motor Vehicle
Department
12 The Explosive Act (&
Rules) 1884 (1983)
Sets out the regulations as to
regards the use of explosive
and precautionary measures
while blasting & quarrying
No
Material will be
procured from
already approved
quarries
13 Public Liability And
Insurance Act. 1991
Protection to the general
public from accidents due to
hazardous materials
Yes
Hazardous
materials like
Bitumen shall be
used for road
construction
State Pollution
Control Board
14
Hazardous Waste
(Management and
Handling) Rules, 1989
Protection to the general
public against improper
handling and disposal of
hazardous waste
No
Hazardous waste
shall be generated
in the period of
maintenance &
vehicles repaire
works
15
Chemical Accidents
(Emergency,
Preparedness and
Response) Rules. 1996
Protection against chemical
accident while handling any
hazardous chemicals
No
Handling of
hazardous
(flammable, toxic
and explosive)
chemicals during
road construction
16
Mines and Minerals
(Regulation and
Development) Act. 1957
as amended in 1972
Permission of Mining of
aggregates and sand from river
bed & aggregates from New
Quarry
No
These materials
shall be procured
from approved
quarries
17
The Building and Other
Construction Workers
(Regulation of
Employment and
Conditions of Service)
BOCW Act. 1996
Employing Labour/Workers Yes Employment of
labourers
District Labour
Commissioner
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 27 of 68
CHAPTER-4
ENVIRONMENTAL MANAGEMENT PLAN AND REVIEW FRAMEWORK 4. ENVIRONMENT MANAGEMENT PLAN
The Environmental Management Plan (EMP) states the procedure in which the project proponent would carry out the implementation of
the mitigation measures and ensure compliance with environmental regulations that are binding on the project. This plan also specifies
the organizational requirements and institutional strengthening necessary for sound environmental management of the project. The
major components of the EMP are:
1. EMP Implementing Agency
2. Monitoring of the EMP implementation
3. Training on Environmental management
4.1 EMP Implementing Agency
The project proponent will establish an Environmental Management Cell (EMC) to supervise and implement the mitigation measures as
documented in the EMP. This EMC must also be adequately empowered to discharge the responsibilities as outlined in the EMP. To
ensure smooth implementation of EMP the project proponent will have to collaborate with various government agencies like Public Works
Department, Irrigation Department, Revenue Department, State Pollution Control Board, Police Department and other concerned
departments. The details of EMP implementation and implementation responsibilities are given in Table -4.1.1, This table
comprehensively lists out the tasks to be performed and completed by the Contracting Company and also lists out the agencies that are
involved and Responsible for ensuring the timely completion of the tasks outlined under EMP. The contractors responsibilities in matters
related to protection of environment shall be the part of the tender document. Table -4.1.1 gives the provisions that are built in the bid
document to protect and safeguard the environment through effective implementation of mitigate measures through an implementing
agency/ the Contractor.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 28 of 68
CONSTRUCTION PHASE
S.No Project related Issues
Action to be taken Frequency Implementation Agency / Authority
Supervision Agency
1.
Avenue tree
cutting and
plantation
Prepare an action plan for an estimated 4000
nos. of trees to be affected/felled in the project
stretch and proposed to be planted about 12,000
nos. trees along the project stretch. Single row of
plantation on both sides is suggested through out
the length of 47 Kms (Length excluding bridges,
settlements etc.).
Intimate forest department before cutting trees and
Prepare action plan for avenue plantation.
Avenue Plantation: The avenue plants proposed
along the project stretches are as per IRC-SP-
21:2011. The avenue plants proposed to be planted
in the project are about 42,157 either side of the
road in two rows. The plants proposed are i.e.,
cashew nut, Kapoor, mango, rosewood, Mahogoni
etc.
Monthly Concessionaire NHAI in
consultation with
the Forest dept.
2.
Borrow pits
and Quarry
sites (stone).
There are 19 nos. of borrow areas, 2 nos. Metal
quarries and 2 nos. Sand quarries are identified in
the project and the same shall get NoC from the
private / Government owners well before start of
the work.
Borrow areas shall be carried out up to depth of
2.0m in non-cultivable & elevated lands, 0.45 m in
productive lands etc. with a slope of not steeper
than 1 vertical to 4 horizontal.
Borrow areas shall be 15 m away from the water
bodies identified along the project corridor.
The borrow areas shall be located at least 800 m
away from the villages/towns.
Resurfacing and landscaping of the borrow pits
utilised in the project.
Monthly Contractor or
Concessionaire
Mining Department
/ NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 29 of 68
S.No Project related Issues
Action to be taken Frequency Implementation Agency / Authority
Supervision Agency
3. Site for storage
and
Construction
camp
The project Contractor shall select a Campsite
which is duly confirming the labour laws. Storage of
HSD, Bitumen will be expected as per the stipulated
guidelines. Besides these, emergency response plan
will be in place towards meeting unforeseen
emergencies. Trained personnel will be handling
such materials and care will be taken so that spills
are abated and in case of spills, immediately they
are contained.
Monthly Contractor or
Concessionaire
NHAI
4. Sewerage and
solid
Waste disposal.
For sewerage disposal, septic tanks with soak
pits will be provided at campsites. Proper sanitation
facilities at the construction workers camp shall be
provided as per the IS:2470-1985
Salvage material / demolition wastes will be
reused to the possible extent in embankments,
shoulders, slopes, approach roads and temporary
campsites.
It is envisaged that approximate 300-500 Kg of
domestic solid waste (300-500 gm/person) per day
will be generated from the workers camps which
will be disposed of to the nearest solid waste
disposal sites as discussed above.
The solid waste generated due to construction
and allied activities would mainly consist of earth
materials. These materials will be reused for
rehabilitation of borrow area / quarry sites,
campsites and in temporary diversions and slopes.
The municipal solid wastes generated in
construction & workers camp will be disposed off at
nearest identified location of disposal / landfill sites
of local authority with payments in environmentally
acceptable manner. Domestic refuse shall be
collected separately for bio-degradable waste as
well as the inert waste and the same shall be sent
for the disposal as per the MSW Rules, 2000.
Monthly Contractor or
Concessionaire
Labour department
/ Health
department /NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 30 of 68
S.No Project related Issues
Action to be taken Frequency Implementation Agency / Authority
Supervision Agency
5. Traffic
management The project stretch passes through major towns
and villages like Peddipalem, Anandapuram,
Tagarapu valasa, Bhogapuram, Agraharam,
Pusapati rega and Pydibheemavaram.
Secure assistance from local police for traffic
control during the construction.
Safety measures shall also be undertaken by
installing road signs and markings for safe and
smooth movement of traffic.
Monthly Contractor or
Concessionaire
NHAI
6.
Noise level Stationary equipment shall be placed as far as
possible from residential areas to minimize noise
impacts on the near inhabitants.
Construction activities will be strictly prohibited
between 10.00 p.m. to 6.00 a.m. near habitation.
Provision of ear plugs to workers exposed to high
noise levels in the project who work in batch mix
plants, hot mix plants, quarries etc.
Quarterly Contractor or
Concessionaire
Andhra Pradesh
State Pollution
Control Board /
NHAI
7. Air Quality The mean Respirable Particulate Matter (PM10)
values observed within the range of CPCB standard
of 100 micro gram/m3for residential / industrial
category. However, all the values found to be well
within the stipulated standards.
During construction, a good number of trucks will
carry the construction material for which emission
of air pollutants will increase. We should see that all
the vehicles deployed for construction of the project
will have to keep “Pollution Under Control” certificates. DG sets will also emit air pollutants in
the area during construction period. The emission
generated during Construction will be temporary
and localized in nature.
Vehicles carrying construction material shall be
covered to avoid spilling.
Quarterly Contractor or
Concessionaire
Andhra Pradesh
State Pollution
Control Board /
NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 31 of 68
S.No Project related Issues
Action to be taken Frequency Implementation Agency / Authority
Supervision Agency
Hot mixing plant shall be over 500m away from
Residential neighborhood and 300m away from the
road.
Mixing equipment shall be seated and equipped
with dust removal device.
Water will be sprinkled in morning and evening
hours at the construction yards and the unpaved
sections of the road.
8. Water Quality &
Solid waste Prior permission of the concerned engineer and
regulatory authorities shall be taken regarding the
discharge or disposing of any material arising from
the execution of the works.
During construction it will be ensured that
contractor does not dispose off debris in water
bodies.
Soil laden run off will not be diverted to water
bodies. Provision of waste disposal site for waste
from construction and storage yards shall be made.
Vehicle maintenance and refueling will be
confined to areas under construction yard to trap
discarded lubricant and fuel spills.
Quarterly Contractor or
Concessionaire
Andhra Pradesh
State Pollution
Control Board /
NHAI
9. Water logging
and stagnation
of water in
the Borrow
pits
The majority of the project stretch is plane &
horizontal land which will be act as water logging
areas during the rainy seasons and may cause the
breeding of the vectors in the area.
Uncontrolled digging of approved Borrow pits in
the areas will be avoided to prevent water
accumulation which results in breeding of disease
causing vectors in the area.
Monthly Contractor or
Concessionaire
NHAI
10. Occupational
Health and
Safety
Labourers shall be equipped with proper safety
gears like helmets, gloves and gum boots.
Periodic health checkup of construction workers.
Contractor or
Concessionaire
NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 32 of 68
S.No Project related Issues
Action to be taken Frequency Implementation Agency / Authority
Supervision Agency
11. Basic amenities
And sanitation
facilities for
labourers
Adequate sanitary facilities shall be provided to
the workers to avoid health related problems.
Sanitation Waste from workers camp will not be
diverted to water bodies.
Periodic health checkup of labours shall be done.
Contractor to prepare, NHAI’s approved detailed public health utilities plan for the workers camp and
other working sites, which make adequate provision
for safe disposal of all wastes and prevention of
spillages, leakage of polluting materials etc.
Contractor will be required to pay all costs
associated with cleaning up any pollution caused by
their activities and to pay full compensation to
those affected.
Monthly Contractor or
Concessionaire
Labour department
/Health
Department /NHAI
12. Fuel for
labourers
Adequate supply of fuel (LPG/Kerosene) shall be
provided to the labourers to avoid felling of trees
for cooking and other domestic chores.
Monthly Contractor or
Concessionaire
Labour department
/Health
Department /NHAI
13. Prevention
of erosion and
scouring
Stabilizing the embankment with appropriate
technique immediately after placing.
The high embankment slopes near to the major
bridges are washed out or weaken and the same
shall be strengthened.
Treating high embankment slopes with rip rap,
stone pitching or other technologies to prevent
erosion.
Construction of toe drain all along the road on
both sides.
Avoiding obstruction of existing drainage during
filling.
Contractor or
Concessionaire
NHAI
14. Drainage
system Adequate care has been taken for the purpose of
free flow of flood discharge in the design stage
itself. There are 4 major and 32 minor bridges
proposed along the project corridor to allow free
flow of the natural drainage water in the area.
Monthly Contractor or
Concessionaire
Irrigation Dept
/NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 33 of 68
S.No Project related Issues
Action to be taken Frequency Implementation Agency / Authority
Supervision Agency
Construction of toe drain along the road on both
the sides.
Avoiding obstruction of existing drainage during
filling.
15. Conservation of
Eco resources To preserve earth borrowing areas, piling, and
building temporary camps are prohibited in forests
lands.
Arable lands should not be used as earth
borrowing whenever possible. If needed, the topsoil
(30cm) should be kept and refilled after
construction is over to minimize the impact on
ecosystem and
agriculture.
Construction workers should be told to protect
natural resources and wild animals.
Construction vehicles should run at temporary
accesses to avoid damaging arable lands and
cattle-raising lands.
Monthly Contractor or
Concessionaire
Forests Dept
/NHAI
16. Communications
and
Transportation
Local materials should be used as much as
possible so as to avoid long distance transportation
that of earth, sand and stone.
If there are traffic jammed during construction,
measures should be taken to move the jam with
the coordination of transportation and public
security department.
Temporary access should be built at the
interchange of the highway and other roads.
Passing time on National Highways will be
limited, similar measures will also be applied to
roads with traffic jams.
Quarterly Contractor or
Concessionaire
Transport
Department
/NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 34 of 68
S.No Project related Issues
Action to be taken Frequency Implementation Agency / Authority
Supervision Agency
Materials may be delivery in advance in relatively
leisurely season of traffic.
A transportation plan of materials will be
formulated to avoid delivered of them at peak
hours on existing roads.
17. Rain Water
Harvesting
I) The total project stretch was considered about 47
Km covering major towns and villages.
II). There are about 188 nos. of RWH Pits are
proposed either side of the road at an interval of
500m. The proposed RWHs are having dia. Of 1.5
m with a depth of 3.8 m.
III) The budget provision for the RWH structures
are provided at the rate of Rs. 15,000/pit and the
total amount is estimated to be Rs. 0.385 Crores.
Monthly Contractor or
Concessionaire
GW Department
/NHAI
18. Utilization
of Fly Ash
In the proposed project, There are four existing
Thermal Power Stations and two power stations are
proposed which fall within 500 Km from the project
corridor. Hence, Utilization of Fly Ash in the project
is estimated to be 32,34,382 cum provision made
as per the IRC SP:58 – 2001 and Fly ash
Notification 2007and the subsequent amendments
in 25th March, 2015 and the same shall also be put
under the BoQs.
Monthly Contractor or
Concessionaire
NHAI /Andhra
Pradesh State
Pollution Control
Board
19. Surplus earth/
Muck disposal
Top Soil: Top soil of 15cm will be carefully stripped
and utilized as top layer in median filling and / or
embankment slopes prior to turfing / sodding for
restoration of temporary sites, etc. Excavated Materials: Suitable excavated materials will
be reused in road embankments formation. The
non-usable material will be utilized for reclamation
/ rehabilitation of quarries and borrow pits or can
be used to fill the depression. Overburden: Overburden generated from borrow pits,
quarries will be used for its rehabilitation for
covering the waste material. Final surface will be
made up from top soil rich in NPK will be layered to
receive grass/ vegetation.
Monthly Contractor or
Concessionaire
NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 35 of 68
S.No Project related Issues
Action to be taken Frequency Implementation Agency / Authority
Supervision Agency
OPERATION PHASE 1. Air Quality a) Monitor periodically the AAQ at suggested
locations.
b) Developing road side vegetation for pollutant
sinking.
c) Enforcing different control measures to minimize
pollution.
d) Public will be educated about the regulations on
air pollution of vehicles.
Quarterly Contractor or
Concessionaire
Andhra Pradesh
State Pollution
Control Board /
NHAI
2. Road safety and
traffic
management
Prepare and administer a monitoring system on
road accidents.
Adequate number of road signs with clear
visibility shall be installed.
In case of spill of hazardous materials, report to
the relevant departments at once and deal with it in
accordance with the emergency plan.
Drivers and Public will be educated about the
Safety regulations.
Quarterly Contractor or
Concessionaire
NHAI/Traffic
Police dept.
3. Noise level Provision of noise barriers (earthen berms / thick
green belt development) has been proposed at
sensitive areas and other noise prone areas.
Periodic monitoring of ambient noise levels at
suggested locations
There are two rows of avenue plants proposed
along the project corridor, Section of the NH-361
project, as per IRC-SP- 21: 2011. The avenue
plants proposed to be planted in the project on
either side of the road to prevent the noise levels.
Quarterly Contractor or
Concessionaire
Andhra Pradesh
State Pollution
Control Board /
NHAI
4. Soil
characteristics
Periodic monitoring of soil quality at specified
distance from the corridor for assessing soil
contamination by vehicular emissions. The analyzed
samples shall be compared with the baseline values
monitored at 5 locations along the Project corridor.
Quarterly Contractor or
Concessionaire
Andhra Pradesh
State Pollution
Control Board /
NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 36 of 68
S.No Project related Issues
Action to be taken Frequency Implementation Agency / Authority
Supervision Agency
5.
Maintenance of
road side
plantations
Avenue Plantation: There are two rows of avenue
plants proposed along the project corridor as per
IRC-SP-21: 2011. The avenue plants proposed to
be planted in the project are about 42,157 either
side of the road, parking areas, toll gates, bus bays
and truck laybyes. The plants proposed are i.e.,
cashew nut, Kapoor, mango, rosewood, Mahogoni
etc.
Median Plantation: Since the project is widening
of foue lane to six laning project median will be
utilised as it is. However, a provision of 47 Kms
median plantation is made in the project to cover
the bypassess realignments etc. The median
plantation is proposed in one/two rows and the
numbers of species proposed are 42,157 nos. The
median plant proposed in the project are i.e.,
Bougainvillea, Nerium Oleander, Thevitia, Nerifolia,
Tabernaemontana Coronaria etc.
Employment of local people for the maintenance
of plantation along the corridor
Quarterly Contractor or
Concessionaire
Forests
Department/
NHAI
6. Maintenance of
Drainage
System
The drainage system will be periodically cleared so
as to ensure water flow.
Quarterly Contractor or
Concessionaire
Irrigation Dept
/NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 37 of 68
4.2 Monitoring of EMP Implementation
The EMP will primarily be implemented by the Project Proponent & Civil Contractor. The first is internally by the top management of
Contracting Agency and the second by the National Highways Authorities of India (NHAI). The EMC constituted by the Contracting
Company shall be the prime agency for monitoring all the activities during all the phases. NHAI shall supervise all activities and
accordingly advise the Contracting Company to improve on areas where any short comings are observed. The EMC shall provide all the
monitoring results to NHAI. NHAI shall keep a record of all information and shall suggest suitable measures to be adopted by contracting
Company if any aspect is found to be deviating from the anticipated procedures/ standards. Monitoring shall be carried out during
construction and operation phases. Table -4.2.1: Environmental Monitoring during Construction & Operation phase
Parameters
Location
Duration
Frequency Construction Phase Operation Phase
Air Quality:
PM10, PM2.5,
NOx, SO2, and
CO
Five (5) locations where
baseline monitoring was
carried out
24 hours
continuous
sampling
Once in a season or thrice in a
year twice in a year
(other than monsoon
season)
Noise Level:
L eq(day) and
L eq(night)
Seven (7) locations where
Baseline monitoring was
carried out.
24 hours
continuously Thrice in a year twice in a year
(other than monsoon
season)
Soil Quality:
Physicochemical,
Lead, oil and
grease
Three (3) samples where
baseline monitoring was
carried out
Grab Thrice in a year ( non –monsoon) twice in a year (other
than monsoon season)
Water Quality:
For different
physical, chemical
and biological
parameter
Thirteen (13) samples (Surface
and Ground Water) Grab Thrice in a year during pre-post
Monsoon season and winter
season
twice in a year
(other than
monsoon season)
Maintenance for
road side
plantation
All along the project road.
There are about 97,932 nos. of
avenue plants proposed in the
project.
Throughout the
year Regularly throughout the year for
three years ----------
Monitoring of
sanitary and
environmental
status of Barrow
areas
All the Borrow pits Grab Sampling
for Water and
Soil
Once in a season -----------
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 38 of 68
4.2.2 Common Property Resources (CPRs) and other Utilities
All, fully or partially affected Common property resources has already been shifted by employer however during implementation of project if any CPRs
needs to be taken care shall be carried out as per below mitigation measures with the assistance of employer.
Problems Mitigation measures Applicability Responsibility Avoidance of CPRs Realignment nears all CPRs wherever it is technically
feasible.
Near CPRs Project In-charge, Site Engineer/ Site
Supervisor, Subcontractor
Shifting of
community properties Geometric adjustment while finalizing the alignment to
minimize the loss to any such facilities.
Relocation of wells, hand pumps at suitable locations in
consultation with community
Throughout the
corridor
Project In-charge, Site Engineer/ Site
Supervisor, Subcontractor
Utilities
All telephone and electrical poles/wires and underground
cables should be shifted to avoid any such hazard
Throughout the
corridor
Project In-charge, Site Engineer/ Site
Supervisor, Subcontractor
Environmental
enhancement along the
corridor
Enhancement of Ponds, tree plantations near likely to be
relocated community structures/ landscaping etc.
Enhancement/rehabilitation of borrow areas etc.
Construction of check dams/other water harvesting
structures
Project In-charge, Site Engineer/ Site
Supervisor, Subcontractor
4.3 Environmental Training
The Environmental Management Cell (EMC), in addition to implementing and monitoring different environmental attributes, shall also be actively involved
in imparting training and raising environmental awareness level of Contractors and the construction staff so as to enable them to take the environmental
aspects into consideration as and when required. In the long term, the EMC can impart additional and specialized training in the Environmental Management
of the road system.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 39 of 68
4.0 (A) ENVIRONMENTAL MITIGATION AND ENHANCEMENT The anticipated impacts, even though limited, will be mitigated following the guidance provided in this chapter. It is expected that the construction stage activities will broadly follow the sequence of Table 4 -1. During the post-construction stage, demobilization and operation shall follow the Concessionaire / Contractor‟s plan. Since most of the activities that have noticeable adverse environmental impacts are to occur during construction period, the focus of this plan is mainly during the same period. Details of various mitigation measures to be implemented during pre-construction, construction and operation stage are presented in Table 4-1. The table also gives the details of those responsible for the implementation,
supervision and monitoring of the project.
As part of the Good Environmental Practices, all affirmative actions are deliberated. Based on project specific mitigation
and enhancement measures are proposed. These mitigation and enhancement measures shall lead to generating good will
among the various stakeholders and road users and go a long way in making the project success. 4. A.1 MITIGATION MEASURES As part of project it has been endeavored to mitigate all negative impacts of the project on the physical, biological and
social environment. The RAP details out the mitigation measures adopted to minimize the social impacts. The mitigation
measures to minimize the impacts on physical and environment have been dealt in details in the EIA report. The EMP
table also provides the mitigation measures along with the responsibility and locations in details. Budgetary provisions
have been made to capture the mitigation measures. Some of the mitigation measures on major parameters are
summarized below: 4. A.2 Land
Land acquisition minimized & shall only be limited to locations which require geometric correction
Soil Erosion mitigated through Stone pitching & Turfing
Oil Interceptor will be provided for accidental spill of oil and diesel
Septic tank will be constructed for waste disposal
Quarry & Borrow Area Operation & Management Plans drawn 4. A.3 Water
Relocation of ground water sources
Silt fencing to be provided for surface water source
Rain water harvesting structure & water harvesting structures for storage of water especially during summer and also for the use of local populace
Regular monitoring of water quality
Compliance with statuary regulatory requirements
Provision of oil interceptors & septic tanks at camp sites
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 40 of 68
4. A.4 Air Quality
There will be rise in PM levels during the construction activities, which shall again be within prescribed limit after
the Avenue plantation of broad leaf trees
Sprinkling of Water
Fine materials to be completely covered, during transport and stocking
Plants to be installed in down wind direction from nearby settlement
Compliance with statuary regulatory requirements
All vehicles, equipment and machinery used for construction will be regularly maintained to ensure that the pollution emission levels conforms to regulatory requirements
Provisions of PPE to the workers
Regular monitoring of ambient air quality
4. A.5 Noise
No Horn Zone sign Post
Provision of noise barriers
Machinery to be checked and complied with noise pollution regulations
Camps to be setup away from the settlements, in the down wind direction
Provisions of PPE to the workers & prevent prolonged exposure to noise levels of more than 90 dB (A) per 8 hour shift
All vehicles, equipment and machinery used for construction will be regularly maintained to ensure that the
pollution levels conforms to regulatory requirements
Compliance with statuary regulatory requirements
Regular monitoring of ambient noise quality
4. A.6 National Park / Sanctuary / Bio-sphere Reserve / Notified Animal Corridor
No National Park or Wildlife Sanctuary is located within 10 km radius from the project road. Also, there are no
notified animal corridor/migration route is present in the project area.
4. A.7 Forest Areas
No Protected / Reserve Forest are likely to be affected by the project. 4. A.8 Flora and Fauna
Avenue plantation along corridor, where ever possible given to compensate the loss of trees due to felling
Tree Plantation Strategy prepared which stresses on plantation of native broad leafed indigenous trees species
Construction workers shall be instructed to protect natural resources and fauna, including wild animals and aquatic life.
Hunting and un authorized fishing shall be prohibited
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 41 of 68
4. A.9 ENVIRONMENTAL ENHANCEMENT MEASURES
Environmental Enhancements refer to the positive actions to be taken up during the implementation of the Project for the
benefit of the road users and the communities living close to Project road and are in addition to the mitigation measures
proposed. The objectives of environment enhancement are:
To improve visual qualities of highway by providing aesthetically pleasing landscape features
To integrate the road corridor with surrounding views and landforms.
To improve the environment setting along the road
To improve the condition of neglected Archaeological / Communities sites, if any
Reduce pollution load
To integrate local communities with the project by development community properties along the road.
Provide facilities to Highway user. 4. A.10 ENVIRONMENTAL MANAGEMENT PLAN (EMP)
Environmental impacts could be positive or negative, direct or indirect, local or regional and also reversible or irreversible.
The impacts generated during construction and operational phase of the roads along with management plan for these
impacts has been discussed in Environmental Management Plan. Environmental management considerations in the form of
EMP have been designed for project activities based on sample EMP and the Codes of practices. The EMP shall provide
guidelines & help IE and Concessionaire in implementing and incorporating environmental management practices to
reduce negative environmental impacts of the project. The plan outlines existing and potential problems that may impact
the environment and recommends corrective measures where required. Enhancement measures are also proposed in order
to provide good environmental practices and improve the aesthetics. The enhancement of water body shall be finalized by
IE and Concessionaire in consultation with the local community and Project Proponent. However, the lump sum cost for
enhancement of water body covered in EMP Budget. The other key issues that require special attention along with the
mitigations and enhancement measures to be implemented have been detailed in Table 4.1
4. A.11 GRIEVANCE REDRESSAL MECHANISM:
A Grievance Redressal Cell (GRC) to be established at the project office. The cell has representation from company,
Ashoka Ranastalam - Anandapuram Road Project (ARARL)., Sub-Contractor, local administration and concerned
stockholders. The company facilitator will look into complaints and concerns about ownerships disputes historic structures,
religious structures, public utilities, distribution of compensation among heirs, missing affected assets and persons in the
census etc. the procedure will not replace existing legal processes. Company will forward the grievance to the concerned
authority.
4. A.12 ONGOING REPORTING TO THE PAC (PROJECT AFFECTED COMMUNITIES):
Company/ ABSRL facilitator will play pro-active role in mitigation measures mentioned infeasibility report and suggested
by Client and same will be reported to the Client
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 42 of 68
Chapter-05
Environmental Management System
5.0 PRECAUTIONS FOR SAFEGUARDING THE ENVIRONMENT
5.1 Borrow-pits for Embankment Construction The Concessionaire M/S ARARL shall not be dug Borrow pits within the Right-of-Way of the road. Arable
lands will not be used for earth borrowing. The Concessionaire will ensure that proper excavation techniques are
used to improve stability and safety of the borrow area. The excavation shall be carried out in such a way that the
area does not inundate during monsoons or generate cesspools of water to become mosquito-breeding sites. The
depth of the pits shall be so regulated that the sides of the excavation will have a slope not steeper than 1 vertical
to 4 horizontal, from the edge of the final section of the bank.
5.2 Quarry Operations The Concessionaire shall obtain material from licensed quarries only after the consent of the forest department or
other concerned authorities. The quarry operation shall be undertaken within the purview of the rules and
regulations in force. The Concessionaire shall ensure scheduling the movement of transport carrying material to
and from the site during non-peak hours. The trucks carrying all the dusty material, red earth, moorum and fly
ash/ pond, ash shall be covered with a tarpaulin and provided with adequate free board to prevent spillage. End
boards shall be provided in loaders to prevent spillage. Stockpiling of material shall be properly planned so as to
ensure that no traffic jam takes place on the highway.
5.3 Control of Soil Erosion, Sedimentation and Water Pollution The Concessionaire shall carry out the works in such a manner that soil erosion is fully controlled, and
sedimentation and pollution of natural water courses, ponds, tanks and reservoirs is avoided. In borrow pits, the
depth of the pits shall be so regulated that the sides of the excavation will have a slope not steeper than 1 vertical to 4
horizontal, from the edge of the final section of the bank.
5.4. Precautions against Dust The Concessionaire shall take all reasonable steps to minimize dust nuisance during the construction of the
works. All existing highways and roads used by vehicles of the Concessionaire or any of his sub-contractors or
suppliers of materials or plant, and similarly any new roads which are part of the works and which are being used
by traffic shall be kept clean and clear of all dust / mud or other extraneous material dropped by the said vehicles
or their tyres. Similarly, all dust / or mud or other extraneous material from the works spreading on these
highways shall be immediately cleared by the Concessionaire. Clearance shall be affected immediately by
manual sweeping and removal of debris, or, if so directed by the Independent Engineer, by mechanical sweeping
and clearing equipment, and all dust, mud and other debris shall be removed entirely from the road surface.
Additionally, the road surface including haul road from Quarries and Plants shall be hosed or watered using
suitable equipment to avoid dust pollution. Special care shall be taken to combat dust problem originating from
use of fly ash/pond ash.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 43 of 68
5.5 Pollution from Hot Mix Plant, WMM Plant, Batching Plant & Crusher and Other Construction
Machinery The Concessionaire shall ensure the use of a relatively new, well maintained hot mix plant (batch type) so that
any emission conforms to the CPCB norms and be fitted with a dust extraction unit to avoid prolonged engine
powered equipment illness. Hot Mix Plant, WMM plant, Batching Plant, Generator set & Crusher shall be
located more than 500 m from any community or residence. The Concessionaire has to obtain necessary
consent/clearance from State Pollution Control Board to operate Hot Mix Plant, WMM plant, Batching Plant &
Crusher before commencement of works.
All vehicles, equipment and machinery needed for construction will be regularly maintained to ensure that
pollution emission levels conform to CPCB norms. All vehicles should be fitted with silencers.
Construction vehicles, machinery & equipment will move or be stationed in designated areas to avoid
compaction of soil to ensure the preservation of the top soil for agriculture.
5.6 Road Safety The Concessionaire shall provide adequate circuit for traffic flow around construction areas, control speed of
construction vehicles through road safety and training of drivers, provide adequate signage, barriers and flag
persons for traffic control. If there are traffic jams during construction, measures shall be taken to relieve the
congestion with the assistance of traffic police. Safety of workers undertaking various operations during
construction will be ensured by providing helmets, masks, safety goggles, etc. One Qualified Safety Officer and
one Safety Supervisor must be available in the Concessionaire‟s working team for the entire construction period.
5.7 Sanitation & Waste Disposal in Construction Camp The Concessionaire shall ensure that construction camps are located at a distance of minimum 200m from water
sources. Special attention shall be paid to the sanitary conditions of the camps. The Concessionaire shall ensure
that sufficient measures are taken i.e. provision for safe disposal of garbage and sanitation facilities. Waste in
septic tanks shall be cleaned periodically. Garbage shall be collected in four collection pits at each construction
site and disposed of daily. The Concessionaire shall provide adequate measures for the health care of workers
and arrange their regular medical check-up to ensure that they do not suffer from any communicable disease. At
every workplace, good & sufficient water supply will be maintained to avoid waterborne / water related diseases.
If any pits are dug at construction / camp sites which are not filled and then may turn into mosquito breeding
sites during monsoons, either these shall be filled up properly to avoid water stagnation and also sprayed
frequently with pesticides to prevent mosquito breeding. In addition the following care may be taken:
1) Avoid usage of Plastic materials like carry bags etc at the Labour camps
2) Provision of first aid facilities at the Labour camps
3) Facilities for proper disposal of sewage at the Labour camps
4) Provide fire extinguishers at storage facilities of fuel and lubricants
5) Use of LPG should be encouraged instead of fire wood for cooking at the labour camp
6) Small incinerators should be provided for burning waste oil, grease materials etc
7) Dedicated service stations with oil & grease interceptors to be provided
8) Store Yard for storing used tires, scrap materials/ released materials etc
9) Tree plantations on the periphery of Crusher Plant, Construction Plant and labour camp etc
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 44 of 68
5.8 Substance Hazardous to Health The Concessionaire shall not use or generate any material in the works, which is hazardous to the health of
persons, animals or vegetation. Where it is necessary to use some such substance which can cause injury to the
health of the workers, the Concessionaire shall provide suitable protective clothing or appliances to his workers,
viz. earplugs, helmets or dust masks.
5.9 Damage to Existing road/CD Structures
Any structural damage caused to the existing roads/structures to be retained as per Concession Agreement by the
Concessionaire‟s construction equipment shall be made good without any extra cost.
5.10 Use of Nuclear Gauges Nuclear gauges shall be used in consultation with the Independent Engineer. The Concessionaire shall provide
the Independent Engineer with a copy of the regulations governing the safe use of nuclear gauges he intends to
employ and shall abide by such regulations. Without written approval, no such equipment shall be used at any
level of the work.
5.11 Environmental Monitoring In order to carry out periodic checks, environmental monitoring will be carried out by the Concessionaire as per
schedule and if any parameter is found above the acceptable standards, mitigation measures / control measures
shall be adopted in consultation with the Independent Engineer. Specified locations shall be at least three times
per year for two years/construction period whichever is more.
5.12 Protection of Existing Trees Some of the existing trees within the right of way are likely to be cut down by the Authority prior to handing
over of the site to the Concessionaire.
The Concessionaire shall take all necessary measures to ensure safety and protection of the remaining trees from
any action whatsoever relating to his construction operations in the adjoining areas.
5.13 Disposal of Materials outside Work Site Notwithstanding other relevant provisions in the Agreement, the excess material generated by dismantling,
excavation, waste material and lubricants, used oil, gasoline and other such substance etc., shall be removed
from site outside the right of way at regular intervals and site shall kept clean from all such disposable materials.
Grease, cotton and other waste construction materials shall be disposed off in shallow soakage wells constructed
at each construction site. Also safety measures should be taken in to account for safe disposal/handling of
Hazardous materials such as explosive, fuels etc such intervals shall not exceed one month under any
circumstances. The selection of the disposal site in consultation with Independent Engineer shall be the
responsibility of the Concessionaire and he shall ensure that the selected site does not result in any claim for
damages to the Authority or violation of any existing laws.
5.13.1 Disposal of Unserviceable Materials The Concessionaire shall responsible to identify the locations of Disposal sites have to be selected and approval
from the Environmental Specialist of IE as follows.
1) Locating the disposal sites is the sole responsibility of the Concessionaire with the approval of Independent
Engineer.
2) Joint inspection of all disposal sites shall be done by Independent Engineer and Concessionaire prior to
approval.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 45 of 68
3) No residential area are located downwind side of these locations,
4) Disposal sites are located at least 1000 m away from sensitive locations like Settlements, Water body notified
forest areas, Sanctuaries or any other sensitive locations.
5) Disposal sites do not contaminate any water sources, rivers etc for this site should be located away from
water body and disposal site should be lined properly to prevent infiltration of water.
6) Public perception about the location of debris disposal site has to be obtained before finalizing the location.
7) Permission from the Village/local community is to be obtained for the Disposal site selected.
8) Concessionaire will resolve all claims arising out of waste disposal at his own cost.
9) Concessionaire shall utilize the suitable burrow areas, abandoned quarries and other waste land for the debris
disposal.
Concessionaire needs to plan the disposal in the following way:
10) Identify the disposal area.
11) Prepare a Concessionaires debris disposal plan with design drawings for each identified area and get it
approved by the Independent Engineer.
12) Need to photograph the present land use and condition of the area.
13) Construct all required structures (e.g. retaining wall).
14) The dumpsites filled only up to the ground level with compaction of the debris materials in layers after
disposal.
15) The 30 cm top layer of disposal pit shall be provided with good earth suitable for development of
vegetation/plantation.
16) After levelling, the site could be suitably rehabilitated by planting local species of grass (turfing), shrubs
and other plants as decided by the Independent Engineer.
5.13.2. Construction of Water Recharge Pits
Storm water recharge pits shall be located such that it should be in the valley of the surface layout nearby cross
drainage structures and other water bodies along the project road. Water recharge pits shall be located at an
height of 3 m. above the ground water table of the area as per the Central Ground Water Board norms. Recharge
pits are constructed by the side of the guiding drains such that all the storm water shall be directed to the
recharge pit. Any proposal for change in number and location recharge pits by the Concessionaire shall be
checked and approved by the Independent Engineer.
Pits, trenches, abandoned dug wells, recharge wells or abandoned bore wells shall be connected by the rain water
harvesting system with the consent of the respective owner or as approved by the Independent Engineer.
5.13.3. Construction of Silt Traps
Silt fences shall be planned such that each recharge pit will have one silt fence to prevent silt from entering the
nearest water bodies and also prevent choking of recharge pit by the silt coming from runoff water and increase
the life of recharge pits. Silt fence are mounted in guiding drains at a distance of 3 to 5 M in the upstream
direction depending on the gradient of the guiding drains. However any proposal for change in number and
location silt fences by the Concessionaire shall be checked and approved by the Independent Engineer. Sand / silt
removal facilities such as sand traps, silt traps and sediment basins should be provided to remove sand / silt
particles from run-off.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 46 of 68
5.13.4. Scarified Bitumen Disposal Pits
Scarified bitumen generated out of scarification of existing pavement is used for approach roads by mixing it
with fresh bitumen or other granular materials to achieve the required strength followed by profiling and
compaction.
The left out portion of the scarified bitumen is disposed safely in a clay lined pit. or as directed and approved by
the Independent Engineer. A typical clay lined bitumen disposal pit with standard dimensions has been worked
out. The dimension of the bitumen disposal pit may change provided the clay lining of required thickness is
adhered to.
The selection of sites for disposal of scarified bitumen is made on following lines:
1) Locating the bitumen disposal sites is the sole responsibility of the Concessionaire with the approval of
Independent Engineer.
2) Selection of bitumen disposal site is avoided in the quarry regions. If the disposal site has to be located in the
abandoned quarry, region is suitably treated to seal the fractures and fissures.
3) Joint inspection of all disposal sites shall be done by Independent Engineer and Concessionaire prior to
approval.
4) Disposal sites shall be located at least 1000 m away from sensitive locations like Settlements, Water body
notified forest areas, Sanctuaries or any other sensitive locations.
5) Disposal sites do not contaminate any water sources, rivers etc for this, site should be located away from
water body and disposal site should be lined properly to prevent infiltration of water.
6) Public perception about the location of bitumen disposal site has to be obtained before finalizing the location.
7) Permission from the Village/local community is to be obtained for the Disposal site selected.
8) Concessionaire will resolve all claims arising out of waste disposal at his own cost.
Concessionaire needs to plan the bitumen disposal in the following way:
1) Identify the disposal area.
2) Prepare a Concessionaires bitumen disposal plan with design drawings for each identified area and get it
approved by the Independent Engineer.
3) Need to photograph the land use and condition of the area during pre, during, post project implementation
stages.
4) Construct all required structures (e.g. retaining wall) along with clay lining and measures to prevent the
seepage of bitumen leachate.
5) The dumpsites filled only up to the ground level with compaction of the materials in layers after disposal.
6) The 30 cm top layer of disposal pit shall be provided with good earth suitable for development of
vegetation/plantation.
7) After leveling, the site could be suitably rehabilitated by planting local species of grass (Turfing), shrubs and
other plants as decided by the Independent Engineer.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 47 of 68
5.13.5. Provision of Oil Interceptors
The ARARL Provide location of Oil Interceptors shall be considered such that each construction camp having
refueling stations, oil and lubricants storage places will have one oil interceptor to stop & separate the floating
oils. However the number of interceptors shall be increased as the situation demands or during the accidental
spillages with the consent of the Independent Engineer.
5.13.6. Environmental Monitoring
Environmental Monitoring of Air, Noise, Water and Soil parameters shall be carried by the Concessionaire as
per the consents and latest environmental norms, guidelines and policies of national and state level
environmental authorities. The Concessionaire shall comply by all obligations and make sure that there are no
deviations from them or from the Agreement. Environmental standards for Air, Noise, Water and Soil.
Frequency of Environmental Monitoring at construction establishments and other specified locations shall be at
least three times per year for two years/construction period whichever is more.
5.13.7. Landscape and Tree Plantation
The Concessionaire shall plant the trees during the construction to overcome the pollution of GHG in the extent
use of plants, machinery, and emission from using vehicles that total emission of carbon dioxide from the
combustion of diesel in the total life cycle of the project and environmental loss due to construction camp, labour
camp, quarry operation, borrow operation and impacts due to other construction activities. Tree shall be planted
at open available space at camp sites and other available space on and off the project site to recover the loss. For
the plantation strategy IRC: SP-21, IRC – 66 shall be followed. Although, the landscaping shall be carried – out
as per the extant police of Authority.
5.13.8. Welfare Facilities to the Labours/Workers
The Concessionaire responsible for provide all welfare facilities to the Labours/Workers as per Environmental
norms, Acts and Rules.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 48 of 68
Chapter – 05 (A)
Applicable Law and Acts
Apart the above, the ABL shall obtain all applicable Permits and NOC required for environmental protection and
conservation from the Competent Authority as provision under the acts and rules governed in India and applicable for
this project.
The following Rules and Regulation are applicable :-
Environment Protection Act :1986 - – Applicable
The Water (Prevention & control of pollution ) Act, 1974 - – Applicable
The Water (Prevention & Control of pollution) Cess Act, 1977, including rules, 1978 - – Applicable
The Air (Prevention & control of pollution ) Act, 1984 - – Applicable
The Hazardous Waste (Management & Handling) Rules, 2000 - – Not Applicable
Manufacture, Storage & Import of Hazardous Chemicals Rules, 1989 - – Applicable
Forest clearance for tree cutting (Local, State and Centre if required) –- Applicable
Local authority or Grampanchyat permission (NOC) for establishment of plant - – Applicable
District Industry Centre permission for industry - – Applicable
Factory Act: 1948 (Crusher VSI & HMP ) Plant Establishment - – Applicable
State Factory Rule (Director of Industrial Safety and Health requirement) - – Applicable
Building and Other Construction worker Act, 1996 Applicable & Central rules - 1998
The Mines & Minerals Act, 1957 -– Applicable
Land acquisition Rule-1998 –Applicable
Petroleum Rules, 1976 (Petroleum & Explosive Department) - – Applicable
The Indian Electricity Rules, 1956 - – Applicable
Batteries Act, 1989 - – Applicable
Minimum Wages Act, 1948 - – Applicable
National Environmental Tribunal Act, 1995
National Environment Appellate Authority Act, 1997
Notification on Fly Ash – IRC : SP 56:2001
Motor Vehicle Rules (1989) and Amendments of 1994, 2000 & 2002
Environmental (Protection) Amendments Rules, 2003
Forest ( Conservation) Act, 1980
The Andhra Pradesh Preservation of Trees Act, 1976
Public Liability Insurance Act, 1991
Labour (Regulation & Abolition) Act, 1970 & Rules -1971
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 49 of 68
CHAPTER-06 ENVIRONMENTAL STIPULATION FROM THE COMPETENT AUTHORITY
SEIAA, MOEFCC&CC, SPCB, FOREST DEPARTMENT AND CHECK LISTS OF
ENVIRONMENTAL REMIDIAL MEASURES
Based on the findings during the EIA study the following can be safely deduced and focus on the potential impacts due to the proposed project
and to propose mitigation measures through an appropriate EMP for the project.
The project is a neither a new Highway nor a NH expansion projects in hilly terrain (above 1000 MSL) and nor located in any notified
ecologically sensitive areas. Thus the project doesn‟t qualify as a category A / B project as per EIA notification of 14th Sept. 2006 and
its subsequent amendments. Hence no Prior Environmental Clearance required from MOEFCC/SEAC.
However, due to widening and realignment, land acquisition (LA) involved at some of the locations where insufficient ROW. The Land
shall be acquired as per Andhra Pradesh State High way Act 1964 laid down by the Andhra Pradesh State Govt. under LAP and R&R
policy and Compensation will be given as per LARR 2013 Act.
Similarly, the avenue plantations along the project road have been identified at different locations and since the existing road is going to
be widened the trees coming under the widening works need to be felled. Thus tree cutting permission is required from Forest
Department. The Project Proponent need to apply for tree cutting permission.
The project road doesn‟t lie within 1.0 km radius from the protected area (like Sanctuary, National Park, Biosphere Reserve etc). Thus
NOC from Wild life board is not required for this road.
No presence and impact on Archaeological features. Thus no archaeological clearances / permissions to be obtained.
Based on the above conclusions and the EIA study, it is found that the projects is an improvement and widening project and involve
acquisition of Agricultural land and felling of trees along the road which shall have some environmental impacts as per EIA study. Thus
the project falls under Category „B‟ as per WB Operational Policy 4.01 of World bank and Environmental analysis is required beyond
environmental screening for the project.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 50 of 68
Chapter-07 ENVIRONMENT MONITORING PLAN
To mitigate the potential negative impacts of the proposed project, an Environmental Monitoring Plan and Performance Monitoring are
developed typically to identify the mitigation measures to be undertaken during construction, and operation stages. The formulation of an
appropriate environmental monitoring plan and its diligent implementation are keys to overall success for the project.
Environmental monitoring of Air, Noise, Water and Soil shall be conducted during Pre-construction, construction and operational phase in
conformity to the Environmental Protection Act, 1986. The ARARL will appoint the Environmental Testing Laboratory approved from
Ministry of Environment, Forest and Climate Change (MOEFCC&CC).
7.1 Environmental Monitoring Plan
The Environmental Monitoring Plan is given in table 7.1 below.
Environmental
Component
Monitoring Institutional Responsibility
Parameters Special Guidance Standards Location Frequency Duration Implementation Supervision
Pre-construction and Construction Stage
Air
As per CPCB Standard
procedures in direction of
Environment specialist of IE
Sampler to be
located in the
down wind direction.
Use method
specified by CPCB
for analysis
Air (Prevention
and Control of
Pollution)
Rules, CPCB,
1994
location near
construction
stretch and labour camp
covering location of
baseline monitoring as
per EIA
Three seasons
(Except rainy
season)
annually for
construction
period
As per
MOEFCC
notification on
Ambient Air
Standard dated
16th November
2009 or its
subsequent
amendments
Concessionaire/
Contractor
through
approved agency
NHAI
/ IE Water Quality
pH, Turbidity, TSS, TDS,
COD, BOD, DO,
Chlorides, Hardness, Oil &
Grease, TSS, TDS, Total
Coliform, Iron, Fluorides,
Nitrates, E. coli, Total
coliform, faecal coliform etc.
as per IS 10500:2012
Grab sample
collected from
source and analysis
as per Standard
Methods for
Examination of
Water and
Wastewater
Water quality
standards by
CPCB
4 locations around the
Construction stretch
and camp covering
location of baseline
monitoring as per EIA
Once during
pre-monsoon
season
Grab Sampling
Noise levels
Noise levels on dB (A)
scale
Equivalent Noise
levels using an
integrated noise level
meter
Noise
standards by
CPCB
6 locations near
Construction stretch,
Noise barrier locations,
and camp covering
location of baseline
monitoring as per EIA
Once during
season for three
seasons
annually for
construction
period
24 hourly
monitoring
Soil Quality
pH, Conductivity, Texture,
Bulk Density, Porosity,
Organic Matter, Sulphate,
Composite sampling
at different depth
need to be done
ICAR criteria
of soil fertility
4 location in and around
the camp area covering
location of baseline
Pre-monsoon
and Post-
monsoon
Composite
sampling
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 51 of 68
Environmental
Component
Monitoring Institutional Responsibility
Parameters Special Guidance Standards Location Frequency Duration Implementation Supervision
Moisture, Sodium Sulphate,
NPK, etc.
monitoring as per EIA season
Construction
Sites and
Construction
Camps
Monitoring of: Storage Area
Drainage arrangements
Sanitation in Construction
Camps
The parameters
mentioned are
further elaborated in
the reporting
formats. These are
to be checked for
adequacy.
To the
satisfaction of
the employer
and the
standards
Storage and camps area
Quarterly in the
construction
stage
Concessionaire/
Contractor
Operation Stage
Air
As per CPCB Standard
procedures in direction of
Environment specialist of IE
Sampler to be
located in the
downwind direction.
Use method specified
by CPCB for analysis
Air
(Prevention
and Control of
Pollution)
Rules, CPCB,
1994
At 2 location
along the road
stretch as per
recommendation of IE
and WB
Three seasons
(Except rainy
season)
annually for
construction
period
As per MOEFCC
notification on
Ambient Air Standard
dated 16th November
2009 or its subsequent
amendments
Concessiona
ire/
Contractor
through
approved
agency
NHAI / IE Water Quality
pH, Turbidity, TSS, TDS,
COD, BOD, DO,
Chlorides, Hardness, Oil &
Grease, TSS, TDS, Total
Coliform, Iron, Fluorides,
Nitrates, E. coli, Total
coliform, faecal coliform etc.
as per IS 10500:1991
Grab sample
collected from
source and analyse as
per Standard
Methods for
Examination of
Water and Waste
water
Water quality
standards by
CPCB
2 locations along the
road stretch as per
Recommendation of IE
and WB
Once during
pre-monsoon
season
Grab Sampling
Noise Levels Noise levels on dB (A)
scale
Equivalent Noise
levels using an
integrated noise level
meter
Noise
standards by
CPCB
2 location along
the road stretch
as per
recommendation of IE
and WB
Once / Annum 24 hourly monitoring
Soil Quality
pH, Conductivity, Texture,
Bulk Density, Porosity,
Organic Matter, Sulphate,
Moisture, Sodium
Sulphate, NPK, etc.
Composite sampling
at different depth
need to be done
ICAR criteria
of
soil fertility
2 location in and
around the camp
area covering
location of
baseline monitoring as
per EIA
Once / Annum Composite sampling
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 52 of 68
Chapter 08 HEALTH AND SAFETY
ARARL will take care of Construction workers and management staff by providing training and personnel protective equipment as per work
criteria.
8.1. Environment, Health and Safety guiding principles
Safety Requirements aim at reduction in injuries, loss of life and damage to property resulting from accidents on the Project Highway,
irrespective of the person(s) at fault.
Users of the Project Highway include motorized and non-motorized vehicles as well as pedestrians and animals involved in, or associated
with accidents. Vulnerable Road Users (VRU) include pedestrians as well as riders of motorized two-wheelers, bicycles and other vehicles
which do not provide adequate occupant protection.
Safety Requirements apply to all phases of construction, operation and maintenance with emphasis on identification of factors associated
with injuries, consideration of the same, and implementation of appropriate preventive measures.
Safety Requirements include measures associated with traffic management and regulation such as road signs, pavement marking, traffic
control devices, roadside furniture, highway design elements, enforcement and emergency response.
Environmental Requirements to be applied to the Development, Construction and Operation of the Project Highway are for reducing to
acceptable levels, the potential to harm the bio-physical environment in the areas near where project activities, including those inside and
outside the RoW are carried out by the Concessionaire.
Environmental Requirements include the preventive, mitigation and enhancement measures that are to be implemented by the
Concessionaire to comply with the conditions of EIA & Road Specific EMPs.
8.2 The Summary of safety concerns during Road and Bridge construction is as follows:
Sr. No. Aspects Safety Measures
S 1.1 Personnel Safety
Measures for Labour
Concessionaire shall provide:
--Protective footwear, protective goggles and nose masks to the workers employed in asphalt works, concrete works, crusher etc.
--Welder‟s protective eye-shields to workers who are engaged in welding works.
--The Concessionaire shall comply with all regulations regarding safe scaffolding, ladders, working platforms, gangway, stairwells,
excavations, trenches and safe means of entry and egress.
The Concessionaire shall comply with all the precautions as required for ensuring the safety of the workmen as per the International Labour
Organization (ILO) Convention No. 62 as far as those are applicable to this Agreement.
The Concessionaire shall make sure that during the construction work all relevant provisions of Building and other Construction Workers
(regulation of Employment and Conditions of Services) Act, 1996 are adhered to.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 53 of 68
Sr. No. Aspects Safety Measures
The Concessionaire shall not employ any person below the age of 14 years for any work and no woman shall be employed on the work of
painting with products containing lead in any form.
The Concessionaire shall also ensure that paint containing lead or lead products is used except in the form of paste or readymade paint.
All buildings, rooms and equipment and the grounds surrounding them shall be maintained in a clean and operable condition and be
protected from rubbish accumulation.
Each structure made available for occupancy shall be of sound construction, shall assure adequate protection against weather, and shall
include essential facilities to permit maintenance in a clean and operable condition. Adequate heating, lighting, ventilation or insulation
when necessary to reduce excessive heat shall provide for comfort and safety of occupants.
Each structure made available for occupancy shall comply with the requirements of the Uniform Building Code. This shall not apply to tent
campus.
S 1.2 Traffic and Safety
Before taking up of construction on any section of the existing lanes of the highway, a Work Zone Safety Checklist shall be devised by the
Concessionaire and approved by the IE.
During construction, the Concessionaire shall ensure that all aspects of the Traffic Management Plan prepared by the Authority are well
implemented and maintained throughout the construction period.
S 1.3 Risk from electrical
Equipments
The Concessionaire shall take all required precautions to prevent danger from electrical equipment and ensure that
- No material shall be so stacked or placed as to cause danger or inconvenience to any person or the public.
- All necessary fencing and lights shall be provided to protect the public in construction zones.
All machines to be used in the construction shall conform to the relevant Indian Standards (IS) codes, shall be free from patent defect, shall
be kept in good working order, shall be regularly inspected and properly maintained as per IS provision and to the satisfaction of the
Environmental Expert of IE.
S 1.4 Risk force measure
Concessionaire shall take all reasonable precautions to prevent danger to the workers and public from fire, flood etc. resulting due to
construction activities.
Concessionaire shall make required arrangements so that in case of any mishap all necessary steps can be taken for prompt first aid
treatment. Construction Safety Plan prepared by the Concessionaire shall identify necessary actions in the event of an emergency.
S 1.5 First Aid
The Concessionaire shall arrange for –
A readily available first aid unit including an adequate supply of sterilized dressing materials and appliances as per the Factories Rules in
every work zone.
Availability of suitable transport at all times to take injured or sick person(s) to the nearest hospital.
Equipment and trained nursing staff at construction camp.
S 1.6 Informatory Signs
and Hoardings
The Concessionaire shall provide, erect and maintain informatory/safety signs, hoardings written in English and local language (Kannada),
wherever required or as suggested by the Environmental Specialist of IE.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 54 of 68
8.3 PPE Matrix
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 55 of 68
8.4 Emergency Preparedness Plan
The Emergency Response plan is necessary as a moral and legal obligation of management to protect
the safety people, property and environment. The objective of this “Emergency Response Plan“ is to provide the organizational guidelines and directions to ensure fast and effective response in any
emergency situation in order to save life, property and environment.
We have formed our Emergency Response Team in Base Camp to combat with the Emergency
situations.
EMERGENCY PROCEDURES REMOVE
Anyone in immediate danger
ONLY IF SAFE TO DO SO!
ALERT
Others in immediate area
Fire Wardens
Activate Whistle, Air Horn, Bell, Siren etc. 3 times for 30
sec.
Other Tenants and Adjacent Neighbors
RING THE EMERGENCY SERVICES
1. Fire Brigade, Police or Ambulance.
Advise Site:
Advise address:
Advise nearest cross street:
Provide your Name & phone number...................
Provide details of incident...................................
DO NOT HANG UP UNTIL THE ADDRESS HAS BEEN
REPEATED
CONTAIN THE FIRE
Use correct Fire Extinguisher or Fire Hose Reel
Turn OFF Electricity, Air Conditioning
Close doors and windows to contain fire
ALL IF ONLY IF SAFE TO DO SO!
EVACUATE Proceed to the nearest exit.
Gather together at Exit, if safe to do so, then
Evacuate via exit and proceed to the Assembly Area
Incident Controller
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 56 of 68
Fire Fighting Team Leader
Rescue Team Leader
First Aid Team Leader
Fire Chief
Rescue Chief
First Aid Chief
Vehicle Co-Ordinator
Electrical Co-Ordinator
Emergency Contact Number
List of Emergency contact number will be prepare and display at suitable locations so that in case
of emergency all employees can use the numbers. The Emergency number includes
Sr. No. Description Contact Number
1. Fire Brigade / Stations 101
2. Ambulance 102 /108
3. Police
100,
Anandapuram PS – 08933 – 222133
Bhogapuram PS – 08922 – 240433
Pusapatirega PS – 08922 - 258833
4. Crane / Hydra
5. Hospitals Anil nerukonda hospital, Anandapuram –
08500359232
6. Security
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 57 of 68
CHAPTER 09
ENVIRONMENTAL REPORTING AND FREQUENCY
ARARL will maintain the reporting system for environmental management indicators and report to the
Independent Engineer as per the monitoring plan.
The formats for reporting and monitoring of environmental aspects during the entire project cycle on a
regular basis are given in table 8.1.
Table 9.1: Reporting Format
Format No. Environmental Attributes Project Stage Frequency
ARARL / FR/ EMP / 01. EMP mitigation measures plan Construction Quarterly
ARARL / FR / EMP / 02. Construction site and Service Area
Details Construction Quarterly
ARARL / FR / EMP / 03
Environmental Pollution Monitoring
Report as NAAQ Norms
3.1 Ambient Air monitoring,
3.2 Noise level monitoring
3.3 Prevention and control of Water
pollution
3.4 Drinking water test
Construction Quarterly
ARARL / FR / EMP / 04 CFO compliance Construction Quarterly &
Annually
ARARL / FR / EMP / 05 Community grievance/ Problems during
construction Construction Monthly
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 58 of 68
FORMAT NO. 1. ARARL/ FR / EMP -01
Environmental Supervision and Monitoring Schedule- Construction Phase
Action Plan for mitigation measures of environment management plan
Implementation Agency / Authority : Concessionaire / Contractor
S.No
Project related Issues
Action to be taken Frequency Supervision Agency
Action plan Current Status
Implementation status
1.
Avenue tree
cutting and
plantation
Prepare an action plan
for an estimated 6300
nos. of trees to be
affected/felled in the
project stretch and
proposed to be planted
along the project
stretch. Single row of
plantation on both
sides is suggested
throughout the length
of 47 Kms
NHAI in
consultation
with
the Forest
dept.
Intimate forest
department before
cutting trees and
Prepare action plan for
avenue plantation.
Avenue Plantation: The
avenue plants
proposed along the
project stretches are
as per IRC-SP-
21:2011.
2.
Borrow pits
and Quarry
sites (stone).
There are 9 nos of
borrow areas which
was identified and
tested, in these
suitable 7 no’s borrow
areas for required CBR.
2 nos Sand quarries
are identified in the
project and the same
shall get NoC from the
Government / owners
well before start of the
work.
Monthly Mining
Department
/ NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 59 of 68
Borrow areas shall
be carried out up to
depth of 2.0m in non-
cultivable & elevated
lands, 0.45 m in
productive lands etc.
with a slope of not
steeper than 1 vertical
to 4 horizontal.
Borrow areas should
be 15 m away from the
water bodies which are
identified along the
project corridor.
The borrow areas
shall be located at
least 800 m away from
the villages/towns.
Resurfacing and
landscaping of the
borrow pits utilized in
the project.
S.No
Project related Issues
Action to be taken Frequency Supervision Agency
Action plan Current Status
3. Site for storage
and
Construction
camp
The project
Contractor shall select
a Campsite which is
duly confirming the
labour laws. Storage of
HSD, Bitumen will be
expected as per the
stipulated guidelines.
Besides these,
emergency response
plan will be in place
towards meeting
unforeseen
emergencies. Trained
personnel will be
handling such
materials and care will
be taken so that spills
are abated and in case
of spills, immediately
they are contained.
Monthly NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 60 of 68
4. Sewerage and
solid
Waste disposal.
For sewerage
disposal, septic tanks
with soak pits will be
provided at campsites.
Proper sanitation
facilities at the
construction workers
camp shall be provided
as per the IS:2470-
1985
Monthly Labour
department
/ Health
department
/NHAI
Salvage material /
demolition wastes will
be reused to the
possible extent in
embankments,
shoulders, slopes,
approach roads and
temporary campsites.
It is envisaged that
approximate 300-500
Kg of domestic solid
waste (300-500
gm/person) per day
will be generated from
the workers camps
which will be disposed
of to the nearest solid
waste disposal sites as
discussed above.
The solid waste
generated due to
construction and allied
activities would mainly
consist of earth
materials. These
materials will be
reused for
rehabilitation of borrow
area / quarry sites,
campsites and in
temporary diversions
and slopes.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 61 of 68
The municipal solid
wastes generated in
construction & workers
camp will be disposed
off at nearest identified
location of disposal /
landfill sites of local
authority with
payments in
environmentally
acceptable manner.
Domestic refuse shall
be collected separately
for bio-degradable
waste as well as the
inert waste and the
same shall be sent for
the disposal as per the
MSW Rules, 2000.
S.No
Project related Issues
Action to be taken Frequency Supervision Agency
5. Traffic
management The project stretch
passes through major
towns and villages like
Peddipalem,
Anandapuram,
Tagarapuvalasa,
Bhogapuram,
Agraharam,
Pusapatirega and
Pydibheemavaram.
Secure assistance
from local police for
traffic control during
the construction.
Quarterly NHAI
Safety measures shall
also be undertaken by
installing road signs
and markings for safe
and smooth movement
of traffic.
6.
Noise level Stationary equipment
shall be placed as far
as possible from
residential areas to
minimize noise impacts
on the near
inhabitants.
Quarterly Andhra
Pradesh
State
Pollution
Control
Board /
NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 62 of 68
Construction activities
will be strictly
prohibited between
10.00 p.m. to 6.00
a.m. near habitation.
Provision of ear plugs
to workers exposed to
high noise levels in the
project who work in
batch mix plants, hot
mix plants, quarries
etc.
7. Air Quality The mean Respirable
Particulate Matter
(PM10) values observed
within the range of
CPCB standard of 100
micro gram/m3for
residential / industrial
category. However, all
the values found to be
well within the
stipulated standards.
During construction, a
good number of trucks
will carry the
construction material
for which emission of
air pollutants will
increase. We should
see that all the
vehicles deployed for
construction of the
project will have to
keep “Pollution Under Control” certificates. DG sets will also emit
air pollutants in the
area during
construction period.
The emission
generated during
Construction will be
temporary and
localized in nature.
Vehicles carrying
construction material
shall be covered to
avoid spilling.
Quarterly Andhra
Pradesh
State
Pollution
Control
Board /
NHAI
Andhra
Pradesh
State
Pollution
Control
Board /
NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 63 of 68
S.No
Project related Issues
Action to be taken Frequency Supervision Agency
Hot mixing plant shall
be over 500m away
from
Residential
neighborhood and
300m away from the
road.
Mixing equipment shall
be seated and
equipped with dust
removal device.
Water will be sprinkled
in morning and
evening hours at the
construction yards and
the unpaved sections
of the road.
8. Water Quality &
Solid waste Prior permission of
the concerned engineer
and regulatory
authorities shall be
taken regarding the
discharge or disposing
of any material arising
from the execution of
the works.
Quarterly Andhra
Pradesh
State
Pollution
Control
Board /
NHAI
During construction it
will be ensured that
contractor does not
dispose off debris in
water bodies.
Soil laden run off will
not be diverted to
water bodies. Provision
of waste disposal site
for waste from
construction and
storage yards shall be
made.
. Vehicle maintenance
and refueling will be
confined to areas
under construction
yard to trap discarded
lubricant and fuel
spills.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 64 of 68
9. Water logging
and stagnation
of water in
the Borrow
pits
The majority of the
project stretch is plane
& horizontal land which
will be act as water
logging areas during
the rainy seasons and
may cause the
breeding of the vectors
in the area.
Monthly NHAI
Uncontrolled digging
of approved Borrow
pits in the areas will be
avoided to prevent
water accumulation
which results in
breeding of disease
causing vectors in the
area.
10. Occupational
Health and
Safety
Labourers shall be
equipped with proper
safety gears like
helmets, gloves and
gum boots.
Periodic health
checkup of
construction workers.
NHAI
S.No
Project related Issues
Action to be taken Frequency Supervision Agency
11. Basic amenities
And sanitation
facilities for
labourers
Adequate sanitary
facilities shall be
provided to the
workers to avoid health
related problems.
Monthly Labour
department
/Health
Department
/NHAI
Periodic health checkup
of labours shall be
done.
Contractor to prepare,
NHAI’s approved detailed public health
utilities plan for the
workers camp and
other working sites,
which make adequate
provision for safe
disposal of all wastes
and prevention of
spillages, leakage of
polluting materials etc.
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 65 of 68
12. Fuel for
labourers
Adequate supply of fuel
(LPG/Kerosene) shall
be provided to the
labourers to avoid
felling of trees for
cooking and other
domestic chores.
Monthly Labour
department
/Health
Department
/NHAI
13. Prevention
of erosion and
scouring
Stabilizing the
embankment with
appropriate technique
immediately after
placing.
NHAI
Treating high
embankment slopes
with rip rap, stone
pitching or other
technologies to prevent
erosion.
Construction of toe
drain all along the road
on both sides.
Avoiding obstruction
of existing drainage
during filling.
14. Drainage
system
Adequate care has
been taken for the
purpose of free flow of
flood discharge in the
design stage itself.
There are 2 major and
17 minor bridges
proposed along the
project corridor to
allow free flow of the
natural drainage water
in the area.
Monthly Irrigation
Dept /NHAI
S.No
Project related Issues
Action to be taken Frequency Supervision Agency
Construction of toe
drain along the road on
both the sides.
Avoiding obstruction
of existing drainage
during filling.
15. Conservation of
Eco resources To preserve earth
borrowing areas,
piling, and building
temporary camps are
prohibited in forests
lands.
Monthly Forests
Dept /NHAI
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 66 of 68
Arable lands should
not be used as earth
borrowing whenever
possible. If needed, the
topsoil (30cm) should
be kept and refilled
after construction is
over to minimize the
impact on ecosystem
and agriculture.
Construction workers
should be told to
protect natural
resources and wild
animals.
16. Communications
and
Transportation
Local materials
should be used as
much as possible so as
to avoid long distance
transportation that of
earth, sand and stone.
If there are traffic
jammed during
construction, measures
should be taken to
move the jam with the
coordination of
transportation and
public security
department.
Temporary access
should be built at the
interchange of the
highway and other
roads.
A transportation plan
of materials will be
formulated to avoid
delivered of them at
peak hours on existing
roads.
Quarterly Transport
Department
/NHAI
S.No
Project related Issues
Action to be taken Frequency Supervision Agency
17. Rain Water
Harvesting
I). There are about 27
nos. of RWH Pits are
proposed
Monthly GW
Department
/NHAI
18. Utilization
of Fly Ash
In the proposed
project, There are four
existing Thermal Power
Stations and two
Monthly NHAI
/Andhra
Pradesh
State
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 67 of 68
power stations are
proposed which fall
within 500 Km from
the project corridor.
Pollution
Control
Board
19. Surplus earth/
Muck disposal
Top Soil: Top soil of
15cm will be carefully
stripped and utilized as
top layer in median
filling and / or
embankment slopes
prior to turfing /
sodding for restoration
of temporary sites, etc.
Monthly NHAI
Excavated Materials:
Suitable excavated
materials will be
reused in road
embankments
formation.
Overburden: Overburden
generated from borrow
pits, quarries will be
used for its
rehabilitation for
covering the waste
material
ARARL Environment Management Plan
Rev-02, Dated 10th April-2019
Page 68 of 68
FORMAT NO - ARARL/ FR / EMP -02
Environmental Supervision and Monitoring Schedule- Construction Phase
Construction site and Service Area Details
Independent Engineer:
Concessionaire: Contract Package:
Road section:
Location:
Chainage: Km________ to Km________
Environmental Features of the Location
Terrain: Flat/Undulating/Rolling
Wind Direction:
Land use in adjoining area:
Name and Distance of settlements in a 2 km radius of the site
Mitigation
Measures
Employed
Chainage Construction Site
Site 1
(Chainage)
Site 2
(Chainage)
Site 3
(Chainage)
Site 4
(Chainage)
Dust Control
Measures employed
Traffic Management
Storage Site
Maintenance Shed
and service area
Furnish details of public consultation held with the local populace.
Supervised and Checked by
(Name and Signature with Date)
Concessionaire’s Site Engineer: Environmental Engineer, IE:
Divisional Forest Offi cer
ffi=c-litv-'*l iF.-.-" e '1 ,r:-:' 'r i Srikakulam.l"Lliv;*' I +* ,*+.'
10ruL20$Fr,-fr :ffi ,L*:';?",mix"ffi ';i"lm[:'Kilj{ir.:il,::fi .i:':
^, -",. St."torif ir'lq'"t'"oi- i"ilitg-"f trces * Permission - Accorded - Regarding'
Ittl,li t,:_ ' ,'. .. --:.:-:-... ^ . --, \!,r^r r -Har p. No NHAwtu /VSKp/61r
;explained by the applicant in tfre referenccs,lll-eil.3I;111i;
111*::.::: - : :- i;;:-*ij' project Direcror, NHAr Lleltel Rc. No. N'IA'PIU /VSKP/6laning/
Ananoapuram- Anal:apall i 20 I 6- t 7 d t 24'0 4'20 17
zl',":J"i.ili*".''-ffielutt".R".No.N}IAI/PIU/VSKP/6laning/Ranasthala' to Anandapuram- 2016-17 dt 15 '06'2017
3) F";fi"s"bf?;r iiil'"uru* n'''No' 3U201IISKLM dt0s'07 '2417
**
Rc.No.99l/201714'6,
Ddted 07.07 .2017 .
ORDER:Under tho circumslances
Government of Andhra Pradesh
For€st DePartmentOffice of the
"Divisional
Forest Officer'
r",,", "YJln"J
#li ::lBT:5ff :\"1q1""4#"'lT3*:*: f fS:fi:i,::$ *"-Ti::lHehr*{t*tiir":1,':limxll"lir'*ru"ru'l;T:lu;;'#'f i:?;"Jix"?Li Nuai, a"thoritiesr.Visakhapatnam for felling of
ofS.No Rord Str€tch No of Trees I Oral
From To Rieht Side Left Side
I 3 4
1211 Nos 1763 Nos 29?4 NosI 634
465 Nos2 . 633 634 149 Nos J lo l\os
1J60 Nos --r43y rlosTotal
^ 1l
the trees ln the abgve Propos
(
ffi';T5ffiHt#il'r;;r, ,;;J'i,"",ii Rules 1e70 and orher rules in vogue. rhe
i;i;;;t;;il; is accordetl ,uuji* * ouvt"nts (if anv )io be
Sade to the Forest Depanment'
,H;t, #;il|;. """"rai"g
i.fii"g p".lii'..i"", riile certificate from Thasildhar concerned is tu
;'ffiff;. ;;;;;;; i;" ;""' ili"ig''i" rjiinr i rt/trnistry or Road rransport and-Highxars ) '
Undertaking given by the l,o;ot ol"itoi, NHAI ii consirlered on the ownership of the lands in
which the tre€s are existing. Wftif" ""tlyi'tU"*
felling' the user agencv has-1:.*ll?1^::n:t:lj
TG-Nr'r-qt autnorities allowed to fcll the trees in the abqve prop' ir,o .r.\^r,a
should be felled.before Sf.Of.ZOii. if any irregularities at" nbri"id while working tire above
felling operation, action will be t"t"t.*;'":th" lt::llt:lt":l ?:r*fll""*Tt":::::' fi:
rrynlcn Ing Ir(,es ale €^r)Llr6. rrurrv v$"r"rDv"- -- o' ianiid outjusr adjac€nt to the
rn"n uJ -uoftin".y to safeguard the passerby' as the work is to be , ^ ^--^v chr'
fiff'1T ff##',i;;?;:ffiil'; ffi iii' on"" uguin t''i"."::l-q::*:,ij":;5:** 'n"";ffil;;Ji,';;;;;;;;.i;;,;n,niiog unv ,ni.r,i'ps wh'e executi'g fe'ing operation.
Sd/{h.SanthiswarooPDivisional Forest Offi cer
Srikakulam-
uli.r*:*CoPY 1o the
instructions to
committingagainst the
Produce
FiGII sri ct.santhi swarooP, s.F's ,
Rules 1970.
136 6!1,000 634.0002l o.65
L37 633.000 634,O0022 0_6 7 a
138 633.00q 6:4.000t9 0.65 5
139 633.000 6f4.O0020 0.52 I l0
140 633.000 634-0000,61 2 11
L4\ 633-OOO
633.000
634,O000.6a 9
t42 634,000a,r5 3 12
143 633.000 634.0O022 o,53 1.5
63:,00o 634.00022 o.6a 1,4
1{5 613.000 634.0OO N.T N,T 23 0.62 8
146 633.-000 6ln.o00 r{.7 N.',l 1a 0-7 15 15
633.000 634.000 Peltophorum pt.rocarPud 19 0.45 - a
633.O00 614.000 Peltophorum pt.rocarpllm zo 0,49 9
149 63t,000 6t4,@O P.ltophorum pterocarplm 21 0.5 3 tt Sound(-.
i
(- ildt^,tt1
NF# ]
ntnL
E nunflekh'on Y' \Is
sT ''J Un ftrz +' x{f { ,t t
a\e- su'hm"tted e
2bt'1.t^ho\M--
\bl*o '
ftssl- nuana'
(l,,,uanes|).-i*+
(trt '
\th*h.t tL. obou- u^"""usfrJ t'uzc P t *-E O'W!'' ol ';
oJL kz tLIfr4A'24/-"-t')
wtAglrs]orlT'" !W\
l,l"r; t--4 ,." I 7Dl6lP-Fprest Section Officdr' KANDTVALASA n-P&-,_--
.A'B'o
eH*')
6ar.., L+* *O
From Km 614.000 to krn 643.000 - RHS
;J 'tttl:xU*n a**n" ,*.rl;;;T DlstanceGirth (lY)
t'teioht of II
'j:.T _1
I
Height of I
-;;J
Condition ofwood (Sound /
1170 24 642-000 643.000 Turai 0.49 6 Unsound
1171 642.000 643.000 Turai 0.5 6 5 7 unsouno
26. 642.OOO 543.000 Turai 20 0.55 6 Unsound
!173 642.000 643.000 'Turaa 25 o.75 5 7 unsound
I174 28 642.000 643.ooo 26 0.50 6 8 Lnsouno
7r7 5 29 642.000 643.000 I ural 0.50 7 10 Unsound
1176 30 542.000 643.000 Turai 11 0,75 8 0qo Unsouno
!177 642.000 643.000 Turar 12 0.50 6 8 Unsound
'T7B642.000 643,000 Turai 0,40 7 9 Ltnsound
1179 642.000' 643.000 I ural 11 0,48 5 B Unsound
1180 34 642.000 643.000 tural t2 0.60 7 10 Unsound
1181 642.000 643,000 Tutar t4 0.55 6 8 Unsoutd
1182 36 642:000 643.000 I ural 0.60 l 9 Ungpund
1183 642.000 643.000 Turai 18 o.63 6 I Unsound
1184 38 642,OO0 643.bOO I UTAI 17 0.60 Unsound
1185 39 642.000 543.000 Turair- 0.63 5 Unsound
1185 40 542.000 643.OOO Turai 18 o -67 7 9 Unsound
1187 cr 642.000 643.000 Turai 19 o.57 6 8 Unsound
1188 42 ff2.000 643.000 Tutai 0.40 5 7. Urrsound
1189 43 642.000 643.000' Turai 17 0.58 5 8 Unsound
1190 44 642.000 643.000 Tuaaa 1B 0.60 5 7 Unsound
1191 45 642.000 641.000 Tuiai 19 0.50 4 6'Unsounci
r192 46 642.000 643.000 Turai t7 0.51 5 B UnsoLrnd
1193 4t 642.000 643.O00 18 0.48 7 unsound
1194 4a 642.000 643.000 Tural 19 0.70 I Unsound
1195 49 &2.000 643.000 Turaa o.70 6 9 unsouno
1i96 50 642-000 643.000 I ural 0.s2 6 8 tlnsound
119? 5t 642.000 643.000 1a o.70 6. Unsound
1198 642.000 .643.000 Turai 0.60 6 a Unsound
1199 .53 q2.oo0 643.O00 1B 0.70 7 Unsound
1200 542.000 643.000 I Ural 0.68 6 a Un5ound
1201 642.OOO g 3.000 Turai 18 0.40 6 Unsound
642.000 643.000 Tu rai 7 9 Unsound
1203 57. 642.000 641.000 I Llral 1B 0.56 ? 9 Unsound
1204 58 642,000 643.000 Turai 15 0.40 6 8 Unsound
1205 59 642.O00 643.000 Ecoi'n1. 1B 0,43 7 (% tJnsound
1206 60 642.000 643.000 rffiiYlij 0.50 7 9 Unsound
1207 642.000 643:000 NT 18 0.6 5 6 8 Unsound
1208 642.000 643.000 NT 19 0.70 5 5 Unsound
12.19 63 642.000 643.000 NT 18 5 7 Unsound
1210 64 642.000 643.000 l!T 19 o.80 5 Unsound
1211 65 642.000 643.000 NT 0.8s 3 Unsound
Vtt 4"l *, t*t.r'*^ZA 4* e @..d\t'zz4/'
(
n'l'B&'r4-" 'I''t"'t''."ot''o''rr'u.
vtsu*"ot^tu tt'
I
-ESbo{ao
(
UrnArJ'tto'ti.rrt- O.i.vkrl Eaa
roL{TR^i'Sgil
F om Km 634.000 to Kn 643,000 - !H5
Sl.N oTreeNo,
Existing chainag(! (Km)Name of Tree
(Local)
Distancefrom ECL
(M)
Girth(M)
Height olStem(M)
Height ofTree(M)
Condition of
(sound /Unsoufld)From
-l'o
1723 78 642.000 64r.000 Thati 21.5 O.BB 5.0 Sound
L7 24 79 642.000 643.000 Turar 21.5 0.88 6.0 7,4 Sourid
1725 80 642.O00 643.O00 22.5 0.80 7.O . 8.0. Sound
81 oq).ooo 643.000 Nidaa Ganneru 1.50 8.0 9.0 Sounc,
t727 82 642.U00 643.000 I Ural 0.l0 5.0 5.0 Sound
7724 83 642.000 643.000 'fu13i 0.20 4.O Sound
1l29 84 642,000 643.000 Thati 2 t.5 0.90 5.0 7.O Sound
1730 85 642,000 643.O00 'I! rai 0.1s 8.0 9.O Sound
1731 86 642.O00 643.000 N,dra Ganneru 21.5 1.30 1.5 10.o Sound
).7 32 87 542.000 643,000 TLrrai 22.5 0,40'/.o Sound
1733 88 642,000 643.000 Turai 20.5 0.89 6.0 8.0 Sound
1734 89 642.000 643.000 TLrrei 24.5 0.80 e 7.0 8.q,. Sound
1735 90 642.O00 543.000 2t.5 0.60 5.0 6.0
91 642.000 643.O00 T,J ral 21.5 0.7 2 2.0 5.0 Sound
t737 92 642.000 643.000 Turai 22.5 o.25 'j.3-o 10.0 Sound
1738 93 642.000 641.000 Turai 0.90 6.0 Sound
1739 94 642.040 643.000 Turai 24.5 0.50 7,0 8.0 Sound
1740 95 542.000 643.000 Tu,rai 0.30 2.0 9.0
7741 95 642.000 643.000 Turai 21.5 0.40 6.0 sound
L142 97 642.000 643 OOO T!rai 0.30 1.0 10.0 Sourd
t743 98 642.000 643.000 Turai zi-5 0.45 6.0 sound
\J44 99 642.000 643.000 T!rai 0.80 2.0 11.0 sound
1745 100 642.000 643-000 Thatr 21.5 0.90 5.0 6.0 Soulld
7)46 101 642.000 643.O00 -lami 21.5 1.50 8.0 9.0 Sound
1747 102 642.000 643.000 I ural 2i.s 0.80 5;0 6.0 Sound
1748 103 642.000 643.000 21.5 7.O 8.0 Sound
!749 104 642.000 643.000 I Ural 12.0 Sound
LV50 105 92.000 643.O00 Turai 21.5 0.60 3.O 10.0 . sound
7757 106 642.000 643.000 TurDt 21.5 0.42 4.O 5.0 Sound
L752 to7 542.000 643.000 25.5 0.45 1-5 9,0 Sound
17 53 108 642.000 643,000 Turai 26.5 0.60 6.0 sound
t 7s4 109 642.000 643.O00 Turai 21.s 0.10 7.O Sound
110 642.000 643.000 tural 22.s 0.?.5 9.O Sound
1756 111 642.000 643.000 Tulal 23.5 o.2-t 8-O Sound
t7s7 '| 1) 642.000 F43.000 Tural 24.6 0.35 2.0 2.5 Sound
1758 113 642.000 643.000 Turai 25.5 0.25 7.0 Sound
1759 114 642.000 e3.000 Turai 26.5 0.30 2-O Sound
1760 115 642.000 tr3.000 tural 21.5 o.37 8.0 Sound
!76r 116 642.000 64 3.000 Turai 22.5 0.30 5o\rnd
1762 1\7 642.000 643.000 Tura, 25.s 0,3 s 2.5 9.O Soun(
1763 118: 642.000 643.000 Turai 21.5 o.40 2.O soun+
\o Cohg.zk1r."r".,t't *l-!^'t( aJt "oe
J
\.SF.lXlKUl-a&
4dsrj/, D;rocio,6;fi396{a11ttdfr"/- au?horin' ^r r'!.r;o
aa;
Rc. no 43/2017 ,dt. 18-08_2017
From:Sri P. Anjaneya Raju,rorest Range Officer.Wsakhapatnam.Sir,
GOVEI?NMENT OF ANT]HRA PRADESHFOREST DEPARTMENT
Office of the Forest Range Officef .
l_o: Visakhapatnam
The Diyisional Forest Officer,Visaklf6patnam.
Yours faithfully
i'1* ,i . ,.- I'
Foresl Range t)fficer,
(
{
sub: Ap Forest Department - widening of Nationar High way intc 6 rane iroi,:Anandapuranr l:,1"r1,:?:[ ,"1 pjrt""t wioentng rhe NH from Ranasrnalarr .Anandapuram.-under N*Dp - v"i*ii* of kees existing on both sides of rheRoad from liajapulova to n"fr"k.*'V"im
Rer; 1 Divisionerr Forest orricer, visar<',ap"tnali::::" J:ff:;'"n"0'"ndt. 27 _0:3 -20 1 7, 1 6_06-2A 1 7, 07 -OB_20 1 7
2. Forest Section Officer, pendurthy report dt. 1g-08-2017
,n.,,,"Lj'l'J[.'j;U?" 'L". '?j;"1'' .:,,,:*^,T^ ?yi:-,"llj Foresr orneer, Visakhaparnan,
Iri:r1,a3;ii;ff ;;,i1"{!i,}.t::iuid[,.,?,,:,J"6:"?tiln,ili,:j,j ji:#;i;rnrs connection' r submit tn"llip Nationar
trign \^i"; fr"r.n3rg,nurola toinrx""p"iri'i" rurri,,gI"JJfill'ffj"i[fi3:fli "',," rhereroie, r r:isiiucreo the Forest secrion onicerrr*o
"u.ti'on L"j;;';"";;1,;",;i1ff,i"1:,1;.,::?:,11fl,'J,:,i;':?"1*l ti:r"l rltff:iiH h"t#il"ff'?3'{"va
10 Reb;ka' rl"*io,l,'inu rso, pendurthy enumerated ihearongwith the vatuation ,n ,nu"ljr1?"YilnAnandapurm
and submitted tn" "ni,r"iuiii,i
o"triro
- As per'the report oflhe,Forest section officer, pendurthy, there are 3440 nos. ofrrees comprising of 1301 no,' Non Exempted, raad-na. E1emn1ed, rs8 ;.. irrii o""nnsJ01 nos' Eucaryptus treer; are-existrng ,i" *," .Lo
"]ie. out of 3440 tree, approximateiy2185'653 cum of rimber and 521.zzd
"u*. rr"iio-"oi,"y be cJerived. In addition ro rneaoove trees there 4410 nos. Pairnyra tr"." "r" u"rll!. tnu a"t"it"d enumeral,on ,sr rsenclosed herewith for favour gr n"1rr"r.' in" r"i"rii"i'ti"" officer, pendurthy coJrectec lnc
'ocal market rate for the limber, r:er-wil "il;"";;a Trees. As per the rocar markerrates, the total proo'uce wi, wo*h ns.,szz'tiii.io. ln3 .tut"n,',"nt showing the varuation oftrees is enclosed herewith {or favour of peiu*f ,rj ."""".rrry action.
This is submitteC for favour of informaiion anci necessary action.
II
Encl: As above.
.^ Visakhapatnam.
"1fu,
t 3 9"sq*E9€iE=tso-'c.rEuSFi*
rlF.oi6r
00
rY)
c{
rt!
NCD(\ot
(o
rJ1
c\l
coN
ro
Fa!
N@o
rt)
o't
(ot{rnN!otYl
F
o
=64
sid.(u
aroi1
00
N
a{(oro6l
@N ot
F
a\lNlY)
an(l)
c)
F FF,-i
a{F..i ci
FOr(o./j
qt
.;
l\I(otY!
N(0
AT
q)
|t|
orn (\ (\ 6I
oa{ a!
oa\ a! a{
zo-oEi:
(u
t\
t\(t
oor
rn
F t\(o
rn.\la.{
Nal(0a.,l
rnrn(oroN
or\ d)rl'tYl
rl
otto(o
.1(o
ooF.+
rnr\rn
N14
Fmt\
FNoq
FF
(!&,
oor
o(r)
a\N
oorYi
o oln
(U
ooz
gr 6l qrf-
r\ ol r\ or oN
-@ qr o @ rt
t{
G,
co (o o (oto
c)cztt)'oq,o-
!oGIoEx!,coz c,F
ril
F
al0,
CIEQ'xtlr
o
bo
zvOJ
F
c,oo.
o(J
E(!
(1,
0,,z
oc
E(u(u
z|!(u
ooa
oo
d.9 !
llt!oF!co(,
l\l t'. @
.r. i
--ro\#--'{ uf!cf,l oor,(,c,
. -. I q, O.
o,)
Eo
(!;s
.9pt(!co(!zo
(,!t6.co
ao
ttotl'o,Efc
ET
tu
9c-'_ |!(r:ctL.||!'i; Eqb8<a, ij.9ot>=
.9.6:E=|! .:::.(, t!rEd'6(!C'
€t
EoC'oILg,
ogt!€,
'6o.9u0trEo,cttl
coE(,|!ttr
't,
t(
.(
ANDHRA PRADESH POLLUTION CONTROL BOARD
ZONAL OFFICE :: VISAKHAPATNAM D.No.39-33-20/4/1,Madhavadhara Vuda Colony, Visakhapatnam - 530018.
Ph : 0891 - 2719380
ORANGE CATEGORY
CONSENT & AUTHORIZATION ORDER
Consent Order No : 9361/APPCB/ZO-VSP/VZN/CFO/W&A/2018- Date:05.02.2018 CONSENT is hereby granted for Operation under section 25/26 of the Water (Prevention &
Control of Pollution) Act, 1974 and under section 21 of Air (Prevention & Control of
Pollution) Act 1981 and amendments thereof and Authorization under Rule 6 of the
Hazardous and other Wastes (Management and Transboundary Movement) Rules, 2016 &
Amendments thereof and the rules and orders made there under (hereinafter referred to as 'the Acts’, `the Rules’) to:
M/s. Ashoka Buildcon Limited,
R. Sy. No. 241P, 248P and 249P of
Bantupalli Village, Denkada (M)
and 323P, 325P, 326P of
Bhogapuram (V & M),
Vizianagaram District.
(Hereinafter referred to as 'the Applicant') authorizing to operate the industrial plant to
discharge the effluents from the outlets and the quantity of emissions per hour from the
chimneys as detailed below:
i) Outlets for discharge of effluents:
Outlet
No.
Outlet
Description
Max Daily
Discharge
Point of Disposal
1 Domestic 0.5 KLD Septic Tank followed by soak pit
ii) Emissions from chimneys:
Chimney
No.
Description of Chimney Quantity of Emissions
at peak flow (m3/hr)
1 Attached to DG sets of capacity 125 KVA, 250KVA,
750KVA and 600 KVA.
----
iii) HAZARDOUS WASTE AUTHORISATION (FORM – II) [See Rule 6 (2)]:
M/s. Ashoka Buildcon Limited, R. Sy. No. 241P, 248P and 249P of Bantupalli Village,
Denkada (M) and 323P, 325P, 326P of Bhogapuram (V & M), Vizianagaram District is
hereby granted an authorization to operate a facility for collection, reception, storage,
treatment, transport and disposal of Hazardous Wastes namely:
HAZARDOUS WASTES WITH RECYCLING OPTION:
Sl.
No
Name of
Hazardous Waste
Stream Quantity Method of disposal
1. Waste Lubricating
Oil
5.1 of
Schedule – I
20
Lt./Month
Shall be sent to authorized
Re-Processors / Re-Cyclers
of waste oil
This consent order is valid for the following products along with quantities indicated only:
S.No. Products Quantity
1. Hot mix plant (Dense Bituminous macadam,
Bituminous Concrete)
1600 TPD
2. Stone Aggregate (40mm, 20mm & 10mm) 1400 TPD
3. Wet mix macadam 1280 TPD
4. Concrete batching plant 600 cu.m/day
This order is subject to the provisions of `the Acts’ and the Rules’ and orders made
thereunder and further subject to the terms and conditions incorporated in the schedule A,
B & C enclosed to this order.
This combined order of consent & Hazardous Waste Authorization shall be valid for a
period ending with the 31.12.2020.
JOINT CHIEF ENVIRONMENTAL ENGINEER
To
M/s. Ashoka Buildcon Limited,
R. Sy. No. 241P, 248P and 249P of
Bantupalli Village, Denkada (M)
and 323P, 325P, 326P of
Bhogapuram (V & M),
Vizianagaram District.
Copy to Environmental Engineer, Regional Office, Vizianagaram for information and
necessary action.
N V Bhaskara RaoDigitally signed by N V Bhaskara
Rao
Date: 2018.02.05 19:28:32 +05'30'
SCHEDULE-A
1. Any up-set condition in any industrial plant / activity of the stone crusher, which result
in, increased effluent / emission discharge and/ or violation of standards stipulated in
this order shall be informed to this Board, under intimation to the Collector and
District Magistrate and take immediate action to bring down the discharge / emission
below the limits.
2. The stone crusher should carryout analysis of waste water discharges or emissions
through chimneys for the parameters mentioned in this order on quarterly basis and
submit to the Board.
3. All the rules & regulations notified by Ministry of Law and Justice, Government of India
regarding Public Liability Insurance Act, 1991 should be followed as applicable.
4. The stone crusher should put up two sign boards (6x4 ft. each) at publicly visible
places at the main gate indicating the products, effluent discharge standards, air
emission standards, hazardous waste quantities and validity of CFO and exhibit the
CFO order at a prominent place in the factory premises.
5. Not withstanding anything contained in this consent order, the Board hereby reserves
the right and powers to review / revoke any and/or all the conditions imposed herein
above and to make such variations as deemed fit for the purpose of the Acts by the
Board.
6. The stone crusher shall file the water cess returns in Form-I as required under section
(5) of Water (Prevention and Control of Pollution) Cess Act, 1977 on or before the 5th
of every calendar month, showing the quantity of water consumed in the previous
month along with water meter readings. The stone crusher shall remit water cess as
per the assessment orders as and when issued by Board.
7. The applicant shall submit Environment statement in Form V before 30th September
every year as per Rule No.14 of E(P) Rules, 1986 & amendments thereof.
8. The applicant should make applications through Online for renewal of Consent (under
Water and Air Acts) and Authorization under HWM Rules at least 120 days before the
date of expiry of this order, along with prescribed fee under Water and Air Acts and
detailed compliance of CFO conditions for obtaining Consent & HW Authorization of
the Board. The stone crusher should immediately submit the revised application for
consent to this Board in the event of any change in the raw material used, processes
employed, quantity of trade effluents & quantity of emissions. Any change in the
management shall be informed to the Board. The person authorized should not let out
the premises / lend / sell / transfer their industrial premises without obtaining prior
permission of the State Pollution Control Board.
9. Any person aggrieved by an order made by the State Board under Section 25, Section
26, Section 27 of Water Act, 1974 or Section 21 of Air Act, 1981 may within thirty days
from the date on which the order is communicated to him, prefer an appeal as per
Andhra Pradesh Water Rules, 1976 and Air Rules 1982, to Appellate authority
constituted under Section 28 of the Water(Prevention and Control of Pollution) Act,
1974 and Section 31 of the Air(Prevention and Control of Pollution) Act, 1981.
SCHEDULE-B
WATER POLLUTION:
1. The source of water being ground water / bore well. The following is the permitted
water consumption:
S No. Purpose Quantity
1 Process 30.0 KLD
2 Domestic 1.0 KLD
Total 31.0 KLD
Separate meters with necessary pipe-line shall be maintained for assessing the
quantity of water used for each of the purposes mentioned above for Cess
assessment purpose.
AIR POLLUTION:
2. The emissions shall not contain constituents in excess of the prescribed limits
mentioned below:
Chimney No. Parameter Emission Standards
1 SPM 115 mg/Nm3
3. The stone crusher shall comply with ambient air quality standards of PM10 (Particulate
Matter size less than 10m) - 100 g/ m3; PM2.5 (Particulate Matter size less than 2.5
m) - 60 g/ m3; SO2 - 80 g/ m3; NOx - 80 g/m3, outside the factory premises at
the periphery of the stone crusher.
Standards for other parameters as mentioned in the National Ambient Air Quality
Standards CPCB Notification No.B-29016/20/90/PCI-I, dated 18.11.2009.
Noise Levels: Day time (6 AM to 10 PM) - 75 dB (A)
Night time (10 PM to 6 AM) - 70 dB (A)
4. The stone crusher shall comply with emission limits for DG sets of capacity upto 800
KW as per the Notification G.S.R.520 (E), dated 01.07.2003 and G.S.R.448(E), dated
12.07.2004 under the Environment (Protection) Act Rules. In case of DG sets of capacity
more than 800 KW shall comply with emission limits as per the Notification G.S.R.489
(E), dated 09.07.2002 at serial no.96, under the Environment (Protection) Act, 1986.
GENERAL:
5. The industry shall maintain set back distance of 500 meters from the National Highway
to the crusher as committed.
6. The industry shall dismantle the temporary crusher once the road work is completed
i.e., 910 days from the work appointed date.
7. The industry shall maintain GI sheets of 20 ft height as wind breaking wall with sheets
towards the direction of poultry farm.
8. The stone crusher shall handle the dust in complete wet condition and the same shall be
directly transported and consumed in their hot mix plant & wet mix plant and excess
quantity of dust will be transported to stock yard within their premises. The dust stock
yard shall completely covered with tarpaulin to avoid dust nuisance to the
surroundings.
9. The stone crusher shall maintain the following air pollution control measures by
31.03.2017 to control dust emissions to the surroundings :
a. Wetting of raw material before crushing.
b. Covering of vibrating screens with MS sheet cladding.
c. Wetting of material at crushing and at conveyor belts by water sprinklers / high
speed rain guns.
d. Installation of Blower for dust collection.
e. Covering of conveyor belt carrying dust to the dust tank.
f. Wind breaking wall all along the boundary of the stone crushing unit.
g. Construction of the metallic roads within the premises.
h. Regular cleaning and wetting of the ground within the premises.
10. The stone crusher shall provide water meter with recording facility to record the water
used for sprinkler system.
11. The industry shall provide separate energy meter to the air pollution control system
and shall maintain log register for the operation of the air pollution control equipment.
12. The stone crusher shall regularly operate the air pollution control systems/measures to
ensure that the suspended particulate matter measured between 3 to 10 meters from
any process equipment of a stone crushing unit shall not exceed 600 µg/m3.
13. The stone crusher shall maintain 5 mtrs width of green belt along the boundary of the
site in the 50 mtrs width buffer zone of the stone crushing unit. This green belt shall be
developed on outer side of the buffer zone so as to act as a barrier.
14. The industry shall ensure that there shall not be any spillages of hot mix on the ground
within or outside the premises.
15. The stone crusher shall dispose solid waste (NON HAZARDOUS ) as follows
SNo. Name of the Solid
Waste
Quantity Disposal
1. Dust 600 TPD Shall be utilized in the hot and wet plants
within the premises.
16. The stone crusher shall not cause dust/air pollution to the surrounding environment.
17. The industry shall maintain good house-keeping through regular sweeping through
sweeping machines to remove the dust / ready mix concrete on the ground to control
the fugitive emissions.
18. The stone crusher shall not increase the capacity beyond the permitted capacity
mentioned in this order, without obtaining CFE/CFO of the Board.
19. The stone crusher shall submit a compliance report on CFO conditions for every 6
months as on 01st January and 01st July of the year at Regional Office and Zonal Office.
SCHEDULE – C
[See rule 6(2)]
[CONDITIONS OF AUTHORISATION FOR OCCUPIER OR OPERATOR HANDLING
HAZARDOUS WASTES]
1. All the rules and regulations notified by Ministry of Environment and Forests,
Government of India under the E(P) Act, 1986 in respect of management, handling,
transportation and storage of the Hazardous wastes should be followed.
2. The person authorised shall not store hazardous waste for more than 180 days as per
the Hazardous and Other Wastes (Management and Transboundary Movement) Rules,
2016 and amendments thereof.
3. The person authorised shall store Used / Waste Oil and Used Lead Acid Batteries in a
secured way in their premises till its disposal to the manufacturers / dealers on
buyback basis.
4. The person authorised shall maintain 6 copy manifest system for transportation of
waste generated and a copy shall be submitted to concerned Regional Office of APPCB.
The driver who transports Hazardous Waste should be well acquainted about the
procedure to be followed in case of an emergency during transit. The transporter
should carry a Transport Emergency (TREM) Card.
5. The person authorised shall maintain proper records for Hazardous Wastes stated in
Authorisation in FORM-3 i.e., quantity of Incinerable waste, land disposal waste,
recyclable waste etc., and file annual returns in Form- 4 as per Rule 20(2) of the
Hazardous and Other Wastes (Management and Transboundary Movement) Rules,
2016.
6. The authorised person shall comply with the provisions of the Environment
(Protection) Act,1986, and the rules made there under.
7. The person authorised shall not rent, lend, sell, transfer or otherwise transport the
hazardous and other wastes except what is permitted through this authorization.
8. Any unauthorised change in personnel, equipment or working conditions as mentioned
in the application by the person authorised shall constitute a breach of his
authorization.
9. The person authorised shall implement Emergency Response Procedure (ERP) for
which this authorisation is being granted considering all site specific possible scenarios
such as spillages, leakages, fire etc. and their possible impacts and also carry out mock
drill in this regard at regular interval of time.
10. The person authorised shall comply with the provisions outlined in the Central
Pollution Control Board guidelines on Implementing Liabilities for Environmental Damages due to Handling and Disposal of Hazardous Waste and Penalty .
11. The hazardous and other waste which gets generated during recycling or reuse or
recovery or pre-processing or utilization of imported hazardous or other wastes shall
be treated and disposed of as per specific conditions of authorisation.
12. Any other conditions for compliance as per the Guidelines issued by the Ministry of
Environment, Forest and Climate Change or Central Pollution Control Board from time
to time.
13. Annual return shall be filed by June 30th for the period ensuring 31st March of the year.
JOINT CHIEF ENVIRONMENTAL ENGINEER
N V Bhaskara
Rao
Digitally signed by N V
Bhaskara Rao
Date: 2018.02.05 19:28:51
+05'30'
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Rel
ianc
e G
ener
al In
sura
nce
Com
pany
Lim
ited
SID 8
Registered Office: H Block, 1st Floor, Dhirubhai Ambani Knowledge City, Navi Mumbai 400710.Corporate Office: Reliance Centre, South Wing, 4th Floor, Off. Western Express Highway , Santacruz (East), Mumbai - 400 055.Corporate Identity No.U66603MH2000PLC128300. RGI/MCOM/CO/2711/WL/Ver. 1.1/010218Trade Logo displayed above belongs to Anil Dhirubhai Ambani Ventures Private Limited and used by Reliance General Insurance Company Limited under License
Reliance General Insurance Company Limited. An ISO 9001:2008 Certified Company IRDAI Registration No. 103.
M/S ASHOKA RANASTALAM ANANDPURAM ROAD LTD &ITS SUBCONTRACTOR
5/89/1, 1ST FLOOR UPSTAIR OF BANK OF BARODA,ANANDPURAM , VISAKHAPATNAM , CHODAVARAM,VISAKHAPATNAM, ANDHRA PRADESH, 531022,
We are pleased to inform you that you have been insured under Policy No. 170421827110000543. Attached herewith yourpolicy document, with all the details which have been prepared based on the details furnished to us. We request you to kindlygo through the same.
Subject : Reliance Employees Compensation Insurance Policy Schedule Policy No : 170421827110000543Dear M/S ASHOKA RANASTALAM ANANDPURAM ROAD LTD & ITS SUBCONTRACTOR,
Welcome to the Reliance General Insurance family!
We are delighted to have you as our valuable customer and are truly thankful that you have chosen Reliance GeneralInsurance for your Insurance requirements.
For any discrepancy in the document, kindly write to us immediately for necessary rectification. In the absence of anycommunication from your end, the contents and coverage of the policy shall stand accepted by you.To enable us to serve you better, you are requested to mention your Policy Number in all your further correspondencesWith Reliance General Insurance, you get nothing less than excellent and unparalleled services.Thanking you once again for choosing us. Look forward to a long lasting and delightful relationship.Yours sincerely,
For Reliance General Insurance Company Limited
Authorized Signatory
Page 1 Of 8
Rel
ianc
e G
ener
al In
sura
nce
Com
pany
Lim
ited
Employees Compensation Insurance Policy Schedule
From 04/08/2018 to 03/08/2019 (both days inclusive)
Risk Locations : Anandpuram ROAD PROJECT,,Vishakhapatnam,,,ANANDAPURAM,ANDHRA PRADESH,531163
RELIANCE CENTRESOUTH WING,4TH FLOOR,OFF.WESTERN EXPRESSHIGHWAY,SANTACRUZ(EAST),MUMBAI -400 055
Insured : Period Of Insurance :
Proposal No : R01081844306
Communication Address & Place of Supply: Policy issuing office address :
Business : Policy servicing address :
Details of previous policy (if renewal) : Date of proposal & declaration :
Previous policy No :
Policy Number : 170421827110000543
Email ID : Mobile No :
GSTIN/UIN of the Insured : 37AAPCA4244C1ZS R01081844306 & 02/08/2018Tax Invoice No. & Date :
IG
M/S ASHOKA RANASTALAM ANANDPURAM ROADLTD & ITS SUBCONTRACTOR
5/89/1, 1ST FLOOR UPSTAIR OF BANK OF BARODA,ANANDPURAM , VISAKHAPATNAM , CHODAVARAM,VISAKHAPATNAM, ANDHRA PRADESH, 531022,
Road, Infrastructure - Development & Maintenance
170421727110000205
106,107,108 1ST FLOOR, SPACE COSMOS BUILDING,ASHOKSTAMBH, NASHIK NASHIK NASHIK MAHARASHTRA
02/08/2018Renewal
Subject otherwise, to the terms, conditions &Exclusions of the Policy, the amount of liabilityincurred by the insured as per act for anydeath/PPD/TTD/PTD arising out of an accident.
Laws : The Policy covers Liability of the Insured under the following Law(s) shown as covered, subject to claim being otherwise admissibleas per terms, conditions and exclusions of the Policy and subject to Limit of Indemnity as stipulated against each Law :
Law / Act Limit of indemnity CoverageEmployee’s Compensation Act, 1923 andsubsequent amendments thereof prior tothe date of issue of this Policy
(a) Yes
(b) The Fatal Accidents Act, 1855 Subject otherwise, to the terms, conditions &Exclusions of the Policy
Yes
(c) Common Law Subject otherwise, to the terms, conditions &Exclusions of the Policy
Yes
Amount (`)
Net Premium
Premium Details
238219.00
IGST (@18.00%) 42879.42
(`)Total Premium 281098.00
. .GSTIN :27AABCR6747B1ZG, SAC :9971,Description of services : Other non-life insurance services
IGST0
Consolidated Stamp duty Paid vide Letter of Authorisation No. CSD/77/2018/2732-33/18 dated 17th July 2018**Not Applicable for the State ofJ&K
Description of work done byEmployees
DeclaredNumber ofEmployees
DeclaredWages duringthe Period of
Insurance
Class. No.Endt No.
Occupancy Designation
Details of Employees Covered
Road Paving, Tarring and Road Making Construction,Maintenance & RoadMaking project.Anandpuram ROADPROJECT. Wokingsincludes like work onroad, bridges & realtedconstrcutions, quarryworks
300 124 402 045000000.00
Page 2 Of 8
Digitally signed byRaman AroraDate: 2018.08.02
Rel
ianc
e G
ener
al In
sura
nce
Com
pany
Lim
ited
Reliance General Insurance Company Limited.Registered Office: H Block, 1st Floor, Dhirubhai Ambani Knowledge City, Navi Mumbai 400710.Corporate Office: Reliance Centre, South Wing, 4th Floor, Off. Western Express Highway , Santacruz (East), Mumbai - 400 055.Corporate Identity No.U66603MH2000PLC128300. RGI/MCOM/CO/2711/PS/Ver.1.1/010218Trade Logo displayed above belongs to Anil Dhirubhai Ambani Ventures Private Limited and used by Reliance General Insurance Company Limited under License
IRDAI Registration No. 103. An ISO 9001:2008 Certified Company
Slaters and Tilers (Roofs) where carried on as aseparate trade-Exceeding 9 meters in height
Woker working above9 Meter
100 527A 015000000.00
Total 60000000.00400
Direct/Direct
Intermediary Code/Name Intermediary Contact No. Intermediary E-mail ID
Subject to following clauses Conditions:
This policy would be governed by:1.The Employee's Compensation Act, 1923 and subsequent amendments of the said Act prior to the date of issue of the Policy2.Common Law (Payment under common law shall not exceed the payment under WC act)3.Fatal Accident 1855Including Cover for Contractors & sub Contractors workers - subject to submission of details at the time of claim.Previous Loss History:NILWarranted that attendance and wage register is maintained at the place of employment by the Insured as per statutory requirements/compliance and to be submitted when required by insurer.The change in place or nature of employment as when if any during the policy period to be informed to the insurer mandatorily and thesame shall be covered at the sole discretion of Insurer and if additional premium is required the same shall be chargedThe total number of employees/workers mentioned against each job description and occupation should not exceed at any time and if it isexceeding the same should be informed to the insurer and premium should be paid accordingly and in case of any violation claim shall notbe admissibleWarranted that no tunneling work/ underground work and/ or blasting is carried out at the work site.Losses / damage due to war , Civil war , Nuclear energy and radio active effects are excludedOccupational Diseases stand excluded.The workman under the influence of liquor or drugs is excluded.The willful disobedience by the workman of orders and rules expressly given to secure the safety of the workmen is excluded.Workers to follow all safety measures as per industry standards at all times.Onus of proof lies with the insured for employment and coverage under the policy for the person on behalf of whom the claim is made, tofurnish the total number of employees/workers working on site at the time of accident.Endorsement no :124 : It is hereby understood and agreed that any work in connection with the use of explosives or in connection with theconstruction of sewers exceeding in any part a depth of 3 Metres from the surface or in connection with tunnelling is expressly excludedfrom the indemnity granted under this PolicyPolicy is subject to No past insurance claims history.Medical Extension : provided
Exclusion :Losses suffered in the course of manufacturing and / or supplying and / or producing, storing, filling, breaking down, transportinga.-Fireworks, ammunitions, fuses, cartridges, powder, nitro-glycerine, or any explosives.b.-Gases and or air under pressure in containers.c.-Petrochemicals and also chemicals of a "toxic" (as defined under Indias Public Liability act 1991), noxious, explosive and or highlyflammable nature.d.-Asbestos and or asbestos products other thanThe storage, Transport and / handling of any of the substances above mentioned other than (d) which is merely incidental to the operationsand/or trade of the insured not otherwise excluded, is hereby covered.Losses suffered in the course of the construction, maintenance and demolition of towers, steeples, bridges, flyovers and other walkways androad bridges not longer than 300 meters and road bridges with unsupported span longer than 100 meters. Losses suffered in the course of shipbuilding, ship repairing and ship breaking other than pleasure crafts, stevedoring and or harbour / longshore work and Sub-aqueous workService in any kind of armed forces (including, but not limited to military, police, security services).
Page 3 Of 8
Rel
ianc
e G
ener
al In
sura
nce
Com
pany
Lim
ited
Reliance General Insurance Company Limited.Registered Office: H Block, 1st Floor, Dhirubhai Ambani Knowledge City, Navi Mumbai 400710.Corporate Office: Reliance Centre, South Wing, 4th Floor, Off. Western Express Highway , Santacruz (East), Mumbai - 400 055.Corporate Identity No.U66603MH2000PLC128300. RGI/MCOM/CO/2711/PS/Ver.1.1/010218Trade Logo displayed above belongs to Anil Dhirubhai Ambani Ventures Private Limited and used by Reliance General Insurance Company Limited under License
IRDAI Registration No. 103. An ISO 9001:2008 Certified Company
Workers engaged in underground and/or underwater mines and underground services.Subaqueous work.Quarries where explosives are used.Employees stationed outside India.
In Witness whereof this policy has been signed at Mumbai on policy tax invoice date in lieu of Proposal No. as mentioned in the policy.Warranted that in case of dishonor of premium cheque(s) the company shall not be liable under the policy and the contract shall be void ab-initio"This document shall be treated as a Tax Invoice as per Rule 9(2) of the Goods and Services Tax Invoice Rules
IGSTIn case of a renewal, the benefits provided under the policy and/or terms and conditions of the policy including premium rate may be subject tochange.Grievance Clause :For resolution of any query or grievance, Insured may contact the respective branch office of the Company or may call at
1800 3009 or may write an email at [email protected]. In case the insured is not satisfied with the responseof the office, insured may contact the Nodal Grievance Officer of the Company at [email protected]. Inthe event of unsatisfactory response from the Nodal Grievance Officer, insured may email to Head Grievance Officer [email protected]. In the event of unsatisfactory response from the Head Grievance Officer, he/shemay, subject to vested jurisdiction, approach the Insurance Ombudsman for the redressal of grievance. Details of theoffices of the Insurance Ombudsman are available at IRDAI website www.irda.gov.in or on company websitewww.reliancegeneral.co.in or on www.gbic.co.in. The insured may also contact the following office of the InsuranceOmbudsman within whose territorial jurisdiction the branch or office of the Company is located.Office of the InsuranceOmbudsman,3rd Floor,Jeevan Seva Annexe,S. V. Road,Santacruz (W), Mumbai - 400 054. Tel.: 022 - 26106552 /26106960 Fax: 022 - 26106052 Email: [email protected] | Shri. A. K. Sahoo Office of the InsuranceOmbudsman,Jeevan Darshan Bldg.,3rd Floor,C.T.S. No.s. 195 to 198,N.C. Kelkar Road,Narayan Peth, Pune – 411 030.Tel.: 020-41312555 Email: [email protected]
For: Reliance General Insurance Co Ltd.
Authorised Signatory
Page 4 Of 8
Rel
ianc
e G
ener
al In
sura
nce
Com
pany
Lim
ited
Forming A Part Of Policy No 170421827110000543Employees Compensation Endorsement 345 (Erstwhile Tariff)Coverage for Medical Expenses:In consideration of the payment of an additional premium it is hereby understood and agreed that this Policy subject to its terms provisions andconditions is extended to indemnify the Insured in respect of the reasonable medical surgical and hospital expenses (including costofconveyance to hospital) incurred by the Insured for treatment of injury to which the indemnity granted under this policy applies had disablementexceeded three days.
For: Reliance General Insurance Co Ltd.
Authorised Signatory
Provided always that the liability of the Company under this endorsement shall be limited to Rs 50000.00 /- in respect of each Employee perperson per accident, and the aggregate liability of the Company for all accidents during the Period of Insurance to Rs 1200000.00 /-.
.
Page 5 Of 8
Rel
ianc
e G
ener
al In
sura
nce
Com
pany
Lim
itedAttached to and Forming A Part Of Policy No. 170421827110000543
EMPLOYEES COMPENSATION POLICY
WHEREAS the INSURED by Proposal which shall be the basis of this contract and deemed to be incorporated herein has applied to theRELIANCE GENERAL INSURANCE COMPANY LIMITED (hereinafter called the “Company”) for the insurance hereinafter contained for theBusiness described in the Schedule and has paid or agreed to pay the premium stated in the Schedule as consideration for such insurance.
NOW THIS POLICY WITNESSETH, subject to the terms exceptions and conditions contained herein or endorsed hereon, that if at any timeduring the Period of Insurance any Employee of the Insured shall sustain personal Injury by accident arising out of and in the course of hisemployment in the Business, for which the Insured is liable to pay compensation under any Law(s) specified in the Schedule, then Companyshall indemnify the Insured upto the Limit of Indemnity against all sums for which the Insured shall be so liable, including costs and expenses fordefending any claim for such compensation incurred with the Company’s consent
PROVIDED ALWAYS that in the event of any change in the Law(s) or the substitution of other legislation therefore, this Policy shall remain inforce but the liability of the Company shall be limited to such sum as the Company would have been liable to pay if the Law(s) had remainedunaltered
DEFINITIONSCertain words used in this Policy and shown in bold are defined hereunder and shall have such meaning wherever they appear in this PolicyBusiness means the Business of the Insured as specified in the Schedule in respect of which this Policy is issued.Injury means physical bodily injury including death resulting from such Injury arising out of an accident but does not include any mental sickness,disease, Occupational Disease or illness, unless caused by such physical bodily injury.Insured means the person or organization specified in the Policy Schedule but does not include their Contractors or Sub Contractors.Occupational Disease means any disease listed under Schedule III of the Employees’ Compensation Act. 1923 contracted by an Employee dueto employment in the Business.Wages means the remuneration payable to an Employee by the Insured for the employment in the Business and includes any privilege or benefitwhich is capable of being estimated in money other than a travelling allowance or the value of any travelling concession or a contribution paid bythe employer of a employee towards any pension or provident fund or a sum paid to a employee to cover any special expenses entailed on himby the nature of his employment
Employee means such person or persons in direct employment under the Insured in the Business covered under this Policy, but shall not includeany person employed under a Contractor or Sub-Contractor of the Insured unless specifically shown as covered in the Schedule.Schedule means the Schedule attached to and forming part of this Policy.Limit of Indemnity means the maximum amount of indemnity as specified in the Schedule that will be provided under this Policy by the Companyin respect of
a) any particular claim by an Employee andb) all claims arising out of all accidents for any number of Employees during the Period of Insurance.
Limit of Liability means the maximum amount of indemnity specified in the Schedule that will be provided under this Policy by the Company inrespect of
a) any particular claim by an Employee andb) all claims arising out of all accidents for any number of Employees during the Period of Insurance.
EXCLUSIONSa) This Policy shall not cover liability of the Insuredb)For Injury caused to Employee by accident directly or indirectly caused by or arising from or in consequence of or attributable to war,invasion, act of foreign enemy, hostilities (whether war be declared or not) civil war, mutiny, insurrection, rebellion, revolution or military orusurped power, nuclear weapons material, ionising radiations or contamination by radioactivity from any nuclear fuel or from any nuclearwaste form the combustion of nuclear fuel.
c) For Occupational Diseases contracted by an Employeed) For interest and/or penalty imposed on the Insured under any law or otherwise.e) Under any Law for medical expenses in connection with treatment of any Injury sustained by an Employeef) For persons employed in the Business under a Contractor or Sub-contractor of the Insured unless specificallyg) For Injury sustained by person whilst in the employ of the Insured otherwise than in the Business and/or who has is not declared forinsurance under this Policyh) Assumed by agreement which would not have attached in the absence of such agreementi) For any sum which the Insured would have been entitled to recover from any party but for an agreement between the Insured and suchparty.j) For any accident occurring whilst the Employee is under the influence of Intoxicating liquor or drugs.
Reliance General Insurance Company Limited. An ISO 9001:2008 Certified CompanyRegistered Office: H Block, 1st Floor, Dhirubhai Ambani Knowledge City, Navi Mumbai 400710.Corporate Office: Reliance Centre, South Wing, 4th Floor, Off. Western Express Highway , Santacruz (East), Mumbai - 400 055.Corporate Identity No.U66603MH2000PLC128300. RGI/MCOM/CO/2711/PS/Ver.1.1/010218Trade Logo displayed above belongs to Anil Dhirubhai Ambani Ventures Private Limited and used by Reliance General Insurance Company Limited underLicense.
IRDAI Registration No. 103.
Page 6 Of 8