india coal sector environmental social ......investigation report’ on the india coal sector...

15
INDIA COAL SECTOR ENVIRONMENTAL AND SOCIAL MITIGATION PROJECT (CREDIT NO. 2862-IN) MANAGEMENT REPORT ON STATUS OF OUTSTANDING ISSUES FOLLOWING THE INSPECTION PANEL INVESTIGATION REPORT No. 24000 AND MANAGEMENT’S RESPONSE January 5,2007 38449 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 21-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

INDIA COAL SECTOR ENVIRONMENTAL AND SOCIAL MITIGATION PROJECT

(CREDIT NO. 2862-IN)

MANAGEMENT REPORT ON STATUS OF OUTSTANDING ISSUES FOLLOWING THE INSPECTION PANEL INVESTIGATION REPORT No. 24000 AND

MANAGEMENT’S RESPONSE

January 5,2007

38449

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

List o f Acronyms

CASS C B A Act C C L CD/R&R C I L CSESMP CSRP DEA EMP GO1 IPDP M O C NDO NGO OBC PAF PAP PIC R&R RAP XISS

Chotanagpur Adivasi Sewa Samiti Coal Bearing Areas Act o f 1957 Central Coalfields Ltd. In Jharkhand (formerly part o f Bihar) Community DevelopmentResettlement and Rehabilitation Officer Coal India Ltd. (A public sector enterprise o f the Government o f India) Coal Sector Environmental and Social Mitigation Project Coal Sector Rehabilitation Project Department o f Economic Affairs, Ministry o f Finance Environmental Management Plan Government o f India Indigenous Peoples Development Plan Ministry o f Coal World Bank New Delhi Office Non-Governmental Organization Other Backward Castes Proj ect-Affected Family Proj ect-Affected Person Public Information Center Resettlement and Rehabilitation Resettlement Action Plan Xavier Institute o f Social Service, facilitating NGO in Parej East

Page 3: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

INDIA COAL SECTOR ENVIRONMENTAL AND SOCIAL MITIGATION PROJECT

(CREDIT NO. 2862-IN)

MANAGEMENT REPORT ON STATUS OF ISSUES FOLLOWING THE INSPECTION PANEL INVESTIGATION REPORT No. 24000 AND

MANAGEMENT’S RESPONSE

INTRODUCTION

1. A Board meeting held on July 22,2003 discussed the findings o f the Inspection Panel’s Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively on the Parej East mine, which was one o f the 25 mines that received support under the project, and involved 643 (6%) o f the 10,214 total project affected people. “The Board endorsed the findings o f the Panel, while noting that the project had positively influenced Coal India’s policies on environmental and social issues and that nearly 90% o f the project affected persons in Parej East mine had improved or restored their incomes at the time o f project completion”2 on June 30,2002.

2. supervise the project and assist the key stakeholders - the project affected persons (PAPS), the NGO Chotanagpur Adivasi Sewa Samiti (CASS), the implementing agency Coal India L imi ted (CIL), i t s subsidiary Central Coalfields Limited (CCL), and the Government o f India (GOI) - to reach substantial resolution on issues related to resettlement and environment. Management also agreed to report to the Board on the status o f these issues at regular intervals.

At this meeting, Management, as part o f i t s Action Plan, stated i t s commitment to continue to

Box 1: The Coal Sector Rehabilitation Project (Loan No. 4226-IN) and the Coal Sector Environmental and Social Mitigation Project (Credit No. 2862-IN )

The US$1.2 bi l l ion Coal Sector Rehabilitation Project (CSRP), co-financed by the Wor ld Bank and the Japanese Bank for International Cooperation, was designed to support market-oriented reforms in the Indian coal sector and the commercialization o f C I L operations through financial restructuring, corporatization, and productivity improvement. The investment component o f the CSRP, which provided support for the modernization and expansion o f 25 already existing open cast coal mines, was going to generate substantial environmental and social impacts. The Coal Sector Environmental and Social Mit igat ion Project (CSESMP) was a US$63 mi l l ion free-standing project designed to mitigate the impacts deriving f rom the CSRP.

The CSESMP became effective in July 1996, and i t s objectives were to: (i) enhance Coal India’s capacity to deal more effectively with environmental and social issues; (ii) implement appropriate policies for environmental mitigation and resettlement and rehabilitation o f people affected by coal projects and provide support to communities, in particular tribals, living in coal mining areas; and (iii) test the effectiveness o f these policies in the 25 coal mines that received financial support under the CSRP.

At the time o f CSESMP closure on June 30,2002, CIL’s capacity to deal with environmental and social issues had improved, and policies on Environment, Resettlement and Rehabilitation, and Community Development had been adopted company-wide. During the six years o f implementation, the project’s 14 Resettlement Action Plans and 24 Indigenous Peoples Development Plans had offered assistance with the restoration o f livelihoods or living standard improvements to a total o f nearly 200,000 people.

T h e Inspection Panel’s Investigation Report was issued on November 25,2002, in response to the Request for Inspection was submitted to the Inspection Panel on June 21,2001.

Wor ld Bank N e w Release No: 2004/30/SAR. July 25,2003.

Page 4: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

3. Over the past three and a hal f years, Management has carried out i ts commitment to the Board through regular reporting, participating in technical briefings and informal Board meetings, and has made extensive efforts to facilitate the resolution o f outstanding issues. Since the Board meeting on July 22, 2003, the supervision team has made nearly a dozen visits to the project area, the Country Director for India has held five meetings with GO1 specifically to seek their active cooperation, and the Bank has devoted US$650,000 and over 170 staff weeks in service o f this commitment.

4. At the Board’s request, the team provided a Technical Brief ing to Board members in September 2004, a presentation to the full Board in March 2005, and submitted reports to the Board in April 2005 and January 2006 on the status o f the Management Action Plan. In its April 2005 Report, Management informed the Board that given the outcome o f i t s ongoing dialogue with GO1 and other key stakeholders, as well as the progress made to date in some areas and the vaned impact o f Bank involvement in others, Management would reassess the nature and extent o f i t s involvement. The result of this reassessment would be a revised action plan, which would end supervisory responsibilities for selected issues, and would modify Bank involvement to providing advice and technical assistance as needed and/or requested, on others. September 30,2005 was set as the target date for reviewing progress, in order to allow for two further Bank missions - the f irst o f which took place in M a y 2005, and the second in August 2005.

5. The findings o f Management’s reassessment were presented in i ts January 2006 Report, and documented the issues where the level o f stakeholder cooperation was not contributing to progress towards resolution, as wel l as the issues where Bank involvement was no longer having a beneficial impact. In this Report, Management informed the Board o f i t s decision to conclude i t s involvement on two issues, modify i t s involvement on four issues, and remain engaged on three issues for another six months.

6. identified in the Inspection Panel’s November 2002 Investigation Report, and present the case for bringing to closure the Bank’s involvement in this Inspection Panel case.

The purpose o f this Report i s to inform the Board o f Management’s efforts to resolve the issues

STATUS OF ISSUES

Issue 1: Economic rehabilitation of 73 project affected persons (PAPs) who reported a decrease in income during the project period

7. At the time o f project closure on June 30,2002, data from Parej East indicated that nearly 90% o f PAPs had been able to maintain or increase their income^.^ These data also show that during the period o f RAP implementation (from 1997 to 2002) the percentage o f female PAPs earning an income increased dramatically, from 4.1% to 57.8%. Among the 270 female PAPs in Parej East, 97.8% have been able to maintain or increase their incomes during the project period. The affected tribal population experienced similar improvements. In Parej East, there were 194 PAPs belonging to one o f the Scheduled Tribes who provided income information for both the 1997 and 2002 censuses. Of these, 88.7% maintained or increased their incomes during the project period. In addition, the number o f tribal PAPs with above- poverty-line incomes more than doubled during the project period.

8. (CD)/Resettlement and Rehabilitation (R&R) Officer in Parej East would undertake a survey to investigate the reasons why 73 PAPs had experienced a decrease in income. CCL also agreed to hire the Xavier Institute o f Social Service (XISS), the former facilitating NGO, to verify the survey results and develop an action plan for any hr ther assistance. After some init ial delays and resistance from the PAPs

During the November 2003 mission, the Bank and CCL agreed that the Community Development

All income information has been adjusted for inflation. 3

Page 5: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

themselves, XISS began the assignment on September 9,2004 and submitted the interim report o n February 25,2005. Following the March 1 , 2005 briefing to the Board, the Bank team reviewed the interim report with XISS, and discussed the draft action plan w i th XISS, CIL, and CCL.

9. According to the final report, the caseload for remedial action had decreased from 73 PAPs to 9 PAPs as follows:

XISS submitted i t s final survey report with a proposed action plan on September 30,2005.

24 PAPs have increased their annual income through employment with the company, daily wage work and some self-employment;

12 PAPs have moved out o f the area and settled elsewhere and are thus not covered by the report;

10 PAPs are sicwaged and supported by their relatives;

0

0

0 9 PAPs have died;

0

0

9 PAPs continued to experience a decrease in income;

8 PAPs are s t i l l in possession o f their land;4

1 person was included in the l i s t by error and determined to be a non-PAP.

10. X ISS interim survey, the following actions had been initiated to assist the PAPs with economic rehabilitation:

During the August 2005 mission, CCL informed the Bank that on the basis o f the findings o f the

0 PAPs were informed by letter and in person by the CD/R&R Officer on nine separate occasions about the employment opportunities available to them;

PAPs have been listed into two ‘labor pools’ and the l i s ts were supplied to the two construction contractors for recruitment. The PAPs were informed accordingly by letter and in person, but to date none o f the PAPs have indicated interest in this work;

The Forest Department has also been given the l i s t o f these PAPs and advised to engage them in plantation activities under the project, but to date none o f the PAPs on the l i s t have expressed interest in this work;

The 9 PAPs, who according to the survey continued to experience a decrease in income, are presently working as coal loaders in the coal dump, and the Coal Dump Supervisor has been instructed to employ them on a preferential basis. A register i s being maintained by the Dump Supervisor which i s checked by the Parej East Project Officer on a monthly basis.

0

1 1. Taking into account the five years o f income restoration support provided under the project, four years o f Bank follow-up supervision, additional efforts by CCL, and the information provided by XISS on the status o f the 73 PAPs, o f which the 9 PAPs who by February 2005 had not restored their incomes, are presently employed in coal loading, Management i s o f the view that this issue i s substantially resolved.

12. Management concludes its involvement on this issue.

Issue 2: Settlement of claims for PAPs cultivating land under customary tenure

These 8 PAPS will only be displaced over the next five years as part o f normal mine expansion. Assistance will be provided in accordance with CIL’s R&R Policy and Indian L a w at the time o f displacement.

Page 6: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

13. Consistent with the Wor ld Bank’s OD 4.30, CIL’s R&R Policy states that “tribals cultivating land under traditional rights” should be recognized as entitled to compensation. Under Indian law, PAPs must establish that they have a valid claim to the land before compensation can be paid. Claims for rights to land cultivated under customary tenure-referred to as Ghair M a m a Khas (GMK) land in the Hazaribagh area-are examined on a case-by-case basis by the District Authorities. The disputes over GMK land stem from the fact that there are ambiguous historical records o f occupancy, dating back to the pre-independence era, and thus o f tenancy. Occupancy rights need to be verified, which has proven to be a protracted process, before compensation can be paid. For recognized claims, the compensation amount i s calculated in the same manner as for tenancy land.5

14. Since 2003, the District Authorities have conducted more than a dozen land settlement camps in Parej East in an effort to resolve claims over GMK land. The Bank supervision team has also held meetings with the District Collector and the Jharkhand State Secretary for Land Revenue to request their active cooperation in ensuring a timely resolution o f th is issue.

15. In total, 4 1 claims for land being cultivated under customary tenure were filed with the as t r i c t and State authorities by families from the two villages - Parej and Duru Kasmar - affected by the Parej East mine. Of the 26 claims from Parej village, 13 claims have been settled in favor o f project affected families (PAFs) and the requisite compensation paid to 12 PAFs. In the case o f 1 deceased PAF, the dependents have yet to come forward to claim the compensation. The remaining claims by 13 families were rejected due to ineligibility andor lack o f evidence, and 8 o f these families have chosen to f i le an appeal with the State Tribunal, in which the Union o f Ind idCCL and the State o f Jharkhand are also parties. Evidence on behalf o f the claimants was completed in 2004, while the evidence on behalf o f Government o f India/CCL i s s t i l l in progress.

16. will not be required for mining, and 6 claims have been rejected. The remaining 6 claims have been authenticated and compensation assessed. Payment o f compensation has been delayed due to a disagreement between the Distr ict Revenue Department and the Forest Department, which maintains that the land in question i s forest land and that claims for compensation thus should be settled in favor o f the Forest Department rather than o f the affected people.

Of the 15 claims from Duru Kasmar village, 3 claims are not applicable as the land in question

17. Bank team along with project authorities met with the Additional District Collector, Hazaribagh, who assured the team o f his cooperation. In addition, the Country Director wrote to the Chief Secretary, Government o f Jharkhand in November 2005 to request urgent resolution o f the dispute and payment o f compensation to the 6 PAPs. In i t s January 2006 Report, Management proposed to monitor this issue for a further six months.

In an effort to expedite the process o f disbursement o f compensation to the above 6 claimants, the

18. During the most recent supervision mission in September 2006, CIL informed the Bank team that the dispute had been settled and the payment o f compensation was in process. No appeals have been filed with the State Tribunal by the 6 families whose claims have been rejected. In light o f the above, Management considers this issue to be substantially resolved, and i s o f the view that continued involvement by the Bank will have no influence on the outcome o f the eight appeals from Parej village filed with the State Tribunal.

19. Management concludes its involvement on this issue.

See para. 63 inManagement Response to the Inspection Panel of July 19,2001.

Page 7: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

Issue 3: Provision o f long-term leases to PAPs for their house plots in the resettlement site

20. Security o f land tenure i s considered a critical aspect o f successful resettlement, and the Bank f i r s t raised this issue with GO1 in 1992, during the early stages of project preparation. By the time the original 1994 RAP for Parej East was prepared, CCL had already acquired the Pindra resettlement site under the Coal Bearing Areas (CBA) Act, which does not al low for the provision o f land title to individuals or families. As providing the PAPs with outright t i t le to the land would not be possible at Pindra, Management and GO1 began discussing the option o f providing PAPs with long-term leases. In July 1997, GO1 agreed in the Minutes o f the CSRP Negotiations to "take the necessary action to obtain from the relevant authorities written waivers or consent to grant PAPs renewable long-term leases ....'I t o their house plots.

2 1. supervision mission, ,and the following key developments have occurred:

Since 1997, the Bank team has raised the issue o f land titles or long-term leases during every

0

0

0

0

0

0

0

M a r c h 1999 - Apat ta (land title) format for long-term renewable leases proposed by CIL was forwarded to the Ministry o f Coal (MOC) for approval.

April 2000 - Draft lease agreement, specifically for the Pindra resettlement site in Parej East, was sent to the Director, Department o f Coal in MOC for approval. This matter was then referred to the Ministry o f Law.

May 2001 - Ministry o f Law informs CIL that while ownership cannot be transferred to the PAPs, it i s willing to consider requests from the subsidiaries to enter into agreements (long-term leases) with individual PAPs regarding their use o f the land, on a case-by-case basis. CIL re- submits individual case applications to the Ministry o f Law.

February 2002 - Additional Secretary, MOC, informed the supervision team that M O C i s in discussions with the Ministry o f Law and a solution i s forthcoming.

November 2003 - The Bank requests C IL and M O C to provide information on the causes for delay and to suggest ways to proceed which would expedite the resolution o f this issue.

M a r c h 2004 - CCL writes follow-up letter to MOC requesting assistance in resolving this issue.

May 2004 - CCL writes follow-up letter to M O C requesting assistance in resolving this issue.

June 2004 - M O C informed the supervision mission that i t expected to be able to resolve this matter with the Ministry o f Law within the next three months.

September 2004 - GO1 informed the Bank that the commitment i t made during the CSRP Negotiations was inconsistent with Indian Law and could not be fulfilled.

February 2005 - Country Director holds further meetings with GO1 on this issue. Subsequently the Department o f Economic Affairs (DEA) informs the Bank that MOC has finalized amendments to the CBA Act to provide long-term leases to PAPs, which have been vetted by the Ministry o f Law. DEA also informs the Bank that these amendments will be submitted during the current session o f Parliament.

October 2005 - Country Director writes to MOC to request clarification regarding the status o f the amendments.

September 2006 - CIL informs the Bank supervision team that the mine plan for Parej East indicates that the land at the Pindra resettlement site will not be required for mining during the l i fe o f the mine (the year 2020), thus providing de facto security o f tenure to PAPs.

Refer to paragraph 38 in the Minutes o f CSRP Negotiations.

Page 8: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

22. obtaining formal t i t le or long-term leases for their plots in the Pindra resettlement site. Although Management i s encouraged that the details o f the Parej East mine plan indicate that the PAPs will be provided with de facto security o f tenure, i t i s forced to conclude that a formal agreement i s not achievable, and that no further action on i t s part wil l b e able to secure such an agreement.

23.

Over the past 14 years, the Bank has made extensive and continued efforts to assist the PAPs in

Management concludes its involvement on this issue.

Issue 4: Disbursement of subsistence allowance funds by GO1

24. the Inspection Panel in January 2002. Although CIL’s R&R Policy does not mention the type o f subsistence allowance referred to by CASS, the August 1994 Resettlement Action Plan (RAP) for Parej East, Section 3.4.4 refers to an additional ‘subsistence a l l ~ w a n c e ’ ~ payable for 20 years to those project affected families (PAFs) who lose their land and do not opt for a j ob or do not qualify for a job.

CASS f i rst raised this issue with the Bank in one o f the two additional documents it submitted to

25. In July and November 2003, Management recommended that GO1 make funds available or explore additional ways o f realizing this entitlement. A letter received in September 2004 from GO1 concluded that the additional subsistence allowance for PAFs in Parej East was included in the 1994 RAP by oversight. None o f the RAPS for the other CIL subsidiaries under the project included this type o f subsistence allowance, as it was not based on CIL’s R&R Policy, or required by the Bank’s policy. Bo th CIL and GO1 have clearly stated to the Bank that providing the additional subsistence allowance would set an unacceptable precedent which would be unsustainable for CIL’s 500 mines.

26. reevaluate employment compensation as a means o f economic rehabilitation for families who would lose their land to mining activities within the next f ive years. A survey and consultation exercise, which focused on 121 PAFs, was subsequently undertaken by XISS and the final report was submitted on September 30,2005. The survey report indicated that among the 121 PAFs:

However, in i t s discussions with the Bank supervision team, C C L indicated i t s willingness to

0 54 PAFs have yet to lose their land, and according to mine plans, were only expected to do so in the next five to ten years;

42 PAFs who have already lost their land and received compensation have also either been given a mine job or have received monetary compensation in l i eu o f a job; and

25 PAFs would lose their land within the next five years.

In response to the survey, CCL has begun the process o f providing employment or monetary

0

0

27. compensation in l ieu o f employment to a l l 25 PAFs who will lose their land within the next five years. As part o f this process, the families have been requested to submit a family chart, designate a nominee for employment, and submit an application for employment.’ Once this information has been verified by the

T h e unit o f entitlement for th is subsistence allowance, as specified in the 1994 Parej East RAP, i s not the individual, but the family. For families losing up to one acre o f land, a subsistence allowance “at the rate o f Rs.300 per month + an ex-gratia amount o f Rs. 100 per month” would be provided for twenty years. For families losing more than one acre o f land, a subsistence allowance o f “Rs.300 per month per acre subject to a maximum o f Rs. 1,000 per month + an ex-gratia amount o f Rs. 100 per month” would be provided for 20 years. The 1994 Parej East RAP also indicates that 54 percent o f the PAFs there were landless (while another 40 percent owned less than 2.5 acres o f land).

wil l be shared. T h ~ s process i s sometimes lengthy as co-sharers need to agree on a designated nominee or how the compensation

Page 9: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

D i s t r i c t Authorities, the employment application completed, and company approval has been obtained, employment or compensation in l i e u o f employment i s received in approximately three months.

28. employment, one family had received compensation in l i e u o f employment, applications for employment for eight nominees were under review, nine families have yet to submit a family chart and designate a nominee, three designated nominees have yet to submit an employment application, and according to CCL, three families have declined the offer o f employment. CCL has demonstrated, through its actions, substantial compliance with the agreed measures to provide the required compensation to the identified PAFs.

At the time o f the most recent Bank mission in September 2006, one nominee had received

29. on this issue.

Management finds that this issue has been substantially resolved and concludes its involvement

Issue 5: Delivery o f compensation and relocation entitlements

30. under the project. A total o f 27 PAFs f i led cases wi th the State Tribunal for increased compensation. The State Tribunal has awarded higher payment to 9 PAFs, and this judgment has been appealed to the High Court by CCL. Evidence and arguments for both parties have been completed, and a judgment i s awaited from the High Court.

Compensation and relocation entitlements have been paid to a l l PAFs who have been resettled

3 1. State procedures, over which the Bank has n o influence, Management considers this issue to be substantially resolved.

32.

As the process for compensation and relocation entitlements are governed by well established

Management concludes its involvement on this issue.

Issue 6: Water quality at the resettlement sites

33. place for monthly monitoring o f water quality in al l resettlement sites together with independent verification, as well as measures to mitigate any results outside the parameters defined by Indian law. Since that time, all Bank missions have continued to examine testing records to ensure that regular monitoring was undertaken, and that any deviation from accepted parameters was mitigated.

In i t s Report o f July 2003, Management recommended that institutional arrangements be put in

34. monitoring was assessed as being satisfactorily addressed by the Central M ine Planning and Design Institute (CMPDI). The CMPDI continues to monitor the water quality on a monthly basis.

The Bank concluded its supervisory responsibility of this issue in Apr i l 2005, since water quality

Issue 7: Reclamation of mine land for agricultural use

35. was proposed by the Wor ld Bank in late 1997, and pursued in al l successive supervision missions. Despite agreements reached during the midterm review in February 1999 regarding five land-based income generating pilots (including in CCL), reluctance on the part o f CIL to fol low up on i t s commitments resulted in only one such pi lot being implemented in another subsidiary.

The provision o f replacement land for PAPs through utilization o f unused or reclaimed mine land

36. reclaimed land could be used to undertake land-based income generation activities for PAPs. In early 2005, at the request o f the Bank team, project authorities prepared a map which identified unused or reclaimed mine land which could potentially be utilized for land-based income generation activities.

In i t s Report o f July 2003, Management recommended that CCL consider ways in which

Page 10: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

However, CCL's future need o f the land for underground mining, lack o f legal clarity regarding use rights, and CCL's obligation to return the land to the State government once mining operations have been completed, have further complicated a decision on this matter.

37. incomes, and in light o f the existing legal complexities, Management finds this issue to be substantially resolved and concludes that further progress on t h i s issue i s unlikely.

38. Management concludes its involvement on this issue.

A s more than 95% o f the PAPs in Parej East have now been able to restore or increase their

Issue 8: Mechanisms for consultation and dissemination o f project related information to PAPs

39. As detailed in earlier reports to the Board: the existence o f incomplete information as wel l as misinformation in Parej East has had a significant impact on the Bank's ability to facilitate the resolution of various issues. Hence, the supervision team considered ensuring access to accurate information a top priority. In December 2004, with assistance from the Bank team and the Senior External Affairs Officer from the New Delh i Office, CCL developed an information and communication strategy to ensure public access to project-related information, particularly for the affected community, and to improve the relationship between the project authorities and stakeholders.

40. February 18,2005 with representatives from each o f the social groups in the affected area (Muslims, Ganjus, Turis, Manjhis, Prasads, etc.) to discuss the potential benefits and risks o f various options for economic rehabilitation. During this meeting:

C C L began i t s efforts to improve their relationship with the community by holding a meeting on

0 Community leaders were encouraged to raise all their doubts and questions and seek resolution to any gnevances;"

CCL outlined i t s rehabilitation policies and plans, and redistributed this information in writing; and

XISS explained the purpose, process, and results o f the latest survey.

0

0

41. In August 2005, the Bank team noted the good rapport established by the Project Officer with the PAPs, and that timely remedial measures" in response to gnevances raised during the February 2005 meeting have helped in gaining the confidence o f the PAPs. As agreed with the Bank, C C L officials have continued to meet with the PAPs on a regular basis to listen to and address their concerns.'*

42. The communication strategy also involved the development o f an ongoing dialogue between CCL and CASS. CCL's Area General Manager (AGM) for the project initiated this with a one-to-one meeting with CASS on December 17,2004, but attempts to continue these discussions during the f i rs t six months o f 2005 did not materialize, due to his transfer to another subsidiary. During the August 2005 field visit, i t was agreed that the new AGM would hold at least two meetings with CASS to discuss how to resolve outstanding issues. The f i rs t o f these meeting was held on September 22,2005, and the second on M a y 6, 2006.

See Management's April 2005 and January 2006 Reports to the Board. 9

lo The key issues raised related to eligibility criteria for the subsistence allowance, opportunities for economic rehabilitation., authentication o f GMK land, and requests for more work in the coal dump. l1 These measures included improvements in the condition o f the school building, making the school operational by facilitating the recruitment o f a local teacher, providing electricity connections to individual houses at the Pindra resettlement site, and organizing regular health check-ups for PAPs. l2 Recent requests f rom the PAPS, including the construction o f a temple, and repairs to the school gate and hand pump have been met by the project.

Page 11: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

43. their differences, Management finds that this issue has been substantially resolved and concludes its involvement in this issue.

As the stakeholders are now communicating directly with one another as a means of resolving

Issue 9: Constitution of an Independent Monitoring Panel (IMP)

44. had already been completed, and the institutional arrangements in place were sufficient to handle what remained. In its letter to the Bank in September 2004, GO1 confirmed its view that circumstances on the ground did not warrant the constitution o f an Independent Monitoring Panel.

45.

In 2003 GO1 stated that there was no need for an IMP as the majority of the rehabilitation work

The Bank accepted the position of GOI, and concluded its involvement in this issue in April 2005.

CONCLUSION

46. resolution to the issues identified in the Inspection Panel’s Investigation Report. These include follow-up missions, technical assistance, continued engagement with al l stakeholders, follow-up by the Country Director with relevant officials at the federal and state levels, and support for external assessments. The Bank has worked wi th al l key stakeholders to support resolution, and has endeavored to create an environment which encourages direct communication and multi-stakeholders problem solving.

47. Overall, the key issues raised by the Inspection Panel have been substantially resolved. However, despite the Bank’s active and sustained engagement, constraints in the existing legal context have prevented the achievement o f full resolution on l imited aspects o f the Management Act ion Plan. On these aspects, Management concludes that the process has been taken forward to its fullest extent, and that further developments are restricted by broader policy issues, w h c h extend beyond the coal sector. In light o f the above, Management has decided to bring to closure i t s involvement in the Coal Sector Environmental and Social Mitigation Project, and expects that this wi l l b e the last Progress Report submitted in reference to this Inspection Panel case.

In keeping wi th its commitment to the Board, the Bank has made extensive efforts to facilitate

IMPLICATIONS FOR FUTURE OPERATIONS

48. involvement i s Inspection Panel cases, including the CSESMP, to in form future Bank projects. However, the experience o f Coal India already suggests that project level interventions may not be able to fully address the problems involved in land acquisition, resettlement o f communities, and the provision o f compensation to households. These challenges often emanate from systemic problems in the broader policy framework governing land acquisition processes and resettlement and compensation mechanisms, especially for vulnerable communities l ike tribal groups. Ineffective implementation mechanisms and the resulting capacity constraints also add to the complexity o f managing such issues at the project level. The Bank recognizes that there i s a need to address these problems at a broader policy level with direct capacity support for government that i s cross-sectoral in nature.

49. on safeguard management in India this fiscal year. I t s objective i s to support the Government o f India with the review and assessment o f existing land acquisition, resettlement and rehabilitation policies and legislation, as well as identify possible changes that may result in more efficient and equitable outcomes. This new approach to safeguard management i s one that complements the project level interventions by identifying gaps and providing support to strengthen existing country systems. I t i s hoped that supporting the creation o f a better policy environment will reduce the problems faced in safeguarding the interests o f poor people at the project level.

The South Asia Region i s in the process o f writing a formal note on the lessons learned from i t s

Drawing on t h i s important lesson, the Bank has introduced a formal technical assistance program

Page 12: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively
Page 13: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

. . ..... . . I I

I . I. .

. .

0 . . .

m

Page 14: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

0

n

e, e

Page 15: INDIA COAL SECTOR ENVIRONMENTAL SOCIAL ......Investigation Report’ on the India Coal Sector Environmental and Social Mitigation Project (CSESMP). This Report focused exclusively

S W

0 e 0

e

x,

m + d

e 0