IndustrialHeating & Piping Co.

Madawaska School Department Energy upgrades to the heating system at the

Madawaska High and Middle School

IndustrialHeating & Piping Co.

Madawaska Town MeetingHeating Project Special meeting

February 16th, 2011

Introductions

Todd Leroy, Superintendent, Madawaska School Department

Mike McCormick, Owner, McCormick Facilities Management, Construction Manager for this project

Maynard Pelletier, President, Industrial Heating & Piping, Prime Contractor for this project

IndustrialHeating & Piping Co.

Organizational structure for our“team approach”

Todd LeRoySchool Superintendent

(Primary school contact)

Mike McCormickConstruction Manager

(overall project responsibility)

Maynard PelletierGeneral Contractor

(mechanical installation and sub trades management)

IndustrialHeating & Piping Co.

Role of our team members

Mike McCormick will meet with your Board committee

• Discuss what you would like to do in this project

• Long-term building goals• Energy conservation• Alternative/Renewable opportunities• Financing the project• Operations and Maintenance goals• Review previous studies and efforts

IndustrialHeating & Piping Co.

Role of our team members

Industrial Heating & Piping will be instrumental to the ultimate success of this project

They will:• work with the committee and CM to obtain an

understanding of the desired outcomes• investigate existing project conditions within

the building• perform the construction and manage sub

tradesCondensate return tank steam escaping

IndustrialHeating & Piping Co.

We are a team specifically assembled to best serve the districts interests

• We aspire to make this YOUR project• We are here to assist and advise what will work for building

systems• We will meet with your Board and Committees to fully

understand your needs and desired direction• We will fully investigate the existing conditions• We will explore multiple solutions and present them to you

with the pros and cons of each

IndustrialHeating & Piping Co.

Approach to the project

1. Meet with the Board Committees

2. Perform thorough building and systems investigations

3. Conduct an energy audit and heating load calculations

4. Review green and alternative energy opportunities

5. Design final solution (s)

6. Construction complete before end of 2011

IndustrialHeating & Piping Co.

Existing conditions

• Aged and inefficient heat generation, distribution, and terminal devices

• No mechanical air exchanges within building

• Higher than average utility costs

IndustrialHeating & Piping Co.

There are 2 projects:• #1 is the installation of a wood chip fired

boiler and accessories to be the primary heat source• Budgeted at $1.4 million

• #2 is to convert the steam system to a hot water system, and other energy improvements• Budgeted at $2.7 million

• Together they will provide a comfortable and energy efficient school environment

IndustrialHeating & Piping Co.

Bio mass project description

• Construct a new boiler house to accommodate the wood boiler and wood chip storage

• Install a 4.3 MMBTU wood chip boiler and new oil fired back up boiler

• Install thermal storage tank and roof top solar units for domestic water and heating water supplement

• Connect wood fired system to new building distribution system

IndustrialHeating & Piping Co.

Steam to hot water conversion project

• Replace both existing boilers with one oil fired hot water boiler

• Reuse as much existing piping as possible and replace as needed

• Replace univents and terminal device• Add fresh air systems with heat recovery• Rebuild exhaust fans and air handlers, café and gym

• Install solid state direct digital building controls• Remove equipment from existing boiler room• Remove brick chimney• Install new lights and sensor in gym

IndustrialHeating & Piping Co.

IndustrialHeating & Piping Co.

Possible location for new bio mass plant

IndustrialHeating & Piping Co.

Fuel savings

Fuel savings spreadsheet

Annual 1st year – $196,704

10 year savings – $1,967,036

15 year savings – $2,950,554

Savings over oil

IndustrialHeating & Piping Co.

??Questions and Answers??

Thank you for attending tonight and supporting this exciting project for your school department and community.