BMS Belt Cleaners Limited (BMS Overseas Limited) P.O. Box 19 Richmond, North Yorkshire, England DL10 5YX Telephone: +44 (0) 1325 483 916 Fax: +44 (0) 1325 483 746 E.mail: [email protected] General Notes: For maximum cleaning efficiency, correct belt tension must be maintained at all times. Ensure spindle is mounted at 90º to the belt line. Only the ideal scraper positions are shown, for alternatives, refer to BMS Belt Cleaners. detail of chute cut-outs Installation & Operating Instructions Note: All dimensions shown in millimetres BMS E2000 Torsion Arm Belt Cleaner - Standard Duty option 2. installation arrangement Note: Spindle can also be mounted thus Important: Support rollers installed to ensure scraper cleaning efficiency 1000 MAX 100 MIN 300 400 Nip Point Belt Line option 3. installation arrangement (when existing conveyor cannot be altered) Important: Support rollers installed to ensure scraper cleaning efficiency Note: Spindle can also be mounted thus 1000 MAX 100 MIN 300 Nip Point 15º If this angle of 15º is exceeded, material flow off the blade & skirt will be restricted Belt Line 400 option 1. installation arrangement Note: Spindle can also be mounted thus Nip Point 100 MIN Snub Pulley Belt Line 1 2 3 Rubber Cover available from BMS 148 175 380 MAX 180 MAX 300 W 60 dia 76 dia 101 dia Carrier Shafts Shaft dia. W dia. 60 76 101 80 100 130 Installation Side Opposite Side belt width X (min) X (max) Y (min) Y (max) Z A B hole dia ‘O’ shaft dia spindle dia fixed lug 650 750 900 1050 1200 1350 1500 1600 1800 2000 45 135 470 570 15 125 140 18 60 M42 No.2A 50 150 470 570 15 125 140 18 76 M42 No.3 60 160 460 580 15 125 140 18 101 M42 No.4 recomended 95 recomended 530 recomended 110 recomended 530 recomended 125 recomended 540 Y X B Hole D Y X Hole D B Y X B Hole D 90º A Z 400 90º A Z 90º A Z 1) Observe the belt condtion: - check any damage to the belt surface, which can influence the cleaning efficiency of the scraper. 2) Check mechanical or vulcanized joint for any damage and repair if necessary. Mechanical joints should be skived or at least as a minimum dressed to avoid any high points. 3) Check direction of the belt: remember that the BMS scraper musr be installed AGAINST THE DIRECTION of the belt travel. 4) Check the condition of the head or snub pulley lagging. 5) Check if the belt reverses. 6) Check if the belt is supported around the installa- tion point of the scraper and if not, install extra rollers around the installation point of the scraper to flatten out the belt in this area. INSTALLATION PREPERATION ©

Upload: vuongkhue

Post on 15-Sep-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

BMS Belt Cleaners Limited(BMS Overseas Limited)P.O. Box 19Richmond, North Yorkshire,England DL10 5YX

Telephone: +44 (0) 1325 483 916Fax: +44 (0) 1325 483 746E.mail: [email protected]

General Notes:

For maximum cleaning efficiency, correct belt tension must be maintained at all times.

Ensure spindle is mounted at 90º to the belt line.

Only the ideal scraper positions are shown, for alternatives, refer to BMS Belt Cleaners.

detail of chute cut-outs

Installation & Operating Instructions Note: All dimensions shown in millimetres

BMS E2000 Torsion Arm Belt Cleaner- Standard Duty

option 2. installation arrangement

Note:Spindle can alsobe mounted thus

Important: Support rollers installed toensure scraper cleaning efficiency

1000MAX

100MIN

300

400

Nip Point

Belt Line

option 3. installation arrangement (when existing conveyor cannot be altered)

Important: Support rollers installed toensure scraper cleaning efficiency

Note:Spindle can also be mounted thus

1000MAX

100MIN

300Nip Point

15ºIf this angle of 15º is exceeded, material flow off the blade & skirt will be restricted

Belt Line400

option 1. installation arrangement

Note:Spindle can also be mounted thus

Nip Point

100MIN

Snub Pulley Belt Line

1

2

3

Rubber

Cover available from BMS

148175

380MAX

180MAX

300

W

60 dia76 dia

101 dia

Carrier Shafts

Shaftdia.

Wdia.

6076

101

80100

130

Installation Side Opposite Side

beltwidth

X(min)

X(max)

Y(min)

Y(max)

Z A B holedia ‘O’

shaftdia

spindledia

fixedlug

650

750

900

1050

1200

1350

1500

1600

1800

2000

45 135 470 570 15 125 140 18 60 M42 No.2A

50 150 470 570 15 125 140 18 76 M42 No.3

60 160 460 580 15 125 140 18 101 M42 No.4

recomended

95

recomended

530

recomended

110

recomended

530

recomended

125

recomended

540

Y

X

B

Hole D

YX

Hole D

B

Y

X

B

Hole D

90º

AZ

400

90º

AZ

90º

AZ

1) Observe the belt condtion: - check any damage to the belt surface, which can influence the cleaning efficiency of the scraper.

2) Check mechanical or vulcanized joint for any damage and repair if necessary. Mechanical joints should be skived or at least as a minimum dressed to avoid any high points.

3) Check direction of the belt: remember that the BMS scraper musr be installed AGAINST THE DIRECTION of the belt travel.

4) Check the condition of the head or snub pulley lagging.

5) Check if the belt reverses.

6) Check if the belt is supported around the installa-tion point of the scraper and if not, install extra rollers around the installation point of the scraper to flatten out the belt in this area.

INSTALLATION PREPERATION

©

!IMPORTANT

BRACKET BASE AT90º TO BELT LINE

!IMPORTANT

BRACKET BASE AT

90º TO BELT LINE

!IMPORTANTBRACKET BASE AT

90º TO BELT LINE

BLADE MINIMUM TENSION(Inefficient Belt Cleaning)

BELTCLEANING

ZONE

BELTCLEANING

ZONE

BLADE OVER TENSIONED (Inefficient Belt Cleaning)

BLADE RECOMMENDED TENSION (Efficient Belt Cleaning)

BELTCLEANING

ZONE

IMPORTANT:It is critical to the correct set up and installation of the E2000 Multiblade Scraper that the MOUNTING BRACKETS and SCRAPER SHAFT are positioned PARALLEL to the belt line.

!Check

90º

!IMPORTANT

SHAFT AT 90º TO BELT LINE

90º

!IMPORTANT

SHAFT AT 90º TO BELT LINE

!IMPORTANT

SHAFT AT 90º

TO BELT LINE

90º

INSTALLATION OPTION 2INSTALLATION OPTION 1 INSTALLATION OPTION 3

RECOMMENDED BLADE TENSIONING POSITION

BELT LINEBELT LINE BELT LINE

Adjusting Nuts

Cut-out

ParallelMounting Bracket

Belt

Procedure: Procedure:

Cut-out

Alternative BracketMounting Position

Alternative BracketMounting Position

Torsion Arm Mount

Spindle

Bracket

Set Bolts

Procedure:

Torsion Arm Mount

Scraper Assembly(Shaft & Holder)

Spindle

Bracket

Set Bolts

Procedure:

Stop Screw

Locknut

Torsion armMount

Scraper Assembly

Preloading Procedure:

Carrier Shaft

Procedure:

X XZ Z

Centre ofBelt

!Check

Procedure:

CarrierShaft

AdjustingNuts

AdjustingNuts

Stop Screw

Torsion Arm

Set Bolts

90º

10mm

EngineersSquare

!Check

1. 2. 3. 4. 5. 6.

7.

8.

Note: Once this instruction is completed the Carrier Shaft, with Blades / Torsion holders will be in a hanging position.

1.Raise the Carrier Shaft until the blades lightly touch the belt.

Note:Adjusting the top and bottom nuts on the spindle, allows the Carrier Shaft to be moved vertically up or down.

1.Rotate the Carrier Shaft 180º so that the Blades / Holders are in a vertical position.

Note: If you have followed the instructions correctly, the position the blades will be a little way off touching the belt.

Attach the spindle to the prepared bracket on one side of the conveyor.

1.Bolt spindle to bracket, one side only.

Install the mounting brackets and cutouts asspecified in the installation drawing.

1. Prepare cutouts (both sides of chute).

2. Install brackets (both sides of chute) parallel tothe conveyor belt line.

1.Insert the Carrier Shaft into the Torsion Mount /Spindle assembly bolted to the conveyor structure.

2.Attach the other Torsion Mount and Spindle to make a second assembly.

3.Slide the second assembly onto the end of the Carrier Shaft and lift the Scraper Unit (which now includes the second Torsion Mount / Spindle assembly) and bolt to the conveyorstructure with two 16mm bolts.

1.Attach one of the Spindles and one of the Torsion Mounts to make an assembly.

Note: At this stage the position of the Torsion Mount on the spindle should be:

i. if the spindle is to be installed in a "hangingposition" 31.75mm of thread showing from the end of the spindle.

or;

ii. if the spindle is to be installed in a "standing position" 31.75mm of thread showing from the foot of the spindle.

2.Bolt this assembly onto the conveyor structure with two 16mm bolts.

1.Adjust the Stop Screw until it touches the Torsion Mount Arm, continue to adjust the Stop Screw a further 10mm.

The Torsion Mount is now preloaded.

At this stage you should:

i. Centralize the Carrier Shaft to the belt width.

ii. Provisionally set the Carrier Shaft parallel to the belt line.

iii. Provisionally check that the Torsion Mount / Carrier Shaft is horizontal on the spindles.

iv. Now lightly tighten the three set bolts in each of the Torsion Mounts, but only sufficiently to ensure that the Carrier Shaft does not tip over.

Note:Please do not over tighten the set bolts at this stage as the final setting of the Carrier Shaft will take place later.

To establish that the Carrier Shaft is parallel with the belt line, use an Engineers Square to check that the 200 x 100mm flat on top of the Carrier Shaft is parallel with the belt. If not slacken off the three set bolts in each of the Torsion Mounts to enable the shaft to rotate.

After satisfying yourself the Carrier Shaft is parallel with the belt line ensure that the three set bolts ineach of the Torsion Mounts are firmly tight.

Finally, turn the Stop Screw counta-clockwise to create a gap of 10mm from the Torsion Arm.

The Scraper is now set.

10mm

BMS Belt Cleaners continuously modify and improve its product range, therefore, information given in this leaflet may be subject to change without prior notice.

!Check

START-UP OF THE BELT

Unlock the conveyor.

Perform a test run with material on the belt.

Check the belt tracking.

Installation is complete.

Note:If cleaning efficiency is not being achieved adjust spindle nuts to raise the shaft assembly until correct cleaning efficiency is achieved.

BLADE SETTING

In order to ensure that the BMS Multi- Bladed Scraper operates correctly, it is essential that all blades are inclined in the direction of the belt travel using the belt scraper principal like a "paint scraper"

©