AboutthePresenter BassamSamman,PMP,PSP,EVP,GPMholdsa Bachelor’sDegreeinCivilEngineeringfrom KuwaitUniversi tyandaMaste rsDegreein EngineeringandAdministraonfromGeorge WashingtonUniversity.Heiscurrently pursuingaPhDattheUniversityofSalford, UK.HeisaceredProjectManagement Professional(PMP),acered Planningand SchedulingProfessional(PSP), EarnedValue Professional(EVP)andGreenProject Management(GPM).Heisthoroughly experiencedincompleteProjectManagement includingprojectmanagementcontrol systems,computerizedPCSSoOware,risk analysis,site management,cl aimsanalysis and prevenonandalternavedisputeresoluon. Bassamhas30 yearsexperienceinProject ManagementConsultancy. © 2009 CMCS FZCO

Upload: farid-yandouz

Post on 03-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 1/56

AboutthePresenter

BassamSamman,PMP,PSP,EVP,GPMholdsaBachelor’sDegreeinCivilEngineeringfrom

KuwaitUniversityandaMastersDegreeinEngineeringandAdministraonfromGeorge

WashingtonUniversity.Heiscurrently

pursuingaPhDattheUniversityofSalford,

UK.HeisacerfiedProjectManagement

Professional(PMP),acerfiedPlanningand

SchedulingProfessional(PSP),EarnedValue

Professional(EVP)andGreenProject

Management(GPM).HeisthoroughlyexperiencedincompleteProjectManagement

includingprojectmanagementcontrol

systems,computerizedPCSSoOware,riskanalysis,sitemanagement,claimsanalysisand

prevenonandalternavedisputeresoluon.

Bassamhas30yearsexperienceinProject

ManagementConsultancy.

© 2009 CMCS FZCO

Page 2: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 2/56

IntegrangRiskManagementandEarnedValuePerformance

Management

§  HowTheEarnedValue’sEsmateToCompletecalculaonsprovideanexcellentprojectperformancetool

§  HowtheMonteCarlosimulaoncanprovidethepredictedesmatetocompleteatdifferent

confidencelevels.

© 2009 CMCS FZCO

Page 3: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 3/56

HowTheEarnedValue’sEsmateToCompletecalculaonsprovideanexcellentprojectperformancetool

© 2009 CMCS FZCO

Page 4: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 4/56

ManagingPerformanceWithEarnedValue

Performancemanagement involvesapplying controls that ensure the project stayswithin theagreeduponbudget.

Theearnedvaluetechniqueisusedtoimplementperformancemeasurement.

The earned value technique compares the cumulave value of the budgeted cost of workperformed (EV) at the original allocated budget amount to both the budgeted cost of workscheduled(PV)andtotheactualcostofworkperformed(AC).

© 2009 CMCS FZCO

Page 5: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 5/56© 2009 CMCS FZCO

BudgetatCompleon(BAC)

Thesumtotaloftheme-phasedbudget.AlsoknownasProjectPlannedBudget

Page 6: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 6/56

PlannedValue(PV)

Isthebudgetcostfortheworkscheduledtobecompletedforanacvityuptoagivenpointinme.

Used to be known as Budget Cost of Work Scheduled (BCWS) or Budget Quanty of Work

Scheduled(BQWS)

  PlannedValueCostisthecostoftheworkthatshouldhavebeenaccomplishedasofthe

datadate,iftheprojecthadproceededaccordingtothebaselineplan.

  PlannedValueCost=BudgetatComple?onxSchedule%Complete.

  Answerstheques?on:Howmuchworkshouldbedone

© 2009 CMCS FZCO

Page 7: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 7/56

PerformanceManagementBaseline(PMB)

© 2009 CMCS FZCO

Project Performance

0

5,000

10,00015,000

20,000

25,000

30,00035,000

40,000

45,000

50,000

55,00060,000

65,000

70,000

Jan- 07 F eb- 07 Mar -07 Apr -07 May -07 Jun- 07 Jul- 07 Aug- 07 Sep- 07 Oct- 07 Nov -07 Dec- 07

Time

       A       E       D

Planned

Page 8: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 8/56

ManagementReserve(MR)

Timeorcostaddedtotheprojecttodealwithunknownunknownrisks.Thatisrisksthathavenotbeenidenfied.

© 2009 CMCS FZCO

Page 9: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 9/56

TotalAllocatedBudget(TAB)

TotalAllocatedBudget

ManagementReserve

BudgetAtComple?on

DistributedBudget

ControlAccounts

DiscreteWorkPackages

Appor?onedWorkPackages

LevelofEffortWorkPackages

SummaryPP

PlanningPackages

PlanningPackages

PlanningPackages

UndistributedBudget

© 2009 CMCS FZCO

Page 10: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 10/56

ControlAccount

Amanagementcontrolpointwheretheintegraonofscope,budget,actualcost,andscheduletakesplace,andwherethemeasurementofperformancewilloccur.

Controlaccountsareplacedatselectedmanagementpointsoftheworkbreakdownstructure.Eachcontrolaccountmayincludeoneormoreworkpackages,buteachworkpackagemaybeassociatedwithonlyonecontrolaccount.

Each control account is associated with a specific single organizaonal component in theorganizaonalbreakdownstructure(BS).

AControlAccountisamajormanagementcontrolpointfor:

§ CostSummarizaon§ VarianceAnalysisandReporng§ ResponsibilityAssignment§ ScopeDescripon§ CorrecveAconPlanning

© 2009 CMCS FZCO

Page 11: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 11/56

ControlAccountMatrix

© 2009 CMCS FZCO

Page 12: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 12/56

ControlAccountDetails–BeforeUpdate

Page 13: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 13/56

ProjectAuthorizedBudget/TotalAllocatedBudget

© 2009 CMCS FZCO

Project Performance

0

5,000

10,00015,000

20,000

25,000

30,00035,000

40,000

45,000

50,000

55,00060,000

65,000

70,000

Jan- 07 F eb- 07 Mar -07 Apr -07 May -07 Jun- 07 Jul- 07 Aug- 07 Sep- 07 Oct- 07 N ov -07 Dec- 07

Time

       A       E       D

Planned

Management Reserve

Page 14: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 14/56

EarnedValue(EV)

Isthebudgetedamountoftheworkactuallycompletedonthescheduleacvityduringagivenmeperiod.

UsedtobeknownasBudgetCostofWorkPerformed(BCWP)orBudgetQuantyofWork

Performed(BQWP)

  EarnedValueCostisthemonetaryvalueoftheworkperformedbyaresourceasofthe

datadate.

  EarnedValueCost=BudgetatComple?onxPerformance%Complete

  Answerstheques?on:Howmuchworkisdone

© 2009 CMCS FZCO

Page 15: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 15/56

© 2009 CMCS FZCO

EarnedValue

Project Performance

0

5,000

10,00015,000

20,000

25,000

30,00035,000

40,000

45,000

50,000

55,00060,000

65,000

70,000

Jan- 07 F eb- 07 Mar -07 Apr -07 May -07 Jun- 07 Jul- 07 Aug- 07 Sep- 07 Oct- 07 Nov -07 Dec- 07

Time

       A       E       D

Planned Ear ned

Management Reserve

Page 16: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 16/56

ActualCost(AC)

Is the total cost incurred in accomplishingwork on the schedule acvityduring a givenmeperiod.

Used to be known as Actual Cost of Work Performed (ACWP) or Actual Quanty of Work

Performed(AQWP)

  ActualCostistheactualtotalcostincurredfortheworkaccomplishedasofthedatadate.

  ActualCost=ActualLaborCost+ActualNonlaborCost+ActualExpenseCost+Actual

MaterialCost

  Answerstheques?on:Howmuchdidthecompletedworkcost

© 2009 CMCS FZCO

Page 17: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 17/56

© 2009 CMCS FZCO

ActualCost(AC)

Project Performance

0

5,000

10,00015,000

20,000

25,000

30,00035,000

40,000

45,000

50,000

55,00060,000

65,000

70,000

Jan- 07 F eb- 07 Mar -07 Apr -07 May -07 Jun- 07 Jul- 07 Aug- 07 Sep- 07 Oct- 07 Nov -07 Dec- 07

Time

       A       E

       D

Planned Earned Actual

Management Reserve

Page 18: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 18/56

ControlAccountDetails–AOerUpdate

Page 19: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 19/56

PerformanceHistogram

© 2009 CMCS FZCO

Page 20: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 20/56

PerformanceManagementBaseline(PMB)

© 2009 CMCS FZCO

Page 21: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 21/56

PerformanceBarchart

© 2009 CMCS FZCO

Page 22: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 22/56

ScheduleVariance(SV)

Thedifferencebetweenthebudgetedcostofworkperformedand thebudgetedcostofworkscheduledatanypointinme.

SV=EV-PV

© 2009 CMCS FZCO

Page 23: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 23/56

© 2009 CMCS FZCO

ScheduleVariance

Project Performance

0

5,000

10,00015,000

20,000

25,000

30,00035,000

40,000

45,000

50,000

55,00060,000

65,000

70,000

Jan- 07 F eb- 07 Mar -07 Apr -07 May -07 Jun- 07 Jul- 07 Aug- 07 Sep- 07 Oct- 07 Nov -07 Dec- 07

Time

       A       E

       D

Planned Earned Actual

Management Reserve

SV = EV-PV

SV = 22,500 – 31, 500 = -9,000

Page 24: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 24/56

© 2009 CMCS FZCO

ScheduleVariance(SV)

Variances

-10,000

-9,000

-8,000

-7,000

-6,000

-5,000

-4,000

-3,000

-2,000

-1,000

0

Jan- 07 F eb- 07 Mar -07 Apr -07 May -07 Jun- 07 Jul- 07 Aug- 07 Sep- 07 Oct- 07 Nov -07 Dec- 07

Time

       A       E       D

SV

Page 25: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 25/56

SchedulePerformanceIndex(SPI)

Rao of work accomplished versus work planned, for a specified me period. The SPI is anefficiencyrangforworkaccomplishment,comparingworkaccomplishedtowhatshouldhave

beenaccomplished

SPI=EV/PV

© 2009 CMCS FZCO

Page 26: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 26/56

SchedulePerformanceIndex(SPI)

© 2009 CMCS FZCO

Project Performance

0

5,000

10,00015,000

20,000

25,000

30,00035,000

40,000

45,000

50,000

55,00060,000

65,000

70,000

Jan- 07 F eb- 07 Mar -07 Apr -07 May -07 Jun- 07 Jul- 07 Aug- 07 Sep- 07 Oct- 07 Nov -07 Dec- 07

Time

       A       E

       D

Planned Earned Actual

Management Reserve

SPI = EV/PV

SPI = 22,500 / 31, 500 = 0.71

Page 27: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 27/56

SchedulePerformanceIndex(SPI)

© 2009 CMCS FZCO

Indices

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

Jan- 07 Feb- 07 Mar -07 Apr -07 May -07 Jun- 07 Jul- 07 Aug-07 Sep-07 Oct- 07 Nov -07 Dec- 07

Time

         I       n         d

       e       x

SPI

Page 28: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 28/56

© 2009 CMCS FZCO

CostVariance(CV)

Thedifferencebetweentheearnedvalueandtheactualcost.

CV=EV-AC

Page 29: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 29/56

© 2009 CMCS FZCO

CostVariance(CV)

Variances

-10,000

-8,000

-6,000

-4,000

-2,000

0

2,000

4,000

6,000

Jan- 07 F eb- 07 Mar -07 Apr -07 May -07 Jun- 07 Jul- 07 Aug- 07 Sep- 07 Oct- 07 Nov -07 Dec- 07

Time

       A       E       D

SV CV

Page 30: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 30/56

© 2009 CMCS FZCO

CostPerformanceIndex(CPI)

Raoofworkaccomplishedversusworkcostincurredforaspecifiedmeperiod.TheCPIisan

efficiencyrangforworkaccomplishedforresourcesexpended.

CPI=EV/AC

Page 31: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 31/56

© 2009 CMCS FZCO

CostPerformanceIndex(CPI)

Indices

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

Jan- 07 Feb- 07 Mar -07 Apr -07 May -07 Jun-07 Jul- 07 Aug- 07 Sep- 07 Oct- 07 Nov -07 Dec- 07

Time

         I       n

         d       e       x

SPI CPI

Page 32: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 32/56

PerformanceIndex

© 2009 CMCS FZCO

Page 33: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 33/56

© 2009 CMCS FZCO

EVMeasuresandIndices

SV > 0 & SPI > 1.0 SV = 0 & SPI = 1.0 SV < 0 & SPI < 1.0

CV > 0 &

CPI > 1.0

Ahead of Schedule

Under Budget

On Schedule Under 

Budget

Behind Schedule

Under Budget

CV = 0 &

CPI = 1.0

Ahead of Schedule

On Budget

On Schedule On

Budget

Behind Schedule On

Budget

CV < 0 &

CPI < 1.0

Ahead of Schedule

Over Budget

On Schedule Over 

Budget

Behind Schedule

Over Budget

SchedulePerformance

Measures

Cost

Page 34: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 34/56

EsmateToComplete(ETC)

Theesmatetocompletetheremainingworkforanacvity,workpackageorcontrolaccount.

ETC=BAC-EV

© 2009 CMCS FZCO

Page 35: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 35/56

© 2009 CMCS FZCO

EsmateToComplete(ETC)

Project Performance

0

5,000

10,00015,000

20,000

25,000

30,00035,000

40,000

45,000

50,000

55,00060,000

65,000

70,000

Jan- 07 F eb- 07 Mar -07 Apr -07 May -07 Jun- 07 Jul- 07 Aug- 07 Sep- 07 Oct- 07 Nov -07 Dec- 07

Time

       A

       E       D

Planned Earned Actual

Management Reserve

ETC = BAC – EVETC = 65,000 – 22,500

ETC = 42,500

Page 36: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 36/56

FuturePerformance

Future performance may be

different to current

performance

Proactive measures are

taken to recover variances

Nature of future work isdifferent to completed

work

Completed work includes

learning that will not applyto future work

Future activities are easier or 

more difficult than completed

activities

Completed work includes

non-recurring elements

Page 37: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 37/56

© 2009 CMCS FZCO

HowToReflectFuturePerformanceUsingETCCalculaon

ETCwillnotbeinfluencedbypastprojectperformance-pmisc

§  ETC=(BAC-EV)

ETCwillbeinfluencedbyfactorsofpastcostperformance–MostLikely

§  ETC=(BAC-EV)/CPI

ETCwillbeinfluencedbypastcostandscheduleperformance-Pessimisc

§ ETC=(BAC-EV)/(CPIXSPI)

Page 38: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 38/56

© 2009 CMCS FZCO

EsmateAtCompleon(EAC)

Thecostoftheamountofworktocompletescheduleacvies.Itisaforecastofthemostlikely

totalvaluebasedonprojectperformanceandriskquanficaon.

EAC=AC+ETC

Page 39: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 39/56

© 2009 CMCS FZCO

EsmateAtCompleon(EAC)

Project Performance

0

5,000

10,00015,000

20,000

25,000

30,00035,000

40,000

45,000

50,000

55,00060,000

65,000

70,000

Jan- 07 F eb- 07 Mar -07 Apr -07 May -07 Jun- 07 Jul- 07 Aug- 07 Sep- 07 Oct- 07 Nov -07 Dec- 07

Time

       A

       E       D

Planned Earned Actual

Management Reserve

EAC = AC + ETCEAC =18,000 – 42,500

EAC = 60,500

Page 40: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 40/56

© 2009 CMCS FZCO

VarianceAtCompleon(VAC)

Thevariancebetweenbudgetandesmateatcompleon.

VAC=BAC–EAC

AlsoknownasVariance(VAR)

( )

Page 41: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 41/56

© 2009 CMCS FZCO

VarianceAtCompleon(VAC)

Project Performance

0

5,000

10,00015,000

20,000

25,000

30,00035,000

40,000

45,000

50,000

55,00060,000

65,000

70,000

Jan- 07 F eb- 07 Mar -07 Apr -07 May -07 Jun- 07 Jul- 07 Aug- 07 Sep- 07 Oct- 07 Nov -07 Dec- 07

Time

       A

       E       D

Planned Earned Actual

Management Reserve

VAC = BAC - EACVAC =65,000 – 60,500

VAC = 4,500

E d V l P f Hi

Page 42: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 42/56

EarnedValuePerformanceHistogram

©2009CMCSFZCO

Planned

Actual

     I    n     $     1 ,     0

     0     0     ’    s

BudgetatCompleon(BAC)

1 2 3 4 5 6 7 8 9 10

Months

     T    a    r    g    e    t     C    o    m    p     l    e         o    n

     D    a    t    e

     C    u    r    r    e    n    t     C    o    m    p     l    e         o    n

     D    a    t    e

200

400

600

800

1000

1200

11

1300

Planned=$500K:DataDate

Actual=$400K

200

400

600

800

1000

12001300

ProbableScheduleDelay=4weeks

Probable

Cost

verrun

=$300K

EsmateatCompleon(EAC)

CostVariance-$100K

Schedule

Variance(Time)

-4wks

ScheduleVariance($)

-$200K

Earned

Earned=$300K

Page 43: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 43/56

HowtheMonteCarlosimulaoncanprovidethepredicted

esmatetocompleteatdifferentconfidencelevels

© 2009 CMCS FZCO

E port Control Acco nt Details To XLS Template

Page 44: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 44/56

ExportControlAccountDetailsToXLSTemplate

Project Risk Categories

Page 45: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 45/56

ProjectRiskCategories

© 2009 CMCS FZCO

Risk

Technical

Higherperformance

goalsTechnologyshis

PlaormchangesNewindustrystandards

Complextechnology

Unproventechnology

ProjectManagement

Schedule Budget

Quality Scope

Resources Projectteam

Communica?on

Organiza?onal

Weakinfrastructure

Unclearorganiza?onalobjec?ves

Intra-organiza?onal

resourceconflicts

Shiingfundingavailability

External

Legalchallenges

Shiingcustomergoals

Naturaldisasters

Legalshis

Impact f Risk n Project bjecves

Page 46: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 46/56

ImpactfRisknProjectbjecves

RISK ITEM

CONTRACTOR

PROVIDES

DEFECTIVE

SERVICE

IMPACT

ON

SAFETY

IMPACT

ON

TEAM

WORKING

IMPACT

ON

QUALITY

IMPACT

ON

COST

IMPACT

ONTIME

© 2009 CMCS FZCO

Risk Impact Scales n Four Major Project bjecves

Page 47: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 47/56

RiskImpactScalesnFourMajorProjectbjecves

How Does Monte Carlo Simulaon Works?

Page 48: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 48/56

© 2007 CMCS FZCO 48

HowDoesMonteCarloSimulaonWorks?

Import Control Account With ETC Value To Risk Simulaon SoOware

Page 49: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 49/56

ImportControlAccountWithETCValueToRiskSimulaonSoOware

The imported values in Acumen Risk with Uncertainty

Page 50: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 50/56

TheimportedvaluesinAcumenRiskwithUncertainty

MonteCarloSimulaon

Page 51: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 51/56

Monte Carlo Simulaon

80%confidencechartforEAC

Page 52: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 52/56

Thetornadoandotherriskcharts

Page 53: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 53/56

Thetornadoandotherriskchartsforeachcontrolaccount

Page 54: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 54/56

Thetornadoandotherriskcharts

Page 55: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

7/29/2019 Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013

http://slidepdf.com/reader/full/integrating-risk-management-and-performance-management-by-bassam-samman- 55/56

Page 56: Integrating Risk Management and Performance Management- By Bassam Samman - iCompetences PPM2013