interlock and protection systems for sc accelerators: machine protection system for the lhc
DESCRIPTION
The Risks The Challenge The LHC Layout The Systems for Protection The Glue The impact of LHC Machine Protection has been recently discussed at the LHC Workshop in Chamonix 15-19 January, and I will use some of the material that has been presented - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/1.jpg)
Interlock and Protection Systems for SC Accelerators:Machine Protection System for the LHC
The Risks The Challenge The LHC Layout The Systems for Protection The Glue
The impact of LHC Machine Protection has been recently discussed at the LHC Workshop in Chamonix 15-19 January, and I will use some of the material that has been presented
(contributions from O.Brüning, H.Burkhardt, E.Carlier, H.Mess, R.Lauckner, M.Lomperski, F.Rodriguez-Mateos)
R.Schmidt - Villars 30/01/2001
![Page 2: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/2.jpg)
p. 230/01/2001 R.Schmidt, Villars
Energy in two LHC Beams: 700 MJ
– Two systems, one for each beam
Energy in dipole magnets (one sector): 1.3 GJ– Eight systems in the LHC
Energy in quadrupole magnets (one sector): 40 MJ – Sixteen systems in the LHC
Energy in 600 A circuits (i.e. chromaticity correction): 10-100 kJ– Some 100 systems
In total about 11 GJ
50 tons at 600 km/h = heating + melting of 950 kg copper
180 kg at 40-120 km/h
3 * 10000 kg at 200 km/h
The Risks: Energy in Magnets and Beams
![Page 3: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/3.jpg)
p. 330/01/2001 R.Schmidt, Villars
LHC magnets operate at 1.9 K - Little enthalpy - Temperature margin about 1.4 K
Nominal beam intensity : 3 * 1014 Protons / beam
Energy at 7 TeV to quench a dipole magnet corresponds to about 10 7 Protons
Energy at 450 GeV to quench a dipole magnet corresponds to about 10 9 Protons
Energy to quench a superconducting dipole magnet is small
First beam tests with one bunch, very low intensity, below quench threshold
Beam Monitors must work for such parameters
![Page 4: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/4.jpg)
p. 430/01/2001 R.Schmidt, Villars
The beam can leave in a very short time….
Beam energy
Magnet energy
SPS + RF
EDF via PC
LHC Experiments (10 hours)Collimation System (10 hours)Magnets / Cryogenics (10 hours)LHC BEAM DUMPS (2 Systems) 89 micro.seconds
Back to PC (20 min)Magnets / Cryogenics(some 100 ms for quench)LHC POWER DUMPSsome 100 systems(2 min)
Time constants: 23 micro.sec 20 minutes Time constants: 10 hours 89 micro.sec
Time constants: 20 minutes
BEAM DUMPTRIGGER
- Published in Chamonix 20001 Workshop - (O.Brüning)
Power trip of power converter for D1 warm separation magnet– in collision the beam would start to suffer after 5 turns (2 mm orbit displacement)
Wrong functioning of the damper for injection oscillations and instabilities– at injection energy the beam would start to suffer after 6 turns
Power trip of power converter for one of the warm quadrupoles in the collimation section– in collision the beam would start to suffer after 18 turns
Quench of one main dipole magnet– in collision the beam would start to suffer after 280 turns
![Page 5: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/5.jpg)
The energy in the LHC magnet system corresponds to about 20000 tons of snow, sliding down by about about 600 m
…….the bad news: an energy release can be easily triggered by some innocent (ski)-operator
…… the good news: LHC operators are far away from the LHC tunnel
![Page 6: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/6.jpg)
The LHC machine need protection systems, but….
Machine Protection is not an objective in itself, it is to
maximise operational availability by minimising down-time (quench, repairs) avoid expensive repair of equipment and irreparable damage
Side effects from LHC Machine Protection System compromising
operational efficiency must be minimised
operational availability versus equipment safety
0
10
20
30
40
50
60
70
80
90
100
0 1 0 2 0 3 0 4 0 5 0 6 0 7 0 8 0 9 0 1 00
machine safety
op
eratio
nal availab
ilit
y [
%]
Downtime dominated by too complex Protection Systems
Downtime for repairs due to insufficient protection systems
![Page 7: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/7.jpg)
p. 730/01/2001 R.Schmidt, Villars
LHC Machine Protection is to...
Prevent an uncontrolled release of stored energy, thus avoiding: damage of equipment unnecessary down-time - example: BEAM DUMP to avoid quenches
and will include: tools for consistent error and fault tracing ……. POST MORTEM
Related topic:– access and interlock system to protect people is separate system, however, there are links between the access system and
the machine protection
![Page 8: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/8.jpg)
Sector
Continuous Cryostat/Cryoline Superconducting bus-bars runthrough cryostat connecting magnets.Current feeds at extreme ends.
Other central insertion elementseg. Low Betas, separator dipoles, matching
COLD (<2K) 2.9km
WARM500m
1
5
DC Power feed
3
Oct
ant
DC Power
Main Arc FODO cellscontaining; main dipoles andquadrupoles, chromaticity sextupoles, octupoles, tuning and skew quadrupoles, spool pieces,orbit correctors
End of Continuous Cryostatcontaining; dispersion suppressors,Some of the matching section, and the electrical feedbox.
2
4 6
8
7LHC27 km Circumference
LHC is divided into 8 Sectors
Slide from P.Proudlock
![Page 9: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/9.jpg)
p. 930/01/2001 R.Schmidt, Villars
LHC Machine Protection = Integration of systems
The interlocks deal with the integration of systems into the LHC MACHINE PROTECTION SYSTEM,……, with the glue that links systems such as:
BEAM DUMP SYSTEM BEAM LOSS MONITOR SYSTEM QUENCH PROTECTION and POWERING SYSTEM BEAM CLEANING SYSTEM (two long straight section for collimators) Access, RF, Vacuum, Collimators, Warm magnets, Experiments, ….
and an architecture of the MACHINE INTERLOCK SYSTEM is required
![Page 10: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/10.jpg)
p. 1030/01/2001 R.Schmidt, Villars
They “lazy” approach …can we copy another system ?
FERMILAB - TEVATRON operates since more than 15 years DESY - HERA operates since more than10 years BNL - RHIC operates since less than 2 years (evolution of FERMILAB system)
=> No major accidents during operation
LHC is specific: energy much larger many more components powering of the machine in sectors very different from other machines time constants involved together with energy require different solutions
After visits to FERMILAB, BNL, and DESY (…+ K.H.Mess - associate from DESY here for one year) a systems is proposed with an different architecture, but with using some ideas from BNL and HERA
![Page 11: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/11.jpg)
p. 1130/01/2001 R.Schmidt, Villars
With respect to BEAM OPERATION: Energy stored in beams
Fault detected => BEAM ABORT, beam is directed into BEAM DUMP BLOCK
Two systems - one BEAM DUMP SYSTEM for each beam
With respect to POWERING: Energy stored in magnets of one cryostat:
Fault detected => POWER ABORT, and most of the magnetic energy is dumped into ENERGY EXTRACATION RESISTORS
four large such systems for each sector - 2 for MB, 1 for QF, 1 for QD (in total 32) some hundred smaller (600 A) systems around the LHC
Electrical circuits in one continuous cryostat independent from circuits in other cryostats
String II - Commissioning of Power and Magnet Interlock System soon
Separation of POWER ABORT and BEAM ABORT
![Page 12: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/12.jpg)
p. 1230/01/2001 R.Schmidt, Villars
Architecture of Power Permit in one LHC sector
LHC-B T Q4D2 Q5 Arc Q4D2 T Atlas
DFBX DFBM DFBM DFBA DFBA DFBM DFBX
QP
PPC
PC
QP
18
Slide from K.H.Mess
![Page 13: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/13.jpg)
Architecture of BEAM PERMIT in the LHC
Pt.1
Pt.2
Pt.3
Pt.4
Pt.5
Pt.6
Pt.7
Pt.8ATLAS
CMS
LHC-BALICE
Momentumcleaning
RFBeam Dump
Betatroncleaning
BEAM 1clockwise
BEAM 2counter-clockwise
InjectionBEAM II from SPS
InjectionBEAM I from SPS
BEAM DUMPCONTROLLERS
Beam Permit Loopsoptical fibre at 10 MHz
BPC
BPC
BPC
BPC
BPC
BPC
BPCBPCBPC BPC
BPCBPCBPCBPC BPC
BPC
BPC
BPC
BPC
BPC
BPC
BPC
![Page 14: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/14.jpg)
BEAM PERMIT CONTROLLER
p. 14
Timing system
power in from UPS
BEAM PERMITCONTROLLER
ALL CIRCUITS OK
Link to Control system
BEAM PERMIT LOOPS
CRITICAL CIRCUITS OK
PPC arc cryostat
PPC triplet cryostat
PPC Q3 cryostat
PPC Q4 cryostat
PPC Q6 cryostat
PPC Q4D2 cryostat
Signals fromCRYOSTATPOWER PERMIT CONTROLLERS
Signals fromsubsystems to give BEAM PERMISSIONand ABORT
Machine Status
Other systemsBeam LossAccessExperimentsVacuumRFBEAM DUMPInjectionWarm magnets
![Page 15: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/15.jpg)
p. 1530/01/2001 R.Schmidt, Villars
With respect to POWERING
CIRCUITS connecting magnets with LARGE amount of stored energyQuenches propagate to magnets in other circuits
=> All power in continuous cryostat will be switched off after detecting a quench
CIRCUITS connecting magnets with SMALL amount of stored energy=> In the (unlikely) case of a quench, only the corresponding circuit is de-excited
With respect to BEAM OPERATION
CIRCUITS that are very critical for operation with beam Fault always causes total beam loss
=> In case of a fault - always BEAM DUMP
CIRCUITS that are less critical for operation with beamFault might cause beam losses, depending on machine status: energy, beam intensity..
=> In case of fault - BEAM DUMP IF ……other conditions are met / not met
Classification of electrical circuits
![Page 16: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/16.jpg)
BEAM PERMIT / ABORT for the entire LHC accelerator– Fast system - the beam can be dumped in a few turns
– BEAM PERMIT CONTROLLERS (BPC) linked via optical fibres with 10 MHz signal (fast data
transmission)– Absence of BEAM PERMIT triggers BEAM DUMP– 16 BEAM PERMIT CONTROLLERS are required– Input from variety of systems, such as powering and protection, access, BLM, vacuum, and others
POWER PERMIT / ABORT for each continuous cryostat– System is less fast, the power is extracted in several seconds– Impact beams after some 10 ms - therefore more time to react
– About 48 POWER PERMIT CONTROLLERS (PPC) are required, one per cryostat (two for long arc cryostat)
– Links in tunnel could be via current loop and non-critical communication between controllers via control system
Some Parameters of the Protection Systems
![Page 17: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/17.jpg)
p. 1730/01/2001 R.Schmidt, Villars p. 17
sector
alcove
IP
Quench loop (current loop)
Power converter
Power status link possibly via WORLD FIP
HEATER ACTIVATION Link
BEAM PERMIT LOOPS (one for each beam)
IP
Orbit corrector link (possibly via WORLD FIP)
BPC
Quenchdetector
PMC
Heater powersupply
severalPPC
Inputs fromother systems
Power converter
Heater powersupply
Quenchdetector
BPC PMCseveralPPC PMC
alcove
PMC BPC PMCseveralPPC
Inputs fromother systems
BPC PMCseveralPPC
Post Mortem Link
a c c e l e r a t o r t u n n e l
Information links for Machine Protection System
![Page 18: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/18.jpg)
p. 1830/01/2001 R.Schmidt, Villars
Beam loss due to trip of power converter for orbit corrector
0
5 00
1 000
1 5 00
2 000
2 5 00
3 000
3 5 00
4 000
0.00 20.00 40.00 60.00 80.00 100.00
time [ms]
beam position
helium temperature
corrector current
beam current
radiation monitors
quench signal
beam abort
Post Mortem Diagnostics MUST be a part of the system- Artist view of the requirement
![Page 19: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/19.jpg)
p. 1930/01/2001 R.Schmidt, Villars
Summary of architecture for the machine protection
General Separation of BEAM PERMIT and POWER PERMIT Separation of POWER PERMITS for cryostats - one (two for arcs) PPC per cryostat Diagnostics after fault is integral part of the system
Classification of Electrical Circuits Powering: Main circuits (CRYOSTAT POWER ABORT) and auxiliary circuits (CRYOSTAT POWER
FAULT) Beam Operation: CRITICAL CIRCUITS and LESS CRITICAL CIRCUITS
Inventory About 60 electronics crates Two fast links for BEAM ABORT with optical fibres (plus some reserve fibres) Several slower links for POWER ABORT, possibly using current loops Fail-safe links, and input signals to electronics
![Page 20: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/20.jpg)
p. 2030/01/2001 R.Schmidt, Villars
Outlook
Require POWER PERMIT CONTROLLER for first sector (octant) test in 2004– Functional Specification for Summer 2001– Start development of hardware by this Summer
Require full functionality of BEAM PERMIT CONTROLLER for 2006– Functional Specification for End of 2001– Possibly reduced functionality for 2004 (injection test)
POST MORTEM Facilities to be defined– Some definitions BEFORE electronics development starts– Unique CLOCK required
How to use beam loss monitor systems to request BEAM DUMP?– Studies continuing...
![Page 21: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/21.jpg)
p. 2130/01/2001 R.Schmidt, Villars
With respect to BEAM OPERATION
Energy stored in beams to be safely deposited with BEAM DUMP SYSTEM
BEAM ABORT - POWER ABORT
Beam energy
Magnet energy
SPS + RF
EDF via PC
LHC Experiments (10 hours)Collimation System (10 hours)Magnets / Cryogenics (10 hours)LHC BEAM DUMPS (2 Systems) 89 micro.seconds
Back to PC (20 min)Magnets / Cryogenics(some 100 ms for quench)LHC POWER DUMPSsome 100 systems(2 min)
Time constants: 23 micro.sec 20 minutes Time constants: 10 hours 89 micro.sec
Time constants: 20 minutes
BEAM DUMPTRIGGER
With respect to POWERING
Energy stored in magnets to be safely deposited with POWER DUMP SYSTEM
Both systems are largely independent
No signals from BEAM DUMP SYSTEM to POWER DUMP SYSTEM Signal from POWER DUMP SYSTEM to BEAM DUMP SYSTEM in case of power fault
Beam energy
SPS + RF
EDF via PCLHC Experiments (10 hours)
Collimation System (10 hours)
Magnets/Cryogenics (10 hours)
LHC BEAM DUMPS (2 Systems) 89 micro.seconds
Back to PC (20 min)
Magnets / Cryogenics(some 100 ms for quench)
LHC POWER DUMPSsome 100 systems(2 min)
Time constants: 10 hours 89 micro.sec
BEAM DUMPTRIGGER
Magnet energy
![Page 22: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/22.jpg)
p. 22
Timing system
power from UPS
Link to Control system
Main circuitQuench detectors
Cryostat POWER ABORT
Correctorpower converter
DischargeSwitch
Main MBpower converter
DISCHARGESWITCH MB
Quench detectorlocal
selected HEATERfire Trigger
DischargeSwitch OpenFault
HEATER ACTIVATION LINK
CircuitStatusCircuit Status
power from UPS
CryoOK
Post Mortem trigger
Up to 40 ofsuch circuits
Up to 40 ofsuch circuits
AccessOK
PC Fault
AccessOK
PC PERMIT
PC FaultCircuitStatusCircuit Status
Correctorpower converter Circuit Status
Quench Loop
CircuitStatusCircuit Status
PC Fault
AccessOK
Discharge Request
PC FaultCircuitStatusCircuit Status
CircuitStatus
Circuit Status
Quench Loop
MQF MQD
MQF MQD
Main circuitQuench detectors
Cryostat POWER ABORT
DISCHARGESWITCH MB
DischargeSwitch Trigger
selected HEATERfire Trigger
PC FaultCircuitStatusCircuit Status
CircuitStatus
Circuit Status
Quench Loop
Quench detectors
Quench detectorlocal
Quench LoopQuench detectors
Circuit Status
Circuit Status
Interface toBEAM PERMITCONTROLLER
POWER PERMITControllerodd point
Interface toBEAM PERMITCONTROLLER
DischargeSwitch Trigger
DischargeSwitch OpenFault
POWER PERMITController even point
PC FAST ABORT
PC FAST ABORT
PC PERMIT
ProtectionOK
Timing system
Link to Control system
CryoOK
Post Mortem trigger
AccessOK
ProtectionOK
Main circuitQuench detectors
Heater Power supplies
CRITICAL CIRCUITS OK
ALL CIRCUITSOK
BEAM PERMITCONTROLLER
CRITICAL CIRCUITS OK
ALL CIRCUITSOK
BEAM PERMITCONTROLLER
Sector left part Sector right part
PC SLOW ABORT
PC Fault
AccessOK
PC PERMIT
PC FAST ABORT
PC SLOW ABORT
PC SLOW ABORT
MQMpower converter
PC Fault
AccessOK
PC FAST ABORT
PC PERMIT
PC SLOW ABORT
Correctorpower converter
DischargeSwitch
Quench detectorlocal
Up to 40 ofsuch circuits
Up to 40 ofsuch circuits
PC Fault
AccessOK
PC PERMIT
Correctorpower converter
Quench LoopQuench detectors
Quench detectorlocal
Quench LoopQuench detectors
PC FAST ABORT
PC SLOW ABORT
PC Fault
AccessOK
PC PERMIT
PC FAST ABORT
PC SLOW ABORT
MQMpower converter
PC Fault
AccessOK
PC FAST ABORT
PC PERMIT
PC SLOW ABORT
Tunnel
![Page 23: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/23.jpg)
p. 23
Timing system
power from UPS
Link to Control system
Main circuitQuench detectors
Cryostat POWER ABORT
Correctorpower converter
DischargeSwitch
Main MBpower converter
DISCHARGESWITCH MB
Quench detectorlocal
selected HEATERfire Trigger
DischargeSwitch OpenFault
HEATER ACTIVATION LINK
CircuitStatusCircuit Status
CryoOK
Post Mortem trigger
Up to 40 ofsuch circuits
Up to 40 ofsuch circuits
AccessOK
PC Fault
AccessOK
PC PERMIT
PC FaultCircuitStatusCircuit Status
Correctorpower converter Circuit Status
Quench Loop
CircuitStatusCircuit Status
PC Fault
AccessOK
Discharge Request
PC FaultCircuitStatusCircuit Status
CircuitStatus
Circuit Status
Quench Loop
MQF MQD
MQF MQD
Quench detectors
Quench detectorlocal
Quench LoopQuench detectors
Interface toBEAM PERMITCONTROLLER
DischargeSwitch Trigger
POWER PERMITController even point
PC FAST ABORT
PC FAST ABORT
PC PERMIT
ProtectionOK
Main circuitQuench detectors
CRITICAL CIRCUITS OK
ALL CIRCUITSOK
BEAM PERMITCONTROLLER
Sector left part
PC SLOW ABORT
PC Fault
AccessOK
PC PERMIT
PC FAST ABORT
PC SLOW ABORT
PC SLOW ABORT
MQMpower converter
PC Fault
AccessOK
PC FAST ABORT
PC PERMIT
PC SLOW ABORT
![Page 24: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/24.jpg)
p. 2430/01/2001 R.Schmidt, Villars
Interfaces between BPC and PPC to other systems
POWER PERMIT CONTROLLERS
Interfaces for Interlocks Power Converters Quench Protection System Cryogenic System Access System Beam Permit System
Interfaces for Services Control System Timing System Power Supply for electronics Post Mortem System
BEAM PERMIT CONTROLLERS
Interfaces for Interlocks POWER PERMIT CONTROLLERS Beam Loss Monitors and other BI Beam Dump System Collimators RF System Vacuum System Experiments Injection System Access System
Interfaces for Services Control System Timing System Power Supply for electronics Machine Status (Energy, Current, ..) Post Mortem System
![Page 25: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/25.jpg)
p. 2530/01/2001 R.Schmidt, Villars
….and what concerns the interface between Machine Protection and LHC Experiments
Next Milestone - 2004 - the Experiments will not be concerned, however, since time passes….
Risk analysis for the experiments– How could large fraction of the beam hit the experiments? – What would be the consequence?– How to avoid such accidents?
BEAM ABORT signals from the experiments– One BEAM ABORT stops the LHC for at least 2 hours
Hardware interfaces - what signals should be exchanged?
Initially one representative for all 4 experiments could follow discussions on Machine Protection. For specific topics, other representatives from the experiments could attend. To be re-considered at a later date.
![Page 26: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/26.jpg)
Timing system
power from UPS
Link to Control system
Main circuitQuench detectors
Cryostat POWER ABORT
Correctorpower converter
DischargeSwitch
Main MBpower converter
DISCHARGESWITCH MB
Quench detectorlocal
selected HEATERfire Trigger
DischargeSwitch OpenFault
HEATER ACTIVATION LINK
CircuitStatusCircuit Status
CryoOK
Post Mortem trigger
Up to 40 ofsuch circuits
Up to 40 ofsuch circuits
AccessOK
PC Fault
AccessOK
PC PERMIT
PC FaultCircuitStatusCircuit Status
Correctorpower converter Circuit Status
Quench Loop
CircuitStatusCircuit Status
PC Fault
AccessOK
Discharge Request
PC FaultCircuitStatusCircuit Status
CircuitStatus
Circuit Status
Quench Loop
MQF MQD
MQF MQD
Quench detectors
Quench detectorlocal
Quench LoopQuench detectors
Interface toBEAM PERMITCONTROLLER
DischargeSwitch Trigger
POWER PERMITController even point
PC FAST ABORT
PC FAST ABORT
PC PERMIT
ProtectionOK
CableWaterOK(to be discussed)
Main circuitQuench detectors
CRITICAL CIRCUITS OK
ALL CIRCUITSOK
BEAM PERMITCONTROLLER
Sector left part
PC SLOW ABORT
PC Fault
AccessOK
PC PERMIT
PC FAST ABORT
PC SLOW ABORT
PC SLOW ABORT
MQMpower converter
PC Fault
AccessOK
PC FAST ABORT
PC PERMIT
PC SLOW ABORT
p. 26
![Page 27: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/27.jpg)
BEAM PERMIT CONTROLLERChannel Name Conditional Bit pattern Nr
0 RF system YES 0 0 0 0 0 01 Beam Loss monitors I YES 0 0 0 0 1 12 Beam Loss monitors II YES 0 0 0 1 0 23 Beam excursion (?) YES 0 0 0 1 1 34 arc cryostat - ALL CIRCUITS OK YES 0 0 1 0 0 45 triplet cryostat - ALL CIRCUITS OK YES 0 0 1 0 1 56 Q3 cryostat - ALL CIRCUITS OK YES 0 0 1 1 0 67 Q4 cryostat - ALL CIRCUITS OK YES 0 0 1 1 1 78 Q5 cryostat - ALL CIRCUITS OK YES 0 1 0 0 0 89 Q6 cryostat - ALL CIRCUITS OK YES 0 1 0 0 1 9
10 Q4D2 cryostat - ALL CIRCUITS OK YES 0 1 0 1 0 1011 spare YES 0 1 0 1 1 1112 spare YES 0 1 1 0 0 1213 spare YES 0 1 1 0 1 1314 spare YES 0 1 1 1 0 1415 spare YES 0 1 1 1 1 1516 Experiments NO 1 0 0 0 0 1617 Warm magnets NO 1 0 0 0 1 1718 Access system NO 1 0 0 1 0 1819 Extraction system NO 1 0 0 1 1 1920 arc cryostat - CRITICAL CIRCUITS OK NO 1 0 1 0 0 2021 triplet cryostat - CRITICAL CIRCUITS OK NO 1 0 1 0 1 2122 Q3 cryostat - CRITICAL CIRCUITS OK NO 1 0 1 1 0 2223 Q4 cryostat - CRITICAL CIRCUITS OK NO 1 0 1 1 1 2324 Q5 cryostat - CRITICAL CIRCUITS OK NO 1 1 0 0 0 2425 Q6 cryostat - CRITICAL CIRCUITS OK NO 1 1 0 0 1 2526 Q4D2 cryostat - CRITICAL CIRCUITS OK NO 1 1 0 1 0 2627 Collimators NO 1 1 0 1 1 2728 Beam Loss monitors at collimators NO 1 1 1 0 0 2829 Vacuum valves beam I NO 1 1 1 0 1 2930 Vacuum valves beam II NO 1 1 1 1 0 3031 spare NO 1 1 1 1 1 31 p. 27
![Page 28: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/28.jpg)
p. 2830/01/2001 R.Schmidt, Villars
How fast does the beam has to be dumped?
Quench in one MB magnet at top current– massive quench in a dipole magnet due to beam loss would lead to an orbit change of 2 mm in 20 ms (see EXCEL
calculation), assuming beta = 100 m - beam dump in the order of 10 ms. Quench in other magnets
– quadrupole quenches lead to betratron tune change
– sextupole quenches lead to change of chromaticity - beam loss and instabilities Loss of RF - de-bunching of the beam
– action in some hundred milliseconds Access door forced or emergency button pushed
– less than one second Beam loss monitor indicates too large losses
– assuming integration time of 5 ms, activation of the beam dump should be in the order of 1 ms Experiments dump the beam - to be discussed with the experiments Main Power converter failure
– depends on the power converter, but a fast action before the current decays substantially would always make sure that the beam is lost in a controlled way
Other systems (cryogenics, vacuum, …) - to be discussed
![Page 29: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/29.jpg)
p. 2930/01/2001 R.Schmidt, Villars
Example for Classification
All main circuits are considered to be critical The final list of critical circuits will be established (much) later, and could be
modified during LHC beam operation
Classification of some electrical circuits in continuous arc cryostat
PRELIMINARY !
Name Description Main circuit Critical circuitCryostat POWER ABORT
Unconditional BEAM ABORT
MB Main dipoles YES YESMQ Main quadrupole YES YES
MQM Matching quadrupoles YES YESMS Chromaticity sextupoles NO YES
MQTL Tuning quadrupoles, long depends dependsMQT Tuning quadrupoles, short NO dependsMCS "Spool piece" sextupoles NO NOMCD "Spool piece" decapoles NO NOMCO "Spool piece" octupoles NO NOMO Octupoles NO NO
MCB Orbit corrector dipoles NO NO
![Page 30: Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC](https://reader036.vdocument.in/reader036/viewer/2022062308/56812f90550346895d950d6b/html5/thumbnails/30.jpg)
– Enable: A system that allows to switch on (equipment interlock system)- power converters- beam injection enable- other systems and test modes - to be defined
this is in general not time critical and includes many systems (eg. Cryogenics)
– A system that stops beam - BEAM ABORT- beam dumps (as fast as technical possible - see Oliver)
this is VERY time critical and must be fail safe, and includes less systems
– A system that stops power - POWER ABORT- fire quench protection heaters (local action) - act on power converter (10ms - 1s)- open energy extraction switches (10ms - 1s)- discharge circuits (time constants between 1 and 104 seconds)
this is time critical and must be fail-safe (failure could lead to heavy equipment damage)
– A system recording the data for post-mortem analysis of any ABORT- Clear diagnostics (example - get info MB 112 in sector 5 quenched)
Three-Fold Functionality
p. 30