introduction of concerto as information system in larsen & toubro

Upload: nikhil-rathod

Post on 07-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    1/22

    2007 Realization Technologies, Inc. All Rights Reserved. 1

    Introduction of Concerto as Information

    System in Larsen & Toubro.

    By : Group 9Swarup Saha 80118110095Nikhil Rathod 80118110092Tapan Sangvi 80118110097Shashank Saraf 80118110098SANJAY Khambe 80118110048

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    2/22

    The Information System: Concerto

    2

    A project planning software

    Its a latest technology in the field of project management.

    Used globally to efficiently manage projects.

    Its a product of Realization Inc.

    Realization was founded in 1999 to help organizations around

    the world execute projects efficiently and faster so that they

    can more fully realize their potential.

    Works in multi project environment.

    This system is based on Dr.E M Goldratts Theory of

    Constrain principle. Realizations system was bourn out of book called Critical

    Chain by Dr. E.M Goldratt.

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    3/22

    Case Study: Introducing Concerto in L&T

    3

    Concerto was introduced in Larsen & Toubro as a project

    management tool in 2004. Larsen & Toubro Heavy Engg div introduced this. L&T HED designs and manufacture customized products for

    Oil and Gas Industry. Every project its manufactures is unique in nature.

    It has unique project start date : ZERO DATE And an unique Contractual Delivery Date :CDD L&T HED has three manufacturing centre: Powai, Baroda &

    Surat. It has more than six SBUs with separate order booking

    All the orders are executed in these three commonManufacturing Center. Clash of priority, non availability of resources, Improper scheduling of projects in multi project environment. Resulting into delay in all the projects and LD

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    4/22

    Change Management: Introduction of the new IS into anold system.

    4

    A very new concept in project management.

    Old systems were running through decades. No proper training and clear road map for implementation. Faces huge flack at the beginning. People reluctant to use this tool effectively because of

    ignorance.

    No synchronization between planning through concerto andactual working schedule in shop.

    But top management was adamant to implement this at any

    cost . This created a catchy or chaotic situation in the production

    shops resulting in to various conflicts among projectmanagers. It took almost 5-6 years to implement this across various

    production centers with a centralized Concerto Planning

    Server.

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    5/22

    5

    Two Concepts on which Concerto works: Critical Chain &TOC

    Day 0:

    Critical Chain is the longest chain ofresource AND taskdependencies in a project

    T1 T2 T3

    T5

    T4 PB

    T7T6 FB

    X, 10d X, 10d X, 10d X, 10d

    X, 10d

    10dY, 10dY, 10d

    25d

    Critical Chain

    Feeding Chain

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    6/22

    Concepts on which Concerto works: Critical Chain & TOC

    6

    Theory of Constraints (TOC) is an overallmanagement philosophy introduced by Dr.

    Eliyahu M. Goldratt in his 1984 book titled The Goal,

    The underlying premise of Theory of Constraints is that

    organizations can be measured and controlled by variations

    on three measures: throughput, operational expense, andinventory.

    Throughput is the rate at which the system generates money

    through sales.

    Inventory is all the money that the system has invested in

    purchasing things which it intends to sell.

    Operational expense is all the money the system spends in

    order to turn inventory into throughput."The Goal" itself is to

    "make money". All other benefits are derived, in one way or

    another, from that single primary goal.

    http://en.wikipedia.org/wiki/Management_philosophyhttp://en.wikipedia.org/wiki/Eliyahu_M._Goldratthttp://en.wikipedia.org/wiki/The_Goal_(novel)http://en.wikipedia.org/wiki/The_Goal_(novel)http://en.wikipedia.org/wiki/Eliyahu_M._Goldratthttp://en.wikipedia.org/wiki/Management_philosophy
  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    7/22

    Concepts on which Concerto works: Critical Chain & TOC

    7

    "The Goal" itself is to "make money". All other benefits are

    derived, in one way or another, from that single primarygoal.

    The five focusing steps

    Goal achievement is limited by at least one constraining

    process. Assuming the goal of the organization has been

    articulated the steps are:

    Identify the constraint (the resource that prevents the

    organization from obtaining more of the goal): DRUM

    RESOURCE

    Decide how to exploit the constraint (get the most capacity

    out of the constrained process)

    Subordinate all other processes to above decision (align the

    whole system or organization to support the decision made

    above)

    Elevate the constraint (make other major changes needed tobreak the constraint)

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    8/22

    Critical Chain Project Management: CCPM

    8

    A very new concept in project management.

    Old systems were running through decades. No proper training and clear road map for implementation. Faces huge flack at the beginning. People reluctant to use this tool effectively because of

    ignorance.

    No synchronization between planning through concerto andactual working schedule in shop.

    But top management was adamant to implement this at any

    cost . This created a catchy or chaotic situation in the production

    shops resulting in to various conflicts among projectmanagers. It took almost 5-6 years to implement this across various

    production centers with a centralized Concerto Planning

    Server.

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    9/22

    1. Identify the Constraint

    2. Exploit the Constraint

    3. Subordinate everything

    to the Constraint

    4. Elevate the Constraint

    5. Repeat for the new

    Constraint

    Theory of Constraints - FIVE FOCUSING STEPSTheory of Constraints - FIVE FOCUSING STEPS

    (Which will Strengthen the Chain)

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    10/22

    CCPM in Multi Project Environment

    10

    The goal is to protect the Critical Chain of each project by

    suitably and efficiently allocating Drum Resources( constraints ) to each of the critical paths of different projects.

    In L&T the Drum resources are the Rolling Machines, Skoda,

    Vertical boring Machine or sometimes cranes or welding

    machine.

    These resources are to be allocated in such a fashion that

    Critical Chain of all the projects are protected.

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    11/2211

    SYSTEM COMPONENTS of CONCERTO

    Critical Chain

    Buffering

    Pipelining

    BufferManagement

    PROJECT

    PLANNING

    ConcertoDatabase& Server

    Windows Client Used by Project Managers Integrated with MS Project

    Windows Client Used by Master Scheduler

    Web Clients Used by all

    PIPELINE

    PLANNING

    EXECUTION

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    12/2212

    WORKING WITH MS PROJECT: Project Planning

    Concerto window

    MS Project Window

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    13/22

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    14/2214

    CRITICAL CHAIN PLANNING EXERCISE: NETWORK

    Procurement of

    Nozzles

    Procurement of

    Plates

    Procurement of

    Tube Sheet

    forgings

    Procurement of

    dished ends

    Manufacture of

    Nozzles

    Manufacture of

    main shell

    Machine & Drill

    Tube Sheets

    Fabrication of

    header shells

    Procurement of

    Hardware &

    Gaskets

    Engineering

    Machine headers

    Hydro test Tube

    side

    Fabrication of

    headers

    Assemble tubes

    and tube sheet

    Hydro test shell

    side

    Procurement ofTubes

    Final Inspection

    & Despatch

    Receive customer

    order

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    15/2215

    Buffer Management: Execution: TASK LIST WITHPRIORITIES

    Users see only the tasks they are assigned

    Provides synchronized priorities and sense of urgency (what to do and how urgently)

    These tasks

    are ready to

    start today

    Priority

    Order

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    16/2216

    REPORTING ESCALATED/BLOCKED TASKS

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    17/2217

    SAMPLE TREND CHART

    % Chain Complete

    %

    BufferC

    onsumed

    -10 0 10

    What does the direction of the graph tell us?

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    18/2218

    % Chain Complete

    %

    Buff

    erC

    onsume

    d

    90%

    80%

    5%

    10%

    BUFFER STATUS

    20%

    8%

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    19/22

    Success: Current scenario in L&T

    19

    Though the initial hiccups, this information system is a grand

    success in L&T

    All the projects are executed scientifically, and the Delivery

    Index has improved phenomenon ally.

    There is less conflicts among project managers. Only

    centralized server decides priority of a task in a particular

    resource.

    The manufacturing shops now work with a specific target and

    purpose.

    Instead of delaying all the project simultaneously, Concerto

    gives guide lines to finish first priority and then move on to the

    next.

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    20/22

    Success: Current scenario in L&T

    20

    Marketing and estimation are able to do what if analysisduring bidding of a project to get the expected delivery date

    of the project before committing to customer.

    Customer rely more on the reported generated by concerto

    projecting the progress of his project rather than individualcommitment.

    Gives a clear guideline whether company will bid certain

    project or taking into account the existing work load.

    All the SBUs of L&T get equal priority to a certain shopfacility. Completely unbiased.

    Efficient project Progress Review tool for Shop floor & PMG.

    Action points are easily identified. Top management review.

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    21/22

    Conclusion: The success story of an IS

    21

    It is a big investment for the company. Lots of road blocks.

    But ultimately paying back the company in big ways.

    This cutting edge technology has changed the work

    environment and taken the company into next level in termsof global competition. This is an example of successful Operation and Management

    Support System.

  • 8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro

    22/22

    Thank You