introduction of concerto as information system in larsen & toubro
TRANSCRIPT
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
1/22
2007 Realization Technologies, Inc. All Rights Reserved. 1
Introduction of Concerto as Information
System in Larsen & Toubro.
By : Group 9Swarup Saha 80118110095Nikhil Rathod 80118110092Tapan Sangvi 80118110097Shashank Saraf 80118110098SANJAY Khambe 80118110048
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
2/22
The Information System: Concerto
2
A project planning software
Its a latest technology in the field of project management.
Used globally to efficiently manage projects.
Its a product of Realization Inc.
Realization was founded in 1999 to help organizations around
the world execute projects efficiently and faster so that they
can more fully realize their potential.
Works in multi project environment.
This system is based on Dr.E M Goldratts Theory of
Constrain principle. Realizations system was bourn out of book called Critical
Chain by Dr. E.M Goldratt.
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
3/22
Case Study: Introducing Concerto in L&T
3
Concerto was introduced in Larsen & Toubro as a project
management tool in 2004. Larsen & Toubro Heavy Engg div introduced this. L&T HED designs and manufacture customized products for
Oil and Gas Industry. Every project its manufactures is unique in nature.
It has unique project start date : ZERO DATE And an unique Contractual Delivery Date :CDD L&T HED has three manufacturing centre: Powai, Baroda &
Surat. It has more than six SBUs with separate order booking
All the orders are executed in these three commonManufacturing Center. Clash of priority, non availability of resources, Improper scheduling of projects in multi project environment. Resulting into delay in all the projects and LD
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
4/22
Change Management: Introduction of the new IS into anold system.
4
A very new concept in project management.
Old systems were running through decades. No proper training and clear road map for implementation. Faces huge flack at the beginning. People reluctant to use this tool effectively because of
ignorance.
No synchronization between planning through concerto andactual working schedule in shop.
But top management was adamant to implement this at any
cost . This created a catchy or chaotic situation in the production
shops resulting in to various conflicts among projectmanagers. It took almost 5-6 years to implement this across various
production centers with a centralized Concerto Planning
Server.
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
5/22
5
Two Concepts on which Concerto works: Critical Chain &TOC
Day 0:
Critical Chain is the longest chain ofresource AND taskdependencies in a project
T1 T2 T3
T5
T4 PB
T7T6 FB
X, 10d X, 10d X, 10d X, 10d
X, 10d
10dY, 10dY, 10d
25d
Critical Chain
Feeding Chain
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
6/22
Concepts on which Concerto works: Critical Chain & TOC
6
Theory of Constraints (TOC) is an overallmanagement philosophy introduced by Dr.
Eliyahu M. Goldratt in his 1984 book titled The Goal,
The underlying premise of Theory of Constraints is that
organizations can be measured and controlled by variations
on three measures: throughput, operational expense, andinventory.
Throughput is the rate at which the system generates money
through sales.
Inventory is all the money that the system has invested in
purchasing things which it intends to sell.
Operational expense is all the money the system spends in
order to turn inventory into throughput."The Goal" itself is to
"make money". All other benefits are derived, in one way or
another, from that single primary goal.
http://en.wikipedia.org/wiki/Management_philosophyhttp://en.wikipedia.org/wiki/Eliyahu_M._Goldratthttp://en.wikipedia.org/wiki/The_Goal_(novel)http://en.wikipedia.org/wiki/The_Goal_(novel)http://en.wikipedia.org/wiki/Eliyahu_M._Goldratthttp://en.wikipedia.org/wiki/Management_philosophy -
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
7/22
Concepts on which Concerto works: Critical Chain & TOC
7
"The Goal" itself is to "make money". All other benefits are
derived, in one way or another, from that single primarygoal.
The five focusing steps
Goal achievement is limited by at least one constraining
process. Assuming the goal of the organization has been
articulated the steps are:
Identify the constraint (the resource that prevents the
organization from obtaining more of the goal): DRUM
RESOURCE
Decide how to exploit the constraint (get the most capacity
out of the constrained process)
Subordinate all other processes to above decision (align the
whole system or organization to support the decision made
above)
Elevate the constraint (make other major changes needed tobreak the constraint)
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
8/22
Critical Chain Project Management: CCPM
8
A very new concept in project management.
Old systems were running through decades. No proper training and clear road map for implementation. Faces huge flack at the beginning. People reluctant to use this tool effectively because of
ignorance.
No synchronization between planning through concerto andactual working schedule in shop.
But top management was adamant to implement this at any
cost . This created a catchy or chaotic situation in the production
shops resulting in to various conflicts among projectmanagers. It took almost 5-6 years to implement this across various
production centers with a centralized Concerto Planning
Server.
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
9/22
1. Identify the Constraint
2. Exploit the Constraint
3. Subordinate everything
to the Constraint
4. Elevate the Constraint
5. Repeat for the new
Constraint
Theory of Constraints - FIVE FOCUSING STEPSTheory of Constraints - FIVE FOCUSING STEPS
(Which will Strengthen the Chain)
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
10/22
CCPM in Multi Project Environment
10
The goal is to protect the Critical Chain of each project by
suitably and efficiently allocating Drum Resources( constraints ) to each of the critical paths of different projects.
In L&T the Drum resources are the Rolling Machines, Skoda,
Vertical boring Machine or sometimes cranes or welding
machine.
These resources are to be allocated in such a fashion that
Critical Chain of all the projects are protected.
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
11/2211
SYSTEM COMPONENTS of CONCERTO
Critical Chain
Buffering
Pipelining
BufferManagement
PROJECT
PLANNING
ConcertoDatabase& Server
Windows Client Used by Project Managers Integrated with MS Project
Windows Client Used by Master Scheduler
Web Clients Used by all
PIPELINE
PLANNING
EXECUTION
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
12/2212
WORKING WITH MS PROJECT: Project Planning
Concerto window
MS Project Window
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
13/22
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
14/2214
CRITICAL CHAIN PLANNING EXERCISE: NETWORK
Procurement of
Nozzles
Procurement of
Plates
Procurement of
Tube Sheet
forgings
Procurement of
dished ends
Manufacture of
Nozzles
Manufacture of
main shell
Machine & Drill
Tube Sheets
Fabrication of
header shells
Procurement of
Hardware &
Gaskets
Engineering
Machine headers
Hydro test Tube
side
Fabrication of
headers
Assemble tubes
and tube sheet
Hydro test shell
side
Procurement ofTubes
Final Inspection
& Despatch
Receive customer
order
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
15/2215
Buffer Management: Execution: TASK LIST WITHPRIORITIES
Users see only the tasks they are assigned
Provides synchronized priorities and sense of urgency (what to do and how urgently)
These tasks
are ready to
start today
Priority
Order
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
16/2216
REPORTING ESCALATED/BLOCKED TASKS
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
17/2217
SAMPLE TREND CHART
% Chain Complete
%
BufferC
onsumed
-10 0 10
What does the direction of the graph tell us?
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
18/2218
% Chain Complete
%
Buff
erC
onsume
d
90%
80%
5%
10%
BUFFER STATUS
20%
8%
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
19/22
Success: Current scenario in L&T
19
Though the initial hiccups, this information system is a grand
success in L&T
All the projects are executed scientifically, and the Delivery
Index has improved phenomenon ally.
There is less conflicts among project managers. Only
centralized server decides priority of a task in a particular
resource.
The manufacturing shops now work with a specific target and
purpose.
Instead of delaying all the project simultaneously, Concerto
gives guide lines to finish first priority and then move on to the
next.
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
20/22
Success: Current scenario in L&T
20
Marketing and estimation are able to do what if analysisduring bidding of a project to get the expected delivery date
of the project before committing to customer.
Customer rely more on the reported generated by concerto
projecting the progress of his project rather than individualcommitment.
Gives a clear guideline whether company will bid certain
project or taking into account the existing work load.
All the SBUs of L&T get equal priority to a certain shopfacility. Completely unbiased.
Efficient project Progress Review tool for Shop floor & PMG.
Action points are easily identified. Top management review.
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
21/22
Conclusion: The success story of an IS
21
It is a big investment for the company. Lots of road blocks.
But ultimately paying back the company in big ways.
This cutting edge technology has changed the work
environment and taken the company into next level in termsof global competition. This is an example of successful Operation and Management
Support System.
-
8/6/2019 Introduction of Concerto as Information System in Larsen & Toubro
22/22
Thank You