introduction of zte mw hardware installation guide
TRANSCRIPT
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
1/34
Oct 2015
Introduction of ZTE MW Hardware Installation
and configuration guide
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
2/34
Agenda |
ZTE Microwave Hardware Installation Flow
ZTE Microwave NR8250 Installation Detail
ZTE Microwave NR8950 installation Detail
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
3/34
ZTE Microwave NR8250 Installation Flow
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
4/34
ZTE Microwave NR8250 Installation (IDU installation)
Installing the IDU inside a 19-inch Portal Frame
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
5/34
ZTE Microwave NR8250 Installation (IDU installation)
Installing a Board
Step 1
Step 2
Step 3
Step 4
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
6/34
ZTE Microwave NR8250 Installation(ODU installation)
ZTE Microwave hardware InstallationAdjusting the Polarization Mode of an ODU
Vertical Polarization Horizontal Polarization
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
7/34
ZTE Microwave NR8250 Installation(ODU installation)
Adjusting the Polarization Mode of an ODU
Step 1 remove the Guide Pin Step 2 Adjusting the Polarization
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
8/34
ZTE Microwave NR8250 Installation(ODU installation)
Integrated Installation(1+0)
Step 1 remove the waveguide diagram Step 2 put the lubricant
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
9/34
ZTE Microwave NR8250 Installation(ODU installation)
Step 3 installation ODU Step 4 Securing Screws
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
10/34
ZTE Microwave NR8250 Installation(ODU installation)Separate Installation(1+0 )
Step 2 Install the ODU on the ODU install brackStep 1 Install the ODU installation bracket
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
11/34
ZTE Microwave NR8250 Installation(ODU installation)Separate Installation(1+0 )
Step 3 Install the waveguide Step 4 Use flexible waveguide clamps
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
12/34
ZTE Microwave NR8250 Installation(ODU installation)Separate Installation(2+0 Dual-Polarization )
Step 1 Install the two ODU installation bracket Step 2 Install the ODU on the ODU install br
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
13/34
ZTE Microwave NR8250 Installation(ODU installation)Separate Installation(2+0 Dual-Polarization )
Step 3 Install the waveguide Step 4 Use flexible waveguide clamps
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
14/34
ZTE Microwave NR8250 Installation(cable installation)Installing the IDU protective Grounding Cable
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
15/34
ZTE Microwave NR8250 Installation(cable installation)Installing the ODU protective Grounding Cable
a. Cut the protective
grounding cable and
crimp the terminals.
b. Fix one terminal of the
grounding cable on the
grounding screw of the
ODU
c. Connect the other end of
the protective grounding
cable to the grounding
busbar of the metal
tower.
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
16/34
ZTE Microwave NR8250 Installation(cable installation)Installing Power Cable
Step 1:Markning the terminal Step 2:Connect Power to the IDU
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
17/34
ZTE Microwave NR8250 Installation(cable installation)Installing Power Cable
Step 3:Install B1 on the DCPD4A Step 4:Bind the power cable
Step 5:Paste the engineering
labels at the two ends of the power
cable
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
18/34
ZTE Microwave NR8250 Installation(cable installation)Installing Intermediate Frequency Cable
Step 2:Layout and route the IF CableStep 1:Making IF Cable
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
19/34
ZTE Microwave NR8250 Installation(cable installation)
Routing the IF cable indoors vertically
Routing Intermediate Frequency Cable
Routing the IF cable indoors Horizontally
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
20/34
ZTE Microwave NR8250 Installation(cable installation)Grounding the IF Cable
a. If the antenna is installed on the metal tower , the IF cable should be grounded
at a point about 1-2m below the ODU ,and then be grounded at a point 1.5mbefore the bent part where the cable is routed downwards along the tower .
b. If the IF cable is shorten than 20m, it must be grounded at the first two
grounding points
c. If the IF cable is longer than 20m but shorter than 60m,it must be grounded at
the three grounding points
d. If the IF cable is longer than 60m, an additional grounding point must be made
for every additional 20m IF cable.
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
21/34
ZTE Microwave NR8950 Installation Flow
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
22/34
ZTE Microwave NR8950 Installation DetailAdjusting the Polarization Mode of an ODU
Rotate the guide pin 90deg clockwiseRemoving the guide pin place the guide pin on the h
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
23/34
ZTE Microwave NR8950 Installation DetailIntegrated Installation(1+0)
Remove the waveguide diaphragm Put the lubricant
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
24/34
ZTE Microwave NR8950 Installation DetailIntegrated Installation(1+0)
Install AOU Fasten screws
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
25/34
ZTE Microwave NR8950 Installation DetailSeparate Installation(1+0)
Step 1: Install the ODU installation bracket Step 2: Install the NR8950 on the ODU install brac
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
26/34
ZTE Microwave NR8950 Installation DetailSeparate Installation(1+0)
Step 3: Installing the Flexible Waveguide Step 4: Fix the Flexible Waveguide and resu
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
27/34
ZTE Microwave NR8950 Installation DetailSeparate Installation(2+0)
Step 1: Install the ODU installation bracket Step 2: Install the NR8950 on the ODU install brac
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
28/34
ZTE Microwave NR8950 Installation DetailSeparate Installation(2+0)
Step 3: Install the Flexible Waveguide Step 4: Fix the Flexible Waveguide and result
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
29/34
ZTE Microwave NR8950 Installation DetailInstalling the Protective grounding cable
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
30/34
ZTE Microwave NR8950 Installation DetailInstalling the Power Cable
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
31/34
ZTE Microwave NR8950 Installation DetailInstalling the Ethernet Cable
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
32/34
ZTE Microwave NR8950 Installation DetailInstalling the Optical Fiber
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
33/34
ZTE Microwave NR8950 Installation DetailInstalling the XPIC Cross-Connect Cables
-
7/25/2019 Introduction of ZTE MW Hardware Installation Guide
34/34