Introduction & Up-date 20 th August 2012. Contents. The Background The Teams The Facilities Location & Layout The Planning Communications Your Input. The Background. Current Campus Designed for Max Capacity of 1200 students We are now c.1150 & growing - PowerPoint PPT Presentation

TRANSCRIPT

  • Introduction & Up-date20th August 2012

  • Contents

    The Background The Teams The Facilities Location & Layout The Planning Communications Your Input

  • The Background

    Current Campus Designed for Max Capacity of 1200 studentsWe are now c.1150 & growing

    Campus Master Plan - completed 2008Find it on InsideASH>Search Campus Master PlanHistorically 5 small locations in & around The HagueNew Campus 20 years agoMS temporary wing added 15 years agoNew ES Wing in 2003

    Purchased Land from Municiapality of Wassenaar for ECC Boerderij (farm) Ter Weer (area name)Located on small Deijlerweg, 5/7 minutes walkConstruction commenced early 2102

    *

  • The BackgroundThe key parties in the negotiations: Municapality of Wassenaar owned the land & farmhouse Boerderij Ter WeerSJW Youth Club had clubhouse in the Farmhouse - were already being re-located by GemeenteOlympia 72 Handball Club will share sports facilitiesASH now own land & buildings

    *

  • Location & Layout*

  • Location & Layout

    *

  • *Ground cleared & prepared late 2011/ early 2012Groundbreaking Ceremony took place 16th February 2012Handball fields complete (for new handball season)Construction drawings & foundation work completed over the summer - passed a key risk phaseSport complex and Gym due for completionend of December 2012 Main ECC instructional areas doe for completion July 2013. Currently on schedule weather permittingNow: Fixtures & Fittings & LandcapingThe Planning

  • The TeamsASHECC Project TeamTim Messick, Ton Ravensbergen, Rick Spradling, Hans Carmiggelt, Lesley Murphy, Project Managers (External) ECC Design TeamTim Messick, Fereshteh Dastani, Matthew Steuer, Ann Pleij, Carla Bruzual, Hans Carmiggelt, Project ManagersExternal Project Manager ThemelionArjen Brandon, Marije BierenbroodspotArchitect Kraaijvanger UrbisHans GoverdeLandscape Architect recently selected Design Studio Van Ginneken*

  • Communications*

  • Your InputThank you for you valuable input to date. We welcome your ideas about any aspect of the project:

    Contact a member of The Design Team or The Project Team

    Watch out for up-dates on the website, InsideASH & PTO Bulletin

    Check out the model in the main entrance

    Get students involved

    Direct non-staff members with inquiries to email: [email protected]

    Let us know in advance when you would like to visit well pick time slots per week - hard hats must be worn at all times on the construction site.*