Involuntary Resettlement Due Diligence Report (DDR) ________________________________________ Social Due Diligence Report March 2020 PAK: Second Power Transmission Enhancement Investment Program, Tranche 1 EXTENSION AND AUGMENTATION OF GRID STATION, REWAT Prepared by National Transmission and Despatch Company (NTDC) for the Asian Development Bank. This document is made publicly available in accordance with ADB’s Access to Information Policy and as agreed between ADB and the borrower.

Upload: others

Post on 05-Sep-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Involuntary Resettlement Due Diligence Report (DDR)

________________________________________

Social Due Diligence Report

March 2020

PAK: Second Power Transmission Enhancement

Investment Program, Tranche 1

EXTENSION AND AUGMENTATION OF GRID STATION,

REWAT

Prepared by National Transmission and Despatch Company (NTDC) for the Asian Development

Bank. This document is made publicly available in accordance with ADB’s Access to Information Policy and as agreed between ADB and the borrower.

Page 2: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

NOTES

(i) The fiscal year (FY) of the Government of the Islamic Republic of Pakistan and its

agencies ends on 30 June.

(ii) In this report “$” refer to US dollars.

This social due diligence report is a document of the borrower. The views expressed herein do

not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation

of or reference to a particular territory or geographic area in this document, the Asian

Development Bank does not intend to make any judgments as to the legal or other status of any

territory or area.

Page 3: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

1

ISLAMIC REPUBLIC OF PAKISTAN

GOVERNMENT OF PAKISTAN

National Transmission and Despatch Company (NTDC)

Proposed Multitranche Financing Facility (MFF II) Pakistan: Power Transmission Enhancement Investment Program II

(ADB Project No. 48078)

EXTENSION AND AUGMENTATION OF GRID STATION, REWAT

SOCIAL DUE DILIGENCE REPORT (INVOLUNTARY RESETTLEMENT AND INDIGENOUS PEOPLES)

March 2016

Prepared by National Transmission and Despatch Company,

Environment and Social Impacts Cell in concert with Resettlement Specialist of Project Preparatory Technical Assistance (PPTA).

Page 4: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

2

NATIONAL TRANSMISSION AND DESPATCH COMPANY, PAKISTAN

POWER TRANSMISSION ENHANCEMENT INVESTMENT PROGRAM (Project Number 48078)

EXTENSION AND AUGMENTATION OF GRID STATION, REWAT

SOCIAL DUE DILIGENCE REPORT (INVOLUNTARY RESETTLEMENT AND

INDIGENOUS PEOPLES)

March 2016

Prepared by National Transmission and Despatch Company,

Environment and Social Impacts Cell in concert with Resettlement Specialist of Project Preparatory Technical Assistance (PPTA).

Page 5: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

3

CONTENTS

CONTENTS ............................................................................................................... 3

LIST OF ANNEXES ....................................................... Error! Bookmark not defined.

ABBREVIATIONS ..................................................................................................... 5

I. INTRODUCTION ................................................................................................ 6

A. Background ................................................................................................. 6

B. Need for Due Diligence Review of Involuntary Resettlement (IR) and Indigenous Peoples (IPs) ..................................................................................... 6

C. Methodology ............................................................................................... 6

II. FINDINGS OF DUE DELIGENCE WORK .......................................................... 9

A. Brief history of Grid Station and Land Acquisition: ................................ 9

B. Scope of Land Acquisition and Resettlement: ........... Error! Bookmark not defined.

C. Resettlement Related Impacts: ................................................................ 10

D. Indigenous Peoples: ................................................................................. 10

E. Land Acquisition and Resettlement Framework: ................................... 10

F. Institutional Arrangements: ..................................................................... 11

III. CONCLUSION AND RECOMMENDATIONS ................................................... 12

Page 6: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

4

LIST OF ANNEXES Annex-I: List of subprojects ...................................................................................... 17

Annex-II: Location of Sub-project Rewat .................................................................. 17

Annex-III: Confirmation Letter from NTDC regarding no resettlement impacts in sub-projects .................................................................................................................... 20

Annex-IV: Site identified for augmentation/extension work within Grid station Rawat ................................................................................................................................. 21

Page 7: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

5

ABBREVIATIONS

ADB Asian Development Bank

CAP Corrective Action Plan

DDR Due Diligence Report

ESIC Environment and Social Impact Cell

GOP Government of Pakistan

kV Kilo Volt

IR Involuntary Resettlement

IPs Indigenous Peoples

IPDP Indigenous Peoples Development Plan

LARP Land Acquisition and Resettlement Plan

LARF Land Acquisition and Resettlement Framework

MFF Multi tranche financing facility

NTDC National Transmission and Dispatch Company (Pakistan)

PPTA Project Preparatory Technical Assistance

SPS Safeguard Policy Statement 2009

WAPDA Water and Power Development Authority

Page 8: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

6

I.INTRODUCTION

A. Background

1. The Government of Pakistan (GOP) plans to implement the “Power Transmission Enhancement Investment Program (PTEIP) with financial assistance of Asian Development

Bank (ADB) through a multi tranche financing facility (MFF). The objective of the investment

program is to improve Pakistan’s power transmission infrastructure and management. To achieve this objective, the investment program consists of staged physical investments in the

high-voltage transmission system, including the rehabilitation, augmentation and expansion

of transmission lines, substations and supporting infrastructure. Thus, the major aim of PTEIP

is enhancement in the capacity of the transmission system by rehabilitation, extension,

augmentation & expansion of existing 500 kV & 220 kV network of NTDC, to meet the growing

power demand in the country.

2. The National Transmission and Despatch Company (NTDC) will implement the

investment program through different tranches of MFF with each tranche time sequenced and

containing several subprojects based on the subproject readiness. The tranche 1 of MFF II

contains 10 subprojects (Annex A) which mainly involve extension and augmentation of

substations and rehabilitation and setting up of existing and transmission lines.

3. Rawat Substation – A Subproject of Tranche I of proposed MFF: The 500 kV

Rawat- augmentation of 500/200 kV transformer is one of the 10 subprojects proposed under

tranche 1 of MFF. The substation is expected to enhance the capacity of existing grid station

through extension and augmentation of existing 500/220 kv T/Fs of 450 MVA with 750 MVA

and 220/132 kv transformers of 160 MVA capacity with 250 MVA capacity at Rewat, district

Rawalpindi (Annex 2 Location of Substation).

B. Need for Due Diligence Review of Involuntary Resettlement (IR) and Indigenous Peoples (IPs)

4. A detailed due diligence work has been undertaken with the purpose to (i) examine

the IR and IPs aspects of the Rawat Substation; (ii) identify any land acquisition and

resettlement and indigenous peoples related impacts; and recommend preparation of

appropriate safeguards document (land acquisition and resettlement plan, indigenous peoples

plan and/or a due diligence report) as applicable but in accordance with ADB’s Safeguard Policy Statement (SPS) 2009.

C. Methodology

5. The due diligence work was guided by the following methodology:

a. Desk Review of project documents:

i. Concept note

ii. ADB SPS 2009

iii. Ad memoirs

Page 9: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

7

iv. List of sub projects identified under the trance 1 of investment program

v. Earlier documentation work related to social safeguards including IR and

IP

vi. PC-1s (Project description)

vii. Route maps of transmission lines and lay out map of sub stations

viii. Google Maps

b. Meetings and consultations with NTDC/Environment Social Impact Cell and officials

of sub stations

i. Field visit to grid station:

ii. Transect Walk

iii. Field observation

iv. Photographs (field evidence)

v. Project design/GS layout, location map and any route maps as applicable

6. Meetings with Grid Station Officials: Consultative meeting with superintendent

engineer and three executive engineers was held on 14th march 2016 to discuss the scope of

the sub project, history of grid station, previous up gradation work and new extension and

augmentation work planned for Rewat substation, land acquisition and compensation aspects

matters of previous and proposed extension and augmentation work and IP aspects. The

following officials from GS participated in the meeting:

Purpose of Meeting

Date and Venue of Meeting

Participants Key discussions

Discuss subproject and any LAR and IPs impacts.

14 March 2016. Superintending Engineers Office, 500 KV GSO Circle Substation, NTDC, Rewat, Rawalpindi.

- Mr. Muhammad Ayub (SE 500 KV GSO)

- Pir Tariq Sai (XEN EHV Rawalpindi)

- Malik.Nawab Khan (XEN NTDC GSO Circle Rewat)

- Mr. Tassawar Abbas (AE Construction)

History of GS Land Acquisition and Resettlement Aspects of GS Evidence of Land owned by NTDC Site visit and findings.

7. Meeting with PPTA Consultants and NTDC/ESIC Officials: After the field visit, a

meeting was held with PPTA consultants and NTDC/ESIC officials held on 15th March 2016,

the purpose of which was to share the field findings with ESIC and PPTA team leader and

seek clarifications from ESIC and PPTA team leader about the filed findings. The due

diligence team confirmed to the ESIC and PPTA team leader that the extension and

augmentation of Rewat GS neither involved any land acquisition and resettlement impacts

nor any impacts related to the Indigenous Peoples. The GS station was established in 1992

and land acquired and APs fully compensated during that time.

Purpose of Meeting

Date and Venue of Meeting

Participants Key discussions

Page 10: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

8

Discuss subproject and any LAR and IPs impacts.

Office of Environment Social Impact Cell NTDC, Lahore

- Mahr Khalid Mehmood (Director ESIC)

- Mss. Samina Bilal, Assistant Director

- Mr. Shahid, Assistant Director Environment

- Mr. Irfan, Deputy Director Environment

- Mr. Shaukat Ali Shahid, PPTA

- Mss. Samira IDC - Mr. Mudessar IDC - Mr. Zafar IDC - Abdul Hameed

(PPTA Team Leader)

- Findings of due diligence in the field

- Conformation of no LAR and IPs impacts.

8. Field visit to Grid Station and Transect Walk: After completing the discussions with

GS officials, the due diligence team conducted a site visit to the GS, had a transect walk inside

the GS that have huge area under it including sites control rooms, storage area and area for

future expansion, bays, transformers and switchyard and other technical electric equipment

installed in GS. The GS officials extended maximum support in transect walk and

accompanied the DDR team and showed the sites for installation of new transformer facility.

The DDR team photographed the sites for record and reference.

9. Review of GS layout map and nature of augmentation work: The DDR team also

reviewed the GS map, diagrams and the sites for augmentation work within the boundary of

GS. This review and copies of maps helped the DDR team in physically examining the sites

for augmentation work and concluding that the subproject did not have any LAR and IPs

impacts.

10. Field observations and photographs were recorded during the site visit and transect

walk to support the DDR team’s conclusion of the GS augmentation work not having any LAR and IPs impact.

Page 11: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

9

II. FINDINGS OF DUE DELIGENCE WORK

11. Key findings of due diligence work are presented below:

A. Brief history of Grid Station and Land Acquisition:

12. The 500KV Grid Station, Rawat is located in the south west area of Rawalpindi at a

distance of about 20km on the main G.T Road. .Total area of the grid station is approximately

137.5 acres. Initially in 1991 500KV Grid Station Rewat was commissioned as 220 KV Grid

Station. Later on in 1997 it was upgraded to 500 KV and further extensions were carried out

at all voltage levels from time to time. The land was acquired in 1991 with no outstanding

compensation issues existing in GS. Present capacity of 500 kv Grid Station Rewat:

Power Type Quantity

500 KV system 500/220 KV 450 MVA auto transformer 3

500 KV transmission lines 5

500 KV 111 MVAR shunt reactors 2

220 KV system 220/132 KV 160 MVA auto transformers 3

220 KV transmission lines. 6

132 KV system 132/11.5 KV 10/13 MVA power transformers.

2

132 KV transmission lines. 13

13. Proposed augmentation works and scope of Land Acquisition and

Resettlement: As indicated in the list of sub projects, the substation Rewat is expected to

enhance the capacity of existing grid station through extension and augmentation of existing

500/220 kv T/Fs of 450 MVA with 750 MVA and 220/132 kv transformers of 160 MVA capacity

with 250 MVA capacity at Rawat, district Rawalpindi. Therefore it is anticipated that any

involuntary resettlement will not occur due to the project. However as per ADB’s SPS 2009 it is important to verify and confirm that no involuntary resettlement and indigenous people plan

will be required. The transect walk, meetings and consultations with NTDC/ESIC officials and

project staff at substation as well as review of project documents concluded that the

augmentation and extension work at the GS will enhance the GS power management capacity

and the equipment installation (sites available within the 137.5 acres of land acquired in 1991)

is strictly within the GS boundary and therefore will not cause any new land acquisition and

resettlement impacts.

Page 12: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

10

B. Resettlement Related Impacts:

14. Similarly to the conclusion of the GS not having any new or old land acquisition impact,

the DDR team also concluded that GS augmentation and extension work is not affecting any

built-up area, private, residential or commercial outside the GS boundary. Therefore, the

subproject does not have any adverse impact to any private structures, crops or trees or any

other resettlement related impact. The table below further confirms no impacts to local

population and their assets.

Assets LAR impacts

DPs and IP Remarks

Land No new impact.

Nil Land, crops, and trees and structures that existed on the land were all acquired and compensated in 1991.

No any LAR and IPs impacts recorded/found during the due diligence process in the field.

Structures; whether residential, agriculture, commercial or communal. Incomes derived from businesses and farming,

No new impact.

Nil

Trees and Crops No cultivation inside GS

NIL

C. Indigenous Peoples:

15. The DDR team carefully assessed the project area and met with local people who

turned out to be Muslims living in hormone with national laws and local culture. The did not

consider themselves to be called another type of population as the indigenous peoples as

ADB’s SPS 2009 describes the IPs to be. Therefore it is concluded that the project area do not have the presence of IPs and an Indigenous Peoples Development Plan (IPDP) is not

required for this project.

D. Land Acquisition and Resettlement Framework:

16. Although augmentation and extension work is not expected to cause any LAR and IPs

impacts, the NTDC has still prepared and endorsed the LARF for its implementation. NTDC

has done this in compliance with the requirements of ADB’s SPS 2009 and to address any

unanticipated LAR and IPs impacts in augmentation and extension subprojects and similar

impacts which NTDC may have address in the transmission line projects under the proposed

investment facility. The framework provides guideline about LAR impacts, entitlement and

Page 13: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

11

compensation payments, institutional arrangements and implementation schedules for

preparation, implementation and monitoring of the land acquisition and resettlement plans

(where needed) and grievance redress mechanism to address any grievances of affected

peoples.

E. Institutional Arrangements:

17. NTDC has established an environment and social impact cell (ESIC) which is

managed by a Director Social and Environment, assisted by assistant and deputy directors

social and environment impacts. The ESIC works closely with project consultants, reviews

and resettlement plans and acts as quality control and safeguards compliance unit for NTDC

for projects funded by ADB and other financiers. ESIC also undertakes internal monitoring of

the implementation of LARPs, DDRs and any corrective action plan (CAPs), and will do the

same for the Rewat GS subproject.

Page 14: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

12

III. CONCLUSION AND RECOMMENDATIONS

18. Due Diligence work included a site visit to the Grid Station and consultations with NTDC/ESIC, GS officials and PPTA team leader, the review of project documents and GS layout maps, sites for augmentation and extension work and NTDC’s confirmation of ownership of land available to the GS. Based on the field findings, it is concluded that the subproject (augmentation and extension work) does not have any land acquisition and resettlement impacts and will not cause any physical and economic dislocation as defined in ADB’s SPS 2009. The subproject also does not have presence of indigenous peoples. The due diligence team also reviewed the NTDC’s written confirmation of availability of land for Rewat GS and confirms that augmentation/extension work will be undertaken on the land acquired in 1991 (which do not have any outstanding compensation or resettlement issues). Since there are no impacts, no APs are therefore affected. The IR and IPs checklists prepared in the field also confirm no LAR and IPs impacts in Rawat GS project. No compensation of any kind is applicable in this subproject. The subproject is categorized as category C for involuntary resettlement and indigenous peoples. No further safeguards documentation work is needed unless there is any change in the impacts situation which NTDC (if it happens so) will inform ADB in advance for appropriate actions. 19. The DDR team makes following recommendations for implementation before any construction activities commence:

i. Establish grievance redress mechanism and make it functional before start of

construction.

ii. Adhere to the project design and proposed augmentation and extension work and

inform ADB about any changes in the design and resulting LAR situation prior to and

during implementation/construction work.

iii. In case of any emerging or unanticipated LAR impact during implementation, prepare

resettlement plan and obtain ADB’s approval prior to implementation.

iv. In case a LARP has to be prepared at any stage of the project implementation,

engage external monitoring agency or an individual to verify and certify

implementation of LARP before startup of civil works activities. Further monitoring

(internal as well as external) will be undertaken in line with monitoring frequency as

specified in the LARP.

Page 15: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

13

Annexes Containing Evidence of:

Site visit

Stakeholders Consultations Sites for Augmentation and Extension Work

Grid Station Location Map NTDC’s Ownership of GS Land

Photographs

Page 16: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

14

Photographic Evidence of Consultation Meetings with PPTA

Consultants and ESIC Officials at WAPDA House Lahore on Tuesday,

March 15, 2016

A view of Meeting at WAPDA House Lahore (E&SIC, ADB & Consultants)

A view of Meeting

Page 17: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

15

Photographic Evidence of Consultation Meeting with Officials of Grid

Station, Rawat. 14 March 2016

A view of meeting with SE 500 KV Grid Station Rawat

Visit to GS control room and interconnection network

Page 18: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

16

Location of Grid Station

System Diagram of 500/200/ 132 KV Grid Station NTDC Rawat

A view of 500 KV Grid Station Rawat

Single line diagram of 500KV Grid Station NTDC Rawat

Page 19: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Augmentation and Extension of Grid Station, Rawat Social Due Diligence Report (IR, IPs)

17

Consultation Meeting with GS Officials and Visit to different parts of GS

A view of Meeting with SE 500 KV Grid Station Rawat

A view of interconnection network of 500/ 200/ 132KV Grid Station

Page 20: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Extension of 500 kV Rewat Grid Station, District Rawalpindi Due Diligence Report, March 2016

17

Annex-I: List of subprojects List of subprojects proposed for Tranche 1 of MFF II is given below:

Proposed Subprojects Scope of Work

1. Extension at 500kV Sahiwal

• 1x600 MVA, 500/220 kV transformer along with allied equipment and accessories.

2. Extension at 500kV Lahore South

• 1x750 MVA 500/220kV Transformer along with allied equipment and accessories.

• Two 500kV Line Bays at 500kV Lahore South Grid Station.

3. Rehabilitation of NTDC system in south area for Improvement in System Reliability to avoid the Frequent Trippings

• Rehabilitation of 11 grid stations in south area of NTDC system have been planned by replacement of the outdated equipment, installation of Shunt Reactors and installation of additional protection equipment including protection relays, fault recorders, fault locators & event recorders

4. 500 kV Faisalabad West (Phase-II)

• 500 kV D/C T/L for In/Out of 500 kV Multan-Gatti S/C at 500 kV Faisalabad West (30 km)

• 220 kV D/C T/L from 500 kV Faisalabad West to 220 kV Lalian New (80 km)

• Extension at 500 kV Faisalabad West (for two 500 kV line bays & two 220 kV line bays).

• Extension at 220 kV Lalian (for two 220-line bays).

5. Extension & Augmentation of 500/220 kV Rewat Substation

• One 220/132 kV 250MVA transformer along with allied equipment. for extension at Rewat

• Two 220/132kV 250 MVA transformers for augmentation of existing 160 MVA T/Fs.

6. 220kV Mirpur Khas G/S along with allied T/Ls

• Two 220/132 kV 250MVA transformers along with allied equipment.

• In/Out of 220 kV D/C T/L from Hala Road to Jamshoro at Mirpur Khas (70 km)

7. 220kV D/C T/L from T.M Khan to Hala Road

• 220 kV D/C T/L from T.M.Khan to Hala Road (10 km)

8. 500kV Lahore North G/S along with allied T/Ls

• 500/220 kV substation with 2x750 MVA transformers and allied equipment & accessories (Two 500 kV T/F bays, four 500 kV line bays and six 220 kV line bays)

• 500 kV D/C T/L from Lahore North to proposed Lahore HVDC switching/converter station. (60 km)

• 500 kV D/C T/L from Lahore North to existing Gujranwala (Gakkhar) substation. (50 km)

• 220 kV double circuit T/Line for In/out of 220 kV Ghazi Road - KSK at 500 kV Lahore North (5 km)

• 220 kV double circuit T/Line for In/out of 220 kV KSK - Ravi at 500 kV Lahore North (5 km)

• 220 kV double circuit T/Line for In/out of Lahore (old) - Ravi at 500 kV Lahore North (10 km)

Page 21: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Extension of 500 kV Rewat Grid Station, District Rawalpindi Due Diligence Report, March 2016

18

Page 22: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Extension of 500 kV Rewat Grid Station, District Rawalpindi Due Diligence Report, March 2016

17

Annex-II: Location of Sub-project Rawat

Page 23: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Extension of 500 kV Rewat Grid Station, District Rawalpindi Due Diligence Report, March 2016

20

Annex-III: Confirmation Letter from NTDC regarding no resettlement impacts in sub-projects

Page 24: Involuntary Resettlement Due Diligence Report (DDR) · 2020. 3. 3. · - Mr. Tassawar Abbas (AE Construction) History of GS Land Acquisition and Resettlement Aspects of GS Evidence

Extension of 500 kV Rewat Grid Station, District Rawalpindi Due Diligence Report, March 2016

21

Annex-IV: Site identified for augmentation/extension work within Grid station Rawat