isaac centre harrogate crescent, bb10 2nx ground

102
Ian Farmer Associates (1998) Limited 14 – 15 Rufford Court, Warrington, Cheshire WA1 4RF Tel: 01925 855440 e-mail: [email protected] LANCASHIRE COUNTY COUNCIL ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND INVESTIGATION REPORT Contract: 42367 Date: October 2019

Upload: others

Post on 22-Feb-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Ian Farmer Associates (1998) Limited 14 – 15 Rufford Court, Warrington, Cheshire WA1 4RF Tel: 01925 855440 e-mail: [email protected]

LANCASHIRE COUNTY COUNCIL

ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND INVESTIGATION REPORT

Contract: 42367

Date: October 2019

Page 2: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Ian Farmer Associates (1998) Limited 14 – 15 Rufford Court, Warrington,

WA1 4RF Tel: 01925 855440

e-mail: [email protected]

GROUND INVESTIGATION REPORT

carried out at

ISAAC CENTRE

HARROGATE CRESCENT, BB10 2NX

Prepared for

LANCASHIRE COUNTY COUNCIL PO Box 78

County Hall Fishergate

Preston Lancashire PR1 8XJ

Contract No: 42367

Date: October 2019

Page 3: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367

Document Control

Project reference: 42367 -2 (00)

Project name: Isaac Centre, Harrogate Crescent

Report title: Ground Investigation Report

Revision Date Description

Rev 00 17th October 2019 Complete draft on ground investigation

Author

Technical Reviewer

Project Manager

H. Hadwin T Downes H. Hadwin

Engineering Geologist Technical Manager Engineering Geologist

Page 4: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367

EXECUTIVE SUMMARY

On the instructions of instructions of Lancashire County Council (LCC), a ground investigation was undertaken to determine ground conditions for the redevelopment of the site for low-rise housing with private gardens.

The site is situated at the former Isaac Centre approximately 2km to the northeast of the town centre of Burnley.

Records indicate superficial deposits of Glacial Till beneath the site. Bedrock beneath the superficial deposits is recorded as mudstone, siltstone and sandstone of Pennine Lower Coal Measures.

The site work was carried out between 27th and 29th August 2019.

The site work comprised four cable percussion boreholes, five dynamic sample boreholes, four hand excavated hand pits.

The sequence encountered generally comprises of Made Ground over Glacial Till.

Traditional strip foundations may be considered. These should be advanced through any Made Ground and soft clay to competent strata. This may require excavation to depths between 1.50 and 2.00m.

Strip foundations of widths about 0.6 to 1.0m, at a minimum depth of 0.75m, should support an allowable bearing pressure about 150kN/m2.

Piled foundations may also be considered to minimise the volume of excavated material for disposal and the volume of concrete.

Design Sulphate Class for concrete may be taken as DS-1 with an ACEC class for the site of AC-1.

The soil analysis results were all below their respective guideline values. Asbestos was not detected. The low concentrations of contamination are consistent with the history of the site. On this basis the risk to the development from contamination in soils is considered to be very low. Remediation of contamination will not be required. In the absence of remediation there will be no requirement for validation and verification reporting.

Page 5: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 1 of 21

CONTENTS

EXECUTIVE SUMMARY

1.0 INTRODUCTION 3

2.0 SITE SETTING 4 2.1 Site Location 4 2.2 Site Description 4 2.3 Geological Setting 4

3.0 SITE WORK 5

4.0 LABORATORY TESTS 6 4.1 Geotechnical Testing 6 4.2 Chemical Testing 6

5.0 GROUND CONDITIONS ENCOUNTERED 7 5.1 Sequence 7 5.2 Made Ground 7 5.3 Natural Soils 8 5.4 Groundwater 9 5.5 Existing Foundations 10

6.0 GEOTECHNICAL ASSESSMENT 11 6.1 Proposed Development 11 6.2 Foundations 11 6.3 Ground Floor Slabs 12 6.4 Excavations 12 6.5 Chemical Attack on Buried Concrete 13

7.0 ENVIRONMENTAL RISK ASSESSMENT IN RELATION TO PROPOSED DEVELOPMENT 14 7.1 Contaminated Land 14 7.2 Risk Assessment 14 7.3 Pollutant Linkage 14 7.4 Risk Assessment – Human Health 15 7.5 Protection of Services 16

8.0 MANAGEMENT OF CONTAMINATION 16 8.1 Remediation and Verification 16 8.2 Management of Unidentified Sources of Contamination 16 8.3 Consultation 17 8.4 Risk Management During Site Works 18

9.0 REFERENCES 19

Page 6: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 2 of 21

APPENDIX 1 - DRAWINGS Figure A1.1 - Site Location Plan Figure A1.2 - Site Plan APPENDIX 2 - SITE WORK General Notes on Site Work ii/i-ii/iii BH01 to BH04 - Borehole Records WS01 to WS05 - Dynamic Sample Borehole Records FP01 - Foundation Pit Records HDP01 to HDP03 - Hand Dug Trial Pit Records APPENDIX 3 - LABORATORY TESTS General Notes on Laboratory Tests on Soils iii/i-iii/iii Test Report 42367 - Results of Geotechnical Tests – Soils Test Report 19/08679 APPENDIX 4 - CHEMICAL TESTS Test Reports 19/08117 - Results of Chemical Tests – Soils and 19/08205 APPENDIX 5 - DESIGN CONSIDERATIONS Guidelines for the Design of Piles - First Approximation of Working Loads v/i-v/v APPENDIX 6 - CONTAMINATION ASSESSMENT General Notes on Chemical Contamination vi/i-vi/vi

Page 7: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 3 of 21

1.0 INTRODUCTION

1.1 On the instructions of instructions of Lancashire County Council (LCC), a ground investigation was undertaken to determine ground conditions for the redevelopment of the site

1.2 It is understood that it is proposed to develop the site for low-rise housing with private gardens.

1.3 This report should be read in conjunction with the Preliminary Investigation, which was reported under reference 42367-1 in September 2019.

1.4 It is recommended that a copy of this report be submitted to the relevant authorities to enable them to carry out their own site assessments and provide any comments.

1.5 This report has been prepared for the sole use of the Client for the purpose described and no extended duty of care to any third party is implied or offered. Third parties using any information contained within this report do so at their own risk.

1.6 The comments given in this report and the opinions expressed herein are based on the information received, the conditions encountered during site works, and on the results of tests made in the field and laboratory. However, there may be conditions prevailing at the site which have not been disclosed by the investigation and which have not been taken into account in the report.

1.7 The comments on groundwater conditions are based on observations made at the time the site work was carried out. It should be noted that groundwater levels vary owing to seasonal or other effects.

Page 8: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 4 of 21

2.0 SITE SETTING

2.1 Site Location

2.1.1 The site is situated south off Harrogate Crescent, some 2km to the northeast of Burnley.

2.1.2 The site may be located by Grid Reference SD 856 348.

2.1.3 A site location plan is included in Appendix 1, Figure A1.1.

2.2 Site Description

2.2.1 The site is approximately 1.47 Hectares in area and slopes gently down to the south west.

2.2.2 At the time of the site investigation, the northern part of the site was occupied by a single and two storey school building of masonry and frame construction.

2.2.3 The school appeared to have been partially cut into the slope as there were embankments to the northeast and east of the buildings.

2.2.4 An asphalt covered car park and playgrounds were located on the west of the site and playing fields were present in the south and western parts of the site.

2.2.5 A number of trees were located around the perimeter of the site and further trees were present to the southeast, northeast and west of the school buildings.

2.3 Geological Setting

2.3.1 Details of the geology underlying the site have been obtained from the British Geological Survey web based geological records database (contains British Geological Survey materials ©UKRI 2019).

2.3.2 The geological map indicates the site to be underlain by superficial deposits comprising Glacial Till.

2.3.3 Bedrock beneath the superficial deposits is recorded as mudstone, siltstone and sandstone of the Pennine Lower Coal Measures.

2.3.4 The Coal Authority Report for the site is included in Appendix 5. The report indicates that the site is underlain by two seams at 120m and 420m below ground level last worked in 1956. The report considers that any movement in the ground associated with these workings should have stopped by now.

2.3.5 The site is within an urban area and, although not indicated as present on the site from the geological maps, the possibility that Made Ground exists on site cannot be discounted.

Page 9: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 5 of 21

3.0 SITE WORK

3.1 The site work was carried out between 27th and 29th August 2019.

3.2 The scope of the works and locations and depths of exploratory holes were determined by LCC.

3.3 The site works were carried out on the basis of the practices set out in CLR 4, (ref. 9.1), BS 5930:2015 (ref. 9.2), BS EN ISO 14688-1:2018 (ref. 9.3) and BS 10175:2011, (ref. 9.4).

3.4 The locations of the exploratory holes were restricted by existing buildings and services.

3.5 Exploratory holes were undertaken as follows:

• BH01 to BH04: Cable percussion boreholes • WS01 to WS05: Dynamic sample boreholes • HDP01, HDP03 to HDP04: Hand excavated trial pits • FP01: Foundation hand excavated trial pits

3.6 A site plan showing the positions of the Exploratory Holes is presented in Appendix 1

as Figure A1.2.

3.7 The depths of exploratory holes, descriptions of strata encountered and comments on groundwater conditions are given in the records presented in Appendix 2.

3.8 A Cable Avoidance Tool (CAT) survey was undertaken at each exploratory hole location prior to excavation. At the location of boreholes an inspection pit was excavated by hand to a depth of 1.20m below ground level to check for buried services.

3.9 Representative disturbed and undisturbed samples were taken at the depths shown on the records. Samples for environmental analysis were collected in appropriate containers and kept in cool boxes for daily despatch to the analytical laboratory.

3.10 Standard penetration tests (SPT), ref. 9.3 were carried out in boreholes in the various strata to assess the relative density or consistency. The values of penetration resistance are given in the borehole records. Energy ratio calibration certification for SPT hammers used on site are presented in Appendix 2.

3.11 Perforated standpipe surrounded by pea shingle and protected by a stopcock cover were installed in boreholes BH02. The details of the installations are presented on the borehole records in Appendix 2.

3.12 The standpipes were protected at surface by lockable flush stopcock covers.

3.13 The ground levels at the exploratory hole locations were not within the required scope of works.

Page 10: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 6 of 21

4.0 LABORATORY TESTS

4.1 Geotechnical Testing

4.1.1 Geotechnical testing schedules were prepared by Ian Farmer Associates (IFA).

4.1.2 Geotechnical testing was undertaken by IFA at their Washington Laboratory. Geotechnical chemical tests were undertaken by Envirolab in Hyde.

4.1.3 Soil samples for testing were prepared in accordance with BS1377: Part One: 1990 ref. 9.9 and representative sub-samples were taken for testing. The following tests were carried out:

• 23 No. Moisture contents • 13 No. Plasticity indices • 4 No. Particle size distribution by wet sieving • 4 No. Sedimentation by pipette • 5 No Undrained shear strength • 2 No. Unconfined compression strength of soil • 2 No. Oedometer consolidation • 16 No. Water soluble sulphate (Envirolab) • 16 No pH value (Envirolab)

4.1.4 The results of the soil tests are presented in Appendix 3, Test Report 42367.

4.1.5 The results of the sulphate and pH tests are presented in Appendix 3, Test Report 19/08679.

4.2 Chemical Testing

4.2.1 Chemical testing schedules were prepared by IFA.

4.2.2 The chemical analyses were carried out on seven samples of soil. The nature of the analyses is detailed below:

4.2.3 L1/1 - arsenic, cadmium, chromium, copper, lead, mercury, nickel, zinc, selenium, boron (water soluble), pH, fraction of organic carbon, total sulphate and total sulphide

4.2.4 L1/2 – asbestos screen

4.2.5 L1/4 – TPH speciated by carbon bonding and aliphatic aromatic split

4.2.6 L1/5 – PAH speciated (USEPA 16)

4.2.7 The results of chemical analysis on soil samples are presented in Appendix 4, Test Reports 19/08117 and 19/08205.

Page 11: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 7 of 21

5.0 GROUND CONDITIONS ENCOUNTERED

5.1 Sequence

5.1.1 The sequence of the strata encountered during the investigation generally confirms the anticipated geology as interpreted from the geological map.

5.1.2 The sequence encountered generally comprises of Made Ground over Glacial Till.

5.1.3 The general sequence of strata is shown on the nominal section; Figure A1.3.

5.1.4 SPTs vs Depth data is plotted as Figure A1.4.

5.2 Made Ground

5.2.1 Made Ground was encountered within all exploratory locations from ground level to depths from 0.80m to 1.20m.

5.2.2 A thin veneer of tarmacadam was encountered within BH01, BH02 and BH04. The thickness of the tarmacadam was in the range 0.05m to 0.10m.

5.2.3 A paving slab was encountered at FP01 with a thickness of 0.05m.

5.2.4 The Made Ground variably comprised cohesive and granular soils.

5.2.5 Made Ground cohesive soils comprised dark brown mottled grey clay and dark brown mottled grey silt with rootlets.

5.2.6 Made Ground granular soil comprised gravel with localised sand. The gravel comprised dark bluish grey material.

5.2.7 Anthropogenic fragments included brick, ash, asphalt and clinker.

5.2.8 Laboratory analysis of Made Ground indicated pH values from 6.81 to 8.49 and soluble SO4 contents from 17mg/l to 113mg/l.

5.2.9 The base of the Made Ground was proven at depths in the range 0.20m to 0.60m within all exploratory holes apart from FP01 and HDP04.

5.2.10 FP01 and HDP04 were terminated at 0.60m and 1.20m respectively within Made Ground.

Page 12: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 8 of 21

5.3 Natural Soils

5.3.1 Natural soils were encountered directly beneath Made Ground at depths from 0.20m to 0.60m within all exploratory holes apart from FP01 and HDP04.

5.3.2 These natural strata are considered to represent Glacial Till.

5.3.3 The majority of the natural strata comprised clay. This was generally described as grey mottled brown, slightly sandy, slightly gravelly clay. A medium cobble content was noted within the Glacial Till.

5.3.4 Sand was encountered at depths greater than 4.00m within WS05. The sand was described as greyish brown, fine and medium.

5.3.5 Soft clay was encountered within WS01 (0.20m to 2.30m), WS02 (0.50m to 2.10m), WS03 (0.20m to 1.50m), BH04 (0.70m to 1.80m) and HDP03 (0.50m to 1.20m). The soft clay described as brown mottled grey, very sandy, slightly gravelly, silty with frequent pockets of sand.

5.3.6 The table below presents a summary of the SPT’s (uncorrected) and laboratory analysis of the Glacial Till.

Clay Sand

No. Max Min No. Max Min

Plasticity Index 13 20 6 - - -

Water content

% 23 25 13 - - -

Plastic limit % 13 23 15

Liquid limit % 13 41 24

% passing 425µm

13 98 55

SPT ‘N’ value 38 50 4 2 19 16

pH 13 8.2 6.88 1 7.09

Soluble SO4

contents (mg/l)

13 68 <10 1 <10

5.3.7 Based on these results the fine soils may be classified as low plasticity clay (four samples), intermediate plasticity clay (six samples), low to intermediate plasticity (three samples).

5.3.8 Plastic index values classify the clay as low volume change potential.

Page 13: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 9 of 21

5.3.9 Field logging indicated consistencies of soft, firm and stiff.

5.3.10 Soft clay was encountered between 1.50m and 2.30m across the site. This softening of the clay is possibly due to water seepage within the Glacial Till.

5.3.11 Two oedometer tests recorded mv values of 0.16 and 0.23m2/MN at pressure stages rising from overburden.

5.3.12 Four triaxial tests recorded undrained shear strengths (Cu) in the range 69 to 164kN/m2. These values indicate medium, high and very high strength materials.

5.3.13 Thirty eight SPT ‘N’ values from 4 to greater than 50 blows were obtained within clay.

5.3.14 The highest SPT values exceeding 50 blows with penetration in the range 20mm to 275mm. These were recorded within BH01 and BH04 at depths in range of 6.5m and 8.00m and within WS04 at 3.00m.

5.3.15 Excluding the highest SPT values the remaining values are in the range of 4 to 28.

5.3.16 Derived Cu values from 24 to 168kN/m2 may be determined from SPT ‘N’ values where full penetration was achieved. These have been based on an f1 value about 6.

5.3.17 Two SPT ‘N’ values of 16 and 19 were obtained within sand at depths of 4.00m and 5.00m within WS05.

5.3.18 The base of the Glacial Till was not proven. All the exploratory holes were terminated at depths in the range of 3.43m to 10.00m within Glacial Till.

5.4 Groundwater

5.4.1 Groundwater strikes within exploratory holes have been summarised below:

5.4.2 Groundwater was not noted in the rest of the exploratory holes during fieldwork.

Exploratory Hole Depth (m) Strata

BH02A 1.20m no rise

Glacial Till

4.00m no rise BH03 1.20m no rise BH04 1.20m no rise HDP03 1.00m no rise WS03 1.00m no rise WS05 3.00m no rise

Page 14: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 10 of 21

5.5 Existing Foundations

5.5.1 One hand pit was excavated around the existing Isaac Centre building.

5.5.2 Existing foundations were encountered in FP01.

5.5.3 The foundation encountered in FP01 was a brick wall founded on concrete at depths of 0.50m.

5.5.4 The base of the foundation was not encountered due to fast inflow of water during excavation.

5.5.5 FP01 encountered a foundation step out of 0.2m.

5.5.6 FP02 was terminated at 1.10m within Made Ground clay.

5.5.7 The dimensions of the foundation layers encountered in FP01 is shown on the sketch in Appendix 2.

Page 15: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 11 of 21

6.0 GEOTECHNICAL ASSESSMENT

6.1 Proposed Development

6.1.1 It is understood that it is proposed to develop the site for low-rise housing with private gardens.

6.1.2 As detailed development plans are not available the foundation recommendations are preliminary.

6.1.3 The comments and discussion below do not fall within the requirements of EC7 (ref. 9.3) and are offered for guidance. The comments and recommendations below should be reviewed as development details become available.

6.2 Foundations

6.2.1 The investigation has proved Made Ground and soft clay to depths from 0.30m to 2.30m overlaying Glacial Till.

6.2.2 The results of laboratory tests indicate clay, where encountered, is of low volume change potential as defined by the National House Building Council, ref 9.12 and other published data, refs 9.13 and 9.14. Changes in moisture content may result small changes in volume, seasonal changes being exacerbated by the presence of trees. It is recommended that for design purposes, low volume change potential should be adopted. On this basis a minimum foundation depth of 0.75m would be required outside the influence of trees.

6.2.3 Traditional strip foundations may be considered. These should be advanced through any Made Ground and soft clay to competent strata. This may locally require excavation to depths between 1.50 and 2.00m.

6.2.4 Strip foundations of widths about 0.6 to 1.0m, at a minimum depth of 0.75m, should support an allowable bearing pressure about 150kN/m2, a figure which would provide an adequate factor of safety against shear failure and limit settlements to the order of 20mm.

6.2.5 Piled foundations may also be considered to minimise the volume of excavated material for disposal and the volume of concrete.

6.2.6 Guidelines for the design of piles are given in Appendix 5.

6.2.7 The carrying capacity of piles depends not only on their size and the ground conditions but also on their method of installation. Pile design and installation are continuously evolving processes and state-of-the-art are often employed before they reach the public domain, perhaps several years down the line. Therefore, it is recommended that specialist Piling Contractors be contacted as

Page 16: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 12 of 21

to the suitability and carrying capacity of their piles in the ground conditions pertaining to the site.

6.2.8 It should be noted that groundwater was present which could affect the installation of piles.

6.2.9 As an alternative to piling a foundation solution based on ground improvement, for example by vibrated stone columns, may be considered in those areas of deeper Made Ground.

6.3 Ground Floor Slabs

6.3.1 On the basis of observation on site together with the results of laboratory tests it is considered that ground floor slabs on formation prepared in competent natural strata may be utilised across much of the site. Any soft or deleterious material should be removed and replaced with properly compacted granular fill.

6.3.2 Within the zone of influence of trees, the floor slabs should be suspended over a void, in accordance with NHBC guidelines.

6.3.3 Where the final levels dictate that the depth of sub floor fill exceeds 600mm, ground floor slabs should be suspended in accordance with NHBC requirements.

6.4 Excavations

6.4.1 On the basis of observations on site, together with the results of in-situ and laboratory tests, it is considered that excavations to less than 1.00m should stand unsupported in the short term. Side support for safety purposes should of course be provided to all excavations which appear unstable, and those in excess of 1.20m deep, in accordance with Health and Safety Regulations.

6.4.2 Groundwater should not be expected in shallow excavations for foundations or services. However, it is possible that perched groundwater could be present in the Made Ground overlying the natural strata. It is considered that this could be dealt with by localised pumping.

6.4.3 Groundwater could be expected in excavations taken to depths in excess of 1.00m.

Page 17: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 13 of 21

6.5 Chemical Attack on Buried Concrete

6.5.1 The site has been classified in accordance with BRE Special Digest 1, ref. 9.18, as natural ground without the presence of pyrite and laboratory testing undertaken accordingly. It is recommended that the guidelines given in BRE Special Digest 1, ref. 9.18, be adopted. Relevant details of this digest are included in Appendix 5, Figure A5.6.

6.5.2 The results of chemical tests in the non-pyritic soils indicate a sulphate concentration in the soil of between <10mg/l and 113mg/l as a 2:1 water/soil extract, with pH values in the range of 6.81 to 8.49.

6.5.3 It is recommended that for conventional shallow foundations the groundwater should be regarded as mobile.

6.5.4 On the basis of the laboratory test results it is considered that a Design Sulphate Class for this material may be taken as DS-1. The site conditions would suggest that an ACEC class for the site of AC-1 would be appropriate.

Page 18: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 14 of 21

7.0 ENVIRONMENTAL RISK ASSESSMENT IN RELATION TO PROPOSED DEVELOPMENT

7.1 Contaminated Land

7.1.1 The statutory definition of contaminated land is defined in the Environmental Protection Act 1990, ref 9.20, which was introduced by the Environment Act 1995, ref 9.21, as;

• ‘Land which appears to the Local Authority in whose area it is situated to be in such a condition, by reason of substances in, on or under the land, that –

• significant harm is being caused or there is a significant possibility of such harm being caused; or

• significant pollution of controlled waters is being caused, or there is a significant possibility of such pollution being caused.’

7.2 Risk Assessment

7.2.1 The definition of contaminated land is based on the principles of risk assessment. Risk is defined as a combination of:

• The probability, or frequency of exposure to a substance with the potential to cause harm, and:

• The seriousness of the consequence.

7.3 Pollutant Linkage

7.3.1 The basis of an environmental risk assessment involves identifying a ‘source’ of contamination, a ‘pathway’ along which the contamination may migrate and a ‘receptor’ at risk from the contamination.

7.3.2 Current legislation defines the various elements of the pollution linkage as:

• A contaminant is a substance which is in or under the ground and which has the potential to cause harm or to cause pollution of controlled waters.

• A pathway is one or more routes through which a receptor is being exposed to, or affected by, a contaminant, or could be so affected.

• A receptor is either a living organism, an ecological system, a piece of land or property, or controlled water.

7.3.3 A pollutant linkage indicates that all three elements have been identified. The site can only be defined as ‘Contaminated Land’ if a pollutant linkage exists and the contamination meets the criteria in Section 7.1 above.

Page 19: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 15 of 21

7.3.4 The guidance proposes a four-stage approach for the assessment of contamination and the associated risks. The four stages are listed below:

• Hazard Identification

• Hazard Assessment

• Risk Assessment

• Risk Evaluation

7.3.5 The hazard identification and hazard assessment have been based upon the Phase 1 Desk Study and formed the conceptual site model, detailed in our report, reference 42367-1, dated September 2019.

7.3.6 The risk assessment and evaluation stages are presented in this phase 2 interpretive report, after an intrusive ground investigation has taken place.

7.4 Risk Assessment – Human Health

7.4.1 The proposed development consists of development of the site for low-rise housing with private gardens. The risk assessment has therefore been based on guidelines for a residential with homegrown produceend use. Should the proposed development be changed in the future then further risk assessment may be required, particularly should a more sensitive end-use be envisaged.

7.4.2 The results of the soil analyses from the current investigation have been compared to CLEA SGVs published in Environment Agency Science Reports SC050021/SR3, ref 9.23 and SC050021, ref 9.24, where available, Generic Assessment Criteria (GAC), determined by LQM and CIEH, ref 9.25, DEFRA C4SL, ref. 9.26 as well as Assessment Criteria (AC) derived in-house using the CLEA Software Version 1.06, ref 9.26. The CLEA AC have been derived by Ian Farmer Associates in accordance with current legislation and guidance.

7.4.3 The guidance values used within this contamination assessment have been tabulated and are detailed within Appendix 6.

7.4.4 Where the concentrations determined on site are at or below the respective Guidance Level, they are considered not to pose a risk and are removed from further consideration, unless otherwise stated.

7.4.5 All the contaminants concentrations are below the Guidance Level.

7.4.6 No asbestos was detected.

7.4.7 On this basis it is considered that significant contamination risks to human health would not be associated with the proposed development of the site.

Page 20: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 16 of 21

7.5 Protection of Services

7.5.1 Guidance from the UKWIR, ref 9.33, sets out the material requirements for newly laid water supply pipes within Brownfield sites. However, the exact requirements should be clarified with the relevant local water utility supplier for the site.

8.0 MANAGEMENT OF CONTAMINATION

8.1 Remediation and Verification

8.1.1 The risk management framework set out in the Model Procedures for the Management of Land Contamination, CLR 11, ref. 9.34, is applicable to the redevelopment of sites that may be affected by contamination.

8.1.2 The risk management process set out in the Model Procedures has three main components:

• Risk assessment • Options appraisal • Implementation

8.1.3 This initial risk assessment has not identified any sources of contamination at the site and therefore a revised conceptual model has not been presented.

8.1.4 In the absence of a contamination source and pollutant linkage a remediation strategy would not be relevant for this site.

8.1.5 In the absence of a site remediation strategy no validation would be required.

8.2 Management of Unidentified Sources of Contamination

8.2.1 There is the possibility that other sources of contamination may be present on the site, which were not detected during the investigation. Should such contamination be identified or suspected during the site clearance or ground works, these should be dealt with accordingly. A number of options are available for handling this material, which include:

• The removal from site and disposal to a suitably licensed tip of all material suspected of being contaminated. The material would need to be classified prior to disposal.

• Short-term storage of the suspected material while undertaking verification testing for potential contamination. The storage area should be a contained area to ensure that contamination does not migrate and affect other areas of the site. Depending upon the amounts of material under consideration, this could be either a skip or a lined area.

Page 21: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 17 of 21

• Having a suitably experienced environmental engineer either on-call or with a watching brief for the visual and olfactory assessment of the material, and sampling for verification purposes.

8.3 Consultation

8.3.1 During the development of a contaminated site, consultation may be required for a number of reasons with a number of regulatory Authorities. The following provides an indication as to the most likely Authorities with which consultation may be required.

• Local Authority. There may be a planning condition regarding contamination and consultation will be required with a designated Contaminated Land Officer within the Environmental Health Department. The Local Authority is generally concerned with human health risks. Some Authorities now require ‘Completion Certificates’ to be signed off following remediation works.

• Environment Agency. Where a site is within a groundwater protection zone or has been designated as a special site, the Environment Agency is likely to be involved to ensure that controlled waters are protected.

• National House Building Council, NHBC. Section 4.1 of the NHBC Standards requires land management to be addressed. For a new housing development to be approved by the NHBC, any remediation will require a validation report.

8.3.2 Based on the results of any consultation, there may be specific remediation requirements imposed by one or more of the Authorities.

Page 22: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 18 of 21

8.4 Risk Management During Site Works

8.4.1 During ground works, some simple measures may have to be put in place to mitigate the risk of contamination affecting the site workers and the environs. The majority of the proposed measures represent good practice for the construction industry and include:

• Informing the site workers of the contamination on site and the potential health effects from exposure.

• Where appropriate, the provision of suitable Personal Protective Equipment (PPE) for workers who may be potentially impacted by working in areas of the contamination.

• Ensuring good hygiene is enforced on site and washing facilities are maintained on the site. Workers are discouraged from smoking, eating or drinking without washing their hands first.

• Dust monitoring, and if necessary, suppression measures should be put into practice where contamination is becoming airborne.

8.4.2 Where contaminated materials are being removed from the site they should be disposed of at a suitably licensed landfill, with a ‘duty of care’ system in place and maintained throughout the disposal operations.

Page 23: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 19 of 21

9.0 REFERENCES

9.1 CLR 4, ‘Sampling strategies for contaminated land’. Report by The Centre for Research into the Built Environment, the Nottingham Trent University, DoE, 1994.

9.2 British Standards Institution: BS 5930:2015 ‘Code of practice for ground investigations.’ BSI 2015.

9.3 British Standards Institution: BS EN ISO 14688-1:2002+A1:2013. ‘Geotechnical investigation and testing – Identification and Classification of Soil – Part 1 Identification and description.’ BSI 2013.

9.4 British Standards Institute: BS 10175 ‘The investigation of potentially contaminated sites. Code of practice’, BSI:2011+A1:2013.

9.5 British Standards Institute: BS EN ISO 22476-3: 2005 + A1: 2011. ‘Geotechnical investigation and testing. Field testing. Standard penetration test.’

9.6 ISO 1997, Part 2:2007, ‘Eurocode 7 – Geotechnical Design – Part 2, Ground Investigation and Design’

9.7 British Standards Institute: BS EN ISO 22476-3: 2005 + A1: 2011. ‘Geotechnical investigation and testing. Field testing. Standard penetration test.’

9.8 ISO 22475-1:2006, ‘Geotechnical Investigation and Testing – Sampling Methods and Groundwater Measurements’ Part 1: Technical Principles for Execution.

9.9 British Standard 1377:1990, Parts1 - 9, ‘Methods of Test for Soils for Civil Engineering Purposes’.

9.10 Stroud, M.A. ‘The Standard Penetration Test in Insensitive Clays and Soft Rocks’, Proceedings of European Symposium on Penetration Testing, Stockholm, 1974.

9.11 Stroud, M.A. and Butler, F.G. 1975 ‘The Standard Penetration Test and Engineering Properties of Glacial Materials’, Symposium of Engineering Behaviour of Glacial Materials, Birmingham University.

9.12 National House-Building Council, Standards, Chapter 4.2, 2003 ‘Building Near Trees’.

9.13 BRE Digest 240, ‘Low-rise buildings on shrinkable clay soils: Part 1’. September 1993

9.14 Geotechnique, June 1983.

9.15 British Standard Code of Practice for Earth Retaining Structures, BS 8002:1994.

9.16 Thorburn, S. ‘Tentative Correction Chart for the Standard Penetration Test in non-cohesive soils’, Soil Engineering and Public Works Review, 58, 1963.

Page 24: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 20 of 21

9.17 Design Guidance for Road Pavement Foundations, Interim Advice Note 173/06, February 2006

9.18 Building Research Establishment, Special Digest 1, ‘Concrete in Aggressive Ground’, 2005.

9.19 Berezantsev, V.G., “Load bearing capacity and deformation of piled foundations”. Proceedings of the 5th International Conference on Soil Mechanics, Paris, 2, 11-12, 1961

9.20 The Environmental Protection Act, Part IIA, Section 78, 1990.

9.21 Environment Act 1995, Section 57, DoE 1995.

9.22 CLR 3, ‘Documentary research on industrial sites’, Report by RPS Consultants Ltd, DoE 1994.

9.23 Environment Agency Science Report SC050021/SR3, 2008, ‘Updated technical background to the CLEA model’

9.24 Environment Agency Science Report SC050021, 2009, ‘Contaminants in Soil: Updated Collation of Toxicological Data and Intake Values for Humans’

9.25 Generic Assessment Criteria for Human Health Risk Assessment (2nd Edition), Nathanial P, McCaffery C, Ashmore M, Cheng Y, Gillett A, Ogden R, and Scott D, Land Quality Press, Nottingham, published July 2009.

9.26 SP1010: Development of Category 4 Screening Levels for Assessment of Land Affected by Contamination – Policy Companion Document. DEFRA. March 2014.

9.27 CLEA Software Version 1.06 (downloaded from the Environment Agency website, http://www.environment-agency.gov.uk)

9.28 ‘Guidance on Comparing Soil Contamination Data with a Critical Concentration’, Chartered Institute of Environmental Health (CIEH) and Contaminated Land: Applications in Real Environments (CL:AIRE) May 2008.

9.29 ‘USEPA Pro UCL Version 4.00.02 software tool’. Downloaded from USEPA website.

9.30 An Analysis of Variance Test for Normality, Shapiro, S. S. and Wilk, M. B. 1965

9.31 Environment Agency Science Report SC050021/SR2 ‘Human health toxicological assessment of contaminants in soil’

9.32 CLR 10, ‘The Contaminated Land Exposure Assessment Model (CLEA): Technical basis and algorithms’. DEFRA/EA, March 2002.

9.33 UK Water Industry Research Ltd, Report 10/WM/03/21, ‘Guidance for the Selection of Water Supply Pipes to be used in Brownfield Sites’, 2010.

Page 25: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre Harrogate Crescent, BB10 2NX

Contract No. 42367 Page 21 of 21

9.34 CLR 11, ‘Model Procedures for the Management of Contaminated Land’, DEFRA and Environment Agency, 2004.

9.35 CLR 2, ‘Guidance on preliminary site inspection of contaminated land’, Report by Applied Environmental, DoE 1994.

9.36 Environment Agency, 2008, ‘Review of the Fate and Transport of Selected Contaminants in the Soil Environment’. Draft Technical Report P5-079/TR1. Bristol: Environment Agency

Page 26: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

APPENDIX 1

DRAWINGS

Page 27: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

PROJECT: 42367 Isaac Centre

FIGURE No. A1.1. SCALE : As above

TITLE: Site Location Plan

Reproduced with the permission of the Controller of Her Majesty’s Stationery Office, Crown copyright. Licence No. AL 100031101

The Site

N

Page 28: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Project Id: Project Title: Location: Client:

42367Isaac Centre, Burnley

Lancashire County Council

Title: Scale: Engineer: Contractor:

Site Plan1:2500HH

Page 29: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Project Id: 42367

Project Title: Isaac Centre, Burnley

Location:

Client: Lancashire County Council

Title: Section line 1

Vertical Scale: 1:92

Horizontal Scale: Not to scale

Engineer: HH

1 1

0 0

-1 -1

-2 -2

-3 -3

-4 -4

-5 -5

-6 -6

-7 -7

-8 -8

-9 -9

-10 -10

Chainage (m)

Offset (m)

Elevation (mAOD)

1.20

95.5

6

126.

70

150.

03

181.

06

197.

21

213.

52

240.

07

273.

66

321.

61

351.

81

361.

52

397.

90

460.

13

1.67

0.60

0.69

0.57

0.20

0.10

0.11

0.28

0.93

0.02

0.08

0.61

0.28

1.26

-11.00

Legend Key

MADE GROUND

Sandy gravelly CLAY

SAND

Silty sandy gravelly CLAY

Sandy CLAY

Silty sandy cobbly CLAY

0.20

1.50

4.00

5.45

WS

05

0.50

1.50

2.10

4.45

WS

02

0.10

0.70

1.80

7.04

BH

04

0.20

0.80

1.20

HD

P01

0.50

1.70

3.43

WS

04

0.050.10

0.60

FP

01

0.10

1.20

HD

P04

0.20

0.50

1.20

HD

P03

0.20

1.70

2.30

5.00

WS

01

0.20

1.50

5.45

WS

03

0.10

0.30

0.70

1.80

2.60

BH

02

0.40

1.50

10.00

BH

02A

0.05

0.30

1.50

9.95

BH

01

0.20

0.60

10.00

BH

03

Page 30: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Project ID: 42367 Project Title:

Client: Lancashire County Council Location:

Date Reported: 04/10/2019 Data Status:

YourLogoKeynetix Limited

www.keynetix.com+44 (0)1527 688888

Fig A1.4 SPT 'N' value versus depth

Isaac Centre, Burnley

0

2

4

6

8

10

12

0 10 20 30 40 50 60

De

pth

(m

bel

ow

gro

un

d le

vel)

CL SD

Page 31: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

APPENDIX 2

SITE WORK

Page 32: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 2 pages ii/i-ii/iii ii/i

APPENDIX 2

GENERAL NOTES ON SITE WORKS

A2.1 SITE WORK

A2.1.1 General

Site work is carried out in general accordance with the guidelines given in ISO 1997, 9.3 and BS 5930, ref 9.2.

A2.1.2 Trial Pits

Shallow trial pits are generally dug by mechanical excavator, however, in difficult access locations or adjacent to structures, such pits may be hand dug. Pits are best used where the ground will stand unsupported and generally, the maximum depth of machine dug pits is 4m to 5m. Where personnel are required to enter pits, it is essential that side support is provided. Entry by personnel into unsupported pits deeper than 1.2m is not allowed for health and safety reasons.

Trial pits allow the in-situ condition of the ground to be examined both laterally and vertically and also allow discontinuities to be recorded. The field record should give the orientation of the pit with details of which face was logged, assessment of stability of sides of pit and groundwater as well as the strata encountered. Photographs of the pit should also be taken.

In-situ testing, such as hand penetrometer, hand vane, Macintosh probe, or similar, can be undertaken in the sides or base of pits while both disturbed and undisturbed samples recovered.

It is generally advisable to backfill the pits as soon as possible, open pits should not be left unattended.

A2.1.3 Light Cable Percussion Boring

For routine soil exploration to depths in excess of 3m, the light cable percussion rig is generally employed for boring through soils and weak rocks, refs 9.2, 9.3 and 9.7. It consists of a powered winch and tripod frame, with running wheels that are permanently attached so that the rig may be towed behind a suitable vehicle. The rig is towed into position and set up using its own winching system.

The locations of services are checked to make sure the borehole is not situated unacceptably near any services. Regardless of the proximity of services, a CAT scan is undertaken at the borehole location and a trial hole dug to 1.20m by hand.

Boreholes are advanced in soil by the percussive action of the cable tool. The force of the cylindrical tool as it is dropped a short distance cuts a plug of cohesive soil that is removed by the tool.

In non-cohesive soils, the borehole is advanced by a ‘shell’, otherwise known as a ‘bailer’ or ‘sand pump’, which incorporates a clack valve. Material is transferred into the shell and retained by the clack valve. The water level in a borehole is maintained above that in the surrounding granular soil to allow for temporary reductions in the head of water as the shell is withdrawn from the borehole. Water should flow from the borehole into the surrounding soil at all times to prevent ‘piping’ and loosening the soil at the base of the hole. The casing is always advanced with the borehole in granular soil so that material is drawn from the base rather than the borehole sides.

Obstructions to boring are overcome by fitting a serrated chiselling ring to the base of the percussion tool. For large obstructions, a heavy chisel with a hardened cutting edge may have to be used.

Disturbed samples are taken in polythene bags, jars or tubs that are sealed against air or water loss.

Undisturbed samples are generally taken in cohesive materials at changes in strata and at one metre intervals to 5 metres then at 1.5 metre intervals to the full depths of the borehole. The general purpose open-tube sampler is suitable for firm to stiff clays, but is often used to retrieve disturbed samples of weak rocks, soft or hard clay and also clayey sand or silts. This has been adopted for

Page 33: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 2 pages ii/i-ii/iii ii/ii

routine use, and usually consists of a 100mm internal diameter tube (U100), which is capable of taking soil samples up to 450mm in length. The undisturbed samples are sealed at each end using micro-crystalline wax to prevent drying.

Standard penetration tests are generally carried out in non-cohesive soils but also in stiff clays and soft rocks at frequencies similar to that of undisturbed sampling.

A2.1.4 Drive-in Window Sampler

The drive-in window sampler, ref 9.8, consists generally of a track mounted window sampler and a series of cylindrical sample tubes, generally varying in diameter from 98mm to 35mm. A cutting shoe is fitted to the bottom of each tube, while a window, representing about a quarter of the circumference, is cut along the length of the tube. Soil samples are extracted through the window of the tube.

The borehole is extended by using progressively smaller diameter tubes.

Alternatively, undisturbed samples may be collected in plastic liners, known as windowless sampling.

A2.2 IN-SITU TESTS

A2.2.1 Standard Penetration Test

The Standard Penetration Test is carried out in accordance with the proposals recommended by ISO 1997, ref 9.3, BS 1377, Part 9, 1990 ref 9.9 and ISO 22476 ref 9.7.

The standard penetration test, SPT, covers the determination of the resistance of soils to the penetration of a split barrel sampler. A 50mm diameter split barrel sampler is driven 450mm into the soil using a 63.5kg hammer with a 760mm drop. The penetration resistance is expressed as the number of blows required to obtain 300mm penetration below an initial seating drive of 150mm through any disturbed ground at the bottom of the borehole. The number of blows to achieve the standard penetration of 300mm is reported as the ‘N’ value.

The test is generally carried out in fine soils, however, it may also be carried out in coarse granular soils, weak rocks and glacial tills using the same procedure as for the SPT but with a 50mm diameter, 60° apex solid cone replacing the split spoon sampler, CPT.

When attempting the standard penetration test in very dense material or weathered rocks it may be necessary to terminate the test before completion to prevent damage to the equipment. In these circumstances it is important to distinguish how the blow count relates to the penetration of the sampler. This may be achieved in the following manner:

Where the seating drive has been completed, the test drive is terminated if 50 blows are reached before the full penetration of 300mm is achieved. The penetration for 50 blows is recorded and an approximate N value obtained by linear extrapolation of the number of blows for the partial test drive.

If the seating drive of 150mm is not achieved within the first 25 blows, the penetration after 25 blows is recorded and the test drive then commenced.

For tests in soft rocks, the test drive should be terminated after 100 blows where the penetration of 300mm has not been achieved.

The N-value obtained from the Standard Penetration Test may be used to assess the relative density of sands and gravels as follows:

Term SPT N-Value : Blows/300mm Penetration

Very Loose

Loose

Medium Dense

0 - 4

4 - 10

10 - 30

Page 34: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 2 pages ii/i-ii/iii ii/iii

Dense

Very Dense

30 - 50

Over 50

A2.3 SAMPLES

U represents undisturbed 100mm diameter sample, the number of blows to obtain the sample also recorded.

U fail indicates undisturbed sample not recovered

HV represents Hand Vane test with equivalent undrained shear strength in kN/m2.

B represents large bulk disturbed samples

D represents small disturbed sample

ES represents amber jar contamination sample

V represents vial contamination sample

W represents water sample

represents water strike

represents level to which water rose

A2.4 DESCRIPTION OF SOILS

A2.4.1 General

The procedures and principles given in ISO 14688 Parts 1 and 2, ref 9.3, supplemented by section 6 of BS 5930, ref. 9.2 have been used in the soil descriptions contained within this report.

Page 35: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

0.05

0.30

(1.20)

1.50

(8.45)

9.95

Strata Description

MADE GROUND: Tarmacadam.MADE GROUND: Blueish grey, sandy GRAVEL. Gravel is angular to subrounded, fine to coarse including slate, brick, charcoal, coal, ash and asphalt.Firm, grey mottled brown, slightly sandy, slightly gravelly, silty CLAY. Gravel is subangular to subrounded, fine and medium including sandstone, mudstone and siltstone.

Firm, greyish brown, slightly sandy, slightly gravelly, silty CLAY. Gravel is subangular to subrounded, fine to coarse including sandstone, siltstone and mudstone.

At 2.00m: very high strength.

Below 4.00m: stiff.

End of Borehole at 10.00m

Legend

1

2

3

4

5

6

7

8

9

10

GroundwaterWaterStrike

Backfill/Installation

0.10 - 0.30 B10.20 ES2

0.30 - 1.20 B3

1.00 ES41.20 SPT(S) N=11 (2,2/3,2,3,3)

1.20 - 1.65 D61.20 - 1.70 B5

2.00 - 2.45 UT7 36 blows. 80% recovery2.00 HVP=133kPa

2.50 D8

3.00 SPT(S) N=12 (4,4/2,3,3,4)3.00 - 3.45 D103.00 - 3.50 B9

4.00 - 4.45 UT11 80 blows. 50% recovery4.00 HVP=114kPa

4.50 D12

5.00 SPT(S) N=15 (3,4/3,3,4,5)5.00 - 5.45 D145.00 - 5.50 B13

6.50 - 6.95 UT 80 blows. No recovery6.50 - 7.00 B15

8.00 SPT(S) 50 (4,5/50 for 200mm)

8.00 - 8.45 D178.00 - 8.50 B16

9.50 SPT(S) N=24 (5,5/6,5,6,7)9.50 - 9.95 D18

Plant used:

Dando 2000Dates:

29/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

BH01Sheet 1 of 1

Cable PercussionBorehole Log

Location:

385538.32E 434731.50NGround level: Logged by:

AMVertical scale:

1:50Project ID:

42367

Checked by:Log status:

HH

DRAFTIFA CPv01.01

SPT Hammer: GH01 Energy Ratio: 80%

ChisellingFrom (m) To (m) Time (mins) Remarks

8.30 8.50 45

Borehole DiameterDepth (m) Dia (mm)

10.00 150

Casing DiameterDepth (m) Dia (mm)

8.20 150

Boring ProgressDate Time Depth (m) Cased (m) Water (m)

29/08 16:30 10.00 8.20 Dry

Remarks:Service inspection pit hand excavated from GL to 1.20m.

Water StrikesStrike (m) Cased (m) Sealed (m) Time (mins)Rose to (m) Remarks

Monitoring InstallationsTop (m) Base (m) Pipe Type Dia (mm)

Page 36: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

0.100.30

(0.40)0.70

(1.10)

1.80

(0.80)

2.60

Strata Description

MADE GROUND: Tarmacadam.MADE GROUND: Dark grey, sandy GRAVEL. Gravel is angular to subrounded, fine to coarse including slate, charcoal and brick.MADE GROUND: Firm, greyish brown, slightly sandy, slightly gravelly CLAY. Gravel is angular to subrounded, fine to coarse including brick, quartzite, sandstone and charcoal.Soft, grey mottled brown, slightly sandy, slightly gravelly CLAY. Gravel is subangular to subrounded, fine and medium including sandstone and siltstone.

Stiff, greyish brown, slightly silty, slightly sandy, slightly gravelly CLAY. Gravel is angular to subrounded, fine and medium including sandstone and quartzite.

End of Borehole at 2.60m

Legend

1

2

3

4

5

6

7

8

9

10

GroundwaterWaterStrike

Backfill/Installation

0.10 - 0.30 B10.20 ES2

0.30 - 0.70 B30.50 ES4

1.00 ES51.20 SPT(S) N=4 (1,0/1,1,1,1)

1.20 - 1.65 D71.20 - 1.70 B6

2.00 - 2.45 UT8 64 blows. 40% recovery

2.50 D9

Plant used:

Dando 2000Dates:

28/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

BH02Sheet 1 of 1

Cable PercussionBorehole Log

Location:

385581.56E 434722.73NGround level: Logged by:

AMVertical scale:

1:50Project ID:

42367

Checked by:Log status:

HH

DRAFTIFA CPv01.01

SPT Hammer: GH01 Energy Ratio: 80%

ChisellingFrom (m) To (m) Time (mins) Remarks

Borehole DiameterDepth (m) Dia (mm)

2.60 150

Casing DiameterDepth (m) Dia (mm)

1.70 150

Boring ProgressDate Time Depth (m) Cased (m) Water (m)

28/08 12:00 2.60 1.70 Dry

Remarks:Service inspection pit hand excavated from GL to 1.20m.Terminated at 2.60m due to obstruction encountered. Relocated to BH02A.

Water StrikesStrike (m) Cased (m) Sealed (m) Time (mins)Rose to (m) Remarks

Monitoring InstallationsTop (m) Base (m) Pipe Type Dia (mm)

Page 37: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

(0.40)0.40

(1.10)

1.50

(8.50)

10.00

Strata Description

MADE GROUND: Grass over soft, dark brown, clayey, slightly sandy SILT with frequent rootlets.

Soft, brown mottled grey, slightly gravelly, very sandy, silty CLAY. Gravel is subangular to subrounded, fine to coarse including sandstone and siltstone.

Firm, greyish brown, slightly sandy, slightly gravelly, silty CLAY with medium cobble content. Gravel is angular to subrounded, fine to coarse including sandstone, siltstone and quartzite. Cobbles are subangular to subrounded of sandstone.

Below 4.00m: stiff.

Below 7.00m: sandy.

At 8.00m: high strength.

End of Borehole at 10.00m

Legend

1

2

3

4

5

6

7

8

9

10

GroundwaterWaterStrike

Backfill/Installation

0.10 - 0.40 B1

0.40 - 1.20 B2

1.20 - 1.65 UT3 20 blows. 50% recovery

1.70 D4

2.00 HVP=109kPa2.20 SPT(S) N=11 (4,2/2,2,3,4)

2.20 - 2.65 D62.20 - 2.70 B5

3.20 - 3.65 UT 100 blows. No recovery3.20 - 3.70 B7

4.00 SPT(S) N=21 (2,3/5,5,6,5)4.00 - 4.45 D94.00 - 4.50 B8

5.20 - 5.65 UT 100 blows. No recovery5.20 - 5.70 B10

6.50 SPT(S) N=18 (2,2/4,5,4,5)6.50 - 6.95 D126.50 - 7.00 B11

8.00 - 8.45 UT13 58 blows. 80% recovery

8.50 D14

9.60 SPT(S) N=25 (3,3/4,5,6,10)9.60 - 10.00 D15

Plant used:

Dando 2000Dates:

28/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

BH02ASheet 1 of 1

Cable PercussionBorehole Log

Location:

385572.90E 434720.29NGround level: Logged by:

AMVertical scale:

1:50Project ID:

42367

Checked by:Log status:

HH

DRAFTIFA CPv01.01

SPT Hammer: GH01 Energy Ratio: 80%

ChisellingFrom (m) To (m) Time (mins) Remarks

Borehole DiameterDepth (m) Dia (mm)

10.00 150

Casing DiameterDepth (m) Dia (mm)

9.20 150

Boring ProgressDate Time Depth (m) Cased (m) Water (m)

28/08 16:30 10.00 9.20 Dry

Remarks:Service inspection pit hand excavated from GL to 1.20m.

Water StrikesStrike (m) Cased (m) Sealed (m) Time (mins)Rose to (m) Remarks

1.20 0 1.204.00 0 4.00

Monitoring InstallationsTop (m) Base (m) Pipe Type Dia (mm)0.00 2.00 Plain2.00 10.00 Slotted

Page 38: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

0.20(0.40)0.60

(9.40)

10.00

Strata Description

MADE GROUND: Grass over soft, dark grey, slightly sandy, slightly gravelly CLAY with rootlets. Gravel is subangular, fine and medium of brick.Soft, brown mottled grey, slightly sandy CLAY with frequent sand lenses.Soft, greyish brown, slightly sandy, slightly gravelly, silty CLAY. Gravel is subangular to subrounded, fine to coarse including mudstone, sandstone and siltstone.

Below 1.50m: firm.

End of Borehole at 10.00m

Legend

1

2

3

4

5

6

7

8

9

10

GroundwaterWaterStrike

Backfill/Installation

0.00 - 0.20 B10.20 - 0.50 B2

0.50 ES30.60 - 1.20 B4

1.00 ES51.20 SPT(S) N=5 (1,1/0,1,2,2)

1.20 - 1.65 D71.20 - 1.70 B6

1.20 HVP=91kPa

2.00 SPT(S) N=11 (3,2/2,3,4,2)2.00 - 2.45 D92.00 - 2.50 B8

3.20 SPT(S) N=11 (2,2/2,3,3,3)3.20 - 3.65 D113.20 - 3.70 B10

4.00 SPT(S) N=11 (2,2/2,2,3,4)4.00 - 4.45 D134.00 - 4.50 B12

5.20 SPT(S) N=20 (2,2/2,3,5,10)5.20 - 5.65 D155.20 - 5.70 B14

6.50 SPT(S) N=20 (3,3/3,5,6,6)6.50 - 6.95 D176.50 - 7.00 B16

8.00 SPT(S) N=19 (3,3/3,5,5,6)8.00 - 8.45 D198.00 - 8.50 B18

9.50 SPT(S) N=28 (3,7/5,6,8,9)9.50 - 9.95 D20

Plant used:

Dando 2000Dates:

27/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

BH03Sheet 1 of 1

Cable PercussionBorehole Log

Location:

385572.07E 434679.59NGround level: Logged by:

AMVertical scale:

1:50Project ID:

42367

Checked by:Log status:

HH

DRAFTIFA CPv01.01

SPT Hammer: GH01 Energy Ratio: 80%

ChisellingFrom (m) To (m) Time (mins) Remarks

Borehole DiameterDepth (m) Dia (mm)

10.00 150

Casing DiameterDepth (m) Dia (mm)

4.70 150

Boring ProgressDate Time Depth (m) Cased (m) Water (m)

27/08 16:30 10.00 4.70 Dry

Remarks:Service inspection pit hand excavated from GL to 1.20m.

Water StrikesStrike (m) Cased (m) Sealed (m) Time (mins)Rose to (m) Remarks

1.20 20 1.20

Monitoring InstallationsTop (m) Base (m) Pipe Type Dia (mm)

Page 39: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

0.10

(0.60)

0.70

(1.10)

1.80

(5.24)

7.04

Strata Description

MADE GROUND: Tarmacadam.MADE GROUND: Blackish grey, clayey, sandy GRAVEL. Gravel is angular to subrounded, fine to coarse including limestone and brick.

Below 0.40m: very clayey.Soft, brown mottled, slightly gravelly, sandy, silty CLAY. Gravel is subrounded, fine including sandstone.

Firm, greyish brown, slightly sandy, slightly gravelly, silty CLAY. Gravel is subangular to subrounded, fine to coarse including sandstone, siltstone, mudstone and quartzite.

Below 3.00m: medium cobble content of subrounded sandstone.At 3.00m: high strength.

End of Borehole at 7.04m

Legend

1

2

3

4

5

6

7

8

9

10

GroundwaterWaterStrike

Backfill/Installation

0.10 - 0.40 B10.20 ES2

0.40 - 0.70 B30.50 ES4

0.70 - 1.20 B5

1.00 ES61.20 - 1.65 UT7 8 blows. 50% recovery

1.20 HVP=48kPa

1.70 D8

2.00 SPT(S) N=14 (2,2/2,3,4,5)2.00 - 2.45 D102.00 - 2.50 B9

3.00 - 3.45 UT11 11 blows. 40% recovery

3.50 D12

4.00 SPT(S) N=17 (3,4/4,3,4,6)4.00 - 4.50 B13

5.00 SPT(S) N=26 (4,14/6,6,6,8)5.00 - 5.45 D155.00 - 5.50 B14

6.50 SPT(C) 50 (8,16/50 for 120mm)

6.50 - 6.77 B16

7.00 SPT(C) 50 (25 for 20mm/50 for 20mm)

Plant used:

Dando 2000Dates:

29/08/2019 - 30/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

BH04Sheet 1 of 1

Cable PercussionBorehole Log

Location:

385531.76E 434780.51NGround level: Logged by:

AMVertical scale:

1:50Project ID:

42367

Checked by:Log status:

HH

DRAFTIFA CPv01.01

SPT Hammer: GH01 Energy Ratio: 80%

ChisellingFrom (m) To (m) Time (mins) Remarks

2.50 2.70 306.70 7.00 60

Borehole DiameterDepth (m) Dia (mm)

7.04 150

Casing DiameterDepth (m) Dia (mm)

6.20 150

Boring ProgressDate Time Depth (m) Cased (m) Water (m)

29/08 16:30 3.00 3.00 Dry30/08 08:00 3.00 5.00 Dry30/08 15:00 7.04 6.02 Dry

Remarks:Service inspection pit hand excavated from GL to 1.20m.

Water StrikesStrike (m) Cased (m) Sealed (m) Time (mins)Rose to (m) Remarks

1.20 20 1.20

Monitoring InstallationsTop (m) Base (m) Pipe Type Dia (mm)

Page 40: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

0.20

(1.50)

1.70

(0.60)

2.30

(2.70)

5.00

Strata Description

MADE GROUND: Grass over soft, dark brown, clayey, slightly sandy, slightly gravelly SILT. Gravel is angular to subrounded, fine including tile, brown and quartzite.Soft locally firm, brown mottled grey, very sandy, silty, slightly gravelly CLAY with frequent pockets of sand. Gravel is subangular to subrounded, fine and medium including sandstone and siltstone.

Soft, greyish brown, slightly silty, slightly sandy, slightly gravelly CLAY. Gravel is angular to subrounded, fine and medium including mudstone, sandstone and charcoal.

Firm, greyish brown, slightly silty, slightly sandy, slightly gravelly CLAY. Gravel is subangular to subrounded fine to coarse including sandstone, mudstone and siltstone.

End of Borehole at 5.00m

Legend

1

2

3

4

5

6

7

8

9

10

GroundwaterWaterStrike

Backfill/Installation

0.10 ES1

0.60 B30.60 ES2

1.20 SPT(S) N=9 (1,1/2,2,3,2)1.20 D4

2.00 D62.00 - 2.45 UT5 31 blows. 100% recovery

2.50 D7

3.00 SPT(S) N=12 (3,3/3,2,2,5)3.00 D8

3.50 D9

3.90 D104.00 UT11 28 blows. 100% recovery4.20 D12

5.00 SPT(S) N=21 (3,2/3,3,5,10)5.00 - 5.45 D13

Plant used:

Dart 416Dates:

29/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

WS01Sheet 1 of 1

Dynamic SampleBorehole Log

Location:

385652.45E 434740.31NGround level: Logged by:

AMVertical scale:

1:50Project ID:

42367

Checked by:Log status:

HHDRAFT

IFA DSv01.01

Remarks:

SPT Hammer: PM1 Energy Ratio: 72%

Dynamic Sample RecoveryTop (m) Base (m) Dia (mm) Recovery % Remarks Service inspection pit hand excavated from GL to 1.20m.

Water StrikesStrike (m) Cased (m) Sealed (m) Time (mins) Rose to (m) Remarks

Monitoring InstallationsTop (m) Base (m) Pipe Type Dia (mm)

Page 41: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

(0.50)

0.50

(1.00)

1.50

(0.60)

2.10

(2.35)

4.45

Strata Description

MADE GROUND: Soft, dark brown, sandy, slightly gravelly, silty CLAY. Gravel is angular to subrounded, fine and medium including brick, charcoal, quartzite and sandstone.

Soft, brown mottled grey, slightly gravelly, very sandy CLAY. Gravel is subangular to subrounded, fine and medium including sandstone and siltstone.

Soft, greyish brown, slightly sandy, slightly gravelly, silty CLAY. Gravel is angular to subrounded, fine and medium including sandstone, mudstone and quartzite.

Stiff, greyish brown, slightly sandy, slightly gravelly, silty CLAY. Gravel is subangular to subrounded, fine to coarse including sandstone, siltstone and mudstone.

At 4.00m: very high strength.

End of Borehole at 4.45m

Legend

1

2

3

4

5

6

7

8

9

10

GroundwaterWaterStrike

Backfill/Installation

0.30 D20.30 ES1

0.70 B40.70 ES3

1.20 SPT(S) N=5 (1,1/1,1,1,2)1.20 - 1.65 D5

2.00 D72.00 - 2.45 UT6 21 blows. 100% recovery

2.50 D8

3.00 SPT(S) N=18 (2,3/2,4,4,8)3.00 - 3.45 D9

3.50 D10

4.00 - 4.45 UT11

Plant used:

Dando 2000Dates:

29/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

WS02Sheet 1 of 1

Dynamic SampleBorehole Log

Location:

385557.41E 434792.76NGround level: Logged by:

AMVertical scale:

1:50Project ID:

42367

Checked by:Log status:

HHDRAFT

IFA DSv01.01

Remarks:

SPT Hammer: PM1 Energy Ratio: 72%

Dynamic Sample RecoveryTop (m) Base (m) Dia (mm) Recovery % Remarks Service inspection pit hand excavated from GL to 1.20m.

Water StrikesStrike (m) Cased (m) Sealed (m) Time (mins) Rose to (m) Remarks

Monitoring InstallationsTop (m) Base (m) Pipe Type Dia (mm)

Page 42: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

0.20

(1.30)

1.50

(3.95)

5.45

Strata Description

MADE GROUND: Soft dark brown, slightly sandy, slightly gravelly SILT. Gravel is subangular to subrounded, fine including sandstone.Soft, brown mottled grey, sandy, gravelly CLAY with frequent pockets of fine to coarse sand. Gravel is angular to subrounded, fine to coarse including sandstone and siltstone.

Firm, greyish brown, slightly sandy, slightly gravelly, silty CLAY. Gravel is subangular to subrounded, fine and medium including mudstone, sandstone, quartzite and siltstone.

End of Borehole at 5.45m

Legend

1

2

3

4

5

6

7

8

9

10

GroundwaterWaterStrike

Backfill/Installation

0.40 D20.40 ES10.70 B40.70 ES3

1.20 SPT(S) N=8 (2,2/1,2,2,3)1.20 - 1.65 D5

1.50 D6

2.00 SPT(S) N=15 (2,2/3,3,4,5)2.00 - 2.45 D7

3.00 SPT(S) N=15 (3,4/3,4,4,4)3.00 - 3.45 D8

3.50 D9

4.00 SPT(S) N=14 (3,3/2,3,4,5)4.00 - 4.45 D10

5.00 SPT(S) N=19 (0,4/4,4,5,6)5.00 - 5.45 D11

Plant used:

Dart 416Dates:

28/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

WS03Sheet 1 of 1

Dynamic SampleBorehole Log

Location:

385610.03E 434731.98NGround level: Logged by:

AMVertical scale:

1:50Project ID:

42367

Checked by:Log status:

HHDRAFT

IFA DSv01.01

Remarks:

SPT Hammer: PM1 Energy Ratio: 72%

Dynamic Sample RecoveryTop (m) Base (m) Dia (mm) Recovery % Remarks1.20 2.00 1002.00 3.00 1003.00 4.00 204.00 5.00 20

Service inspection pit hand excavated from GL to 1.20m.

Water StrikesStrike (m) Cased (m) Sealed (m) Time (mins) Rose to (m) Remarks

1.00 20 1.00

Monitoring InstallationsTop (m) Base (m) Pipe Type Dia (mm)

Page 43: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

(0.50)

0.50

(1.20)

1.70

(1.72)

3.43

Strata Description

MADE GROUND: Soft to firm, dark brown, sandy, slightly gravelly CLAY with frequent rootlets. Gravel is angular to subrounded, fine and medium including brick, charcoal, sandstone and siltstone.

Firm, light grey mottled grey, slightly gravelly, very sandy, silty CLAY. Gravel is subangular to subrounded, fine and medium including sandstone, siltstone.

At 1.20m: medium strength

Stiff, greyish brown, slightly silty, slightly sandy, slightly gravelly CLAY with medium cobble content. Gravel is subangular to subrounded, fine and medium including sandstone, siltstone and mudstone.

End of Borehole at 3.42m

Legend

1

2

3

4

5

6

7

8

9

10

GroundwaterWaterStrike

Backfill/Installation

0.20 D20.20 ES1

0.70 ES30.80 B4

1.20 - 1.65 UT5 32 blows. 100% recovery

2.00 SPT(S) N=12 (3,3/2,3,3,4)

2.50 D6

3.00 SPT(S) 50 (2,4/50 for 275mm)

3.00 - 3.42 D7

Plant used:

Dart 416Dates:

29/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

WS04Sheet 1 of 1

Dynamic SampleBorehole Log

Location:

385580.44E 434759.74NGround level: Logged by:

AMVertical scale:

1:50Project ID:

42367

Checked by:Log status:

HHDRAFT

IFA DSv01.01

Remarks:

SPT Hammer: N/R, Energy Ratio: 72%

Dynamic Sample RecoveryTop (m) Base (m) Dia (mm) Recovery % Remarks Service inspection pit hand excavated from GL to 1.20m.

Water StrikesStrike (m) Cased (m) Sealed (m) Time (mins) Rose to (m) Remarks

Monitoring InstallationsTop (m) Base (m) Pipe Type Dia (mm)

Page 44: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

0.20

(1.30)

1.50

(2.50)

4.00

(1.45)

5.45

Strata Description

MADE GROUND: Soft, dark brown, slightly sandy, slightly gravelly, clayey SILT with frequent rootlets. Gravel is angular to subrounded, fine and medium including glass, brick and sandstone.Soft, brown mottled grey, slightly gravelly, very sandy CLAY. Gravel is subangular to subrounded, fine to coarse including sandstone.

Soft, greyish brown, slightly sandy, slightly gravelly CLAY with frequent interbeds of fine to coarse sand. Gravel is subangular to subrounded, fine and medium including quartzite and sandstone.

Medium dense, greyish brown, fine and medium SAND. Gravel is subangular to subrounded, fine including sandstone.

End of Borehole at 5.45m

Legend

1

2

3

4

5

6

7

8

9

10

GroundwaterWaterStrike

Backfill/Installation

0.10 ES1

0.50 B30.50 ES2

1.20 SPT(S) N=6 (1,2/2,2,1,1)1.20 - 1.65 D4

1.50 D5

2.00 SPT(S) N=22 (2,3/5,6,6,5)2.00 B6

2.00 - 2.45 D62.30 D7

2.80 D83.00 SPT(S) N=15 (1,2/3,4,4,4)

3.00 - 3.45 D9

3.70 D10

4.00 SPT(S) N=16 (3,4/4,4,4,4)4.00 - 4.45 D124.00 - 5.00 B11

5.00 SPT(S) N=19 (6,4/4,5,5,5)5.00 - 5.45 D13

Plant used:

Dart 416Dates:

28/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

WS05Sheet 1 of 1

Dynamic SampleBorehole Log

Location:

385651.57E 434798.99NGround level: Logged by:

AMVertical scale:

1:50Project ID:

42367

Checked by:Log status:

HHDRAFT

IFA DSv01.01

Remarks:

SPT Hammer: PM1 Energy Ratio: 72%

Dynamic Sample RecoveryTop (m) Base (m) Dia (mm) Recovery % Remarks Service inspection pit hand excavated from GL to 1.20m.

Water StrikesStrike (m) Cased (m) Sealed (m) Time (mins) Rose to (m) Remarks

3.00 0 3.00

Monitoring InstallationsTop (m) Base (m) Pipe Type Dia (mm)

Page 45: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

0.050.10

(0.50)

0.60

Strata Description

MADE GROUND: Paving slab.MADE GROUND: Dark grey, gravelly, fine to coarse SAND. Gravel is angular to subrounded, fine including brick, quartzite and sandstone.MADE GROUND: Firm, brown mottled grey, slightly sandy, slightly gravelly CLAY. Gravel is angular to subrounded, fine to coarse including sandstone, quartzite and brick.

End of Trial Pit at 0.60m

Legend Scale

1

2

3

4

5

WaterStrike

Backfill/Installation

0.45 HVP=95kPa0.50 ES1

Plant used:

Hand excavated Dates:

28/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

FP01Sheet 1 of 1

Trial Pit LogLocation:

385596.35E 434761.81NGround level: Logged by:

GHVertical scale:

1:25Contract ID:

42367

Termination: Stability:

Terminated at 0.60m due to flooding.

Dimensions (Length m x Width m):0.50 x 0.50

Trial pit remained stable during excavation

Checked by:Status:

HHDRAFT

IFA TP v01.01

Water StrikesStrike (m) Time (mins) Rose to (m) Remarks

Remarks:Please refer to sketch for further details.

Page 46: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Isaac Centre, Harrogate Crescent, BB10 2NX

Foundation Pit Sketch FP01

Contract No. 42367

Water level

Ground level

0.50m

0.20m

Building

0.60m

Plan view Cross section

Concrete

0.50m

0.50m

0.20m

Page 47: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

0.20

(0.60)

0.80

(0.40)

1.20

Strata Description

MADE GROUND: Grass over soft dark brown, slightly sandy, slightly gravelly, clayey SILT with frequent rootlets.

MADE GROUND: Dark grey, slightly gravelly, very clayey, fine to coarse SAND with low cobble content. Gravel is angular to subrounded, fine to coarse including brick, quartzite, sandstone and charcoal. Cobbles are subangular of brick.

Firm, brown mottled grey, slightly sandy, slightly gravelly, silty CLAY. Gravel is subangular to subrounded, fine and medium including sandstone.

End of Trial Pit at 1.20m

Legend Scale

1

2

3

4

5

WaterStrike

Backfill/Installation

0.40 D20.40 ES1

0.90 HVP=125kPa

1.20 D41.20 ES3

Plant used:

Hand excavatedDates:

28/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

HDP01Sheet 1 of 1

Trial Pit LogLocation:

385550.44E 434766.53NGround level: Logged by:

AMVertical scale:

1:25Contract ID:

42367

Termination: Stability:

Dimensions (Length m x Width m):0.30 x 0.30

Trial pit remained stable during excavation.

Checked by:Status:

HHDRAFT

IFA TP v01.01

Water StrikesStrike (m) Time (mins) Rose to (m) Remarks

Remarks:

Page 48: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

0.20

(0.30)

0.50

(0.70)

1.20

Strata Description

MADE GROUND: Soft, dark brown, slightly sandy, slightly gravelly, clayey SILT with frequent rootlets.

Brown, gravelly, fine and medium SAND. Gravel is angular to subrounded, fine and medium including sandstone and quartzite.

Soft, grey mottled brown, slightly gravelly, sandy, silty CLAY. Gravel is subangular to subrounded, fine and medium including sandstone and siltstone.

End of Trial Pit at 1.20m

Legend Scale

1

2

3

4

5

WaterStrike

Backfill/Installation

0.10 D1

0.40 ES2

1.20 D41.20 ES3

Plant used:

Hand excavatedDates:

28/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

HDP03Sheet 1 of 1

Trial Pit LogLocation:

385627.44E 434762.77NGround level: Logged by:

AMVertical scale:

1:25Contract ID:

42367

Termination: Stability:

Dimensions (Length m x Width m):0.40 x 0.40

Trial pit remained stable during excavation.

Checked by:Status:

HHDRAFT

IFA TP v01.01

Water StrikesStrike (m) Time (mins) Rose to (m) Remarks

1.00 0 1.00

Remarks:

Page 49: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Samples & In Situ Testing

Depth Sample ID Test Result

Strata DetailsLevel

(mOD)Depth (m)

(Thickness)

0.10

(1.10)

1.20

Strata Description

MADE GROUND: Soft, dark brown, slightly sandy, slightly gravelly, silty CLAY with frequent rootlets. Gravel is subangular to subrounded, fine including sandstone and brick.MADE GROUND: Brownish grey, sandy gravelly CLAY. Gravel is angular to subrounded, fine to coarse including brick, sandstone, siltstone, charcoal and quartzite.

End of Trial Pit at 1.20m

Legend Scale

1

2

3

4

5

WaterStrike

Backfill/Installation

0.50 D20.50 ES1

1.20 D41.20 ES3

Plant used:

Hand excavatedDates:

28/08/2019

Project:

Isaac Centre, BurnleyClient:

Lancashire County Council

Location ID:

HDP04Sheet 1 of 1

Trial Pit LogLocation:

385604.16E 434774.47NGround level: Logged by:

AMVertical scale:

1:25Contract ID:

42367

Termination: Stability:

Dimensions (Length m x Width m):0.40 x 0.40

Trial pit remained stable during excavation.

Checked by:Status:

HHDRAFT

IFA TP v01.01

Water StrikesStrike (m) Time (mins) Rose to (m) Remarks

Remarks:

Page 50: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

APPENDIX 3

LABORATORY TESTS

Page 51: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 3 pages iii/i-iii/iii iii/i

APPENDIX 3

GENERAL NOTES ON LABORATORY TESTS ON SOILS

A3.1 GENERAL

A3.1.1 Where applicable all tests are carried out in accordance with the relevant British Standard. The laboratory test procedures are as below:

Test Name Procedures BS1377:1990 Part:Clause Moisture Content 2:3 Liquid Limit 2:4 Plastic Limit and Plastic Index 2:5 Particle Size Distribution 9.2 Sedimentation 9.4 Mass Loss on Ignition 3.4 Sulphate content 3:5 pH Value 3:9 Compaction Test 4:3 California Bearing Ratio 4:7 Consolidation 5:3 Bulk Density 7:2* Laboratory Vane Tests 7:3* Triaxial Compression Total Stress Single-Stage 7:8 Total Stress Multi-Stage 7:9 Desiccation Note 1* Note 1 - BRE Information paper IP4 issued February 1993 * Tests are not included in UKAS accreditation

A3.1.2 Where an external laboratory carried out testing, their report, including test methods is included in this Appendix.

A3.1.3 A summary sheet of laboratory test results undertaken by Ian Farmer Laboratories is included, however where copies of the individual test results are required these will be provided on request.

A3.1.4 Any discussion in this report is based on the values and results obtained from the appropriate tests. Due allowance should be made, when considering any result in isolation, of the possible inaccuracy of any such individual result. Details of the accuracy of results are included in this section, where applicable.

A3.2 MOISTURE CONTENT

A3.2.1 Unless stated to the contrary, the moisture content of a soil sample was determined by the standard oven drying method, BS 1377, Part 1, Test 3. The result is reported to an accuracy of 0.5%

A3.3 ATTERBERG LIMITS

A3.3.1 The Liquid Limit, LL, is the moisture content at which the soil passes from the liquid to plastic state. Unless stated to the contrary, the Liquid Limit was determined using the four point, cone penetrometer method, Test 4. The value is reported to the nearest whole number, to an accuracy of 0.5%.

A3.3.2 The Plastic Limit, PL, is the moisture content at which soil passes from the plastic to solid state and becomes too dry to remain in a plastic condition. The Plastic Limit was determined using the method described in Test 5. The value is reported to the nearest whole number, to an accuracy of 0.5%.

Page 52: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 3 pages iii/i-iii/iii iii/ii

A3.3.3 The Plasticity Index, PI, is the numerical difference between the liquid and plastic limits, corresponding to the range of moisture contents over which a soil is in a plastic state. The determination of the Plasticity Index is covered by Test 5.

A3.4 SOIL CLASSIFICATION

A3.4.1 Classification of soils is usually undertaken by means of the Plasticity Classification Chart, sometimes called the A-Line Chart. This is graphical plot of PI against LL with the A-Line defined as PI = 0.73(LL - 20).

A3.4.2 This line is defined from experimental evidence and does not represent a well defined boundary between soil types, but forms a useful reference datum. When the values of LL and PI for inorganic clays are plotted on the chart they generally lie just above the A-Line in a narrow band parallel to it, while silts and organic clays plot below this line.

A3.4.3 Clays and silts are divided into five zones of plasticity:

Low Plasticity (L) LL less than 35

Intermediate Plasticity (I) LL between 35 and 50

High Plasticity (H) LL between 50 and 70

Very High Plasticity (V) LL between 70 and 90

Extremely High Plasticity (E) LL greater than 90

A3.4.4 In general, clays of high plasticity are likely to have a lower permeability, are more compressible and consolidate over a longer period of time under load than clays of low plasticity. Clays of high plasticity are more difficult to compact as fill material.

A3.5 SHEAR STRENGTH TESTS

A3.5.1 The shear strength tests have been carried out in accordance with the procedures given in BS1377, Part 7.

The type of test referred to is:

A3.5.2 U1(100) - Undrained triaxial compression test on single specimen of 100mm diameter at a lateral pressure approximately equal to overburden pressure.

A3.5.3 UM(100) - Multi-stage undrained triaxial compression test on a specimen of 100mm diameter. An initial low cell pressure is applied and the deviator stress increased until failure is imminent. The cell pressure is then increased and the procedure repeated until the failure stress at three different cell pressures have been determined.

A3.5.4 U1(38) - Undrained triaxial compression test on a single specimen of 38mm diameter at a lateral pressure approximately equal to overburden pressure.

A3.5.5 U(38) - Undrained triaxial compression test on set of three specimens of 38mm diameter at three differential lateral pressures.

A3.5.6 Consolidated undrained triaxial – The Effective Stress Parameters were determined in accordance with the procedure detailed in BS1377: Part 8:1990 Clause 7 and the samples were prepared in accordance with clause 4.

A3.5.7 Small shearbox – The peak, and in some cases residual, shear stress parameters were determined in accordance with the procedure detailed in BS1377: Part 7: 1990 Clause 4 and the samples were prepared in accordance with clause 4.

Page 53: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 3 pages iii/i-iii/iii iii/iii

A3.6 CHEMICAL TESTS

A3.6.1 The total sulphate content of soil was determined using the gravimetric method detailed in BS1377: Part 3:1990, Test 5. The results are recorded to an accuracy of 0.1%.

A3.6.2 The water soluble sulphate content of soil was determined using the gravimetric method detailed in BS1377: Part 3: 1990, Test 5. The results are recorded to an accuracy of 0.1g/l.

A3.6.3 The sulphate content of groundwater was determined using the gravimetric method detailed in BS1377: Part 3: 1990, Test 5. The results are record to an accuracy of 0.1g/l.

A3.6.4 The pH value was determined electrometrically using the procedures given in BS 1377: Part 3: 1990, Test 9. The results are recorded to an accuracy of 0.1 pH units.

A3.6.5 The total sulphur content of soil was determined using the ignition in oxygen method detailed in TRL Report 447, Test 4B.

A3.6.6 The organic content of soil was determined in accordance with the chemical method detailed in BS1377: Part 3:1990 Clause 3. The sample was prepared in accordance with Clause 3.4.2.

A3.6.7 The organic content of soil was determined in accordance with the loss on ignition method detailed in BS1377: Part 3:1990 Clause 4. The sample was prepared in accordance with Clause 4.3.2.

Page 54: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Site:

Job Number:

Originating Client:

Originating Reference:

Date Sampled:

Date Scheduled:

Date Testing Started:

Date Testing Finished:

Amendments:

Authorised By:

Tim RobinsonQuality Technician Report Issue Date: 02/10/2019

Page. 1

Previous Reports Amendments Date Issued

Isaac Centre, Burnley

42367

Lancashire County Council

42367

29/08/2019

03/09/2019

12/09/2019

01/10/2019

F.A.O.

Final Test Report - 42367 / 1

Tim Robinson

Page 55: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

1.20 19.7 98 20.0 41 23 18

4.00 18.3 97 19.0 38 18 20

2.00 18.4 79 22.0 35 15 20

1.20 17.8 74 22.0 33 17 16

2.20 17.5 95 18.0 31 18 13

4.00 18.8 91 20.0 35 16 19

1.20 13.8

3.20 16

5.20 12.8

8.00 17

1.20 15.6 95 16.0 39 21 18

5.00 15.4

1.20 18.7 94 20.0 36 19 17

1.20 25.1

2.00 15.3 66 21.0 38 19 19

2.50 14.9 90 16.0 37 18 19

1.50 16 55 25.0 31 17 14

3.50 16.5

5.00 19.4

3.00 13.5 93 14.0 35 18 17

1.50 14.2 59 21.0 24 18 6

3.00 18.4

4.00 13.6

Site: Isaac Centre, Burnley Job Number: 42367

Natural / Sieved

Natural Water

Content %

Laboratory Test Report 42367 / 1

Liquidity Index Class

Client: Lancashire County Council Page: 2

Determination of Water Content, Liquid Limit and Plastic Limit and Derivation of Plasticity and Liquidity Index

Borehole / Trial Pit Depth (m) Sample Description / Remarks

Percentage %

Water Content %

Sample Passing425 µm Sieve Liquid Limit

%Plastic Limit

%Plasticity Index %

BH01 D6 Natural -0.16 CI Brown slightly gravelly, silty CLAY

BH01 UT11 Natural 0.03 CI Brown slightly gravelly, silty CLAY

BH02 UT8 Natural 0.35 CL/CI Brown sandy, silty, very gravelly CLAY

BH02A UT3 Natural 0.33 CL Brown gravelly, sandy, silty, organic CLAY

BH02A D6 Natural 0.01 CL Brown silty CLAY

BH02A D9 Natural 0.22 CL/CI Brown gravelly, silty CLAY

BH03 D7 Brown slightly gravelly, sandy CLAY/SILT

BH03 D11 Brown slightly gravelly, silty CLAY

BH03 D15 Brown slightly gravelly, silty CLAY

BH03 D19 Brown slightly gravelly, silty CLAY

BH04 UT7 Natural -0.27 CI Brown slightly gravely, silty CLAY

BH04 D15Brown slightly sandy, slightly gravelly, silty

CLAY

WS01 D4 Natural 0.04 CI Brown slightly gravelly, silty CLAY

WS02 D5Brown slightly sandy, slightly gravelly, silty

CLAY

WS02 UT6 Natural 0.09 CI Brown silty, gravelly CLAY

WS02 D8 Natural -0.10 CI Brown gravelly, silty CLAY

WS03 D6 Natural 0.58 CL Brown sandy, gravelly, silty CLAY

WS03 D9 Brown slightly gravelly, silty CLAY

WS03 D11 Brown slightly gravelly, silty CLAY

WS04 D7 Natural -0.22 CL/CI Brown gravelly, silty CLAY

WS05 D5 Sieved 0.42 CL Brown sandy, gravelly SILT/CLAY

WS05 D9 Brown sandy, gravelly SILT

WS05 D12 Brown slightly sandy, gravelly, silty CLAY

Method of Preparation: BS EN ISO 17892 : Part 1 : 2014 : Clause 5.1 Water content test preparationBS 1377 : Part 1 : 2016 : Clause 8.4.3 Preparation of samples for plasticity testsBS 1377 : Part 2 : 1990 : Clause 4.2 Preparation of samples for plastic limit tests

Method of Test: BS EN ISO 17892 : Part 1 : 2014 : Clause 5.2 Water content test executionBS 1377 : Part 2 : 1990 : Clause 4.3 or 4.4 Determination of the liquid limitBS 1377 : Part 2 : 1990 : Clause 5.3 Determination of the plastic limit and plasticity index

Page 56: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

mmmmmmmm

RemarksPreparation and testing in accordance with BS1377 unless noted below

Laboratory Test Report 42367 / 1

Site: Isaac Centre, Burnley Job Number: 42367

Client: Lancashire County Council Page: 3

DETERMINATION OF PARTICLE SIZE DISTRIBUTION

Borehole / Trial Pit Depth (m) Sample Testing Type Description

BH01 1.20 B5 Wet Sieve + Pipette Brown slightly gravelly, sandy CLAY/SILT

Sieving SedimentationParticle Size

mm % Passing Particle Size mm % Passing Dry Mass of sample, g 560

0.0201 650.0060 49 Sample Proportions % dry mass0.0020 36 Very coarse 0

Gravel 5Sand 20Silt 39Clay 36

Grading Analysis20 100 D100 1414 100 D60 0.013810 99 D306.3 98 D105 97 Uniformity Coefficient

3.35 96 Curvature Coefficient2 95 Particle density (assumed)

1.18 94 2.65 Mg/m30.63 920.425 900.3 880.2 85

0.15 830.063 75

Method of Preparation: BS 1377:Part 1:1990, clause 7 3 Initial preparationBS 1377:Part 1:1990, clause 7.4.5 Preparation of particle size tests

Method of Test: BS1377:Part 2:1990, clause 9.2 Determination of particle size distribution by wet sieving methodBS1377:Part 2:1990, clause 9.4 Determination of sedimentation by pipette method

÷÷

ø

ö

çç

è

æ

1m

m

SILTFine Medium Coarse

SANDFine Medium Coarse

GRAVELFine Medium CoarseCLAY COBBLES BOULDERS

0

10

20

30

40

50

60

70

80

90

100

0.001 0.01 0.1 1 10 100 1000

Perc

enta

ge P

assi

ng %

Particle Size mm

Page 57: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

mmmmmmmm

RemarksPreparation and testing in accordance with BS1377 unless noted below

Laboratory Test Report 42367 / 1

Site: Isaac Centre, Burnley Job Number: 42367

Client: Lancashire County Council Page: 4

DETERMINATION OF PARTICLE SIZE DISTRIBUTION

Borehole / Trial Pit Depth (m) Sample Testing Type Description

BH03 1.20 B6 Wet Sieve + Pipette Brown slightly gravelly, sandy CLAY/SILT

Sieving SedimentationParticle Size

mm % Passing Particle Size mm % Passing Dry Mass of sample, g 540

0.0201 550.0060 42 Sample Proportions % dry mass0.0020 29 Very coarse 0

Gravel 9Sand 26Silt 36Clay 29

Grading Analysis20 100 D100 2014 96 D60 0.034710 95 D30 0.002126.3 94 D105 93 Uniformity Coefficient

3.35 92 Curvature Coefficient2 91 Particle density (assumed)

1.18 89 2.65 Mg/m30.63 870.425 840.3 820.2 78

0.15 750.063 65

Method of Preparation: BS 1377:Part 1:1990, clause 7 3 Initial preparationBS 1377:Part 1:1990, clause 7.4.5 Preparation of particle size tests

Method of Test: BS1377:Part 2:1990, clause 9.2 Determination of particle size distribution by wet sieving methodBS1377:Part 2:1990, clause 9.4 Determination of sedimentation by pipette method

÷÷

ø

ö

çç

è

æ

1m

m

SILTFine Medium Coarse

SANDFine Medium Coarse

GRAVELFine Medium CoarseCLAY COBBLES BOULDERS

0

10

20

30

40

50

60

70

80

90

100

0.001 0.01 0.1 1 10 100 1000

Perc

enta

ge P

assi

ng %

Particle Size mm

Page 58: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

mmmmmmmm

RemarksPreparation and testing in accordance with BS1377 unless noted below

Laboratory Test Report 42367 / 1

Site: Isaac Centre, Burnley Job Number: 42367

Client: Lancashire County Council Page: 5

DETERMINATION OF PARTICLE SIZE DISTRIBUTION

Borehole / Trial Pit Depth (m) Sample Testing Type Description

BH04 2.00 B9 Wet Sieve + Pipette Brown gravelly, sandy CLAY/SILT

Sieving SedimentationParticle Size

mm % Passing Particle Size mm % Passing Dry Mass of sample, g 544

0.0201 550.0060 39 Sample Proportions % dry mass0.0020 28 Very coarse 0

Gravel 14Sand 24Silt 34Clay 28

28 100 Grading Analysis20 96 D100 2814 94 D60 0.048210 93 D30 0.002476.3 90 D105 89 Uniformity Coefficient

3.35 87 Curvature Coefficient2 86 Particle density (assumed)

1.18 84 2.65 Mg/m30.63 810.425 790.3 760.2 72

0.15 690.063 62

Method of Preparation: BS 1377:Part 1:1990, clause 7 3 Initial preparationBS 1377:Part 1:1990, clause 7.4.5 Preparation of particle size tests

Method of Test: BS1377:Part 2:1990, clause 9.2 Determination of particle size distribution by wet sieving methodBS1377:Part 2:1990, clause 9.4 Determination of sedimentation by pipette method

÷÷

ø

ö

çç

è

æ

1m

m

SILTFine Medium Coarse

SANDFine Medium Coarse

GRAVELFine Medium CoarseCLAY COBBLES BOULDERS

0

10

20

30

40

50

60

70

80

90

100

0.001 0.01 0.1 1 10 100 1000

Perc

enta

ge P

assi

ng %

Particle Size mm

Page 59: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

mmmmmmmm

RemarksPreparation and testing in accordance with BS1377 unless noted below

Laboratory Test Report 42367 / 1

Site: Isaac Centre, Burnley Job Number: 42367

Client: Lancashire County Council Page: 6

DETERMINATION OF PARTICLE SIZE DISTRIBUTION

Borehole / Trial Pit Depth (m) Sample Testing Type Description

WS05 0.50 B3 Wet Sieve + Pipette Brown clayey, silty, gravelly SAND

Sieving SedimentationParticle Size

mm % Passing Particle Size mm % Passing Dry Mass of sample, g 1195

0.0201 240.0060 17 Sample Proportions % dry mass0.0020 11 Very coarse 0

Gravel 27Sand 41Silt 21

50 100 Clay 1137.5 9528 91 Grading Analysis20 85 D100 5014 81 D60 0.26710 79 D30 0.05096.3 76 D105 75 Uniformity Coefficient

3.35 74 Curvature Coefficient2 73 Particle density (assumed)

1.18 71 2.65 Mg/m30.63 680.425 650.3 620.2 56

0.15 480.063 31

Method of Preparation: BS 1377:Part 1:1990, clause 7 3 Initial preparationBS 1377:Part 1:1990, clause 7.4.5 Preparation of particle size tests

Method of Test: BS1377:Part 2:1990, clause 9.2 Determination of particle size distribution by wet sieving methodBS1377:Part 2:1990, clause 9.4 Determination of sedimentation by pipette method

÷÷

ø

ö

çç

è

æ

1m

m

SILTFine Medium Coarse

SANDFine Medium Coarse

GRAVELFine Medium CoarseCLAY COBBLES BOULDERS

0

10

20

30

40

50

60

70

80

90

100

0.001 0.01 0.1 1 10 100 1000

Perc

enta

ge P

assi

ng %

Particle Size mm

Page 60: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Laboratory Test Report 42367 / 1

Site: Isaac Centre, Burnley Job Number: 42367

Client: Lancashire County Council Page: 7

DETERMINATION OF THE ONE-DIMENSIONAL CONSOLIDATION PROPERTIES

Borehole / Trial Pit Depth (m) Sample Description

BH01 2 UT7 Brown slightly sandy, slightly gravelly CLAY

Initi

al S

peci

men Length of Sample (mm) 382.71 Diameter (mm) 75.02

Depth from top of specimen (mm) 15.20 Particle density (Mg/m³) 2.65 assumed

Condition of Sample: Undisturbed Swelling Pressure (kPa)

Orientation: Vertical Lab Temp. (°C) 21

Initial FinalApplied

PressurekPa

Mvm2/MN

Cv(t50, log)

m2/yr

Cv(t90, root)

m2/yrCsec Voids ratio

Height (mm) 19.02 17.99

Water Content (%) 19.0 18.00.0 - - - - 0.505

2.10 2.2080 0.16 6.5 14 0.00076 0.49140 0.066

0.14 3.7 15 0.00075 0.475

Bulk density (Mg/m³)3.2 21 0.00021 0.501

Dry density (Mg/m³) 1.76 1.86320 0.12 2.5 16 0.0008 0.448160

0.505 0.4231,280 0.047 2 3.4 0.0019 0.368640 0.08

0.033 0.423

Voids Ratio1.9 9.8 0.00098 0.411

Degree of Saturation (%) 100 11440

Remarks / DeviationsGRAVEL REMOVED FROM SAMPLE.

Method of Preparation: BS EN 17892:Part 5:2017, clause 6.2 Specimen preparationBS EN 17892:Part 5:2017, clause 6.4 Preparation of apparatus

Method of Test: BS EN 17892:Part 5:2017, clause 6 Test procedure for incremental loading oedometer testResults corrected for equipment deformation

eo

0.320

0.340

0.360

0.380

0.400

0.420

0.440

0.460

0.480

0.500

0.520

Void

s R

atio

0.002.004.006.008.00

10.00

1 10 100 1000 10000

Cv

m2 /y

r(lo

g tim

e)

Applied Pressure kPa

Page 61: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Laboratory Test Report 42367 / 1

Site: Isaac Centre, Burnley Job Number: 42367

Client: Lancashire County Council Page: 8

DETERMINATION OF THE ONE-DIMENSIONAL CONSOLIDATION PROPERTIES

Borehole / Trial Pit Depth (m) Sample Description

BH04 3 UT11 Brown slightly silty, gravelly CLAY

Initi

al S

peci

men Length of Sample (mm) 388.28 Diameter (mm) 75.02

Depth from top of specimen (mm) 12.62 Particle density (Mg/m³) 2.65 assumed

Condition of Sample: Undisturbed Swelling Pressure (kPa)

Orientation: Vertical Lab Temp. (°C) 21

Initial FinalApplied

PressurekPa

Mvm2/MN

Cv(t50, log)

m2/yr

Cv(t90, root)

m2/yrCsec Voids ratio

Height (mm) 19.01 17.49

Water Content (%) 16.0 15.00.0 - - - - 0.464

2.10 2.26120 0.23 6.5 32 0.001 0.43760 0.075

0.17 3.9 20 0.001 0.408

Bulk density (Mg/m³)19 18 0.00069 0.457

Dry density (Mg/m³) 1.81 1.97480 0.11 1.7 28 0.0012 0.372240

0.464 0.3471,920 0.032 1.7 2.8 0.0014 0.293960 0.058

0.022 0.347

Voids Ratio1.5 3.7 0.00071 0.334

Degree of Saturation (%) 91 11460

Remarks / DeviationsGRAVEL REMOVED FROM SAMPLE.

Method of Preparation: BS EN 17892:Part 5:2017, clause 6.2 Specimen preparationBS EN 17892:Part 5:2017, clause 6.4 Preparation of apparatus

Method of Test: BS EN 17892:Part 5:2017, clause 6 Test procedure for incremental loading oedometer testResults corrected for equipment deformation

eo

0.280

0.300

0.320

0.340

0.360

0.380

0.400

0.420

0.440

0.460

0.480

Void

s R

atio

0.005.00

10.0015.0020.0025.00

1 10 100 1000 10000

Cv

m2 /y

r(lo

g tim

e)

Applied Pressure kPa

Page 62: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Laboratory Test Report 42367 / 1

Site: Isaac Centre, Burnley Job Number: 42367

Client: Lancashire County Council Page: 9

Unconsolidated Undrained Triaxial Compression Test without measurement of pore pressure - single specimen (Definitive Method)

Borehole / Trial Pit

Depth (m) Sample Description

Orientation

BH01 2.00 UT7 Brown slightly sandy, slightly gravelly CLAY

Original Length (mm) 382.71

Depth from Top (mm) 45.61

Condition Undisturbed

Vertical

Length (mm) 210.59

Diameter (mm) 103.21

Moisture Content (%) 21.80

Initi

al S

ampl

e

Test Number 1

Bulk Density (Mg/m3) 2.13

Dry Density (Mg/m3) 1.75

Membrane Thickness (mm) 0.32

Membrane Type Latex

Rate of Strain (%/min) 1.9

Test

Res

ults

Cell Pressure (kPa) 40

Axial Strain (%) 20

Membrane Corr. (kPa) 1.19

Deviator Stress, ( σ1 - σ3 )f

(kPa) 302

Undrained Shear Strength, cu = ½( σ1 - σ3 )f (kPa)

151

Mode of Failure Compound

Deviator stress corrected for area change and membrane effects

Mohr circles and their interpretation is not covered by BS1377.This is provided for information only.

Method of Preparation: BS 1377:PT1:1990:8.3 Preparation of undisturbed samples for testing orBS 1377:PT1:1990:7.7.5.2 Preparation of disturbed samples for testing

Method of Test: BS 1377:PT2:1990:7.2 Determination of density by linear measurement. BS 1377:PT7:1990:8.4 Determination of undrained shear strength in triaxial compression without measurement of pore pressure (Definitive method)

0

50

100

150

200

250

300

350

0 5 10 15 20 25

Cor

rect

ed D

evia

tor S

tress

kPa

Axial Strain %

Deviator Stress v Axial Strain

0

50

100

150

200

250

300

350

0 50 100 150 200 250 300 350

Shea

r Stre

ngth

kPa

Normal Stresses kPa

Mohr Circles

Page 63: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Laboratory Test Report 42367 / 1

Site: Isaac Centre, Burnley Job Number: 42367

Client: Lancashire County Council Page: 10

Unconsolidated Undrained Triaxial Compression Test without measurement of pore pressure - single specimen (Definitive Method)

Borehole / Trial Pit

Depth (m) Sample Description

Orientation

BH02A 8.00 UT13 Brown slightly gravelly, silty CLAY

Original Length (mm) 458.59

Depth from Top (mm) 60.70

Condition Undisturbed

Vertical

Length (mm) 208.83

Diameter (mm) 102.76

Moisture Content (%) 10.90

Initi

al S

ampl

e

Test Number 1

Bulk Density (Mg/m3) 2.14

Dry Density (Mg/m3) 1.93

Membrane Thickness (mm) 0.35

Membrane Type Latex

Rate of Strain (%/min) 1.9

Test

Res

ults

Cell Pressure (kPa) 160

Axial Strain (%) 20

Membrane Corr. (kPa) 1.32

Deviator Stress, ( σ1 - σ3 )f

(kPa) 279

Undrained Shear Strength, cu = ½( σ1 - σ3 )f (kPa)

140

Mode of Failure Plastic

Deviator stress corrected for area change and membrane effects

Mohr circles and their interpretation is not covered by BS1377.This is provided for information only.

Method of Preparation: BS 1377:PT1:1990:8.3 Preparation of undisturbed samples for testing orBS 1377:PT1:1990:7.7.5.2 Preparation of disturbed samples for testing

Method of Test: BS 1377:PT2:1990:7.2 Determination of density by linear measurement. BS 1377:PT7:1990:8.4 Determination of undrained shear strength in triaxial compression without measurement of pore pressure (Definitive method)

0

50

100

150

200

250

300

0 5 10 15 20 25

Cor

rect

ed D

evia

tor S

tress

kPa

Axial Strain %

Deviator Stress v Axial Strain

0

50

100

150

200

250

300

350

400

450

0 50 100 150 200 250 300 350 400 450

Shea

r Stre

ngth

kPa

Normal Stresses kPa

Mohr Circles

Page 64: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Laboratory Test Report 42367 / 1

Site: Isaac Centre, Burnley Job Number: 42367

Client: Lancashire County Council Page: 11

Unconsolidated Undrained Triaxial Compression Test without measurement of pore pressure - single specimen (Definitive Method)

Borehole / Trial Pit

Depth (m) Sample Description

Orientation

BH04 3.00 UT11 Brown slightly silty, gravelly CLAY

Original Length (mm) 388.28

Depth from Top (mm) 46.56

Condition Undisturbed

Vertical

Length (mm) 207.19

Diameter (mm) 103.47

Moisture Content (%) 12.20

Initi

al S

ampl

e

Test Number 1

Bulk Density (Mg/m3) 2.22

Dry Density (Mg/m3) 1.98

Membrane Thickness (mm) 0.35

Membrane Type Latex

Rate of Strain (%/min) 1.9

Test

Res

ults

Cell Pressure (kPa) 60

Axial Strain (%) 20

Membrane Corr. (kPa) 1.32

Deviator Stress, ( σ1 - σ3 )f

(kPa) 299

Undrained Shear Strength, cu = ½( σ1 - σ3 )f (kPa)

150

Mode of Failure Compound

Deviator stress corrected for area change and membrane effects

Mohr circles and their interpretation is not covered by BS1377.This is provided for information only.

Method of Preparation: BS 1377:PT1:1990:8.3 Preparation of undisturbed samples for testing orBS 1377:PT1:1990:7.7.5.2 Preparation of disturbed samples for testing

Method of Test: BS 1377:PT2:1990:7.2 Determination of density by linear measurement. BS 1377:PT7:1990:8.4 Determination of undrained shear strength in triaxial compression without measurement of pore pressure (Definitive method)

0

50

100

150

200

250

300

350

0 5 10 15 20 25

Cor

rect

ed D

evia

tor S

tress

kPa

Axial Strain %

Deviator Stress v Axial Strain

0

50

100

150

200

250

300

350

400

0 50 100 150 200 250 300 350 400

Shea

r Stre

ngth

kPa

Normal Stresses kPa

Mohr Circles

Page 65: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Laboratory Test Report 42367 / 1

Site: Isaac Centre, Burnley Job Number: 42367

Client: Lancashire County Council Page: 12

Unconsolidated Undrained Triaxial Compression Test without measurement of pore pressure - single specimen (Definitive Method)

Borehole / Trial Pit

Depth (m) Sample Description

Orientation

WS02 4.00 UT11 Brown silty, gravelly CLAY

Original Length (mm) 201.06

Depth from Top (mm) 37.38

Condition Undisturbed

Vertical

Length (mm) 134.67

Diameter (mm) 68.88

Moisture Content (%) 14.40

Initi

al S

ampl

e

Test Number 1

Bulk Density (Mg/m3) 2.21

Dry Density (Mg/m3) 1.93

Membrane Thickness (mm) 0.35

Membrane Type Latex

Rate of Strain (%/min) 2.0

Test

Res

ults

Cell Pressure (kPa) 80

Axial Strain (%) 21

Membrane Corr. (kPa) 2.02

Deviator Stress, ( σ1 - σ3 )f

(kPa) 328

Undrained Shear Strength, cu = ½( σ1 - σ3 )f (kPa)

164

Mode of Failure Plastic

Deviator stress corrected for area change and membrane effects

Mohr circles and their interpretation is not covered by BS1377.This is provided for information only.

Method of Preparation: BS 1377:PT1:1990:8.3 Preparation of undisturbed samples for testing orBS 1377:PT1:1990:7.7.5.2 Preparation of disturbed samples for testing

Method of Test: BS 1377:PT2:1990:7.2 Determination of density by linear measurement. BS 1377:PT7:1990:8.4 Determination of undrained shear strength in triaxial compression without measurement of pore pressure (Definitive method)

0

50

100

150

200

250

300

350

0 5 10 15 20 25

Cor

rect

ed D

evia

tor S

tress

kPa

Axial Strain %

Deviator Stress v Axial Strain

0

50

100

150

200

250

300

350

400

450

0 50 100 150 200 250 300 350 400 450

Shea

r Stre

ngth

kPa

Normal Stresses kPa

Mohr Circles

Page 66: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Laboratory Test Report 42367 / 1

Site: Isaac Centre, Burnley Job Number: 42367

Client: Lancashire County Council Page: 13

Unconsolidated Undrained Triaxial Compression Test without measurement of pore pressure - single specimen (Definitive Method)

Borehole / Trial Pit

Depth (m) Sample Description

Orientation

WS04 1.20 UT5 Brown sandy, silty, gravelly CLAY

Original Length (mm) 304.17

Depth from Top (mm) 56.31

Condition Undisturbed

Vertical

Length (mm) 138.23

Diameter (mm) 68.86

Moisture Content (%) 23.60

Initi

al S

ampl

e

Test Number 1

Bulk Density (Mg/m3) 2.19

Dry Density (Mg/m3) 1.77

Membrane Thickness (mm) 0.32

Membrane Type Latex

Rate of Strain (%/min) 2.0

Test

Res

ults

Cell Pressure (kPa) 25

Axial Strain (%) 20

Membrane Corr. (kPa) 1.81

Deviator Stress, ( σ1 - σ3 )f

(kPa) 137

Undrained Shear Strength, cu = ½( σ1 - σ3 )f (kPa)

69

Mode of Failure Compound

Deviator stress corrected for area change and membrane effects

Mohr circles and their interpretation is not covered by BS1377.This is provided for information only.

Method of Preparation: BS 1377:PT1:1990:8.3 Preparation of undisturbed samples for testing orBS 1377:PT1:1990:7.7.5.2 Preparation of disturbed samples for testing

Method of Test: BS 1377:PT2:1990:7.2 Determination of density by linear measurement. BS 1377:PT7:1990:8.4 Determination of undrained shear strength in triaxial compression without measurement of pore pressure (Definitive method)

0

20

40

60

80

100

120

140

160

0 5 10 15 20 25

Cor

rect

ed D

evia

tor S

tress

kPa

Axial Strain %

Deviator Stress v Axial Strain

0

50

100

150

200

0 50 100 150 200

Shea

r Stre

ngth

kPa

Normal Stresses kPa

Mohr Circles

Page 67: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Initial Sample Test Results

Remarks

Axial compressive stress corrected for area change, and membrane effects (if used)

Laboratory Test Report 42367 / 1

Site: Isaac Centre, Burnley Job Number: 42367

Client: Lancashire County Council Page: 14

UNCONFINED COMPRESSIVE STRENGTH OF SOIL - LOAD FRAME METHOD

Borehole / Trial Pit

Depth (m) Sample Description

BH01 4.00 UT11 Brown slightly gravelly, silty CLAY

Test Number 1 Rate of Strain (%/min) 2

Length (mm) 209 Axial Strain (%) 16

Diameter (mm) 102 Unconfined Compressive Strength (kPa) 180

Method of Test: BS EN ISO 17892 : Part 1 : 2014 : Clause 5.2. Water content test executionBS EN ISO 17892 : Part 2 : 2014 : Clause 5.1. Density by linear measurement methodBS 1377 : Part 7 : 1990 : 7.2. Determination of unconfined compressive strength using the load frame method

Moisture Content (%) 18 Mode of Failure Compound

Bulk Density (Mg/m3) 2.07

Dry Density (Mg/m3) 1.75

Method of Preparation: BS EN ISO 17892 : Part 1 : 2014 : Clause 5.1. Water content test specimen preparationBS 1377 : Part 1 : 1990 : 8.3. Preparation of undisturbed samplles for testing

0

20

40

60

80

100

120

140

160

180

200

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32

Cor

rect

ed A

xial

Com

pres

sive

Stre

ss k

Pa

Axial Strain %

Axial Compressive Stress v Axial Strain

Page 68: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Initial Sample Test Results

Remarks

Axial compressive stress corrected for area change, and membrane effects (if used)

Laboratory Test Report 42367 / 1

Site: Isaac Centre, Burnley Job Number: 42367

Client: Lancashire County Council Page: 15

UNCONFINED COMPRESSIVE STRENGTH OF SOIL - LOAD FRAME METHOD

Borehole / Trial Pit

Depth (m) Sample Description

BH04 1.20 UT7 Brown slightly gravely, silty CLAY

Test Number 1 Rate of Strain (%/min) 2

Length (mm) 208 Axial Strain (%) 20

Diameter (mm) 102 Unconfined Compressive Strength (kPa) 22

Method of Test: BS EN ISO 17892 : Part 1 : 2014 : Clause 5.2. Water content test executionBS EN ISO 17892 : Part 2 : 2014 : Clause 5.1. Density by linear measurement methodBS 1377 : Part 7 : 1990 : 7.2. Determination of unconfined compressive strength using the load frame method

Moisture Content (%) 16 Mode of Failure Plastic

Bulk Density (Mg/m3) 2.10

Dry Density (Mg/m3) 1.81

Method of Preparation: BS EN ISO 17892 : Part 1 : 2014 : Clause 5.1. Water content test specimen preparationBS 1377 : Part 1 : 1990 : 8.3. Preparation of undisturbed samplles for testing

0

5

10

15

20

25

30

35

40

45

50

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32

Cor

rect

ed A

xial

Com

pres

sive

Stre

ss k

Pa

Axial Strain %

Axial Compressive Stress v Axial Strain

Page 69: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Site:

Job Number:

Originating Client:

Report Issue Date: 02/10/2019

Page. 16

Isaac Centre, Burnley

42367

Lancashire County Council

All opinions and interpretations contained within this report are outside of our Scope of Accreditation.

This test report shall not be reproduced, except in full and only with the written permission of Ian Farmer Associates Ltd.

Samples will be retained for 28 days from date of issue of the final test report before being disposed of, unless we receive written instruction to the contrary.

Final Test Report - 42367 / 1

Page 70: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 1 of 5

Units 7 & 8 Sandpits Business Park Mottram Road, Hyde, Cheshire, SK14 3AR

FINAL ANALYTICAL TEST REPORT

Envirolab Job Number: 19/08679 Issue Number: 1 Date: 25 September, 2019 Client: Ian Farmer Associates (Newcastle) Unit 4, Faraday Close Pattinson North Industrial Estate Washington Tyne and Wear NE38 8QJ Project Manager: Paul Cathcart; [email protected] Project Name: Isacc Centre, Burnley Project Ref: 42367 Order No: 46910 Date Samples Received: 17/09/19 Date Instructions Received: 17/09/19 Date Analysis Completed: 25/09/19 Prepared by: Approved by:

Melanie Marshall Danielle Brierley Laboratory Coordinator Client Manager

Page 71: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 2 of 5

Envirolab Job Number: 19/08679 Client Project Name: Isacc Centre, Burnley

Client Project Ref: 42367

Lab Sample ID 19/08679/1 19/08679/2 19/08679/3 19/08679/4 19/08679/5 19/08679/6 19/08679/7

Uni

ts

Lim

it of

Det

ectio

n

Met

hod

ref

Client Sample No 3 6 9 4 4 4 8

Client Sample ID BH01 BH01 BH02 BH02A BH03 WS01 WS02

Depth to Top 0.30 1.20 2.50 1.70 0.60 1.20 2.50

Depth To Bottom

Date Sampled 29-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19

Sample Type Soil - B Soil - D Soil - D Soil - D Soil - B Soil - D Soil - D

Sample Matrix Code 5A 5A 5A 5A 5A 5A 5AB

% Stones >10mmA <0.1 <0.1 0.7 <0.1 <0.1 <0.1 5.6 % w/w 0.1 A-T-044

pH BREDM# 7.72 8.03 8.16 7.40 7.27 7.09 8.20 pH 0.01 A-T-031s

Sulphate BRE (water sol 2:1)DM# <10 <10 68 <10 <10 <10 61 mg/l 10 A-T-026s

Page 72: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 3 of 5

Envirolab Job Number: 19/08679 Client Project Name: Isacc Centre, Burnley

Client Project Ref: 42367

Lab Sample ID 19/08679/8 19/08679/9

Uni

ts

Lim

it of

Det

ectio

n

Met

hod

ref

Client Sample No 9 6

Client Sample ID WS03 WS05

Depth to Top 3.50 2.00

Depth To Bottom

Date Sampled 29-Aug-19 29-Aug-19

Sample Type Soil - D Soil - B

Sample Matrix Code 5AB 5A

% Stones >10mmA 30.5 <0.1 % w/w 0.1 A-T-044

pH BREDM# 8.20 8.04 pH 0.01 A-T-031s

Sulphate BRE (water sol 2:1)DM# 49 <10 mg/l 10 A-T-026s

Page 73: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 4 of 5

REPORT NOTES General

This report shall not be reproduced, except in full, without written approval from Envirolab. The results reported herein relate only to the material supplied to the laboratory. The residue of any samples contained within this report, and any received with the same delivery, will be disposed of six weeks after initial scheduling. For samples tested for Asbestos we will retain a portion of the dried sample for a minimum of six months after the initial Asbestos testing is completed. Analytical results reflect the quality of the sample at the time of analysis only.

Opinions and interpretations expressed are outside the scope of our accreditation. If results are in italic font they are associated with an AQC failure, these are not accredited and are unreliable. A deviating samples report is appended and will indicate if samples or tests have been found to be deviating. Any test results affected may not be an accurate record of the concentration at the time of sampling and, as a result, may be invalid. The Client Sample No, Client Sample ID, Depth to Top, Depth to Bottom and Date Sampled were all provided by the client. Soil chemical analysis: All results are reported as dry weight (<40°C). For samples with Matrix Codes 1 - 6 natural stones, brick and concrete fragments >10mm and any extraneous material (visible glass, metal or twigs) are removed and excluded from the sample prior to analysis and reported results corrected to a whole sample basis. This is reported as '% stones >10mm'. For samples with Matrix Code 7 the whole sample is dried and crushed prior to analysis and this supersedes any “A” subscripts All analysis is performed on the sample as received for soil samples which are positive for asbestos or the client has informed asbestos may be present and/or if they are from outside the European Union and this supersedes any "D" subscripts. TPH analysis of water by method A-T-007: Free and visible oils are excluded from the sample used for analysis so that the reported result represents the dissolved phase only. Electrical Conductivity of water by Method A-T-037: Results greater than 12900µS/cm @ 25°C / 11550µS/cm @ 20°C fall outside the calibration range and as such are unaccredited. Asbestos: Asbestos in soil analysis is performed on a dried aliquot of the submitted sample and cannot guarantee to identify asbestos if only present in small numbers as discrete fibres/fragments in the original sample. Stones etc. are not removed from the sample prior to analysis. Quantification of asbestos is a 3 stage process including visual identification, hand picking and weighing and fibre counting by sedimentation/phase contrast optical microscopy if required. If asbestos is identified as being present but is not in a form that is suitable for analysis by hand picking and weighing (normally if the asbestos is present as free fibres) quantification by sedimentation is performed. Where ACMs are found a percentage asbestos is assigned to each with reference to 'HSG264, Asbestos: The survey guide' and the calculated asbestos content is expressed as a percentage of the dried soil sample aliquot used. Predominant Matrix Codes: 1 = SAND, 2 = LOAM, 3 = CLAY, 4 = LOAM/SAND, 5 = SAND/CLAY, 6 = CLAY/LOAM, 7 = OTHER, 8 = Asbestos bulk ID sample. Samples with Matrix Code 7 & 8 are not predominantly a SAND/LOAM/CLAY mix and are not covered by our BSEN 17025 or MCERTS accreditations, with the exception of bulk asbestos which are BSEN 17025 accredited. Secondary Matrix Codes: A = contains stones, B = contains construction rubble, C = contains visible hydrocarbons, D = contains glass/metal, E = contains roots/twigs. Key: IS indicates Insufficient Sample for analysis. US indicates Unsuitable Sample for analysis. NDP indicates No Determination Possible. NAD indicates No Asbestos Detected. N/A indicates Not Applicable. Superscript # indicates method accredited to ISO 17025. Superscript "M" indicates method accredited to MCERTS. Subscript "A" indicates analysis performed on the sample as received. Subscript "D" indicates analysis performed on the dried sample, crushed to pass a 2mm sieve Please contact us if you need any further information.

Page 74: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 5 of 5

Envirolab Deviating Samples Report Units 7&8 Sandpits Business Park, Mottram Road, Hyde, SK14 3AR

Tel. 0161 368 4921 email. [email protected] Client: Ian Farmer Associates (Newcastle), Unit 4, Faraday Close, Pattinson North

Industrial Estate, Washington, Tyne and Wear, NE38 8QJ

Project No:

Date Received:

19/08679

17/09/2019 (am)

Project: Isacc Centre, Burnley Cool Box Temperatures (°C): 12.8

Clients Project No: 42367

NO DEVIATIONS IDENTIFIED If, at any point before reaching the laboratory, the temperature of the samples has breached those set in published standards, e.g. BS-EN 5667-3, ISO 18400-102:2017, then the concentration of any affected analytes may differ from that at the time of sampling.

Page 75: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

APPENDIX 4

CHEMICAL TESTS

Page 76: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 1 of 7

Units 7 & 8 Sandpits Business Park Mottram Road, Hyde, Cheshire, SK14 3AR

FINAL ANALYTICAL TEST REPORT

Envirolab Job Number: 19/08117 Issue Number: 1 Date: 06 September, 2019 Client: Ian Farmer Associates (Warrington) 14/15 Rufford Court Hardwick Grange Warrington WA1 4RF Project Manager: Hannah Hadwin/Michelle Hirst-Watson/Olivia Gatehou Project Name: Isaac Centre Project Ref: 42367 Order No: 46883 Date Samples Received: 29/08/19 Date Instructions Received: 29/08/19 Date Analysis Completed: 06/09/19 Prepared by: Approved by:

Melanie Marshall Danielle Bescoby Laboratory Coordinator Quality Manager

Page 77: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 2 of 7

Envirolab Job Number: 19/08117 Client Project Name: Isaac Centre

Client Project Ref: 42367

Lab Sample ID 19/08117/2 19/08117/4 19/08117/5 19/08117/8 19/08117/12 19/08117/13 19/08117/15

Uni

ts

Lim

it of

Det

ectio

n

Met

hod

ref

Client Sample No

Client Sample ID HDP04 WS05 HDP03 WS03 FP01 HDP01 BH03

Depth to Top 1.20 0.50 0.40 0.70 0.50 0.40 0.50

Depth To Bottom

Date Sampled 28-Aug-19 28-Aug-19 28-Aug-19 28-Aug-19 28-Aug-19 28-Aug-19 27-Aug-19

Sample Type Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES

Sample Matrix Code 5A 5A 4AE 5A 5A 4ABE 5A

% Stones >10mmA 2.7 4.1 10.7 8.4 <0.1 11.1 <0.1 % w/w 0.1 A-T-044

pHDM# 7.59 7.33 7.09 6.80 8.49 7.89 7.29 pH 0.01 A-T-031s

Sulphate BRE (water sol 2:1)DM# 17 11 <10 <10 113 18 <10 mg/l 10 A-T-026s

Sulphate (acid soluble)DM# <200 <200 <200 <200 290 500 <200 mg/kg 200 A-T-028s

SulphideA <5 <5 <5 <5 <5 6 <5 mg/kg 5 A-T-S2-s

Fraction of organic carbonD# 0.0089 0.0029 0.0462 0.0028 0.0059 0.0949 0.0033 N/A 0.0003 A-T-032 FOC

ArsenicDM# 3 4 5 2 3 13 2 mg/kg 1 A-T-024s

Boron (water soluble)DM# <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 mg/kg 1 A-T-027s

CadmiumDM# 1.1 0.7 0.6 0.5 0.6 0.8 0.6 mg/kg 0.5 A-T-024s

CopperDM# 18 6 15 9 13 61 8 mg/kg 1 A-T-024s

ChromiumDM# 28 16 12 17 25 18 18 mg/kg 1 A-T-024s

LeadDM# 18 20 23 11 14 70 13 mg/kg 1 A-T-024s

MercuryD <0.17 <0.17 <0.17 <0.17 <0.17 <0.17 <0.17 mg/kg 0.17 A-T-024s

NickelDM# 43 16 16 20 29 26 25 mg/kg 1 A-T-024s

SeleniumDM# <1 <1 <1 <1 <1 <1 <1 mg/kg 1 A-T-024s

ZincDM# 74 38 50 39 46 168 43 mg/kg 5 A-T-024s

EPH CWG GCxGC FID ChromatogramA Appended Appended Appended Appended Appended Appended Appended A-T-055s

Page 78: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 3 of 7

Envirolab Job Number: 19/08117 Client Project Name: Isaac Centre

Client Project Ref: 42367

Lab Sample ID 19/08117/2 19/08117/4 19/08117/5 19/08117/8 19/08117/12 19/08117/13 19/08117/15

Uni

ts

Lim

it of

Det

ectio

n

Met

hod

ref

Client Sample No

Client Sample ID HDP04 WS05 HDP03 WS03 FP01 HDP01 BH03

Depth to Top 1.20 0.50 0.40 0.70 0.50 0.40 0.50

Depth To Bottom

Date Sampled 28-Aug-19 28-Aug-19 28-Aug-19 28-Aug-19 28-Aug-19 28-Aug-19 27-Aug-19

Sample Type Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES

Sample Matrix Code 5A 5A 4AE 5A 5A 4ABE 5A

Asbestos in Soil (inc. matrix)

Asbestos in soilD# NAD - - - NAD NAD - A-T-045

Asbestos ACM - Suitable for Water Absorption Test?D

N/A - - - N/A N/A - A-T-045

Page 79: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 4 of 7

Envirolab Job Number: 19/08117 Client Project Name: Isaac Centre

Client Project Ref: 42367

Lab Sample ID 19/08117/2 19/08117/4 19/08117/5 19/08117/8 19/08117/12 19/08117/13 19/08117/15

Uni

ts

Lim

it of

Det

ectio

n

Met

hod

ref

Client Sample No

Client Sample ID HDP04 WS05 HDP03 WS03 FP01 HDP01 BH03

Depth to Top 1.20 0.50 0.40 0.70 0.50 0.40 0.50

Depth To Bottom

Date Sampled 28-Aug-19 28-Aug-19 28-Aug-19 28-Aug-19 28-Aug-19 28-Aug-19 27-Aug-19

Sample Type Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES

Sample Matrix Code 5A 5A 4AE 5A 5A 4ABE 5A

PAH-16MS

AcenaphtheneAM# <0.01 <0.01 <0.01 <0.01 <0.01 0.22 <0.01 mg/kg 0.01 A-T-019s

AcenaphthyleneAM# <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 mg/kg 0.01 A-T-019s

AnthraceneAM# <0.02 <0.02 <0.02 <0.02 <0.02 0.27 <0.02 mg/kg 0.02 A-T-019s

Benzo(a)anthraceneAM# <0.04 <0.04 <0.04 <0.04 <0.04 0.56 <0.04 mg/kg 0.04 A-T-019s

Benzo(a)pyreneAM# <0.04 <0.04 <0.04 <0.04 <0.04 0.40 <0.04 mg/kg 0.04 A-T-019s

Benzo(b)fluorantheneAM# <0.05 <0.05 <0.05 <0.05 <0.05 0.51 <0.05 mg/kg 0.05 A-T-019s

Benzo(ghi)peryleneAM# <0.05 <0.05 <0.05 <0.05 <0.05 0.19 <0.05 mg/kg 0.05 A-T-019s

Benzo(k)fluorantheneAM# <0.07 <0.07 <0.07 <0.07 <0.07 0.19 <0.07 mg/kg 0.07 A-T-019s

ChryseneAM# <0.06 <0.06 <0.06 <0.06 <0.06 0.58 <0.06 mg/kg 0.06 A-T-019s

Dibenzo(ah)anthraceneAM# <0.04 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04 mg/kg 0.04 A-T-019s

FluorantheneAM# <0.08 <0.08 <0.08 <0.08 <0.08 1.41 <0.08 mg/kg 0.08 A-T-019s

FluoreneAM# <0.01 <0.01 <0.01 <0.01 <0.01 0.16 <0.01 mg/kg 0.01 A-T-019s

Indeno(123-cd)pyreneAM# <0.03 <0.03 <0.03 <0.03 <0.03 0.21 <0.03 mg/kg 0.03 A-T-019s

Naphthalene AM# <0.03 <0.03 <0.03 <0.03 <0.03 0.03 <0.03 mg/kg 0.03 A-T-019s

PhenanthreneAM# <0.03 <0.03 <0.03 <0.03 <0.03 1.30 <0.03 mg/kg 0.03 A-T-019s

PyreneAM# <0.07 <0.07 <0.07 <0.07 <0.07 1.19 <0.07 mg/kg 0.07 A-T-019s

Total PAH-16MSAM# <0.08 <0.08 <0.08 <0.08 <0.08 7.22 <0.08 mg/kg 0.01 A-T-019s

Page 80: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 5 of 7

Envirolab Job Number: 19/08117 Client Project Name: Isaac Centre

Client Project Ref: 42367

Lab Sample ID 19/08117/2 19/08117/4 19/08117/5 19/08117/8 19/08117/12 19/08117/13 19/08117/15

Uni

ts

Lim

it of

Det

ectio

n

Met

hod

ref

Client Sample No

Client Sample ID HDP04 WS05 HDP03 WS03 FP01 HDP01 BH03

Depth to Top 1.20 0.50 0.40 0.70 0.50 0.40 0.50

Depth To Bottom

Date Sampled 28-Aug-19 28-Aug-19 28-Aug-19 28-Aug-19 28-Aug-19 28-Aug-19 27-Aug-19

Sample Type Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES

Sample Matrix Code 5A 5A 4AE 5A 5A 4ABE 5A

TPH CWG

Ali >C5-C6A# <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 mg/kg 0.01 A-T-022s

Ali >C6-C8A# <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 mg/kg 0.01 A-T-022s

Ali >C8-C10A <1 <1 <1 <1 <1 <1 <1 mg/kg 1 A-T-055s

Ali >C10-C12AM# <1 <1 <1 <1 <1 <1 <1 mg/kg 1 A-T-055s

Ali >C12-C16AM# <1 <1 <1 <1 <1 <1 <1 mg/kg 1 A-T-055s

Ali >C16-C21AM# <1 <1 <1 <1 <1 2 <1 mg/kg 1 A-T-055s

Ali >C21-C35A 2 <1 3 1 <1 18 5 mg/kg 1 A-T-055s

Total AliphaticsA 2 <1 3 1 <1 20 5 mg/kg 1 A-T-055s

Aro >C5-C7A# <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 mg/kg 0.01 A-T-022s

Aro >C7-C8A# <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 mg/kg 0.01 A-T-022s

Aro >C8-C10A 1 <1 <1 <1 <1 2 1 mg/kg 1 A-T-055s

Aro >C10-C12AM# <1 <1 <1 <1 <1 1 <1 mg/kg 1 A-T-055s

Aro >C12-C16A <1 <1 <1 <1 <1 6 <1 mg/kg 1 A-T-055s

Aro >C16-C21AM# <1 <1 1 <1 <1 22 <1 mg/kg 1 A-T-055s

Aro >C21-C35AM# 6 <1 4 3 <1 70 11 mg/kg 1 A-T-055s

Total AromaticsA 7 <1 5 3 <1 101 12 mg/kg 1 A-T-055s

TPH (Ali & Aro >C5-C35)A 9 <1 9 4 <1 121 18 mg/kg 1 A-T-055s

BTEX - BenzeneA# <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 mg/kg 0.01 A-T-022s

BTEX - TolueneA# <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 mg/kg 0.01 A-T-022s

BTEX - Ethyl BenzeneA# <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 mg/kg 0.01 A-T-022s

BTEX - m & p XyleneA# <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 mg/kg 0.01 A-T-022s

BTEX - o XyleneA# <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 mg/kg 0.01 A-T-022s

MTBEA# <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 mg/kg 0.01 A-T-022s

Page 81: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 6 of 7

REPORT NOTES General

This report shall not be reproduced, except in full, without written approval from Envirolab. The results reported herein relate only to the material supplied to the laboratory. The residue of any samples contained within this report, and any received with the same delivery, will be disposed of six weeks after initial scheduling. For samples tested for Asbestos we will retain a portion of the dried sample for a minimum of six months after the initial Asbestos testing is completed. Analytical results reflect the quality of the sample at the time of analysis only.

Opinions and interpretations expressed are outside the scope of our accreditation. If results are in italic font they are associated with an AQC failure, these are not accredited and are unreliable. A deviating samples report is appended and will indicate if samples or tests have been found to be deviating. Any test results affected may not be an accurate record of the concentration at the time of sampling and, as a result, may be invalid. The Client Sample No, Client Sample ID, Depth to Top, Depth to Bottom and Date Sampled were all provided by the client. Soil chemical analysis: All results are reported as dry weight (<40°C). For samples with Matrix Codes 1 - 6 natural stones, brick and concrete fragments >10mm and any extraneous material (visible glass, metal or twigs) are removed and excluded from the sample prior to analysis and reported results corrected to a whole sample basis. This is reported as '% stones >10mm'. For samples with Matrix Code 7 the whole sample is dried and crushed prior to analysis and this supersedes any “A” subscripts All analysis is performed on the sample as received for soil samples which are positive for asbestos or the client has informed asbestos may be present and/or if they are from outside the European Union and this supersedes any "D" subscripts. TPH analysis of water by method A-T-007: Free and visible oils are excluded from the sample used for analysis so that the reported result represents the dissolved phase only. Electrical Conductivity of water by Method A-T-037: Results greater than 12900µS/cm @ 25°C / 11550µS/cm @ 20°C fall outside the calibration range and as such are unaccredited. Asbestos: Asbestos in soil analysis is performed on a dried aliquot of the submitted sample and cannot guarantee to identify asbestos if only present in small numbers as discrete fibres/fragments in the original sample. Stones etc. are not removed from the sample prior to analysis. Quantification of asbestos is a 3 stage process including visual identification, hand picking and weighing and fibre counting by sedimentation/phase contrast optical microscopy if required. If asbestos is identified as being present but is not in a form that is suitable for analysis by hand picking and weighing (normally if the asbestos is present as free fibres) quantification by sedimentation is performed. Where ACMs are found a percentage asbestos is assigned to each with reference to 'HSG264, Asbestos: The survey guide' and the calculated asbestos content is expressed as a percentage of the dried soil sample aliquot used. Predominant Matrix Codes: 1 = SAND, 2 = LOAM, 3 = CLAY, 4 = LOAM/SAND, 5 = SAND/CLAY, 6 = CLAY/LOAM, 7 = OTHER, 8 = Asbestos bulk ID sample. Samples with Matrix Code 7 & 8 are not predominantly a SAND/LOAM/CLAY mix and are not covered by our BSEN 17025 or MCERTS accreditations, with the exception of bulk asbestos which are BSEN 17025 accredited. Secondary Matrix Codes: A = contains stones, B = contains construction rubble, C = contains visible hydrocarbons, D = contains glass/metal, E = contains roots/twigs. Key: IS indicates Insufficient Sample for analysis. US indicates Unsuitable Sample for analysis. NDP indicates No Determination Possible. NAD indicates No Asbestos Detected. N/A indicates Not Applicable. Superscript # indicates method accredited to ISO 17025. Superscript "M" indicates method accredited to MCERTS. Subscript "A" indicates analysis performed on the sample as received. Subscript "D" indicates analysis performed on the dried sample, crushed to pass a 2mm sieve Please contact us if you need any further information.

Page 82: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 7 of 7

Envirolab Deviating Samples Report Units 7&8 Sandpits Business Park, Mottram Road, Hyde, SK14 3AR

Tel. 0161 368 4921 email. [email protected] Client: Ian Farmer Associates (Warrington), 14/15 Rufford Court, Hardwick Grange,

Warrington, WA1 4RF

Project No:

Date Received:

19/08117

29/08/2019 (am)

Project: Isaac Centre Cool Box Temperatures (°C): 15.5, 15.9

Clients Project No: 42367

NO DEVIATIONS IDENTIFIED If, at any point before reaching the laboratory, the temperature of the samples has breached those set in published standards, e.g. BS-EN 5667-3, ISO 18400-102:2017, then the concentration of any affected analytes may differ from that at the time of sampling.

Page 83: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 1 of 8

Units 7 & 8 Sandpits Business Park Mottram Road, Hyde, Cheshire, SK14 3AR

FINAL ANALYTICAL TEST REPORT

Envirolab Job Number: 19/08205 Issue Number: 1 Date: 10 September, 2019 Client: Ian Farmer Associates (Warrington) 14/15 Rufford Court Hardwick Grange Warrington WA1 4RF Project Manager: Hannah Hadwin/Joe Tant/Michelle Hirst-Watson/Olivi Project Name: Isaac Centre Project Ref: 42367 Order No: 46886 Date Samples Received: 30/08/19 Date Instructions Received: 02/09/19 Date Analysis Completed: 10/09/19 Prepared by: Approved by:

Melanie Marshall Danielle Brierley Laboratory Coordinator Client Manager

Page 84: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 2 of 8

Envirolab Job Number: 19/08205 Client Project Name: Isaac Centre

Client Project Ref: 42367

Lab Sample ID 19/08205/1 19/08205/2 19/08205/4 19/08205/6 19/08205/7 19/08205/9 19/08205/11

Uni

ts

Lim

it of

Det

ectio

n

Met

hod

ref

Client Sample No

Client Sample ID BH02 BH02 BH01 BH04 BH04 WS01 WS02

Depth to Top 0.50 1.00 1.00 0.50 1.00 0.60 0.70

Depth To Bottom

Date Sampled 28-Aug-19 28-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19

Sample Type Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES

Sample Matrix Code 6AE 6AE 6AE 6AE 6AE 6AE 6AE

% Stones >10mmA <0.1 2.5 1.5 18.5 1.0 <0.1 <0.1 % w/w 0.1 A-T-044

pHDM# 6.81 - 7.32 7.83 - 6.88 7.75 pH 0.01 A-T-031s

pH BREDM# - 7.36 - - 7.68 6.88 - pH 0.01 A-T-031s

Sulphate BRE (water sol 2:1)DM# - 18 - - 11 38 - mg/l 10 A-T-026s

Sulphate (acid soluble)DM# 560 - <200 670 - <200 <200 mg/kg 200 A-T-028s

SulphideA <5 - <5 <5 - <5 <5 mg/kg 5 A-T-S2-s

Fraction of organic carbonD# 0.0349 - 0.0050 0.0253 - 0.0040 0.0031 N/A 0.0003 A-T-032 FOC

ArsenicDM# 9 - 2 9 - 2 <1 mg/kg 1 A-T-024s

Boron (water soluble)DM# <1.0 - <1.0 <1.0 - <1.0 <1.0 mg/kg 1 A-T-027s

CadmiumDM# 0.8 - <0.5 0.7 - <0.5 <0.5 mg/kg 0.5 A-T-024s

CopperDM# 21 - 9 20 - 3 2 mg/kg 1 A-T-024s

ChromiumDM# 18 - 23 20 - 17 14 mg/kg 1 A-T-024s

LeadDM# 49 - 16 51 - 11 11 mg/kg 1 A-T-024s

MercuryD <0.17 - <0.17 0.35 - <0.17 <0.17 mg/kg 0.17 A-T-024s

NickelDM# 16 - 23 31 - 13 11 mg/kg 1 A-T-024s

SeleniumDM# <1 - <1 <1 - <1 <1 mg/kg 1 A-T-024s

ZincDM# 92 - 43 171 - 21 32 mg/kg 5 A-T-024s

EPH CWG GCxGC FID ChromatogramA Appended - Appended Appended - Appended Appended A-T-055s

Page 85: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 3 of 8

Envirolab Job Number: 19/08205 Client Project Name: Isaac Centre

Client Project Ref: 42367

Lab Sample ID 19/08205/1 19/08205/2 19/08205/4 19/08205/6 19/08205/7 19/08205/9 19/08205/11

Uni

ts

Lim

it of

Det

ectio

n

Met

hod

ref

Client Sample No

Client Sample ID BH02 BH02 BH01 BH04 BH04 WS01 WS02

Depth to Top 0.50 1.00 1.00 0.50 1.00 0.60 0.70

Depth To Bottom

Date Sampled 28-Aug-19 28-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19

Sample Type Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES

Sample Matrix Code 6AE 6AE 6AE 6AE 6AE 6AE 6AE

Asbestos in Soil (inc. matrix)

Asbestos in soilD# NAD - - NAD - - - A-T-045

Asbestos ACM - Suitable for Water Absorption Test?D

N/A - - N/A - - - A-T-045

Page 86: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 4 of 8

Envirolab Job Number: 19/08205 Client Project Name: Isaac Centre

Client Project Ref: 42367

Lab Sample ID 19/08205/1 19/08205/2 19/08205/4 19/08205/6 19/08205/7 19/08205/9 19/08205/11

Uni

ts

Lim

it of

Det

ectio

n

Met

hod

ref

Client Sample No

Client Sample ID BH02 BH02 BH01 BH04 BH04 WS01 WS02

Depth to Top 0.50 1.00 1.00 0.50 1.00 0.60 0.70

Depth To Bottom

Date Sampled 28-Aug-19 28-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19

Sample Type Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES

Sample Matrix Code 6AE 6AE 6AE 6AE 6AE 6AE 6AE

PAH-16MS

AcenaphtheneAM# <0.01 - <0.01 0.08 - <0.01 <0.01 mg/kg 0.01 A-T-019s

AcenaphthyleneAM# <0.01 - <0.01 0.02 - <0.01 <0.01 mg/kg 0.01 A-T-019s

AnthraceneAM# <0.02 - <0.02 0.16 - <0.02 <0.02 mg/kg 0.02 A-T-019s

Benzo(a)anthraceneAM# <0.04 - <0.04 0.51 - <0.04 <0.04 mg/kg 0.04 A-T-019s

Benzo(a)pyreneAM# <0.04 - <0.04 0.43 - <0.04 <0.04 mg/kg 0.04 A-T-019s

Benzo(b)fluorantheneAM# <0.05 - <0.05 0.56 - <0.05 <0.05 mg/kg 0.05 A-T-019s

Benzo(ghi)peryleneAM# <0.05 - <0.05 0.26 - <0.05 <0.05 mg/kg 0.05 A-T-019s

Benzo(k)fluorantheneAM# <0.07 - <0.07 0.17 - <0.07 <0.07 mg/kg 0.07 A-T-019s

ChryseneAM# <0.06 - <0.06 0.56 - <0.06 <0.06 mg/kg 0.06 A-T-019s

Dibenzo(ah)anthraceneAM# <0.04 - <0.04 0.07 - <0.04 <0.04 mg/kg 0.04 A-T-019s

FluorantheneAM# <0.08 - <0.08 1.08 - <0.08 <0.08 mg/kg 0.08 A-T-019s

FluoreneAM# <0.01 - <0.01 0.07 - <0.01 <0.01 mg/kg 0.01 A-T-019s

Indeno(123-cd)pyreneAM# <0.03 - <0.03 0.28 - <0.03 <0.03 mg/kg 0.03 A-T-019s

Naphthalene AM# <0.03 - <0.03 0.05 - <0.03 <0.03 mg/kg 0.03 A-T-019s

PhenanthreneAM# <0.03 - <0.03 0.73 - <0.03 <0.03 mg/kg 0.03 A-T-019s

PyreneAM# <0.07 - <0.07 0.96 - <0.07 <0.07 mg/kg 0.07 A-T-019s

Total PAH-16MSAM# <0.08 - <0.08 5.99 - <0.08 <0.08 mg/kg 0.01 A-T-019s

Page 87: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 5 of 8

Envirolab Job Number: 19/08205 Client Project Name: Isaac Centre

Client Project Ref: 42367

Lab Sample ID 19/08205/1 19/08205/2 19/08205/4 19/08205/6 19/08205/7 19/08205/9 19/08205/11

Uni

ts

Lim

it of

Det

ectio

n

Met

hod

ref

Client Sample No

Client Sample ID BH02 BH02 BH01 BH04 BH04 WS01 WS02

Depth to Top 0.50 1.00 1.00 0.50 1.00 0.60 0.70

Depth To Bottom

Date Sampled 28-Aug-19 28-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19 29-Aug-19

Sample Type Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES Soil - ES

Sample Matrix Code 6AE 6AE 6AE 6AE 6AE 6AE 6AE

TPH CWG

Ali >C5-C6A# <0.01 - <0.01 <0.05 - <0.01 <0.01 mg/kg 0.01 A-T-022s

Ali >C6-C8A# <0.01 - <0.01 <0.05 - <0.01 <0.01 mg/kg 0.01 A-T-022s

Ali >C8-C10A <1 - <1 <1 - <1 <1 mg/kg 1 A-T-055s

Ali >C10-C12AM# <1 - <1 <1 - <1 <1 mg/kg 1 A-T-055s

Ali >C12-C16AM# <1 - <1 <1 - <1 <1 mg/kg 1 A-T-055s

Ali >C16-C21AM# <1 - <1 2 - <1 <1 mg/kg 1 A-T-055s

Ali >C21-C35A 2 - <1 69 - <1 <1 mg/kg 1 A-T-055s

Total AliphaticsA 2 - <1 71 - <1 <1 mg/kg 1 A-T-055s

Aro >C5-C7A# <0.01 - <0.01 <0.05 - <0.01 <0.01 mg/kg 0.01 A-T-022s

Aro >C7-C8A# <0.01 - <0.01 <0.05 - <0.01 <0.01 mg/kg 0.01 A-T-022s

Aro >C8-C10A <1 - <1 2 - <1 <1 mg/kg 1 A-T-055s

Aro >C10-C12AM# <1 - <1 <1 - <1 <1 mg/kg 1 A-T-055s

Aro >C12-C16A <1 - <1 2 - <1 <1 mg/kg 1 A-T-055s

Aro >C16-C21AM# <1 - <1 6 - <1 <1 mg/kg 1 A-T-055s

Aro >C21-C35AM# 4 - <1 85 - 2 <1 mg/kg 1 A-T-055s

Total AromaticsA 4 - <1 96 - 2 <1 mg/kg 1 A-T-055s

TPH (Ali & Aro >C5-C35)A 5 - <1 168 - 2 <1 mg/kg 1 A-T-055s

BTEX - BenzeneA# <0.01 - <0.01 <0.05 - <0.01 <0.01 mg/kg 0.01 A-T-022s

BTEX - TolueneA# <0.01 - <0.01 <0.05 - <0.01 <0.01 mg/kg 0.01 A-T-022s

BTEX - Ethyl BenzeneA# <0.01 - <0.01 <0.05 - <0.01 <0.01 mg/kg 0.01 A-T-022s

BTEX - m & p XyleneA# <0.01 - <0.01 <0.05 - <0.01 <0.01 mg/kg 0.01 A-T-022s

BTEX - o XyleneA# <0.01 - <0.01 <0.05 - <0.01 <0.01 mg/kg 0.01 A-T-022s

MTBEA# <0.01 - <0.01 <0.05 - <0.01 <0.01 mg/kg 0.01 A-T-022s

Page 88: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 6 of 8

Envirolab Job Number: 19/08205 Client Project Name: Isaac Centre

Client Project Ref: 42367

Lab Sample ID 19/08205/13

Uni

ts

Lim

it of

Det

ectio

n

Met

hod

ref

Client Sample No

Client Sample ID WS04

Depth to Top 0.70

Depth To Bottom

Date Sampled 29-Aug-19

Sample Type Soil - ES

Sample Matrix Code 4AE

% Stones >10mmA 22.7 % w/w 0.1 A-T-044

pH BREDM# 7.79 pH 0.01 A-T-031s

Sulphate BRE (water sol 2:1)DM# <10 mg/l 10 A-T-026s

Page 89: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 7 of 8

REPORT NOTES General

This report shall not be reproduced, except in full, without written approval from Envirolab. The results reported herein relate only to the material supplied to the laboratory. The residue of any samples contained within this report, and any received with the same delivery, will be disposed of six weeks after initial scheduling. For samples tested for Asbestos we will retain a portion of the dried sample for a minimum of six months after the initial Asbestos testing is completed. Analytical results reflect the quality of the sample at the time of analysis only.

Opinions and interpretations expressed are outside the scope of our accreditation. If results are in italic font they are associated with an AQC failure, these are not accredited and are unreliable. A deviating samples report is appended and will indicate if samples or tests have been found to be deviating. Any test results affected may not be an accurate record of the concentration at the time of sampling and, as a result, may be invalid. The Client Sample No, Client Sample ID, Depth to Top, Depth to Bottom and Date Sampled were all provided by the client. Soil chemical analysis: All results are reported as dry weight (<40°C). For samples with Matrix Codes 1 - 6 natural stones, brick and concrete fragments >10mm and any extraneous material (visible glass, metal or twigs) are removed and excluded from the sample prior to analysis and reported results corrected to a whole sample basis. This is reported as '% stones >10mm'. For samples with Matrix Code 7 the whole sample is dried and crushed prior to analysis and this supersedes any “A” subscripts All analysis is performed on the sample as received for soil samples which are positive for asbestos or the client has informed asbestos may be present and/or if they are from outside the European Union and this supersedes any "D" subscripts. TPH analysis of water by method A-T-007: Free and visible oils are excluded from the sample used for analysis so that the reported result represents the dissolved phase only. Electrical Conductivity of water by Method A-T-037: Results greater than 12900µS/cm @ 25°C / 11550µS/cm @ 20°C fall outside the calibration range and as such are unaccredited. Asbestos: Asbestos in soil analysis is performed on a dried aliquot of the submitted sample and cannot guarantee to identify asbestos if only present in small numbers as discrete fibres/fragments in the original sample. Stones etc. are not removed from the sample prior to analysis. Quantification of asbestos is a 3 stage process including visual identification, hand picking and weighing and fibre counting by sedimentation/phase contrast optical microscopy if required. If asbestos is identified as being present but is not in a form that is suitable for analysis by hand picking and weighing (normally if the asbestos is present as free fibres) quantification by sedimentation is performed. Where ACMs are found a percentage asbestos is assigned to each with reference to 'HSG264, Asbestos: The survey guide' and the calculated asbestos content is expressed as a percentage of the dried soil sample aliquot used. Predominant Matrix Codes: 1 = SAND, 2 = LOAM, 3 = CLAY, 4 = LOAM/SAND, 5 = SAND/CLAY, 6 = CLAY/LOAM, 7 = OTHER, 8 = Asbestos bulk ID sample. Samples with Matrix Code 7 & 8 are not predominantly a SAND/LOAM/CLAY mix and are not covered by our BSEN 17025 or MCERTS accreditations, with the exception of bulk asbestos which are BSEN 17025 accredited. Secondary Matrix Codes: A = contains stones, B = contains construction rubble, C = contains visible hydrocarbons, D = contains glass/metal, E = contains roots/twigs. Key: IS indicates Insufficient Sample for analysis. US indicates Unsuitable Sample for analysis. NDP indicates No Determination Possible. NAD indicates No Asbestos Detected. N/A indicates Not Applicable. Superscript # indicates method accredited to ISO 17025. Superscript "M" indicates method accredited to MCERTS. Subscript "A" indicates analysis performed on the sample as received. Subscript "D" indicates analysis performed on the dried sample, crushed to pass a 2mm sieve Please contact us if you need any further information.

Page 90: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Page 8 of 8

Envirolab Deviating Samples Report Units 7&8 Sandpits Business Park, Mottram Road, Hyde, SK14 3AR

Tel. 0161 368 4921 email. [email protected] Client: Ian Farmer Associates (Warrington), 14/15 Rufford Court, Hardwick Grange,

Warrington, WA1 4RF

Project No:

Date Received:

19/08205

02/09/2019 (am)

Project: Isaac Centre Cool Box Temperatures (°C): 17.3

Clients Project No: 42367

Lab Sample ID 19/08205/1 Client Sample No

Client Sample ID/Depth BH02 0.50m Date Sampled 28/08/19

Deviation Code F ✓

Key F Maximum holding time exceeded between sampling date and analysis for analytes listed below

HOLDING TIME EXCEEDANCES Lab Sample ID 19/08205/1

Client Sample No Client Sample ID/Depth BH02 0.50m

Date Sampled 28/08/19 Sulphide ✓

If, at any point before reaching the laboratory, the temperature of the samples has breached those set in published standards, e.g. BS-EN 5667-3, ISO 18400-102:2017, then the concentration of any affected analytes may differ from that at the time of sampling.

Page 91: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

APPENDIX 5

DESIGN CONSIDERATIONS

Page 92: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 5 pages v/i-v/iv v/i

APPENDIX 5

GEOTECHNICAL DESIGN CONSIDERATIONS

A5.1 ASSESSMENT OF GRANULAR SOIL CONDITION

A5.1.1 SPT ‘N’ values reported on the borehole logs are as measured in the field with no corrections applied.

A5.1.2 However for general design in sands the ‘N’ values should be normalised to 60% by the following equation:-

A5.1.3 N60 = Er/60.N where:-

N is the blow count and

Er is the energy ratio of the specific test equipment

A5.1.4 Further corrections for rod length and overburden pressure in sands may be applied in accordance with BS EN ISO 22476-3, ref 9.6.

A5.2 ASSESSMENT OF COHESIVE SOIL CONDITION

A5.2.1 In accordance with BS EN ISO 22475-1, ref. 9.8, and BS5930, ref.9.2, the thick walled U100 sample is considered as a Class B sampling technique and will only produce Class 3 to 5 quality samples in accordance with EN 1997-2:2007, ref.9.3.

A5.2.2 Laboratory strength and consolidation testing should only be carried out on Class 1 quality samples, which can be obtained from a Class A sampling technique, ref. 9.5. This is due to possible disturbance during sampling, giving a weaker strength in testing.

A5.2.3 Therefore laboratory test values for cu and mv obtained from thick walled U100 samples should only be used as guidance and not used as absolute values for the shear strength and compressibility properties of the clay and only used to provide guidance to descriptive strength on the borehole records.

A5.2.4 Work undertaken by Stroud, ref. 9.10 determined a relationship between SPT ‘N’ values, plasticity undrained shear strength and compressibility of many over-consolidated clays. Further work by Stroud and Butler, ref.9.11, in which data was analysed from sites covering a wide range of glacial deposits, confirmed there to be a correlation between the ‘N’ value plasticity undrained shear strength and compressibility.

A5.2.5 The relationship was of the form:

Cu = f1 x N

and mv = 1/(f2 x N)

Where cu = Un-drained shear strength

mv = Coefficient of compressibility

f1 and f2 = Factors

A5.2.6 It was determined by Stroud that f1 varied between 4kPa for material of high plasticity and 6kPa for material of low plasticity. Similarly f2 varied between 400kPa and 600kPa.

Page 93: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 5 pages v/i-v/iv v/ii

A5.3 GUIDELINES FOR THE DESIGN OF PILES FIRST APPROXIMATION OF WORKING LOAD

A5.3.1 PILING PARAMETERS – GENERAL

The ultimate carrying capacity, Qu, of a particular pile is taken as the sum of the ultimate shaft friction resistance, Qs, and the ultimate end bearing resistance, Qb. This may be expressed as follows:-

Qu = Qs + Qb

= f.As + q.Ab

where f = unit shaft resistance

As = embedded surface area of pile

q = unit end bearing resistance

Ab = effective cross-sectional area of pile base

A5.3.2 COHESIVE SOILS

A5.3.2.1 Shaft Resistance The ultimate shaft resistance, f, for piles in both compression or tension in cohesive soils is determined by applying a factor to the undrained shear strength, Cs, which exists in the soils along the embedded length of the pile, and is given by:-

f = .Cs

Where is an adhesion factor, which for straight-shafted bored piles may be taken as 0.45 to 0.60.

Ultimate unit shaft friction should not exceed 100kN/m².

A5.3.2.2 End Bearing For piles terminating in cohesive soils, the ultimate unit end bearing resistance q, is given by:-

q = Nc.Cb

where Cb is the undrained shear strength at the base of the pile

and Nc is a bearing capacity factor

The value of Nc for a cohesive material is variable, depending on the depth of the penetration of the pile into the bearing stratum. Generally, Nc could be taken to have a value of 9, except in the case of large diameter short piles where a lesser value should be used.

Page 94: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 5 pages v/i-v/iv v/iii

A5.3.3 COHESIONLESS SOILS

A5.3.3.1 Shaft Resistance For piles driven in cohesionless soils the ultimate unit shaft resistance, f, may be calculated using the following method, which gives:-

f = 0.5 ' (D+d) Ks tan

where ' = average effective unit weight of soil surrounding

the pile

D = depth to the pile toe or to the base of the

granular stratum whichever is the lesser

d = depth to the top of the granular stratum

= angle of friction between pile and soil

(see below)

Ks = a coefficient (see below)

TABLE OF VALUES FOR Ks AND

Pile Type

Ks

Relative Density

Tension Piles Low High

Steel 20° 0.5 1.5 0.5

Concrete 0.75 1.0 2.0 0.5

The value of may be interpreted from standard penetration tests.

For bored and cast-in-place piles, = 22° and Ks = 1 should be used to allow for loosening of the soil during boring.

It has been found that the ultimate unit shaft resistance does not exceed 100kN/m² and therefore this value should not be exceeded in design.

Page 95: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 5 pages v/i-v/iv v/iv

A5.3.3.2 End Bearing The unit ultimate end bearing resistance (q) of piles in cohesionless soils may be calculated as follows:-

q = '.D.Nq

where ' = average effective unit weight of soil surrounding the pile D = depth to pile toe

Nq = bearing capacity factor

Values for Nq, where piles penetrate the bearing stratum by more than five diameters, may be taken from work carried out by Berezantsev, ref.9.19. In addition, the ultimate unit base resistance should not exceed a value of 11,000kN/m². For bored and cast-in-place piles the value of Nq used should correspond to loose soil conditions.

A5.3.4 FACTORS OF SAFETY

A5.3.4.1 Cohesive and Non-cohesive Soils For cohesive and non-cohesive soils a factor of safety of 3 may be used to obtain the allowable or safe carrying capacity of piles from the ultimate carrying capacity.

Page 96: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

APPENDIX 6

CONTAMINATION ASSESSMENT

Page 97: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 6 pages vi/i-vi/v vi/i

APPENDIX 6

GENERAL NOTES ON CONTAMINATION ASSESSMENT

A6.1 STATUTORY FRAMEWORK AND DEFINITIONS

A6.1.1 The statutory definition of contaminated land is defined in the Environmental Protection Act 1990, ref 9.20, which was introduced by the Environment Act 1995, ref 9.21;

‘Land which appears to the local authority in whose area it is situated to be in such a condition, by reason of substances in, on or under the land, that –

(a) significant harm is being caused or there is a significant possibility of such harm being caused; or

(b) pollution of controlled waters is being, or is likely to be, caused.’

A6.1.2 The UK guidance on the assessment of contaminated has developed as a direct result of the introduction of these two Acts. The technical guidance supporting the legislation was originally summarised in a number of key documents collectively known as the Contaminated Land Reports (CLRs), a proposed series of twelve documents. Seven were originally published in March 1994, four more were published in April 2002, while the final guidance document, CLR 11, ref 9.34 was published in 2004. CLR7 to 10 were withdrawn in 2008, with CLR 9 and 10 effectively replaced by the Environment Agency in the form of Science Reports SR2, ref 9.31 and SR3, ref 9.23. CLR11 remains valid and sets out the framework of the investigation process.

A6.1.3 In establishing whether a site fulfils the statutory definition of ‘contaminated land’ it is necessary to identify, whether a pollutant linkage exists in respect of the land in question and whether the pollutant linkage:

is resulting in significant harm being caused to the receptor in the pollutant linkage,

presents a significant possibility of significant harm being caused to that receptor,

is resulting in the pollution of the controlled waters which constitute the receptor, or

is likely to result in such pollution.

A6.1.4 A ‘pollutant linkage’ may be defined as the link between a contaminant ‘source’ and a ‘receptor’ by means of a ‘pathway’.

A6.2 ASSESSMENT METHODOLOGY

A6.2.1 The guidance proposes a four-stage assessment process for identifying potential pollutant linkages on a site. These stages are set out in the table below:

Page 98: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 6 pages vi/i-vi/v vi/ii

No. Process Description

1 Hazard Identification Establishing contaminant sources, pathways and receptors (the conceptual model).

2 Hazard Assessment Analysing the potential for unacceptable risks (what linkages could be present, what could be the effects).

3 Risk Estimation Trying to establish the magnitude and probability of the possible consequences (what degree of harm might result and to what receptors, and how likely is it).

4 Risk Evaluation Deciding whether the risk is unacceptable.

A6.2.2 Stages 1 and 2 develop a ‘conceptual model’ based upon information collated from desk based studies, and frequently a walkover of the site. The walkover survey should be conducted in general accordance with CLR 2, ref 9.35. The formation of a conceptual model is an iterative process and as such, it should be updated and refined throughout each stage of the project to reflect any additional information obtained.

A6.2.3 The extent of the desk studies and enquiries to be conducted should be in general accordance with CLR 3, ref 9.22. The information from these enquiries is presented in a desk study report with recommendations, if necessary, for further work based upon the conceptual model. In the absence of specific information on contamination anticipated to be encountered, specific DoE ‘Industry Profiles’ provide guidance on the nature of contaminants relating to a variety of industrial processes and should be used as the basis for determining which contaminants are more likely to be present on a site.

A6.2.4 If potential pollutant linkages are identified within the conceptual model, a Phase 2 site investigation and report will be recommended. The investigation should be planned in general accordance with CLR 4, ref 9.1. The number of exploratory holes and samples collected for analysis should be consistent with the size of the site and the level of risk envisaged. This will enable a generic quantitative risk assessment (GQRA) to be conducted, at which point the conceptual model can be updated and relevant pollutant linkages can be identified.

A6.2.5 A two-stage investigation may be more appropriate where time constraints are less of an issue. The first stage investigation being conducted as an initial assessment for the presence of potential sources, a second being a more refined investigation to delineate wherever possible the extent of the identified contamination.

A6.2.6 All site works should be in general accordance with the British Standards, BS 5930:2010, ref. 9.2, ISO 1997, ref 9.3 and BS 10175:2011, ref 9.4.

A6.2.7 The GQRA screens the results of the chemical analysis against generic guidance values, appropriate to the end-use of the site. Soils will be compared to Soil Guideline Values (SGV) where published, Generic Assessment Criteria (GAC) developed by LQM/CIEH, ref 9.25, or internal screening values generated using the Contaminated Land Exposure Assessment (CLEA) Software, Version 1.06, ref 9.26. Toxicological and physico-chemical/fate and transport data used to generate the AC has been derived from a hierarchy of data sources as follows:

1. Environment Agency or Department of Environment Food and Rural Affairs

(DEFRA) documents;

2. Other documents produced by UK Government or state organisations;

3. European institution documents;

4. International organisation documents;

5. Foreign government institutions.

A6.2.8 For many of the contaminants considered, input data has been drawn from the relevant SGV where available, or existing toxicological reports published by the Environment Agency which have not yet been withdrawn/replaced. Fate and transport data has been derived in the first instance from Environment Agency (2008), ref 9.36.

Page 99: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 6 pages vi/i-vi/v vi/iii

A6.2.9 Recommendations for tolerable intakes of lead are based on evaluation of the relationship between exposure and blood lead levels. The existing toxicological report for lead considers a health criteria value based on an uptake dose, whereas the CLEA model estimates exposure in terms of an intake dose. At present, the CLEA model is not considered appropriate for determining a screening value for lead. In the absence of a current published assessment criterion, the SGV for lead reported in R&D Publication CLR 10 ref 9.32 have been used in this assessment. This will be updated in due course in light of any further published information.

A6.2.10 Chemical laboratory test results are processed as follows. A statistical analysis of the results is conducted, as detailed in CIEH and CL:AIRE ‘Guidance on Comparing Soil Contamination Data with a Critical Concentration’, ref 9.28. Individual concentrations are compared to the selected guideline values to identify concentrations of contaminants that are above the selected screening criteria.

A6.2.11 Initially the distribution of the data set is tested using the Shapiro-Wilk normality test, ref 9.30 to determine if the data set is, or is not, normally distributed. Where the distribution of the data is shown to be normal, the mean value test is applied to determine whether the mean characteristics of the selected soil unit present a significant possibility of significant harm to human health. Where the data is not normally distributed a method based on the Chebychev Theorem can be applied to test the same hypothesis. The significance of the data is further tested using the maximum value test. This determines whether the highest recorded contaminant concentrations are from the same statistical distribution or whether they may represent a ‘hot spot’.

A6.2.12 Where the risk estimation identifies significant concentrations of one or more contaminants, a further risk evaluation needs to be undertaken.

A6.2.13 The risk evaluation will address the potential pollutant linkages between an identified source of contamination and the likely receptors both on and off site.

A6.2.14 The potential receptors include:

1) Humans – current site occupants, construction workers, future site users and neighbouring site users.

2) Controlled Waters – surface water and groundwater resources

3) Plants – current and future site vegetation

4) Building materials

A6.2.15 The potential hazards to be considered in relation to contamination are:

a) Ingestion and inhalation.

b) Uptake of contaminants via cultivated vegetables.

c) Dermal contact

d) Phytotoxicity (the prevention or inhibition of plant growth)

e) Contamination of water resources

f) Chemical attack on building materials and services

g) Fire and explosion

A6.2.16 Dependent on the outcome of the initial, generic contamination risk assessment, further detailed assessment of the identified risks may be required.

Page 100: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 6 pages vi/i-vi/v vi/iv

A6.3 Generic Guidance Values Used Within Contamination Risk Assessment

Residential End Use with Homegrown Produce

Residential with Homegrown

Produce Determinant

Guidance Value (mg/kg)

Guidance Value (mg/kg)

Guidance Value (mg/kg) Primary Data Source

1% SOM 2.5% SOM 6% SOM

PAH

Acenaphthene 210 510 1100 LQM/CIEH S4UL

Acenaphthylene 170 420 920 LQM/CIEH S4UL

Anthracene 2400 5400 11000 LQM/CIEH S4UL

Benzo(a)anthracene 7.2 11 13 LQM/CIEH S4UL

Benzo(a)pyrene 2.2 2.7 3 LQM/CIEH S4UL

Benzo(b)fluoranthene 2.6 3.3 3.7 LQM/CIEH S4UL

Benzo(ghi)perylene 320 340 350 LQM/CIEH S4UL

Benzo(k)fluoranthene 77 93 100 LQM/CIEH S4UL

Chrysene 15 22 27 LQM/CIEH S4UL

Dibenzo(ah)anthracene 0.24 0.28 0.30 LQM/CIEH S4UL

Fluoranthene 280 560 890 LQM/CIEH S4UL

Fluorene 170 400 860 LQM/CIEH S4UL

Indeno(123-cd)pyrene 27 36 41 LQM/CIEH S4UL

Naphthalene 2.3f 5.6f 13f LQM/CIEH S4UL

Phenanthrene 95 220 440 LQM/CIEH S4UL

Pyrene 620 1200 2000 LQM/CIEH S4UL

Other Organics Phenol 280 550 1100 LQM/CIEH S4UL

Metals

Arsenic 37 37 37 LQM/CIEH S4UL

Beryllium 1.7 1.7 1.7 LQM/CIEH S4UL

Boron 290 290 290 LQM/CIEH S4UL

Cadmium 11 11 11 LQM/CIEH S4UL

Chromium (III) 910 910 910 LQM/CIEH S4UL

Chromium (VI) 6 6 6 LQM/CIEH S4UL

Copper 2400 2400 2400 LQM/CIEH S4UL

Lead 200 200 200 EA C4SL

Mercury 40 40 40 LQM/CIEH S4UL

Nickel 180f 180 180 LQM/CIEH S4UL

Selenium 250 250 250 LQM/CIEH S4UL

Vanadium 410e 410 410 LQM/CIEH S4UL

Zinc 3700 3700 3700 LQM/CIEH S4UL

d = Based on inhalation exposure compared with inhalation ID e = Based on oral and dermal exposure with oral TDI f = Based on comparison of exposure from all pathways with TDI oral

Residential with Homegrown Produce

Guidance Value (mg/kg)

Guidance Value (mg/kg)

Guidance Value (mg/kg) Primary Data Source

1% SOM 2.5% SOM 6% SOM

Aliphatic

EC 5-6 42 78 160 LQM/CIEH S4UL

EC >6-8 100 230 530 LQM/CIEH S4UL

EC >8-10 27 65 150 LQM/CIEH S4UL

EC >10-12 130 (48) 330 (118) 770 (283) LQM/CIEH S4UL

EC >12-16 1100 (24) 2400 (59) 4400 (142) LQM/CIEH S4UL

EC >16-35 65000 (8.48) 92000 (21) 110000 LQM/CIEH S4UL

EC >35-44 65000 (8.48) 92000 (21) 110000 LQM/CIEH S4UL

Page 101: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND

Appendix 6 pages vi/i-vi/v vi/v

Aromatic

EC 5-7 (benzene) 70 140 300 LQM/CIEH S4UL

EC >7-8 (toluene) 130 290 660 LQM/CIEH S4UL

EC >8-10 34 83 190 LQM/CIEH S4UL

EC >10-12 74 180 380 LQM/CIEH S4UL

EC >12-16 140 330 660 LQM/CIEH S4UL

EC >16-21 260f 540f 930f LQM/CIEH S4UL

EC >21-35 1100f 1500f 1700f LQM/CIEH S4UL

EC >35-44 1100f 1500f 1700f LQM/CIEH S4UL

Aliphatic and Aromatic

EC >44-70 1600f 1800f 1900f LQM/CIEH S4UL

BTEX

Benzene 0.087 0.17 0.37 LQM/CIEH S4UL

Toluene 130 290 660 LQM/CIEH S4UL

Ethylbenzene 47 110 260 LQM/CIEH S4UL

p Xylenes 56 130 310 LQM/CIEH S4UL

m Xylenes 59 140 320 LQM/CIEH S4UL

o Xylene 60 140 330 LQM/CIEH S4UL

SOM = Soil Organic Matter Values in brackets indicate the solubility or vapour saturation limit where this is exceeded by the GAC

Page 102: ISAAC CENTRE HARROGATE CRESCENT, BB10 2NX GROUND