[isidor kerszenbaum] inspection of large synchrono
TRANSCRIPT
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
1/190
Inspection ofLarge
Synchronous
Machines
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
2/190
IEEE Press
445HoesLane, P.O.Box
1331
Piscataway, NJ
08855·1331
Editorial Board
JohnB.
Anderson,
Editor in Chief
M.
Eden
M. E.
El-Hawary
S.
Furui
R. Herrick
G. F. Hoffnagle
R.F.Hoyt
S. Kartalopoulos
P. Laplante
R.S.
Muller
W.O. Reeve
E.
Sanchez-Sinencio
D.J.
Wells
DudleyR. Kay,
Director
of
BookPublishing
Lisa Dayne,Review
Coordinator
Denise Phillip, BookProduction Editor
IEEE PowerEngineeringSociety,Sponsor
LeoL. Grigsby, PE-S
Liaison
to IEEEPress
James S. Edmonds
MCMEnterprises, Ltd.
Technical Reviewers
Alan
Wallace
Baker International
GeoffKlempner
Ontario Hydro
IEEE Press Power Systems Engineering Series
Dr. PaulM.Anderson,SeriesEditor
Power MathAssociates,
Inc.
Series Editorial Advisory Committee
Dr.
Roy
Billinton
Dr.
George Karady
University ofSaskatchewan Arizona State University
Dr. Atif S. Debs Dr. Donald W. Novotny
Georgia Institute
of
Technology University o/Wisconsin
Dr. M. El-Hawary Dr. A. G. Phadke
Technical University ofNova Scotia Virginia Polytechnic and State University
Mr. Richard G. Fanner Dr. Chanan Singh
Arizona Public Service Company TexasA & M University
Dr. Charles A. Gross Dr. E. Keith Stanek
Auburn University University
of
Missouri-Rolla
Dr. G. T. Heydt Dr. 1. E. VanNess
Purdue University Northwestern University
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
3/190
Inspection of Large
Synchronous Machines
Checklists, Failure Identification,
and Troubleshooting
Isidor Kerszenbaum
Department
of
Electrical Engineering
California State University, Long Beach
IEEE Power Engineering Society,
Sponsor
IEEE Press Power Systems Engineering Series
Dr. Paul M.Anderson,
Series Editor
•
IEEE
U PRESS
The Institute of Electrical and Electronics Engineers, Inc., New York
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
4/190
This bookmay be purchased at a discountfrom the publisherwhen
orderedin bulk quantities. For more information contact:
IEEEPRESSMarketing
Attn: SpecialSales
P.O. Box 1331
445 HoesLane
Piscataway, NJ 08855-1331
Fax: (908)981-9334
For more information about IEEEPRESSproducts, visit the IEEEHomePage:
http://www.ieee.org/
© 1996by the Instituteof Electrical andElectronics Engineers, Inc.
345 East47thStreet,NewYork, NY 10017-2394
All rightsreserved. No part of this bookmay be reproduced in anyform,
nor
may
it be storedin a retrieval systemor transmitted in anyform,
withoutwrittenpermission from the
publisher.
ANOm
TO
THE
READER
This
book hasbeen
electronically reproduced
from
digital
information
stgre4at lohnWiley
Sons,
Inc.
We
are pleased
thattheuseof
this
new
technology
willenable us to keepworksof enduringscholarly
value inprintas longas there
is
a
reasonable
demand
for them. Thecontent ofthisbookis identical to
previous
printings.
Library of Congress Cataloging-In-Publication Data
Kerszenbaum, Isidor.
Inspection of largesynchronous machines: checklists, failure-
identification, and troubleshooting I IsidorKerszenbaum.
p. em.
Includes bibliographical references and
index.
ISBN0-7803-1148-5
(cloth)
1.
Electricmachinery, Synchronous-Inspection. I. Title.
TK2731.K47 1996
621.31 33-dc20
95-51730
CIP
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
5/190
To Jackie,
Livnat, and Yigal
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
6/190
Contents
List of Illustrations
Preface
Acknowledgments
Part
1 Preparation
Chapter 1: Site Preparation
1.1
Foreign Material Exclusion
1.2 Safety Procedures-Electrical Clearances
1.3 Inspection Frequency
1.3.1
Condition BasedMaintenance (CBM)
References
Chapter 2: Inspection Tools
Chapter 3: Inspection Forms
Form 1: Basic Information
Form2: Nameplate Information
Form
3:
Inspection
Accessibility
Form4: StatorInspection
Form
5:
Rotor Inspection
Form
6:
Excitation Inspection
Form
7:
SalientPolesCondition Report
Form8: Comments
Form9: Wedge Survey
Form 10: Electric TestData
xi
xv
xix
1
3
3
9
12
13
13
15
19
25
26
26
27
30
32
33
34
35
37
vii
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
7/190
viii
Contents
Part 2 Inspection 39
Chapter 4: Descriptionof Stator Items (Form 4) 41
SO1: Cleanliness of Bore 41
S02: Air/Gas DuctsCloggedlUnclogged 42
S03: IronOxideDeposits 43
S04: Hardware Condition 47
S05: High-Voltage Bushings 49
S06: Stand-OffInsulators 50
S07: Bushing Vents 51
S08: GreasinglRed OxideDeposits on CoreBolts andSpringWashers 52
S09: SpaceHeaters 55
S10: Fan-Baffle Support Studs 56
SII
and S12:Heat Exchanger Cleanliness and Leaks 56
S13: Hydrogen Desiccant/Dryer 57
514: Core-Compression ( Belly )Belts 58
S15: Bearing Insulation (at Pedestal or Babbitt) 58
S16: CoilCleanliness (including watercooledwindings) 60
S17: Blocking Condition 61
S18
and S19:TiesBetween Coils 63
S20
and S21:Ties to Surge-Rings 64
522: Surge-Ring Insulation Condition 64
S23: Surge-Rings Support
Assembly
65
S24: Additional End-Winding SupportHardware 67
S25: RIDs and TCs Wiring Hardware 70
526: AsphaltBleeding/Soft Spots 70
S27:
Tape
Separation/Girth Cracking 72
528: Insulation GallinglNecking Beyond Slot 75
829: Insulation BulgingintoAir Ducts 75
S30: Insulation Condition 75
S31: Circumferential Bus Insulation 76
532: CoronaActivity 78
S33:
Wedges Condition 84
534: Wedges Slipping Out 87
S35: FillersSlipping Out 87
536: BarsBottomed in Slot 88
S37: Laminations Bent/Broken in Bore 88
538: Laminations Bulging intoAirDucts 90
539: Terminal Box CurrentTransformer (CT)Condition 92
S40: Bushing
Well
Insulators and 2 SealantCondition 93
841:
End-Winding
Expansion-Bearing BoltsCondition 93
References 95
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
8/190
Contents
Ix
R21:
R22:
R23:
R24:
R25:
R26:
R27:
Chapter 5: Description of Rotor Items (Form 5)
RO I: Rotor Cleanliness
R02: RetainingRings' Visual Appearance
R03: Centering Rings' VisualAppearance
R04: Fan Rings' VisualAppearance
R05: FrettingIMovement at Rings' Interference-FitSurfaces
R06: Fan Blades Condition
R07: Bearing Journals Condition
R08: BalanceWeightslBolts Condition
R09: End-Wedges Condition
RIO: Other wedges
Rll: End-Windings Condition
R12: Top Series Connections
R13: BottomSeries Connections
R14
and R15: Field-PoleKeys in Dovetail and Inter-PoleBlocking
RI6
and R17:Insulation BetweenTurns
RI8: Starting-Bars (DamperWinding)Condition
RI9
and R20: Bull-Ring Segments and Bracing to
Starting-BarsCondition
CollectorRingsCondition
Collector InsulationCondition
Brush-SpringPressure and General Condition
Brush-RigCondition
Shaft-Voltage Discharge-Brush Condition
Inner/OuterHydrogenSeals
Circumferential Pole Slots Condition
References
97
97
98
103
103
105
105
106
108
108
110
111
114
114
114
115
117
119
119
122
123
123
123
123
124
125
130
131
131
128
129
130
127
127
128
128
Chapter 6: Description of Excitation Items (Form 7)
EO1: Cleanliness
E02: Shaft-MountedDiodes Condition
E03: Diodes Connectionsand Support Hardware
E04
to E07: Commutator, Brushes, Springs and
Brush-RigCondition
DC GeneratorStatorCondition
DC GeneratorArmatureCondition
E08:
E09:
EI0
and Ell: Exciter-Drive Motor Cleanliness and StatorCondition
E12: Exciter-MotorRotor
E13: Field DischargeResistor Condition
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
9/190
x
Chapter 7: Description of Generator Auxiliaries
7.1 LubricationSystem
7.2
HydrogenSeal Oil System
7.3 StatorWaterCooling System
7.4 Hydrogen System
Chapter 8: Standard Electrical and MechanicalTests
8.1 ElectricTests
8.1.1 WindingResistance(DC)
8.1.2 InsulationResistance (DC)
8.1.3 PolarizationIndex (PI)
8.1.4 Dielectric(Over-Potentia) or Hi-Pot) test
8.1.5 Tum-to-Tum Insulation(SurgeComparison) Test
8.1.6 ShortedTurns in ExcitationFieldWindings
8.1.7 OpenCircuit Test (for Detectionof Rotor ShortedTurns)
8.1.8 Power Factor Test
8.1.9 Tip-UpTest (for Stator Winding)
8.1.10 DielectricAbsorption
8.1.11
Partial Discharge(PO) Test (for StatorWindings)
8.1.12 Slot-Discharge (SO)Test
8.1.13 Stator InterlaminarInsulationTests
8.1.14 Core-Compression Bolts Insulation Test
8.1.15 Bearing Insulation
Test
8.2
Mechanical
Tests
References
Appendix: Principles of Operation of Synchronous Machines
A.I GeneralDiscussion
A.2
Construction
A.3 Operation
A.3.t No-LoadOperation
A.3.2 Motor Operation
A.3.3 GeneratorOperation
A.3.4 EquivalentCircuit
A.3.5 Performance Characteristics: V curves and RatingCurves
A.4 OperatingConstraints
A.4.1
Volts per Hertz (VlHz)
A.4.2 NegativeSequenceCurrentsand {I
2
)2t
A.4.3 Maximum
Speed
References
Index
Contents
133
133
135
135
136
137
138
138
138
139
141
141
141
144
144
145
146
147
148
148
148
149
149
149
153
153
154
156
157
159
159
160
161
165
165
167
170
170
171
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
10/190
List of Illustrations
Chapter 1
Fig. I-I.
Fig.
1-2.
Fig. 1-3.
Fig.
1-4.
Fig.
1-5.
Fig.
1-6.
Fig.
1-7.
Fig. 1-8.
Fig.
1-9.
Fig.
1-10.
Fig.
I-II.
Fig.
1-12.
Wooden
coverwithdoorat the entranceto the borearea.
Temporary barriererectedto preventcontamination.
Typical hot-airblower.
Lowering a protective tent on the rotorof a largeturbogenerator.
Applying masking tape to vent holesof a 4-pole turbogenerator
rotor.
Same rotoras previous figure, with the ventscovered.
Rotorbodycoveredto avoidcontamination.
Flashlight strappedto the
wrist.
Site of a 1350-MVA unit undergoing overhaul.
Provisions allowing safe accessto theboreof a largegenerator.
Groundleadsappliedto a generatorunit beingoverhauled.
The knuckle area of directlygas-cooled statorcoils.
Chapter 2
Fig. 2-1. Easy-to-carry tool case with themostessential tools.
Fig.
2-2. Commercially available wedgetightness electromechanical
tester.
Fig. 2-3. Commutation performance chartsfrom various manufacturers.
Fig. 2-4.
Boroscope
usedfor
visual inspection
of otherwise inaccessible
areas.
Chapter 3
Fig. 3-1.
An air-cooled, 35-MVA synchronous condenser.
Fig. 3-2. Ahydrogen-cooled, 60-MVA synchronous condenser.
xi
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
11/190
xii
Listof Illustrations
Fig. 3-3. A
vertical, air-cooled, synchronous hydrogenerator.
Fig. 3-4.
A
1182-MVA, 3000-rpm
2-pole
generator.
Fig. 3-5.
A
1620-MVA,
1500-rpm 4-pole
generator.
Fig.3-6. Schematic representation of a typical large turbogenerator.
Chapter 4
Fig. 4-1.
Fig. 4-2.
Fig. 4-3.
Fig.
4-4.
Fig. 4-5.
Fig. 4-6.
Fig.4-7.
Fig. 4-8.
Fig. 4-9.
Fig.4-10.
Fig. 4-11.
Fig. 4-12.
Fig. 4-13.
Fig. 4-14.
Fig.
4·15.
Fig. 4-16.
Fig. 4-17.
Fig. 4-18.
Fig. 4-19.
Fig. 4-20.
Fig.
4-21.
Fig. 4-22.
Fig. 4-23.
Fig. 4-24.
Fig. 4-25.
Fig. 4-26.
Fig. 4-27.
Fig. 4-28.
Fig. 4-29.
Fig.
4-31.
Fig. 4-32.
[SOl] Broken piecesof laminations found in borearea.
[S03] Section of a turbine-generator boreshowing ironoxide
deposits.
[S03] Closeviewof Fig.4-2.
[S03]
Worn
wedges in the statorof a synchronous condenser.
[S03]Sectionof statorlaminations showing insulation partially
lost.
[S03] Close-up of section of lamination shown
in
Fig. 3-5.
[S03]
Twopackets of
broken
laminations.
[504]Section of a large4-poleturbine generator showing gas-
guides.
[S04] Close-up viewof gas deflectors showing damage.
[S06] Stand-offinsulators damaged by surface contamination.
[S07] Crosssection of a typical bushing well.
[S08]
Core-compression hardware of a many-pole machine.
[S08] Springwashers coveredwithresin-soaked glasstape.
[S10]Fan-baffle supportthreaded stud shown.
[S17]Theend-winding of a turbogenerator.
[S17]Close-up of a blocking arrangement.
[522]
Insulated surge-ring supporting hydrogenerator end-winding.
[523]End-winding withtwosurge-rings and support assembly.
[S23]
Schematic of a typical end-winding supportassembly.
[S24] Portion of an end-winding of a water-cooled stator.
[S24]
Manifolds and tubing for4-pole
1150-MVA
turbine
generator.
[S24] Schematics of end-windings, watercooledstators.
[S27]
Tapeseparation shownincoilof a steam-turbine
generator.
[S27] Tapeseparation andgirthcracks.
[527]Coilwithgirthcrackin wall insulation nearcooling
vent.
[S27]
A fissure on the insulation of a coilnear the surge-ring.
[S31] Circumferential busses at connection endof salient-pole
machine.
[531] Portion of circumferential
busses
in a steam-turbine
generator.
[S31]
Greasing at the
region
of the support due tomovement.
[S32] Closeviewof oneof affected areasshownin Fig.4-30.
[532] Installation of embedded statorslot coupler(SSe).
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
12/190
Listof
Illustrations
xiii
Fig.
4-33.
Fig. 4-34.
Fig.
4-35.
Fig. 4-36.
Fig. 4-37.
Fig.
4-38.
Fig.
4-39.
Fig.
4-40.
Fig. 4-41.
Fig. 4-42.
Chapter 5
Fig. 5-1.
Fig. 5-2.
Fig. 5-3.
Fig. 5-4.
Fig.
5-5.
Fig. 5-6.
Fig. 5-7.
Fig. 5-8.
Fig. 5-9.
Fig.
5-10.
Fig. 5-11.
Fig. 5-12.
Fig. 5-13.
Fig. 5-14.
Fig. 5-15.
Fig.
5-16.
Fig. 5-17.
Fig. 5-18.
Fig.
5-19.
Fig. 5-20.
Fig. 5-21.
[833] Movementof loosewedges in oil createsgreaselike
deposits.
[833]Close-upof a looseend-wedgeand greasing.
[S33]Tapping wedges insideboreof a
475-MVA
4-polegenerator.
[S35] Side-coil fillersof a salient-pole synchronous machine.
[S37]Bent laminations from the first packet (closest to edge of
bore).
[837] Samemachineas in Fig. 4-37,differentpackets.
[S38]Lamination bulginginto ventduct in steam-turbine
generator.
[S38]Cross-section of slot showingmigration of duct-spacer
assembly.
[841]A windingsupportbearing-boltwith greasedeposits.
[841] Grease deposits at theheadof thebearing-bolt of Fig.4-31.
[R02lPortionof a retainingring showingrust deposits.
[R02]Retainingringbeingpreparedfor removalby electrical
heating.
[R02]Retainingring of a 2-poleturbinegeneratorwith vent
holes.
[R02]Close viewof venthole from the retainingring in Fig. 5-3.
[R02l Schematicsof spindle-mounted andbody-mounted retain-
ing rings.
[R04]Fan ring and fan bladesof a 2-polecylindrical
rotor.
[R04]2-polecylindricalrotor.
[R06]Salient-polemachinewith radial fansbolted to rotor's
pole-support.
[R06]Arrangement similar to Fig. 5-8, but in a smallermachine.
[R06]Closeviewof a fan blade shown in Fig. 5-8.
[R06]Closeviewof elaborate attachment of fanbladesin Fig. 5-6.
[R09]Narrowstrips are rotorwedgesof a cylindrical rotor,
[R09]Rotorwedgesthat havemigrated.
[R09]A turbinegenerator's rotor witha singlewedgeper slot.
[RIO] Cross-section of aluminum rotorwedgeshowing stressarea.
[R11]Front viewof end-winding of a 2-polecylindricalrotor.
[RII] Topviewof the sameend-winding shown in Fig. 5-16.
[RII] Loose insulatingblockingof end-winding of gas-turbine
generator.
[RI5] A
V-block
wedgingtwo adjacentpoles in a salient-pole
generator.
[RI6] A salient pole with a strip-on-edge winding.
[RI6] A wire-wound salient-pole.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
13/190
xiv Listof Illustrations
Fig. 5-22. [R18]Short-circuiting ringof starting winding of a 60-MVA
condenser.
Fig. 5-23. [RI8] Closeviewof Fig.5-22,pole-face withstarting bars
sheared off.
Fig. 5-24. [R20] Short-circuiting segments.
Fig. 5-25. [R21] Thecollector ring (slip-ring) of a large turbine generator.
Fig. 5-26.
[R27]
Schematic representation of thecircumferential pole
slots.
Chapter 6
Fig. 6-1. [E04] DCgenerator commutator withthe
brushes
removed.
Fig. 6-2. [E09]
Armature
of shaft-mounted exciter.
Chapter 7
Fig. '-I. Typical arrangement of a lubrication system.
Chapter
8
Fig. 8-1.
Fig.8-2.
Fig. 8-3.
Fig. 8-4.
Fig. 8-5.
Fig. 8-6.
Fig. 8-7.
Appendix
Fig. A-I.
Fig.
A-2.
Fig.
A-3.
Fig. A-4.
Fig. A-5.
Fig.A-6.
Fig.A-'.
Fig.
A-8.
Fig.A-9.
Fig.A-IO.
Insulation resistance as a function of timeand dryness.
Typical curve
showing
variation of insulation resistance
with time.
Typical waveform
recorded
from flux probein a 2-pole
turbine
generator.
Typical
arrangement for C-core test to detectshorted
turns.
Typical
traces for theC-coretestof Fig.8-4.
Dependence of insulation powerfactoron number of
voids
in
insulation.
Absorption currentas a function of time.
Hydroelectric generator
from
Lauffen, nowin theDeutsches
Museum.
Schematic cross-section of a synchronous
machine.
Phasordiagrams fora synchronous cylindrical-rotor idealma-
chine.
Steady-state equivalent circuitof a synchronous machine.
Steady-state equivalent circuitandvectordiagram.
Typical V-curves for generator operation.
Typical
capability curves fora synchronous generator.
Typical
saturation curvefor transformers and
machines.
Hysteresis
losses
undernormal and abnormal conditions.
Temperature risemeasured at endof rotorbody.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
14/190
Preface
Many synchronous machines that were designed and manufactured in the last
decadeof the nineteenth centuryare still ineverydayoperation. Theseare mainly
hydrogenerators belonging to long-established utilities. The theory of the syn-
chronousmachinewas alreadywell advancedwhen thesemachinesweremanu-
factured. Since then, a profuse amountof theoretical literaturehas been added,
especially with the adventof the computerto facilitate the implementation of nu-
merical
analysis techniques. Over the years, the continuous push for higher and
higher ratings and operating voltages resulted in the development of more com-
plex mechanical structures, cooling arrangements, and insulation materials. As
the complexity of the machine increased, design margins became less forgiving.
In addition, the growingdependence of societyon electricpower and the prohib-
itive cost of failuresput the issue of reliability foremost. Reliability has been the
drivingforce for the continuous improvement of techniques and instrumentation
designed to monitor the conditionof the machineand for the creationof a wealth
of industrystandards.
Hand in hand with the development of hardware and written literature, a
wealthof expertisehasbeenaccumulated on the practicalaspectsof theoperation
of these machines. This expertise becomes evident during troubleshooting and
inspection activities. In spite of all the instruments andwrittenliterature, there is
no effective substitute for the expert on the spot to troubleshoot or evaluate the
conditionof the machineduringa visual inspection. The recognition of this ex-
pertise is demonstrated by the recent implementation of so-called expert sys-
tems to diagnoseproblemsin large synchronous machines.
xv
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
15/190
xvi
Preface
In spite of the universal reliance on visual inspection of large synchronous
machines as part of their operation andmaintenance, there is no written compre-
hensive compendium to be found on the subject. Succinct guidelines can be
found
in numerous standards, technical papers, manufacturers' bulletins, and
otherpublications. This bookfills this gap by providing a comprehensive
refer-
enceon the visual inspection of large synchronous
machines.
It is basedon the
largebodyof accumulated experience that can be
found
in a
myriad
of publica-
tions, thepersonal experience of the
author,
and foremost, on the contribution of
manyassociates.
Having the in-house capability to performreliable inspection of its genera-
tors and rotary condensers
allows
electric utilities and independent power pro-
ducers to make informed choices regarding repairs/refurbishment of these large
machines.
This independent capacity for evaluating the condition of the ma-
chinescan resultin substantial savings.
This book was written with the machine's operatorand inspector in
mind.
Although
not designed to providea step-by-step guidefor the troubleshooting of
largesynchronous machines, it servesas a valuable sourceof information thatcan
proveto
be
useful
duringtroubleshooting operations. The topics covered arealso
cross-referenced toothersources. Manysuch references are included to facilitate
the
search.
Equations describing the operation of the
machine
were intentionally
leftout frommostof the discussions. There is a vastamount of theoretical litera-
ture available for this
purpose.
The only theoryincluded in thisworkconsists of
descriptions of phenomena affecting the reliability of the
machine
components.
In addition, an appendix is included to review thebasicconcepts of synchronous
machine
operation. This appendix provides a
measure
of understanding of how
to utilize machine performance characteristics and theirsources, and shows how
to perform simplecircuitcalculations.
Aftera description of sitepreparation andinspection
tools,
thebookpresents
a numberof forms adequate for entering
findings
duringthe inspection of a large
synchronous machine. They are written in such a way that most of the items
found in major typesof machines can be accommodated. Items found only in
salient-pole machines are marked and items found only in round-rotor ma-
chinesare marked RR. Subsequently, eachof the itemsis described inChapters 4
through
7 regarding visualappearance andtheessenceof theprocesses involved.
Figures
are introduced
when
available. Theitemscovered appearunderthemain
members of the machine; that is, stator, rotor, and excitation. A list of themost
common
electric and mechanical tests performed in the field is presented in
Chapter8. Eachtestis referenced to thecorresponding ANSI/lEEE standards and
other publications.
Thisbookcan
be
useful to themachine-designing engineerand systems op-
erations engineer. It provides a wealthof information obtained in the field about
the behavior of thesemachines, including typical problems andconditions of op-
eration. Byserving as a sourcefor descriptions of different typesof synchronous
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
16/190
Preface
xvii
machines
and machine components, it canalsobe useful to the studentof electri-
cal rotating machinery.
The author's intention is to keep updating the contents of thisbookfromhis
own and others' experience. Therefore, he wouldappreciate it if readers would
please submit their comments or additions to the publisher for incorporation in
future editions.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
17/190
Acknowledgments
Thecontents of thisbookare
almost
impossible to learn in a class. They are the
resultof personal experience accumulated over
years
of workwith largeelectric
machinery.
Mostof all, theyare the resultof the invaluable long-term contribu-
tionof co-workers and associates. The following two individuals, in particular,
havebeen a continuous sourceof knowledge and inspiration over the
years,
as
wellas
having
beenkindenoughto
review
themanuscript and
provide
numerous
suggestions: Mr. Jack Cohon, large
machines
expert, retired fromSouthern Cali-
fornia
Edison, and
Mr.
TomBaker, SteamDivision Electrical Engineer, Southern
California Edison.
The author is highly indebted to Professor Alan Wallace of Oregon State
University
at Corvallis, ProfessorRadhe DasofCalifornia State
University,
Long
Beach,
James
Edmonds
of MCMEnterprises, Ltd., and GeoffKlempner of On-
tario Hydro for painstakingly reviewing the manuscript and making important
suggestions thatwereincorporated intothe finalmanuscript.
Theauthor
would
alsoliketo thankMr.
Dudley
Kay, the
members
of theed-
itorial department of IEEEPress,reviewers, and all othermembers of the IEEE
Press involved in thepublication of thisbook, for theirsupport inmaking its pub-
lication possible.
IsidorKerszenbaum
Irvine,
California
xix
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
18/190
PART 1
Preparation
Chapter
1
Site
Preparation
Chapter 1 describes how to minimize the risk of machine contamination and to
ensure a safe environment in which to perform the inspection.
Chapter 2 Inspection Tools
Chapter 2 discusses tools needed to perform the inspection.
Chapter
3
Inspection Forms
Chapter 3 includes The Synchronous Machine Inspection and Test Report, com-
prising ten forms applicable to the inspection of most large synchronous ma-
chines.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
19/190
1
Site Preparation
Site preparation is the first significant action to perform immediately before an
inspectioncarried out on, or in the vicinityof, a large electricalmachine.Every
inspectionof a large machine-scheduled or not, longor short-requires a sensi-
ble effort toward site preparation.
The
goal is to minimize the risks of contami-
natingthe machinewithany foreignmaterialor object, aswell as to ensure a safe
environment in which to perform the inspection. Site preparation should be
plannedaheadof time, and it shouldbe maintainedfrom the momentthe machine
is opened for inspectionuntil the time it is sealed and readied for operation.Ne-
glecting to prepare and maintaina properworkingenvironmentin and around the
machine can result in undue risks to personnel safety and machine integrity (see
Figs.
1-1
and 1-2).
1.1
FOREIGN
MATERIAL EXCLUSION
Foreignmaterialexclusion(FME),a termoriginated in thenuclear industry, is the
set of proceduresgeared tominimizethe possibilityof intrusion into the machine
of foreignmaterialsbefore, during, and after the inspection.
In principle, the definitionof foreignmaterial is anythingnot normallypres-
ent during the operationof the machine that might adverselyaffect its constituent
components if left there. For instance, although ambient air is not necessarily
considered a foreign material, the water content of the air is. Water definitively
is an extraneous element that should be kept from condensing on the machine
3
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
20/190
4
Preparation PartI
Fig.
I-I
Wooden
coverwithdoorat theentrance to theborearea
(both sides). These
allow
control
of access to themachine of personnel and tools.
Fig. 1·2 Temporary barrier erected
to
keep vital components from being contami-
nated with foreign objects or
materials.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
21/190
Chap. J Site
Preparation
5
windings, retaining rings, and other parts susceptible to mechanical failure from
corrosion,or fromelectric breakdownof the insulation.
Keepingwater from condensingonto the machinecomponentscan be read-
ily accomplishedby containingboth statorand rotorunderprotectivecovers (i.e.,
tents), and maintaininga flowof hot air.The hot air and the positivepressuredif-
ferential inside the tent eliminate the condensationof any significant amount of
water(Figs. 1-3and 1-4).Althoughthe flowof hot air is normallysuspendeddur-
Flg.1-3
Typical
hot-air
blower.
Fig.
1-4
Loweringa protectivetent on the rotor of a largeturbogenerator.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
22/190
6
Preparation
Part
1
ing the actual inspection for personnel comfort reasons,thus allowing somecon-
densation to occur, the subsequentflow of hot air will most probablyevaporate
themoisture and remove it from the containmentarea [1].
It is important to perform any scheduled electric tests with dry windings.
Otherwise, results obtained will not be representative of the winding condition
under normal operatingconditions.
It is also importantnot to contaminate themachineinadvertently withcorro-
siveliquidssuchas solvents,certainoils, andso forth.Sometimes extraneous flu-
ids can be introduced by walkingover them and thenwalking into the machine.
Therefore, in situationswherestringentFME rulesare applied, paperbootiesare
wornover the shoes.Some inspectors prefer the use of rubberbooties over their
shoesfor better and safergrip.
Paper, rubber, or cloth booties will go a long way in eliminating the intro-
ductionof small pebbles thatmaybe stuck to the soleof the shoe.Whenpressure
is appliedto the end-winding by walkingover it, a small pebblecan puncturethe
insulation, thus creating a region of electric-field concentration. This is worth
avoiding. It is good practicenot to step on the bare coils.A cloth will suffice to
protectthe windingfrom the shoe.
The worst enemies of the windings are any foreign metallicobjects.They
can becomeairbornedue to the highspeedof the coolinggas, and break the insu-
lationwhen striking it. Magnetic particles have been known to cause failures in
water-cooled coils by penetrating the insulation over long periodsof time,due to
the electromagnetic forces acting on the particle. Magnetic as well as nonmag-
netic metallic objects may be subject to eddy-current heating, detrimentally af-
fecting the insulation with which they are in contact. Foreign metallic objects
such as nails, welding beads, or pens inadvertently left in the bore can short-
circuit the laminations of the core.Continuedoperationunderthis conditionmay
result in a winding failure due to localized temperature rise of the core. Precau-
tionsshouldbe takento eliminatethepossibility of metallicpartsor other foreign
objectsenteringthe machine. One step in thatdirectionis maskingthe vent holes
of the rotorwheretheseare locatedoutside the statorbore,andcoveringthe rotor
when not under inspection or refurbishment (see Figs. 1-5 to 1-7).Metallicob-
jects not requiredfor the inspection shouldbe left outside.This entails removing
any coins and otherobjects (suchas medallions, beepers, unnecessary pens,pen-
cils, etc.) frompocketsprior to entering the machine. Inspectiontools shouldbe .
carried into the machineon an as needed basis.When using mirrors or flash-
lights in otherwise inaccessible areas, theseshouldbe securedby strappingthem
toone's wrist(Fig. 1-8).In particularly compromising situations, suchas withnu-
clear-powered generators, takingan inventory of tools is recommended both be-
foreenteringthe machineand afterexiting it. This is a time-consuming practice,
but recommended for all largegeneratorinspections.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
23/190
Chap. J Site Preparation
7
Fig. 1-5 Applying maskingtape to ventholesof a large4-poleturbogenerator rotor,
withthe purposeof eliminatingcontamination of rotorwinding.
Fig. 1-6 Samerotoras previousfigure,with the ventscovered.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
24/190
8
Preparation
Part
1
Fig. 1-7 Rotorbodycoveredto avoidcontamination whileworkingonotherareasof
the rotor (end-windings).
Fig. 1·8 Flashlight strapped to the wrist, to
eliminate the possibility of dropping
it
in inac-
cessibleplaces.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
25/190
Chap. J Site Preparation
1.2 SAFETYPROCEDURES-
ELECTRICAL CLEARANCES
9
Whencarryingout work in an industrial environment, nothingis more important
than adhering to all required safety precautions. Large machines opened for in-
spection often present obstacles in the formof big openings in the floor surface,
crevicesto crawl through,rodsandmachinemembers stickingout, and soon (see
Fig. 1-9).They all demandevaluationof requiredtemporary additionsto the site,
such as beams over the open floor spaces, handrails (Fig. 1-10), secure ladders,
and so on.
The obstaclesjust mentioned are all visible to the peopleengaged in the in-
spection. However, an invisibleand verypowerfulelementto contendwith is the
voltage potential (or range of voltages) that may be present in a machine. Al-
thoughrare, electrical accidents can occur whenwork is performed in large ma-
chines.
A comprehensive inspection of a large machine requires direct physical
contact with all windingsand other elements that are normallyenergizedduring
the operationof the machine. Walkingthe clearance is jargon usedby some to
describetheprocess of inspectingall breakers, cables, and connections that may
besourcesof electric power to any part of the machine,and makingsure theyare
deenergized and secure.This means that none of these will be accidentallyener-
Fig.I-9 Site of a 1350-MVAunit undergoing overhaul.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
26/190
10
Preparation Part 1
Fig. 1·10 Provisions allowingsafe accessto the boreof a largegenerator.
gized during the inspection. The following is a typical (but by no means all-
inclusive) list of safety procedures:
• Personalgrounds (groundingcables) atbothendsof the windingof each
phase will minimize the possibility of receiving an unexpected electric
discharge(Fig. 1-11).
• Phase leads must be open.
• Neutral
transformer (if
present) must be disconnected, or have its leads
opened.
•
Voltage
regulatorsand other excitationequipment must be disconnected.
• Potential transformers are an additional source of voltage to the main
windings, and therefore they must be disconnected and secured. Space
heaters are often overlooked.
To
keep
themoisture out,
space heaters are
normally left on after disassemblingthe machine; thus, it is imperative
to makesure they are disconnectedduring the inspection.
• All switches that may energize any part of the machine must
be
clearly
tagged. A tag can only be removed by the person who installed the tag
originally.
• When inspectingmachineswith direct gas cooling of the stator windings,
discharge resistors are often found on the coil knuckles (see Fig. 1-12).
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
27/190
Chap.
1 Site Preparation
11
Fig.
I-II
Groundleadsappliedto a generator unitbeingoverhauled.
Flg.t-ll Theknuckleareaof directlygas-cooled statorcoils.Thedischarge resistors
are insidethe knucklearea.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
28/190
12
Preparation Part 1
When faulty,
theymay
remain
charged for substantial lengths of
time.
Pre-
caution should be taken when inspecting such
windings,
in particular if
high-voltage testswereperformed beforedisassembling the
machine.
You
canneverbetoo safety-conscious
when
dealing withhigh-voltage
appara-
tus.
• Turning gear must be disconnected (fuses removed) and clearly
tagged
wheninspecting withthe rotor in place.
• Gasmonitors for confined areasmustbe used.
• When inspecting hydrogenerators, in addition to the electrical clearance
walk, a mechanical clearance walkmustbecarriedout.This shouldverify
thewaterturbineand valves are lockedandsecurefrominadvertent move-
ment.If possible, the turbine/penstock should
be
de-watered.
• Additional itemsas each specific casewarrants.
• Followall relevant safetyrulesandregulations.
1.3 INSPECTION FREQUENCY
Certain components in large synchronous machines require routine inspections
(and sometimes maintenance) between scheduled major outages. Other more
comprehensive inspections, requiring various degrees of machine disassembly,
areperformed duringthemorelengthy outages.
However,
experience hasshownthata majorinspection afteroneyearof op-
eration is
highly
recommended for new
machines. During
the initialperiod,
wind-
ingsupport hardware andsomeothercomponents experience harsherthannormal
wear.
Retightening of core-compression bolts may also be required during this
first outage.
Subsequent outages and inspections can be performed at longerplannedin-
tervals. How long an interval? Minor outages/inspections every 30 months, to
majoroutages/inspections every60
months
are typical periodsrecommended by
machine
manufacturers. Thesemajoroutages include
removal
of the rotor, com-
prehensive electrical and
mechanical (nondestructive) tests, and visual inspec-
tions.
Obviously,
these intervals tend to be longerfor machines spending long
periods without operation. Most stations havelogscontaining the actualnumber
of hours theunitwas running andthe number of starts/stops. This information, to-
getherwiththemanufacturer's recommendations, canbe used to schedule the in-
spections and overhauls.
Largeutilities thathavemanygenerators in their systems andmanyyearsof
experience
running
these
machines
have formed their own maintenance and in-
spection criteria and schedules. Although
working
closelywith therespective ma-
chines' manufacturers, theseutilities tend to extend the periods between outages
for thosemachines thatexperience has shownto havegood records of operation,
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
29/190
Chap. J Site Preparation
13
and shorten the periods between outages/inspections for
machines
thathavebeen
characterized by morefrequent failures (asmaybe thecasewithold hydrogener-
atorsand rotating condensers).
Frequently, themajoroutages during
which
theopportunity presents itself to
carry out a major inspection
follow
the need to maintain the prime movermore
thanthegeneratoritself.
1.3.1
Condition-Based Maintenance (CBM)
Highequipment reliability, high outagecosts, and the newcompetitive out-
look permeating the electricpower industry have resulted in a newapproach to
machine maintenance. Condition-based maintenance (CBM) reliesheavily on so-
phisticated on-line instrumentation and evaluation techniques to assess the con-
dition of the machine. In this manner, the periods between major outages/
inspections can be increased
beyond
the fixed, scheduled intervals of the past.
The mainconcept is to basemaintenance on the actual condition of the machine
ratherthanon a fixedschedule.
One suggested method of obtaining significant information on thecondition
of themachine is to retrieve temperature, vibration, PD (partial discharge) activ-
ity, air/gas-gap flux, andother readings on themachine underload(priorto shut-
down), andcompare themwith thesame testdataobtained on previous occasions
undersimilaroperating conditions.
REFERENCES
[1] ANSIIIEEE Std43-1974, Recommended Practice forTesting Insulation Re-
sistance of Rotating Machinery, ItemA2, p. 15.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
30/190
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
31/190
16
Preparation Part 1
Fig.2-)
Easy-to-carry
toolcase with the
most essential tools
for visual inspection of
themachine.
• Disposablepaper or cloth overall.
• Workshoeswithsoft sole (rubber).
• Floodlightwith an extensioncord.
• Flashlights and a set of spare batteries. If a flashlight is at risk of fallingto
inaccessible places, it shouldbe attached to the wrist with string and tape.
• Clean rags.
• A small sealed container with white rags to be used as swabs; useful for
takingsamplesof contamination when required.
• A
set of mirrorswith articulatedjoints andexpandablehandles. If
the
mir-
rors are at risk of falling to inaccessible places, they shouldbe attachedto
the wristwith a stringand tape.
• A hammerwith both a soft (rubber) and hard (plastic) heads, for probing
wedges, insulation blocking, etc. For a wedge survey of the entire ma-
chine, hand-held electromechanical probes are commercially available
(see Fig. 2-2). After an initial setting, the probe identifieseach wedge as
tight
or
loose/hollow.
• A set of magnifying glasses or hand-heldmicroscopes to probe for corro-
sion or electrically originatedpitting on retaining rings and in other criti-
cal locations.
• Charts from manufacturers of commutator brushes depicting observable
signs of bad commutation (Fig. 2-3).
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
32/190
Chap.
2 Inspection Tools
17
Fig.2-2 Commercially available wedge tightness electromechanical tester.
Fig. 2-3 Commutation performance charts from various manufacturers of brushes,
and other useful information.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
33/190
18
Preparation
Part 1
• Boroscope, especiallysuitableto inspectunderthe retainingrings,air/gas
ducts, air/gas-gap of machineswiththe rotor in place, and.other inaccessi-
ble spots (Fig. 2-4).
• Agoodcameracapableof takingclose shots of small areas.
• A smallmagnetfor the extractionof loose ironparticles.
Figure 2-4 Boroscope used for visualinspection of otherwise inaccessible areas of
the
machine.
Lightsourceandoptionalvideoequipmentnot shown.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
34/190
3
Inspection Forms
Chapter 3 includes the Synchronous
Machine
Inspection and Test Report,
which comprises ten inspection forms for largesynchronous machines. The forms
accommodate both salient-pole and round-rotor machines, as well as motors,
generators, and rotarycondensers. Some individual itemson the forms apply to
only one of the above; some apply to all of them. Items that are found only in
salient-pole machines are
marked SP
on the forms. Items found only in round-
rotor (cylindrical) machines aremarked RR on the forms.
Theformsare not intended to cater toevery typeof machine currently being
used in the industry. Their purpose is to serve as an example of howsuch forms
mightbe organized. However, withminoradditions or changes, theycan suffice
to aid in the inspection of mostmachines.
Figures 3-1 to 3-3 depict typical synchronous machines encountered across
the
industry.
Figure 3-4 is a schematic representation of a large 2-pole turbine
generator.
This hybrid-cooled generator has a water-cooled statorand hydrogen-
cooled rotor. The bearings are mounted on the machine'sbrackets (end-shields).
Figure 3-5 shows a large 4-pole turbine generator. The machine has stator and
rotorwindings, bothwater-cooled. Its bearings aremounted on pedestals. In both
Figures 3-4and3-5,certaindetailsof thewaterfeed
system
to the statorwindings
can be seen.
Figure3-6 depictsa typical generatorand itscomponents. Thefigureshows
the
frame
construction and the end-winding supports attached to the
frame.
The
figurealso showssomeof theexternal detailsof thecylindrical
rotor.
19
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
35/190
20
Preparation Part J
Fig.3-1 An
air-cooled,
35-MVA
synchronous
condenser.
Fig. 3-2 A hydrogen-cooled, 60-
MVA
synchronous condenser.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
36/190
Chap. 3 Inspection Forms
21
Fig.3-3 Avertical, air-cooled, synchronous hydrogenerator.
One of the important steps to be taken at the onset of an overhaul is the pri-
oritization of those items to be inspected immediately after disassembly of the
machine. For instance, if a wedge survey is considered necessary,
it
should
be carried out as soon as possible after removal of the rotor. The reason for this is
the relatively long lead time required to purchase a new set of wedges. Pressure-
testing of the hydrogen seals of the rotor of a turbine generator should also be
done as early into the overhaul as possible. The same can be said about non-
destructive examinations (NDEs) of retaining rings and other critical items that
may require replacement.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
37/190
F
g
3
4
A
1
M
3
Q
p
m
2
p
e
a
o
a
o
w
n
n
w
e
c
e
o
o
w
n
n
h
o
c
e
(
R
o
w
h
m
s
o
f
o
m
D
g
a
P
o
m
L
g
S
e
m
T
b
n
G
a
o
1
A
)
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
38/190
:
~
·
j
,
F
g
3
5
A
1
M
S
Q
O
p
m
4
p
e
g
a
o
a
o
a
r
o
o
w
n
n
w
e
c
e
(
R
o
w
h
m
s
o
o
m
D
g
o
m
L
g
S
e
m
T
b
n
G
a
o
1
A
)
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
39/190
w
F
g
3
6
S
m
c
e
e
a
o
a
y
c
a
g
u
b
a
o
T
g
e
h
w
d
t
a
s
o
h
a
m
e
c
u
o
a
t
h
w
n
n
u
s
a
to
h
f
a
m
(
C
g
C
1
E
e
c
P
w
R
c
n
u
e
E
R
E
S
P
w
P
a
R
e
e
V
u
m
1
1
R
n
e
w
h
s
o
)
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
40/190
Chap.
3 Inspection
Forms
SYNCHRONOUS MACHINE INSPECTION ANDTEST REPORT
Form 1: Basic Information
mark withX
GENERATOR
CONDENSER
MOTOR
SALIENT·POLE
ROUND·ROTOR
Station/Company where installed
Unit no.
25
Primemover type:
Serialno. of generator
Steam
Gas
Hydro
__
Diesel
__
Manufacturer _
Date of manufacture _
Frame _
Year
installed _
Dateof last
rewind:
Stator _
Dateof last major inspection
Rotor _
Total
operating hours
__
Operating hourssincelast overhaul
__
Total
numberof starts/stops
__
Numberof hours in turning gear__
Presentinspection performed by
Assisted by _
Dateof inspection
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
41/190
26
Form 2: Nameplate Information
Preparation Part J
Rated
MVAo_
Powerfactor_ Shortcircuit ratio _ Field 1
2
1_
Stator:
Field:
Line voltage kV Rated current amps
DC voltage volts DC current amps
Nominal speed
___ rpm No. of poles_ Frequency__Hz
Stator cooling: Open air _ AirlWater _ Direct
water_
Hydrogen _
Rotorcooling: Air _ Hydrogen_
Water
_
Stator insulation: Asphalt_ EpoxylResin-Mica _ VPI _ Other__
Max.
H
2
pressure[psi]
__
Form
3: Inspection Accessibility
Yes No
Rotor out of bore
Inboardtop-bracket removed
Inboardbottom-bracket removed
Outboard top-bracket removed
Outboardbottom-bracket removed
Bushingwell open
Inboardretaining ring off
Outboard retaining ring off
Exciter's rotor out of bore
Electrical and mechanical clearance
Additional details:
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
42/190
N
F
m
4
S
a
o
n
p
o
T
o
b
o
k
n
M
e
T
o
e
C
o
m
n
F
E
w
n
n
m
k
u
Z
r
n
R
u
r
p
S
a
O
h
_
T
e
G
a
o
n
G
a
co
d
F
a
O
h
_
T
o
w
d
F
a
P
g
b
O
h
_
T
o
s
d
e
s
F
a
;
R
p
e
p
n
;
N
s
n
B
o
c
o
c
n
p
o
h
r
d
a
e
p
o
m
d
Y
;
N
I
w
d
u
v
y
o
m
d
o
o
e
w
d
o
h
o
w
w
d
N
m
o
d
m
g
d
e
s
o
s
n
e
o
w
e
c
o
e
d
w
n
n
O
o
s
I
e
m
D
c
p
o
N
O
I
X
C
e
v
A
o
S
O
C
e
n
n
o
b
e
o
d
e
c
)
S
A
r
d
s
c
o
d
u
o
d
S
I
o
d
d
p
s
?
S
H
d
w
e
o
o
b
s
n
s
e
c
)
S
H
V
b
h
n
S
S
a
n
o
n
u
a
o
s
S
B
h
n
n
s
c
o
d
u
o
d
S
G
e
n
r
e
d
o
d
d
p
s
o
o
e
b
s
?
S
S
h
e
s
S
F
n
b
e
u
s
u
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
43/190
S
a
o
n
p
o
c
o
n
d
6
0
o
s
D
c
p
o
N
O
I
X
C
e
v
A
o
S
H
e
x
h
n
s
c
e
n
n
5
H
e
x
h
n
s
e
k
?
5
H
o
n
c
n
d
y
5
C
e
c
o
m
e
o
b
y
b
s
S
B
n
n
u
a
o
a
p
d
a
o
b
b
)
S
C
c
e
n
n
o
d
e
c
)
S
B
o
k
n
o
o
S
T
e
b
w
n
o
s
g
?
S
T
e
b
w
n
o
s
o
y
S
T
e
o
u
g
n
g
?
S
T
e
o
u
g
n
o
y
S
S
g
n
n
u
a
o
o
o
S
S
g
n
u
a
e
m
y
5
A
o
e
n
w
s
u
h
d
w
e
5
R
D
a
n
T
C
w
r
n
dw
e
S
A
p
b
e
d
n
S
s
p
s
?
5
T
p
e
p
a
o
G
r
h
a
k
n
S
I
n
u
a
o
n
n
k
n
y
o
?
S
I
n
u
a
o
g
n
n
o
r
d
s
?
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
44/190
N
\
C
S
a
o
n
p
o
c
o
n
d
f
o
s
I
e
m
D
c
p
o
N
O
I
X
C
e
v
A
o
S
I
n
u
a
o
o
y
F
a
k
n
S
C
r
c
u
m
e
e
n
a
b
n
ua
o
S
C
o
v
y
S
W
e
d
c
o
o
w
d
u
v
y
o
w
S
W
e
d
p
n
a
en
?
S
F
e
s
p
n
a
e
n
?
S
B
s
b
o
m
d
n
o
?
S
L
m
n
o
b
n
n
e
B
o
n
S
L
m
n
o
b
g
n
n
o
r
d
s
?
5
T
m
n
b
C
s
o
o
S
B
h
n
w
n
u
a
o
s
an
H
e
a
n
c
o
o
S
W
i
n
n
u
b
n
b
c
o
o
R
R
I
e
m
to
o
y
n
o
o
o
m
h
n
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
45/190
C
M
=
F
m
5
R
o
n
p
o
T
o
o
o
S
e
n
,
R
;
R
a
n
n
n
y
M
c
N
m
c
C
S
n
e
m
e
d
B
m
e
d
C
e
o
n
p
o
s
a
m
n
o
e
n
N
m
o
c
o
e
o
n
p
p
a
y
O
T
w
T
e
6
f
I
e
m
D
c
p
o
N
O
I
X
C
e
v
A
o
R
R
o
c
e
n
n
o
d
r
o
c
o
d
)
R
R
a
n
n
n
v
s
u
a
p
a
n
R
R
C
n
e
n
n
v
s
u
a
p
a
n
R
R
F
n
n
v
s
u
a
p
an
R
F
e
n
m
m
n
a
r
n
f
s
?
R
F
n
a
d
c
o
o
R
B
n
o
n
s
c
o
o
R
B
a
n
w
g
s
b
s
c
o
o
R
E
w
d
o
h
n
n
r
n
o
e
R
R
O
O
h
w
d
o
h
ed
o
e
c
a
k
?
R
R
l
E
w
n
n
c
o
o
R
R
T
e
e
c
o
o
S
R
B
o
m
s
e
e
c
o
o
S
R
I
e
m
to
o
y
n
o
oo
m
h
n
S
I
e
m
to
f
o
y
n
a
e
n
-
p
e
m
h
n
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
46/190
}
R
o
n
p
o
c
o
n
d
o
s
I
e
m
D
c
p
o
N
O
I
X
C
e
v
A
o
R
F
e
d
p
e
k
y
n
a
c
o
o
o
S
R
V
s
h
p
d
n
e
p
e
b
o
k
S
R
I
n
u
a
o
w
n
u
n
S
R
F
e
d
o
s
h
f
e
d
d
m
g
d
S
R
8
S
a
n
b
s
(
d
m
w
)
c
o
o
S
R
9
B
-
n
g
m
n
s
o
o
h
n
R
S
a
n
b
s
o
-
n
g
m
n
b
a
n
S
R
C
e
o
n
c
o
o
R
C
e
o
n
u
a
o
o
o
R
B
u
h
s
p
n
p
e
u
e
n
o
o
R
B
u
h
g
o
o
c
e
n
d
m
g
d
e
c
)
R
S
-
v
a
g
d
s
h
g
b
u
h
o
o
R
I
n
o
e
h
o
n
c
o
o
R
R
C
r
c
u
m
e
e
n
a
p
e
o
s
c
o
o
R
R
I
e
m
t
o
o
y
n
o
oo
m
h
n
S
I
e
m
to
f
o
y
i
n
e
n
-
p
e
m
h
n
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
47/190
F
m
6
S
e
n
P
e
C
o
R
p
P
e
C
o
P
e
C
o
P
e
C
o
1
1
2
2
1
2
3
1
2
4
1
2
5
1
2
6
1
3
7
1
3
8
2
3
9
2
3
1
2
3
1
2
3
1
2
3
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
48/190
F
m
7
E
a
o
n
p
o
T
o
e
x
a
o
S
-
e
e
d
S
a
a
o
o
d
s
a
e
S
-
d
v
n
n
a
o
S
a
a
o
g
n
a
o
O
h
_
I
e
m
D
c
p
o
N
O
I
X
C
e
v
A
o
E
O
C
e
n
o
c
b
e
c
)
E
S
m
e
o
o
E
D
o
o
u
h
d
w
e
E
C
m
a
o
c
o
E
C
m
a
o
b
u
h
o
E
C
m
a
o
b
u
h
h
d
a
g
o
E
B
u
h
p
n
p
e
u
e
&
c
o
E
O
S
D
g
a
o
s
a
o
c
o
E
D
g
a
o
a
m
u
e
o
E
O
E
e
d
v
m
o
o
c
e
n
E
E
e
d
v
m
o
o
a
o
c
o
E
2
E
e
m
o
o
o
q
e
c
e
c
)
E
F
e
d
s
g
e
s
o
c
o
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
49/190
34
Form8:
omments
Preparation
Part J
Comments:
- - - - - - - - - - - - - - - - - - - - - - - - -
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
50/190
Chap. 3 Inspection Forms
Form
9: Wedge Survey
35
This is a typical tablefor performing a
wedge
survey. A larger number of
columns
for wedges and/orrows for slotsmaybe required for largermachines.
One way to enter the information is:
• 0 fora tight wedge
• H for a hollow wedge
• L for a loose wedge
s
w
ww
ww
ww
ww ww ww
ww w
ww ww ww
ww
ww ww
W
L
E
E E E E E E
E E E E E E
E E
E E
E E
E E E E E E
E E E E
o D
D D
D D
D D
DD DD
D D
D D D D D D
D D
D D
DD D D D D
T G G G
G G
G G
GO
o
G G 0
G G
o
0
o 0
o
0
o
G
GO G 0 o
G
E E
E E
E E E E E E E E E E E E E E E E E E E E E
E
E E E
I
o
0
o
0
o
0
000
I 1
1
1
1 1
1
I I
1 2
2 2
2 2 2 2 222
I 2
3 4 5 6
7 8
9 0
1 2
3 4 5
6
7 8
9 0
1 2
3 4
5 6
789
1
2
3
4
5
6
7
8
9
10
II
12
13
14
15
16
17
18
19
20
21
22
23
24
2S
26
27
28
29
30
31
32
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
51/190
36
Wedge
Survey continued
Preparation
Pari J
s
w
WW
WW
WW
WW WW WW
WW WW WW WW
WW WW
WW
WW
L E E E E E E E
E E E E E E E E
E E E E
E
E
E E E E E E
E E
o
D
D
D
D D
D
D
DO
D
D
D 0 D D D D
D D D D
D D
DD D 0
D D
T G
G G
G G
G G
o G G 0
G G G G
G G
G 0
G G G G
0 0 G G
o G
E E E E
E E
E E
E E
E E
E E E
E E
E E
E E
E E
E E E E E E
#
o 0 o 0 o 0
o 0 0
I
1
I
I
1
I
1 I
1
I 2 2 2
2 2 2 2
2 2 2
1 2
3 4 5 6
7 8 9 0 I
2 3
4 5
6 7
8 9
o 1
2 3
4
S
6 7 8 9
33
34
S
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
S9
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
52/190
Chap. 3
Inspection
Forms
Form
10: Electric Test Data
37
The following data is a sample of data from tests performed after machine shut-
down (some of these tests to be performed under hydrogen for hydrogen-cooled
machines)
refer to the pertinent standards for
the correct test procedures
- see references for chapter 8 -
MACHINE STATOR
• Measured conductivity for liquid-cooled machines:
__
micro-mhos/em
• Measured meggerreadings of windings to ground(with2500V
megger)
_
3D
s 1 min 10min _
Polarization Index(10 mini min) _
Ambienttemperature Hours after shutdown
_
StatorRTDs temperature I) 2) 3) 4) _
5) 6) (twoof each phase)
Note: Forwater-cooled statorsonly 1 min megger
reading
required
MACHINE
ROTOR
• Measured meggerreadingsof windings to ground(with500V megger) _
30 s 1min 10min _
Polarization Index(10 min/I min) _
ALTERNATOR EXCITER
Stator
• Measured statormeggerreadingsof windings to ground(with 500 V
megger)
_
3D
s 1 min 10min _
Polarization Index(10 minll min) _
Winding temperature _
Rotor
•
Measured
meggerreadings of windings to ground(with 500V
megger)
_
3D
s 1 min 10min _
Polarization Index(10 minll min) _
Winding temperature _
DC
EXCITER
• Measured meggerreadingsof windings to ground(with 2500V megger) _
3D s 1 min 10 min _
Polarization Index(10 minll min) _
Winding temperature _
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
53/190
38
Electric Test Data (continued)
RTDs
•
Megger
test to groundwith500V
Megger
• Measure eachRTD'sresistance with a bridge
•
Compare reading
with
measured
temperature of thewinding
STATOR WATER OUTLET THERMOCOUPLES
Preparation
Part
1
•
Measure
millivolts andcompare
readings
with
measured
temperature of wateror
ambient
air (when
empty)
ADDITIONAL TESTS
• Corona probe(when required-large salient-poles)
• PDActivity readings (beforeshutdown if instrumented)
• Rotor-flux waveforms (if fluxprobeinstalled)
ALARM CHECKS
The following is a sampleof the alarmcircuitsand activators that
require
check
(differ-
ent machines willhavea different set of alarms):
• Air
filters
clogging
alarms
• Statorcoolingwaterpressure low
• Waterpressure at
machine
•
Water
flow
• Statorwaterfilter
• Stator
water-cooling
pump
• Water andoil leakage detectors
• Hydrogen seal-oil enlargement detector
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
54/190
PART 2
Inspection
Chapter
4
escription
of
Stator
IteDls
Chapter 4 describes each stator item on Form 4, Stator Inspection.
Chapter 5 escription ofRotor ItelIls
Chapter 5 describes each rotor item on Form 5, Rotor Inspection.
Chapter
6 escription ofExcitation IteDls
Chapter 6 describes each excitation item on Form 7, Excitation Inspection.
Chapter
7 Generator uxiliaries
Chapter 7 describes auxiliary systems that should not be overlooked in an inspec-
tion, such as lubrication systems, hydrogen seal oil systems, stator-cooling water
systems, and hydrogen systems.
Chapter
8
Standard Electrical
andMechanical Tests
Chapter 8 giyes an overview of the electrical and mechanical tests, which should
only
be
performed
by
trained personnel.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
55/190
4
Description of Stator Items
The Stator Inspection form refers to items comprising the actual stator, as well as
the frame, bearings, and other machine-related components. Each item on the
form is described below with reference to its item number. Figure captions also
include the reference number for the item to which they correspond.
501: Cleanliness of Bore
Important information on the condition of the machine may be obtained
from a general view of the bore area and frame. For instance:
• Excessive discoloration (and perhaps flaking) of paint on the casing,
frame, and bore indicates a probable case of overheating. This could be a
result of overloading, or improper flow of air, gas, or water.
• The presence of large amounts of oil or a dust-oil mixture attests to possi-
ble hydrogen-seal problems.
• In certain types of air-cooled machines, large amounts of carbon dust are
evidence of deficient sealing between the collectors' enclosure and main
bore areas.
• In cylindrical machines (turbine generators), loose copper dust, or dust
mixed with oil andlor other dusts, indicates excessive pounding of the
rotor-field conductors.
41
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
56/190
42
Inspection
Part2
•
Water
found in the bottom of the
machine
may indicate a leak in the heat
exchanger.
• Excessive amounts of ironpowdermixed with oil anddustor found alone
in theborearea tendto indicate a loosecore.
Nuts, bolts,
small pieces of lamination iron,or otherlooseobjects
found
in-
sidethemachine, oftentimes at the
bottom
ofthecasing,
should be
investigated as
to their origin. They may point to loose space heaters, broken laminations or
cooler
fins, and/orotherabnormalities in needof
attention.
Figure 4-1 shows metallic objects found in theboreand
bottom
of thecasing
of an
air-cooled,
gas-turbine generator. In order to retrieve these objects, side
plates
were
opened
and long instruments
with
a grip device at their end were
used.
Subsequent examination of theboreareaidentified thesemetallic objects as
remnants
of
broken
pieces of laminations (seeFig.4-7).
:.
•
.
oil·
.:
....::
•.
A
••
•
,
Fig. 4-1
[SO
1]Brokenpiecesof laminations foundin theboreareaandbottomof
the
casingof an air-cooled gas-turbine
generator.
802:
Air/Gas-Ducts Clogged/Unclogged
Clogged
vents
effectively derate a machine byrestricting theflowof cooling
gas
through
the laminations andcoils. Thisphenomenon is particularly evidentin
open-air machines, which tend to be older and slower: mainly hydrogenerators,
condensers, and industrial motors. Clogged
vents
are particularly
common
in
open-air machines contaminated withoil.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
57/190
Chap. 4 Description ofStator Items
43
The restrictions can show up during operationof the machine as hot spots;
i.e., temperature readings from one or several temperature detectors will
be
higher than those obtained from the rest. (This can also indicate core-insulation
problems,as discussedbelow.)
The clogging need not only be dust or show itself only in old or open ma-
chines. In one case, massive cloggingof the ducts by red iron oxide powderwas
found in a new large hydrogeneratorhavinga very loose core.
Normally, a visual inspection with the aid of a frontal source of light may
suffice. Where possible, a light placed in the back of the core while observing
from the inside can result in good observations of the ducts. In cases where the
rotor has been left in place and clogging of the ducts is suspected, insertion of a
side-view boroscope through the airgap can provide an excellent view of the air
ducts in the inspectionarea.
S03: Iron Oxide Deposits
Iron oxide appears as red powder deposited mainly on the bore and in the
air/gas-ducts of the machine. When mixed with oil, these deposits may be con-
cealed in a mixture of dirt and oil. This mixture should be chemically analyzed
when iron dust is present (or suspected), for content in proportion to weight.A
quick identificationduring the inspectioncan be made by subjecting small por-
tions of the mixture to the field of a magnet (one of the desirable inspection
tools). If the dirt responds to the magneticattraction,then irondust is mostcer-
tainlypresent in significantproportions.
Iron oxide can result both from loose laminationsand loose wedges [1]. In
the case of loose wedges, the iron dust is mainly seen in the contact region be-
tweenwedgeand iron. In the caseof loose laminations,the ironoxide powderde-
posits are distributed on larger sections of the machine, on the iron itself. The
deposits will tend to concentrate in places adjacent to the air/gas-ducts, having
been left there by the flowing gas (see Figs. 4-2 and 4-3). In severe cases, the
large amounts of iron oxide powdergeneratedmight clog air/gas-ducts.
When the amountsof ironoxide powderpresent in the machine are substan-
tial, its origins should be thoroughly investigated. If loose wedges are the cause,
then they should be tightenedby re-wedgingor another effective method. Loose
wedgesmay abrade themselves to the extent they come out of the slot (see Fig.
4-4). They may also indicate a loose winding condition,with detrimental conse-
quences to coil insulation; in particular, the lossof semiconducting paint [2, 3].
If the iron oxide originatesfrom the movementof metallicparts, it probably
indicatesa loose core or loose portionsof the core [4].
Cores are pressure-loadedto given valuesduring the manufactureof the ma-
chine. Duringoperation, the core is subjected to continuouselongationand con-
traction of the laminations (magnetostriction) at twice supply frequency, and
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
58/190
44
Inspection Part 2
Fig.4-2
[S03] Section of a largeturbine-generator boreshowing deposits of red iron
oxide
powder.
Fig.4-3
[503] Close view of Figure
4-2.
The accumulation of the red powder de-
pends on the origin of the powder and the pattern of the flow of cooling gas.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
59/190
Chap. 4 Description
of
Stator Items
45
Fig.4-4 [S03] Wedges in the stator of a synchronous condenserworndue to vibra-
tions to theextentthatseveralcameout of theslot, andotherswerefoundto
beon theirwayout.
elongation and contraction of supporting structures due to thermal cyclesandvi-
brations. Machines having properly designed and stacked cores are supposed to
withstand theseonerous conditions. In many cases, however, after yearsof oper-
ation, this constant movement of the core components and the accompanying
metalfatigue, abrasion, anddeformation resultin a reduction of thecore's loaded
pressure. Theend result, if notcorrected, is abrasion of theinterlaminar insulation
(Figs. 4-5 and 4-6). The consequences of such abrasion are spot-heating of the
core, broken laminations leading to machine contamination with iron particles,
and serious failures of core-compression bolts, bolt insulation, andcore-compres-
sion fingers [4]. Otherdetrimental effectsaredeterioration of the coil insulation
due to hot spotsin thecore,additional core losses, andaugmented vibrations and
increased audible sound levels. An additional test to confirm the presence of a
loosecore is the insertion of a knifebetween the laminations at several locations.
If a lo-mil blade penetrates morethan a quarterof an inch, the core may not be
sufficiently tight.Extreme care shouldbe taken not to break the blade, leaving a
piecein the laminations. This technique shouldbe usedverycarefully, especially
in anymachine withits
windings
in place. (Fora description of the properproce-
dure,seeReference [3].)
Some utilities check the torqueof a sampleof the machine's compression
boltsat every secondor thirdoverhaul, or someotherchosen interval. The mea-
suredtorquevalueis compared withthoserecommended by themachine'smanu-
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
60/190
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
61/190
Chap.
4
Description of StatorItems
47
facturer. If thesebolts are found to be
loose,
theentirecore is retorqued in
accor-
danceto procedures laid downby themanufacturer.
It is important to note that not all lamination
problems
are the result of a
loose
core. For instance, Figure4-7 showsentirepackets of broken laminations
because of lackof sufficient support by the I-shaped duct separators at the top of
the tooth. Thecore of this particular machine (an air-cooled gas-turbine genera-
tor)wasotherwise found tobe tight. In thiscase,repairs included the introduction
of epoxy glass laminates between laminations, and application of penetrating
(low-viscosity) epoxyto the damaged area.
Thesolution to looselaminations is
varied,
depending on location, severity,
and typeof
problem.
It
ranges
from retightening the core-compression bolts to
changing compression platesor parts thereof, introducing nonmetallic shims, and
so
forth.
Fig.4-7 [S03]Two packets of broken laminations belonging to an air-cooled gas-
turbine generator.
504: Hardware Condition
All parts in a generator are exposed to continual vibration, temperature
changes, and other mechanical stresses. They may
become
loose, fractured, or
broken. It is therefore important to
search
for these abnormalities during the in-
spection
before
theydevelop intomajortroubles.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
62/190
48
Inspection
Part2
In particular, all
components
of the winding
support
assembly are subjected
to
mechanical
stresses due to sudden and
large
loadchanges, suchas are present
during lossof load, shortcircuit, pole slipping, and closing out of synchronism.
Machines
subjected to the above-mentioned conditions, as
well
as
machines
op-
erated with
many
starts, aremoresusceptible than
others
to
hardware
failure.
Some of themostsensitive components are:
•
Compression
bolts-Observe if any
greasing
(oilanddustmixed together
bythefriction of twocomponents vibrating within themachine) is present
indicating
looseboltsor
core,
and
integrity
of
nut-locking
device.
•
Surge-ring
supports-Look for cracking and looseness.
• Finger-plates-Look for cracked orbent
fingers.
Observe space heaters for looseness of bolts and nuts, and integrity of con-
nections. Figures ~ and 4-9
present
an example of hardware in the bore of the
machine damaged
during removal
of the
rotor.
Fig.4-8 [S04]Section of a large4-poleturbine generator showing gas-guides made
of insulating material.
-
8/19/2019 [Isidor Kerszenbaum] Inspection of Large Synchrono
63/190
Chap. 4 Description of-Stator
Items
49
Fig.4-9 [504] Close-upview of the gas deflectorsshowingdamageduring the re-
movalof therotor (seeFig.4-8).
805: High-Voltage Bushings
There are too many different arrangements of terminal boxes and bushing
types in large synchronous machines to describethemall in this book.However,
the following general inspection guidelines andcomments apply to any arrange-
ment.
Lead-bushings are susceptible to damagearisingfrom suddenloadchanges,
excessive vibration, overheating of the leads,and normal vibration over long pe-
riods of time. Stator high-voltage bushings should be inspected for evidenceof
cracks, oil leakage (when oil-filled), and looseness of components. All dirt and
tracking residues should
be thoroughly cleaned.
In large turbogenerators, the high-voltage bushings are partly contained in
sealedbushingwells.Someof the lead-bushings haveducts allowingthe flowof
hydrogen. The ducts shouldbe free of oil, grease,or any foreignelements. Many
othersarewater-cooled. In these,connections to thebushings shouldbe inspected
for cracksand leaks.