EN/CV/DC

IT-3673

Presentation done by Elena Perez RodriguezFor further information contact [email protected]

For the purchase of cooling fluids C3F8 and C6F14

2

Index

• Introduction• MS-3673 results• IT-3673 technical specification

– Technical requirements (quality and packaging)– Documentation– Contract execution

• Risk matrix• DQE - Adjudication formula• Contact persons at CERN

EN/CV/DC14/04/2010

14/04/2010 3

Introduction

• Objective:– One or two contracts for the purchase of C3F8

and C6F14 to substitute the IT-3397

• Kind of contract: – 3 years + 1 year (optional) + 1 year (optional)

EN/CV/DC

4

MS-3675 Results

EN/CV/DC14/04/2010

Company MS sentFluid that can supply

Comments on MSReply

approved

Carbagas (subsidiary of Air Liquide Group)

YES C3F8

1- No specification on C3F8 double bound molecules. 2- Product available in 800 kg and 47 kg 3- Incomplete references

YES

F2 Chemicals Limited

YES C3F8 and C6F14

1- C3F8 available in 50 kg cylinders (500kg on request) 2- C6F14 available in 250 kg and 10 kg 3- Annual turnover a little bit smaller than requested (4MCHF us 3.78 MCHF) 4- Is the supplier of C6F14 now 5- The quality requirements for C3F8 are missing some of the parameters

YES

3M (Schweiz) YES C3F8 and C6F14

1- C3F8 available in 940 lb bottles 2- C6F14 available in 20 kg and 300 kg drums, not for rent ! 3- Complies with the specification

YES

Astor YES C3F81- Is the supplier of C3F8 now 2- All requirements fullfilled for C3F8

YES

14/04/2010 5

IT-3675 Technical specification

EN/CV/DC

Quality requirements

Parameter Unit Lower UpperC3F8 organic purity % volume 99.96Other Perfluorocarbons

ppm weight

400

C3F8 double bounded molecules

ppm weight

10

H containing molecules

ppm weight

10

Air (O2, N2, CO2) ppm vol. 200Water ppm

weight1

Free fluoride ppm weight

0.1

C3F8

Parameter Unit Lower Upper

C6F14 organic purity % 98

Other Perfluorocarbons % 2

C6F14 double bounded molecules

ppm weight 10

H containing molecules ppm weight 10

Water ppm weight 10

Free fluoride ppm weight 1

Density g/ml 1.660 1.700

Boiling point ºC 51 59

Certificate of Analyses with every supply

C6F14

14/04/2010 6

IT-3675 Technical specification

Two kind of pressurized containers

Big containers (800 – 500 kg)Small containers (10 – 50 kg)

They shall have liquid exits

EN/CV/DC

Packaging requirements

One sealed container (250 kg)

• Standard connections, DIN 477• Cleaning, degreasing and N2 drying

C3F8 C6F14

14/04/2010 7

IT-3675 Technical specification

• For the invitation to tender– Product specification and safety data sheet– Analyses test methods– Cleaning methods for containers– Description and Quantity Estimate– Impurities elimination procedure during filling– The bid form

• During the contract– Documents will be sent in three copies, one of them in a computer readable and editable form– Test methods description

EN/CV/DC

Documentation

MS Word, MS Excel, MS Project,

AutoCAD

14/04/2010 8

IT-3675 Technical specification

• Delivery schedule– Delivery will be done at the merchandise reception (France or

Switzerland).– The supply should be delivered 20 days after the order

reception confirmation.– CERN Calendar of Official Holidays shall be the reference.

• Safety– CERN rules as described by Safety Commission.– Transport European Directive.– Pressure European Directive for containers.

EN/CV/DC

Contract execution

14/04/2010 9

IT-3675 Technical specification

• Rent of the containers– The rental period begins three months after delivery.– Finishes with a CERN fax/e-mail notification.– Rental will be invoiced annually in December.

• Acceptance of the supply– Shall include a Certificate of Analyses that complies with the

technical specification.– CERN can check it performing chemical analyses to the fluid from

any of the containers.• Penalties (defined in the commercial document)

– Penalty for late delivery.– Penalty for non-compliance with the quality specification + refusal

of the supply.

EN/CV/DC

Contract execution

14/04/2010 10

Risk matrix

EN/CV/DC

RISK LIKELIHOOD IMPACT DECISION HOW TO MITIGATE IT

1 Unforeseen high demand of fluorocarbon fluids

Possible (has already happened) Major Mitigation (fill

in next field ) 1- Implemented minimum stock

2The contractor does not respect the delivery schedule

Possible (has already happened) Major Mitigation (fill

in next field )

1- Penalties for late delivery 2- Implemented minimum stock

3The product does not comply with the quality requirements

Rare (never happens) Moderate Mitigation (fill

in next field )

1- Product refused and returned to the contractor at its own expense 2- Penalties for not compliance with the technical specification 3- Penalties in case of late delivery

4 Termination of contract / company bankrupcy

Rare (never happens) Catastrophic Acceptance

1- Use of the fluid stock already at CERN 2- Prepare for new contract (> 6 months)

Astor is the only known producer of C3F8.

14/04/2010 11

DQE – Adjudication

formula

EN/CV/DC

Product (C3F8)

Rental of the containers

Transport to CERN

TOTAL

14/04/2010 12

DQE – Adjudication

formula

EN/CV/DC

Product (C3F8)

Rental of the containers

Transport to CERN

TOTAL

14/04/2010 13

Contact persons at CERN

• Technical contacts– Michele Battistin– Pierre Bonneau– Elena Perez Rodriguez

• Commercial contacts– Sebastien Sonnerat– Bjorn Jenssen

EN/CV/DC

14

Thank you for your attention

Any questions ?

EN/CV/DC14/04/2010