it takes a team to build a damcalifaep.org/docs/aep_conf_2017_it_takes_a_team_to_build...1 it takes...

63
1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern The CEQA Master Debbie CravenGreen The Permitting Wiz Cullen Wilkerson Protector of the Environment During Construction Nicole Sandkulla The Stakeholder

Upload: others

Post on 20-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

1

It Takes a Team to Build a Dam

Dan WadeThe “Dam” Expert & Program Manager

Chris KernThe CEQA Master

Debbie Craven‐GreenThe Permitting Wiz

Cullen WilkersonProtector of the Environment 

During Construction

Nicole SandkullaThe Stakeholder

Page 2: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

PALO ALTO

SAN MATEO

HAYWARD

SAN JOSE

Calaveras DamLower CrystalSprings Dam

Major Construction Needed on Two Dams to Restore Capacity

2

Page 3: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

WATER SYSTEM IMPROVEMENT PROGRAM

Daniel L. Wade, WSIP Director

Page 4: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

HETCH HETCHY REGIONAL WATER SYSTEMCROSSES 3 MAJOR EARTHQUAKE FAULTS

4

Page 5: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

• 87 Projects2 dams3 tunnels3 treatment facilitiesPipelines, pump stations, reservoirs, tanks, etc.Bioregional Habitat Restoration (BHR) Sites

• 7 Counties• $4.8 Billion• 2019 Completion 

WATER SYSTEMIMPROVEMENT PROGRAM

5

Page 6: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

A (VERY) PUBLIC PROGRAM

With Many Stakeholders

Governmental/Regulatory Agencies

Special Interest               Groups

Elected Officials

Impacted Communities

Oversight Bodies

Labor/Contractor

Wholesale/Retail Customers

6

Page 7: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

ENVIRONMENTALSTRATEGY• Commitment and stewardship

• Pre‐ConstructionAvoidance of ImpactsMinimization of ImpactsMitigation of Impacts

• ConstructionBMPsTrainingMonitoring / Reporting

• OperationsAdaptive Management

7

Page 8: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

• Constructed in 1890• Forms Lower Crystal Springs Reservoir• Maximum Capacity: 22.15 Billion Gallons• Current Capacity: 18.5 Billion Gallons

Lower Crystal Springs Dam

8

Page 9: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Existing Dam Configuration

Parapet Wall

Spillway

Stilling Basin

9

Page 10: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Dam ImprovementsRetrofittedParapet Wall

New Spillway

New Stilling Basin

10

Page 11: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

•11

LCSD ‐ New Spillway

1925 Completion

Page 12: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

•12

LCSD ‐ New Stilling Basin

1925 Completion

Page 13: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

•13

Calaveras Dam

1925 Completion

1918 Dam Failure

1918 Dam Almost Completed

Page 14: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Left Abutment (Observation Hill)

Stilling Basin

Existing Dam (Cofferdam)

Disposal Site

Upper Spillway Chute

Lower Spillway Chute

New Dam Axis

Right Abutment

Calaveras Dam Replacement

14

Page 15: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

SCOPE OF WORK

• Replacement Dam• Spillway• Stilling Basin• Intake/Outlet Works• Borrow Areas• Disposal Sites• Haul Road• Staging Areas• Fish Passage• Habitat Restoration

15

Page 16: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

CROSS SECTION OF REPLACEMENT DAM

• Zoned Earth and Rock‐Filled Dam• 220 feet high & 1200 feet in length• 80 feet wide at crest and 1200 feet wide at base

16

Page 17: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Calaveras Dam Replacement

17

Start of Embankment Dam Construction

Page 18: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

PROTECTION OF SPECIAL STATUS SPECIES

18

Page 19: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Upper Alameda Creek

Lower Alameda Creek

19

Page 20: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

20

Page 21: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Alameda Creek Diversion Dam in Operation –December 1931

21

Page 22: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

FISH PASSAGE FACILITIES AT ALAMEDA CREEKDIVERSION DAM

ACDT Inlet22

Page 23: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

CONSTRUCTION – JUNE 2016Fish Passage Facilities at Alameda 

Creek Diversion Dam

23

Page 24: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

What We Learned

24

Page 25: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Visionary Leadership

25

Page 26: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Lead up, Down, and Sideways

26

Page 27: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

One Team Culture

27

Page 28: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Trust the Team

28

Page 29: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Consistency and Resiliency

29

Page 30: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Transparency & Accountability

30

Page 31: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Communications

31

Page 32: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

CEQA Timeline

• Project Initiation and ScopingFall 2005

• Technical Studies & Draft EIR Preparation2006 – 2009

• Public Review and Response to Comments2010 – 2011

• Final EIR Certification January 2011

32

Page 33: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Project EIR + Program EIR• Water System Improvement Program EIR• 38 project level EIRs

33

Page 34: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Habitats

• Study area 1,900 acres• Wetlands 34 acres• Streams 14.3 miles• Open Water (Reservoir) 1,012 acres• Grasslands 863 acres• Oak woodlands 327 acres• Scrub 79 acres• Riparian forest 38 acres

34

Page 35: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Special‐Status Species• Callippe SilverspotButterfly

• California Red‐Legged Frog

• California Tiger Salamander

• Foothill Yellow‐Legged Frog

• Alameda Whipsnake• Bald Eagle• Berkeley Kangaroo Rat• Western Pond Turtle

• Raptors• Loggerhead Shrike• Grasshopper Sparrow• Tricolored Blackbird• American Badger• Townsend’s Big‐Eared Bat

• Pallid Bat• Western Mastiff Bat

35

Page 36: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Naturally Occurring Asbestos

• Excavation and handling of 4 million cubic yards of NOA containing material

• Worker safety• East Bay Regional Parks employees• Park visitors• Dust control• Monitoring and Reporting• Shutdown conditions• Appeal filed by East Bay Regional Parks

36

Page 37: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Project Changes DEIR to FEIR

• Changes to instream flow schedules for Steelhead

• Fish ladder added at Alameda Creek diversion dam

• Fish screens added at Alameda Creek diversion tunnel and Calaveras dam adits

• Adaptive management plan for Steelhead added

• Spillway grade control structures added

• Intake tower modifications• Additional instrumentation• Electrical distribution line 

upgrade added• Right dam abutment 

excavation expanded• Borrow area E modified• West haul road work area 

modified

37

Page 38: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Permitting CDRP & LCSD

38

Page 39: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

39

Page 40: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

SFPUC

40

Page 41: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

41

Page 42: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

42

Page 43: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

CDRP Spoils Disposal

43

Page 44: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

LCSD Fountain Thistle

44

Page 45: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Ecosystem Level Mitigation

45

Page 46: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Mitigation for Permitted Impacts

46

Page 47: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

47

Bioregional Habitat Restoration (BHR)

Page 48: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

48

Page 49: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

49

Page 50: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

5050

Environmental Construction Compliance

Paleontologists at work recovering a whale vertebrate

Page 51: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

What’s Wrong with this Picture?

51

Page 52: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

And this One?

52

Page 53: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

SFPUC is Committed to Compliance• Agency Mission Manage the resources—human, physical, and 

natural—entrusted to its care• CEQA/NEPA mitigation measures, permit conditions, and Standard Construction Measures

• Avoid:

53

Page 54: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Water System Improvement Program (WSIP)TYPICAL CM ORGANIZATION

PROGRAM LEVEL(SFPUC Headquarters)

REGIONAL LEVEL(Regional Office)

PROJECT LEVEL(Project Office)

WSIP Director

Deputy Director of Construction

Regional PM

QA Inspector

Cost/Schedule Engineer

Field Engineer

Program Controls Manager

QAManager

Contracts Manager

ConstructionControls Mgr

Regional CM

Contract Field Administrator

Last Revised by GBL on 10/3/07

Legend SFPUC PCM Consultant RCM Consultant BEM Consultant

PLA Administrator

Administrative Assistant

Assistant Regional PM

Public Outreach Liaison

Client/Operations Representative

CM Operations Coordinator Program CM

Shutdown Coordinator

DGM

AGM Infrastructure

BEM Manager

Environmental Construction

Compliance Mgr

Project CM

Project Engineer Test & Start-Up Engineer

Lead QA Inspector

Office Engineer

Environmental Project Manager

WSIP Construction Oversight Committee

Regional PE

Safety Manager

NOTE: This is a “typical” organizational chart for larger WSIP projects. CM positions shown may differ for some projects. Smaller WSIP projects may include a greater number of SFPUC CM staff.

Cost Estimators

Regional Environmental

Compliance Mgr

Office Clerk

Environmental Inspector

Environmental Specialist

Regional Env. Coordinator

Regional EPM

SFPUC WSIP Org ChartEnvironmental Construction Compliance Integrated in All Project Phases

54

Page 55: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Construction Management Plan and Procedures

55

Page 56: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Water System Improvement Program (WSIP)TYPICAL CM ORGANIZATION

PROGRAM LEVEL(SFPUC Headquarters)

REGIONAL LEVEL(Regional Office)

PROJECT LEVEL(Project Office)

WSIP Director

Deputy Director of Construction

Regional PM

QA Inspector

Cost/Schedule Engineer

Field Engineer

Program Controls Manager

QAManager

Contracts Manager

ConstructionControls Mgr

Regional CM

Contract Field Administrator

Last Revised by GBL on 10/3/07

Legend SFPUC PCM Consultant RCM Consultant BEM Consultant

PLA Administrator

Administrative Assistant

Assistant Regional PM

Public Outreach Liaison

Client/Operations Representative

CM Operations Coordinator Program CM

Shutdown Coordinator

DGM

AGM Infrastructure

BEM Manager

Environmental Construction

Compliance Mgr

Project CM

Project Engineer Test & Start-Up Engineer

Lead QA Inspector

Office Engineer

Environmental Project Manager

WSIP Construction Oversight Committee

Regional PE

Safety Manager

NOTE: This is a “typical” organizational chart for larger WSIP projects. CM positions shown may differ for some projects. Smaller WSIP projects may include a greater number of SFPUC CM staff.

Cost Estimators

Regional Environmental

Compliance Mgr

Office Clerk

Environmental Inspector

Environmental Specialist

Regional Env. Coordinator

Regional EPM

WSIP Typical Construction Management Organization

56

Page 57: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Regular Field Meetings

57

Page 58: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

• TrainingTraining

58

Page 59: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Compliance Protocols and Methods• Environmental Inspector manual• Checklists and tracking tables• Non‐compliance resolution process• Minor project changes process

59

Page 60: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Managing Migratory Birds

60

Page 61: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Handling Paleontological Discoveries• Carcharodon megalodon or Carcharocles megalodon related to modern great white shark reached lengths greater than 52 feet

61

Page 62: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

Maintaining Creek Flow Simultaneous with Dewatering

62

Page 63: It Takes a Team to Build a Damcalifaep.org/docs/AEP_Conf_2017_It_Takes_a_Team_to_Build...1 It Takes a Team to Build a Dam Dan Wade The “Dam” Expert & Program Manager Chris Kern

12 years of WSIP construction with• No violations• Few incidents of listed species take• Strong relationships with resource agenciesSelf‐reporting encourages trust

• Effective handling of discoveries• Meeting project schedules

Benefits of Commitment to Compliance

63