iwrm in practice - operationalising iwrm at basin level: niger river basin case study

29
International Conference on INTEGRATED WATER RESOURCES MANAGEMENT INTEGRATED WATER RESOURCES MANAGEMENT December 7-9, 2004 (Tokyo Prince Hotel, Tokyo, Japan) “IWRM in Practice - Operationalising IWRM at Basin Level” Niger River Basin Case study By Ousmane S. DIALLO, Water Resources & Environment Specialist, GEF Project & Shared Vision Coordinator (NBA) NIGER BASIN AUTHORITY (NBA) NIGER BASIN AUTHORITY (NBA)

Upload: iwl-pcu

Post on 22-Jun-2015

65 views

Category:

Documents


3 download

DESCRIPTION

Presentation by Ousmane Diallo, Water Resources & Environment Specialist, GEF Project & Shared Vision Coordinator (NBA) at the International Conference on IWRM in Tokyo - December 2004

TRANSCRIPT

Page 1: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

International Conference on INTEGRATED WATER RESOURCES INTEGRATED WATER RESOURCES

MANAGEMENTMANAGEMENT

December 7-9, 2004

(Tokyo Prince Hotel, Tokyo, Japan)

“IWRM in Practice - Operationalising IWRM at Basin Level”

Niger River Basin Case study

By Ousmane S. DIALLO, Water Resources & Environment Specialist, GEF Project & Shared Vision Coordinator (NBA)

NIGER BASIN AUTHORITY (NBA)NIGER BASIN AUTHORITY (NBA)

Page 2: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

Niger River Basin: Rationaland Stakes for Integrated Water

Resources Management

Page 3: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

Overview

I. Niger River Basin: Background

II. IWRM at a glance

III. IWRM in Niger River Basin

IV. Niger River Basin: GEF Project

V. Lessons learned

VI. Conclusions

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

Page 4: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

I. Niger River Basin: Location & Background

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

Main features: a crucial asset

shared by nine countries among the poorest in the World (Benin, Burkina Faso, Cameroon, Cote d’Ivoire, Guinea, Mali, Niger, Nigeria and Chad);

an important source of livelihoods for the region;

the 3rd longest Africa’s river & the 14th in the World (4,200 km);

the 9th in the world largest river Basin (2,2 millions km²).

Page 5: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

I. Niger River Basin: Layout of the Basin

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

Page 6: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

I. Niger River Basin: Background

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

Socio-economics:

The population of the basin is estimated at 107 millions of people (2000) (42% of the West African population).

Population will be 207 millions people in 2020, (the double) while the potential of NR feeding this population will decrease.

The River is important for water supply, agriculture, hydropower generation, fisheries, livestock development, etc.

The total GDP of the countries was 70 Billion US$ in 2000 with an average growth rate of less than 3%. The average GDP per inhabitant in the countries is US$ 350 (less than US$ 300 for sahelian countries). 

Page 7: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

II. IWRM at a glance

Operationalising IWRM in Niger BasinOperationalising IWRM in Niger Basin

WHY?Integrated Water Resources Management (IWRM)

Countries are facing serious water resources challenges that call for a new water management framework.

IWRM relates to the macro-economy: Poor water resources management has negative impacts on health, environment and the economy, jeopardizing poverty reduction efforts.

IWRM is a process which can assist developing countries in achieving of MDGs.

IWRM process is the backbone of commitments to international agreements: Transboundary visions and co-operation.

Page 8: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

II. IWRM at a glance

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

WHAT IS?Integrated Water Resources Management (IWRM)Implementing IWRM process is a question of getting

the “three pillars” right.

Integrated vision

Integrated tools for planning and decision making

Environmentalsustainability

Socialequity

Economicefficiency

1-Enabling environment 2-Institutional framework

3-Management instruments

Page 9: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

II. IWRM at a glance

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

HOW?Integrated Water Resources Management (IWRM)

Establish Status, Goals & Agendas

BuildPolitical

Commitmentto ReformProcess

Analyse Gaps

PrepareStrategy &Action Plan

BuildCommitment

to Actions

ImplementFrameworks

Monitor &EvaluateProgress

The Integrated Water Resources Management Cycle

Page 10: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

III. IWRM in Niger Basin - The strategic framework

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

AFRICA WATER VISIONWEST AFRICA WATER VISION

(2nd WWF)

AFRICAN UNIONNEPAD TRANSBOUNDARY WATER RESOURCES

(Shared basins, Water security, Regional integration)

I W R M(Political will, Strategy, Resources

mobilization)

Shared Vision

GEF Project

European & Other

Initiatives

Page 11: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

III. IWRM in Niger Basin - Shared vision: Critical elements

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

“Political borders crossing natural borders”

«Silting of Midle Niger Basin »

“Population growth”

“Economic growth”

“Water resources are variable and finite"

“Pollution”

“Floods and Droughts”

“Tensions between water users”

“Degradation of natural resources”

Page 12: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

III. Shared vision = Niger Basin version of IWRM

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

Niger River Basin Development challenge is

INTEGRATED LAND AND WATER RESOURCES MANAGEMENT

FOR POVERTY REDUCTION AND

SUSTAINABLE DEVELOPMENT IN THE BASIN

HOW?

DEVELOPING A SHARED VISION

Page 13: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

III. IWRM in Niger Basin - Shared vision

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

Towards an effective Cooperation for sustainable development

Environment

DegradationSustainability

Politics

DisputeCooperation

Economics

FragmentationIntegration

Balance of compromises

Page 14: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

III. IWRM in Niger Basin - Shared vision

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

Framework for planning & action to address common challenges: poverty reduction, potable water & sanitation, health, food security, peace, economic development, etc.

The Shared vision = a set of long-term objectives & commitment to a program of actions;

Opportunity for good governance of shared water resources, for a cooperative & sustainable development of the Basin;

Effective tool for conflicts prevention and resolution among users, uses, development & environmental goals;

Commitment of the riparians to enhance a regional dialogue and to stop fruitless unilteral approach.

Page 15: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

III. IWRM in Niger Basin: European Union Water Initiative

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

The EUWI for Africa has two main components: River basin management;

Provision of water supply and sanitation.

The Mission Statement:Facilitate the implementation of effective IWRM programs through technical support, coordinated financing, dialogue and partnerships; Work with riparian governments and other stakeholders to establish and/or strengthen river basin management, institutions and programs.

The suggested focus for Niger River Basin:Fund the second phase of the Shared vision: Development of a Sustainable Development Action Plan (SDAP);Strengthen organizational frameworks (capacity building, coordination of activities, etc.);Explore new financing mechanisms;Support involvement of civil society on interests based approach.

Page 16: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

IV. Niger Basin GEF Project - IW OP9

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

“Reversing land and water degradation trends in the Niger River Basin”

Project development objective:

To provide the riparians countries, an opportunity to define a transboundary framework for sustainable development of the basin land and water resources, through strenghened capacity and better understanding of the critical issues.

Project global objectives:

To reduce and prevent transboundary water related environmental degradation, through cooperative integrated management of the basin, while ensuring greater public involvement in the decision-making process.

Page 17: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

ProjectImplemen-tation

C5- Demonstration pilots & SGP

C6- TDA & SAPpreparation

C1- Institution buildingC2- Capacity buildingC3- Data management

C4- Regional Forum

Strategic Action Programme (SAP)

formulation

Agreementbetween the

9 NBA Countries,WB & UNDP

Continue in Phase 3

Page 18: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

IV. Niger Basin GEF Project

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

Land & Water are basic to Production, and Production is clearly a factor of Poverty reduction.

To address Poverty reduction, the Project will focus on:Meeting human basic needs;

Environmental degradation;

Water degradation, health and loss of productivity;

Soil degradation and loss of productive land;

Risk management, floods and droughts;

Community-based driven interventions (Pilots & SGP);

Local community capacity building/strengthening.The linkages between the GEF Project and country’s PRSP contribute to promote growth and reduce poverty, as well as external financing needs.

Page 19: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

IV. Niger Basin GEF Project:

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

What is TDA/SAP?

The TDA

Transboundary: Projects are undertaken only when there are water management issues which cross the boundary between two or more countries.

Diagnostic Analysis: Problems are analysed through a scientific diagnosis of causes and effects.

The SAP

Strategic: Solutions usually involve long-term administrative or legal strategies in each country.

Action Programme: The project is not complete until a plan for practical implementation of the solution has been agreed.

Page 20: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

IV. Niger Basin GEF Project: TDA/SAP

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

Two different types of TDA/SAP project with different aims:

A. REMEDIAL

To help countries to change human activities which threaten,

or have already damaged, a water body or its drainage basin.

B. PREVENTATIVE

To achieve environmental benefits by integrating the management and sustainable development of land and water resources.

This is OP 8 of the GEF

This is OP 9 of the GEF

All GEF projects aim to work as a catalyst to achieve more global environmental benefits.

To strengthen the many other national and international Programs which have responsibility for action.

Page 21: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

IV. Niger Basin GEF Project

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

KEY PRINCIPLES OF THE TDA / SAP APPROACH

International experience has shown that there will not be much progress unless the following principles are followed from start to the end:

CONSULTATION / FULL STAKEHOLDER PARTICIPATION

All stakeholders must be genuinely consulted and their views have to be taken into account, before any decision is taken.

ADAPTIVE MANAGEMENT / “LEARNING BY DOING”

Monitoring, adjusting and revising at each step of the work.

COMMITMENT

People responsible must make commitments to take action, at each step of the project.

Page 22: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

IV. Niger Basin GEF Project: The main players & Synergies

IWRM in Practice: Operationalizing IWRM in Niger IWRM in Practice: Operationalizing IWRM in Niger BasinBasin

AfDB Program Heads of State(Summit)

Niger Basin Authority Executive Secretariat(NBA/ES)

Technical Department

National Coordination

Units(NCU-AfDB)

(9) National Project Teams

Beneficiaries

GEF Project

Sub Scientific and

Technical Committee

(STC)

Regional Steering Committee for GEF and AfDB

(RSC)

(9) National Steering

Committees (NSC)

Local Coordination Committees

(LCC)

Local Technical

Committees

Project Management Coordination Unit

(PMCU)

NBA Council of Ministers

NB

A

Org

an

izatio

nR

eg

ion

al

Natio

nal

Local

Page 23: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

IV. Niger Basin GEF Project: The four Steps in GEF IW TDA/SAP Process

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

Step I: Project development

Step II: TDA execution

Step IV: SAP implementation

Step III: SAP preparation

- Stakeholder consultation

- Conduct stakeholder analysis

- Project design and approval

- Formation of Team and Management

- Identify & prioritise transboundary issues

- Technical issues analysis (CCA)

- Political / Governance analysis

- Prepare and adopt TDA

- Long-term EcoQOs

- Feasability study of options

- Operational objectives & targets

- Institutional framework

- Interventions development

- Design of monitoring/evaluation system

- Approval and funding

- Monitor and Evaluate progress

- Build capacity

- Develop synergies with other initiatives

- Link SAP with SDAP of Shared vision

- Draw lessons

Page 24: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

IV. Niger Basin GEF Project

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

PROJECT

DEVELOP-

MENTTDA

SAP

IMPLEM-TATION

SAP

ENABLING

ENVIRONMENT

INSTITUTIONAL

FRAMEWORK

MANGEMENT

INSTRUMENTS

Putting the IWRM into practice at shared basin level: the role of the TDA/SAP Process

Legal/Policy

Analysis

Stakeholder

Analysis &

Consultations

Institutional

Analysis

Page 25: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

V. Lessons learned

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

1. Context is critically important: IWRM in NRB, is a complex process: (i) high number of decision makers at the highest political level, (ii) social & cultural background, and economic situations of each riparian country, (iii) geographical diversity.

2. For the poorest countries, the initial focus is on crucial & urgent issues. The NRB planning process of IWRM is putting emphasis strongly on how to attain the UN MDGs.

3. Linkages between basin level and riparian countries level: convergence and complementarities; transition towards a more integrated approach.

4. The problems are more of institutional nature, that is GOVERNANCE, rather than technical. There is a crucial need for a long-term vision.

Page 26: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

V. Lessons learned

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

5. The GEF project contributes to alleviate poverty

Interactive participation of various stakeholder groups (public & private sectors, civil society, regional, national & local levels) is a key for community ownership.

The potential of the various NR of the basin can be developed and managed, through national actions implemented in compliance with the regional framework.

Integrated development of the transboundary NR on the basis of win-win principles, increases sustainable exploitation and enhances productivity.

Integrated development of these transboundary NR will promote socio-economic development of the riparian countries and enhance cooperation for the protection of the environment.

Page 27: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

V. Lessons learned

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

6. The GEF IW TDA/SAP Process: a tool to operationalise IWRM at shared basin level

TDA/SAP Process may be used to build commitment to reforms and to actions through: political will, awareness, multi-stakeholder dialogue and finance identification.

The TDA execution phase gives opportunity to establish status and goals and analyze gaps by identification and prioritization of transboundary issues, joint fact-finding to ensure regional ownership (process & products).

The TDA execution phase can be shorten: During the Project development phase (PDF-A phase), a preliminary TDA has been prepared and will be finalized during the TDA execution phase.

Synergies developed with AfDB Program, are key for complementarities, resources optimization and future uses.

Page 28: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

VI. Conclusions

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

Challenges for (i) Poverty

reduction, (ii) Water sharing,

and (iii) Sustainable

development in the basin

Challenges for (i) Poverty

reduction, (ii) Water sharing,

and (iii) Sustainable

development in the basin

The joint work needs new partnerships and good coordination.

GEF PROJECTGEF PROJECT

OTHER

INITIATIVES

OTHER

INITIATIVES

SHARED VISIONSHARED VISION

I W R MI W R M

Page 29: IWRM in Practice - Operationalising IWRM at Basin Level: Niger River Basin Case Study

IWRM in Practice: Operationalising IWRM in Niger IWRM in Practice: Operationalising IWRM in Niger BasinBasin

Thank you for your attention