jack in pile installation method

5
METHOD STATEMENT FOR INSTALLATION OF PRECAST REINFORCED CONCRETE PILES USING HYDRAULIC INJECTION SYSTEM PROJECT :- CADANGAN PEMBINAAN IBU PEJABAT POLIS DAERAH SIPITANG, SABAH 1. PURPOSE The purpose of this method statement is to establish guidelines and requirements for the installation of 300mm x 300mm EC piles to the foundations for the Police Headquarters. This method statement is not meant to be exhaustive, sufficient only to define stages and processes. 2. REFERENCE BS 8004 : 1986 Code of Practise For Foundations The main function of bearing piles is to transfer the load to lower levels of the ground which are capable of sustaining the load with an adequate factor of safety and without settling at the working load by an amount detrimental to the structure that they support. Piles derive their carrying capacity from a combination of friction along their sides and end bearing at the pile point or base. The former is likely to predominate for piles in clays and silts and where long sockets are formed in soft rocks. The latter applies to piles terminating in a stratum such as compact gravel, hard clay or rock. Piles should be installed to the prescribed depth, resistance or set per blow without damage to the pile shafts or the bearing stratum and records of the installation process should be maintained. The load should be applied concentrically with the axis of the pile. 3. The System The ZYC Injection System is an innovative hydraulic injection piling system which is free of noise, vibration and pollution. The system allows for a smooth, simple and rapid pile installation process while adhering to the most stringent environmental protection requirements. It is generally more cost effective than conventional piling systems and is more suitable when piling adjacent to sensitive structures or in urban areas where a clean noise-free and vibration-free piling system is essential. The system ensures that piles are installed with a high level of accuracy and a 100% quality check on all injected piles since each pile is

Upload: r-b-kennedy-enis

Post on 07-Sep-2015

1.423 views

Category:

Documents


165 download

DESCRIPTION

Method statement for Jack In Pile

TRANSCRIPT

  • METHOD STATEMENT FOR INSTALLATION OF PRECAST REINFORCED

    CONCRETE PILES USING HYDRAULIC INJECTION SYSTEM

    PROJECT :- CADANGAN PEMBINAAN IBU PEJABAT POLIS DAERAH SIPITANG,

    SABAH

    1. PURPOSE

    The purpose of this method statement is to establish guidelines and

    requirements for the installation of 300mm x 300mm EC piles to the foundations

    for the Police Headquarters. This method statement is not meant to be

    exhaustive, sufficient only to define stages and processes.

    2. REFERENCE

    BS 8004 : 1986 Code of Practise For Foundations

    The main function of bearing piles is to transfer the load to lower levels of the

    ground which are capable of sustaining the load with an adequate factor of

    safety and without settling at the working load by an amount detrimental to the

    structure that they support. Piles derive their carrying capacity from a

    combination of friction along their sides and end bearing at the pile point or

    base. The former is likely to predominate for piles in clays and silts and where

    long sockets are formed in soft rocks. The latter applies to piles terminating in a

    stratum such as compact gravel, hard clay or rock.

    Piles should be installed to the prescribed depth, resistance or set per blow

    without damage to the pile shafts or the bearing stratum and records of the

    installation process should be maintained.

    The load should be applied concentrically with the axis of the pile.

    3. The System

    The ZYC Injection System is an innovative hydraulic injection piling system which

    is free of noise, vibration and pollution. The system allows for a smooth, simple

    and rapid pile installation process while adhering to the most stringent

    environmental protection requirements. It is generally more cost effective than

    conventional piling systems and is more suitable when piling adjacent to

    sensitive structures or in urban areas where a clean noise-free and vibration-free

    piling system is essential. The system ensures that piles are installed with a high

    level of accuracy and a 100% quality check on all injected piles since each pile is

    Win_Pro_x64Rectangle

  • subjected to twice the working load, effectively individually load testing each

    pile. The guesswork and uncertainty associated with conventional piling systems

    is therefore eliminated.

    The system is able to install a wide range of square pile sizes from 125mm x

    125mm to 400mm x 400mm and spun piles from 300mm to 600mm diameter. It

    can be easily manoeuvred around site and with its wide base and low centre of

    gravity it is suitable for various types of ground conditions. It is easily

    dismantled for transportation and is generally of low maintenance.

    The system is also able to handle individually cast pile lengths exceeding 12m,

    thus reducing the number of welded joints within a pile length.

    4. The Machine

    The ZYC Injection Machine utilises a system for installing piles using the

    clamping-type pile driving mechanism, which is the main working mechanism to

    clamp and drive the piles into the ground. It consists of hydraulic cylinders for

    driving the piles, a pile clamping box, and hydraulic cylinders for clamping the

    piles.

    The ZYC Hydraulic Injection machine comprises:

    a) Main body of the machine mounted with crane and operation room on

    top.

    b) Pile driving cylinders and horizontal beam.

    c) Longitudinal moving mechanism.

    d) Horizontal moving mechanism.

    e) Matching weight and matching weight beam.

    f) Steel dead weights.

    The components are delivered by trailers to site where they are assembled using

    mobile crane.

    A copy of the ZYC Hydraulic Injection machine brochure is enclosed.

    The Proposed Injection Machinery for this project consists of 1 No. ZYC320B-B

    (320 tonnes) for installation of 300mm x 300mm piles

    5. The Pile Loading

    The ZYC Injection System injects the piles with a continuous and evenly applied

    loading up to a load of twice the specified working load, with the load held for

    30 seconds after no further penetration has been observed.

    Concrete Pile (for this project)

    300mm x 300mm Piles Design Load 1050 kN

  • A certain quantum of piles within this particular project will not be able to be

    installed with the conventional centre mechanism loading system due to the

    constraints of the site. Therefore, a side piling attachment will be utilised. This is

    basically the same as the centre piling mechanism, with clamping system and

    installation method identical, although the pressure loading capability is reduced

    due to the eccentricity of the overall machine weight.

    For general information purposes, the total weight of the machine with all

    counterweights may be 100 tonnes. However, from experience and machinery

    maintenance view points, the machine is only loaded to about 80 Tonne. Since

    side piling is only able to utilise 50% of the load for pressure injection, the

    maximum load that may be applied when side piling is undertaken will be 400

    kN.

    6. Platform / Access

    All platforms and access at or to the piling locations shall be provided by the civil

    works contractor. The proposed platform levels shall be approved prior to survey

    setting out.

    The ground conditions are to be examined for suitability for the stability and

    movement of the piling rig, and conditions corrected as deemed necessary. Steel

    plates shall be provided if necessary for the even distribution of the weight of

    the machine.

    7. Setting Out

    Based on the design layout of the piles, the positions of the piles are set out on

    site and pegs installed by a competent surveyor engaged by the main contractor.

    These set out pegs are checked for correctness before the piling operation

    commences. Due to the high accuracy of set up and positioning of the machine

    prior to driving, the normal tolerance of 75mm deviation of the pile from

    required position can easily be attained.

    8. Delivery of Piles

    All required piles will be delivered by trailer and offloaded by 25 Tonne mobile

    crane.

    The piles will be stored on firm, flat ground, with timber supports between

    subsequent layers, to avoid any undue bending in the piles.

  • 9. Driving Method

    The driving method ensures that the works are conducted with the minimum of

    noise and disturbance, and with minimum damage to the pile being injected.

    Each pile will be driven continuously until the specified set and/or depth has

    been reached.

    The driving method is by means of clamping and injecting the piles into the

    ground with the following steps:

    a. At first, the pistons of two (2) pile driving cylinders are withdrawn to raise the pile-driving box to the high position.

    b. The pre-cast pile is lifted and placed into the centre of the pile-driving

    box.

    c. The pile-driving cylinders from four (4) directions are then engaged to

    clamp the pile tight.

    d. Then by manipulating the hand lever of the pile-driving valve, the pile-

    driving cylinders are extended to produce pressure to drive the pile

    into the ground.

    e. Once the pile has been driven into the ground, the pile driving

    cylinders release the pile and return to steps (a), (b), (c) and (d) again

    until the pile has been fully driven into the ground.

    The piles are therefore driven into the ground vertically, without any forcible

    corrections, thereby adhering to the requirement for the finished pile to be

    within the maximum deviation from the vertical of 1 in 75.

    In some soils the vertical and lateral displacement or heave resulting from

    subsequent piling may carry with it piles that have already been installed. This

    may cause end bearing piles to be lifted off their bearing stratum. If lifting is

    suspected, careful levelling from a datum unaffected by the piling should be

    made on the heads of piles already driven before and after driving subsequent

    piles. Risen piles which depend largely on end bearing and which are capable of

    being redriven should be redriven to the specified resistance.

    10. Pile Meter and Load Meter

    As the pile is being injected into the ground, both the injected pressure (Mpa)

    and the corresponding load (KN) can be read instantly from the Pressure Meter

    and Load Meter in the control room.

  • A table of injection pressure (Mpa) and the corresponding load (KN) tabulated by

    the machine manufacturer is herein enclosed for reference.

    11. Pile Installation Record

    A pile installation record form is enclosed. For every pile installed, a record is

    kept of the load bearing in KN throughout the length of installed pile at intervals

    of 0.5m. The piles will be marked to show the depth of penetration in 0.5m

    intervals.

    Any unexpected driving conditions will be noted in the record.

    12. Pile Jointing

    Each pile extension subsequent to initial pile is jointed using a full perimeter V-

    Butt weld, with the verticality of the extension pile checked prior to welding.

    The upper and lower end plates are cleared of any undesired material and

    seated. Any concrete laitance is then removed by hand hammer and the joint

    area cleaned using wire brush. Welding is then undertaken using an AC Arc

    Welder utilising 4mm welding rods.

    13. Cutting of Pile Head

    Upon excavation to required level and provision of blinding concrete as working

    surface within the pilecap, breaking of the piles to cut off level will be

    performed. This is done by first vertical cutting into the sides of the protruding

    pile using a petrol driven concrete saw, followed by breaking of the concrete

    using compressed air driven concrete breakers. All debris is then removed from

    within the pilecap, and the resultant protruding reinforcement bars prepared for

    inclusion within the pilecap reinforcement cage.

    The concrete is normally stripped to a level such that the remaining concrete will

    project 50mm to 75mm into the pilecap. The pile reinforcement should be

    exposed for a length sufficient to permit it to be bonded into the pilecap.