Campus Planning 1 January 18, 2007 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Post on 15-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 1 January 18, 2007

Update on Campus Planning and Construction Parnassus and Mission Bay

Lori YamauchiAssistant Vice Chancellor

Campus Planning

Page 2: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 2 January 18, 2007

Parnassus Heights

Page 3: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 3 January 18, 2007

New Construction and Renovation at Parnassus

Kirkham Childcare CenterStem Cell Building

MSB/Moffitt Seismic Joint & Retrofit Cole Hall M/L-13 Bed Expansion

Page 4: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 4 January 18, 2007

Kirkham Child Care Center

Design/Build Project includes:• Space for 80 children (5 classrooms) • 8,987 GSF / 5,910 ASF• $4,374,000 budget• Funding source: Chancellor’s Discretionary Funds • Projected completion: October 2007

Page 5: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 5 January 18, 2007

Institute for Regeneration Medicine

Project includes:• Located south of HSE and HSW• 80,000 GSF • $123,000,000 estimated budget• Funding sources: gifts and state funds• Projected completion: December 2010

Page 6: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 6 January 18, 2007

MSB/Moffitt Seismic Joint and Retrofit

Project involves seismic improvements andspace adjustments:• $35,400,000 approved budget• $17,000,000 in state funds• $6,000,000 in FEMA funds• $4,400,000 in non-state funds• Projected completion: June 2008

Page 7: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 7 January 18, 2007

Cole Hall Renovation

Project involves renovating interior finishes, seating, lighting, and acoustics:• $3,222,000 approved budget• Funding source: Campus Funds • Projected completion: August 2007

Page 8: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 8 January 18, 2007

Renovation Projects

HSW-4 Pathology Remodel:• 9,177 ASF • $8,355,000 approved budget• Projected completion: May 2008

M-3N MRI Suite Renovations:• 3,216 ASF• $14,955,000 approved budget• Projected completion: May 2008

L-13, M-13S Bed Expansion:• 20,000 ASF• $36,200,000 approved budget• Projected completion: February 2008

MSB HVAC Improvements:• $34,730,000 approved budget• Projected completion: March 2008

Page 9: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 9 January 18, 2007

Parnassus Projects to be completed by 2012 (LRDP Horizon)

UC Hall decant and demolition:• Removal of 146,853 GSF from the space inventory • Timetable and Budget TBD

Lab of Radiobiology demolition:• Removal of 18,219 GSF from the space inventory • Timetable TBD

Medical Research IV demolition:• Removal of 12,252 GSF from the space inventory • Timetable TBD

Proctor, Surge and Woods demolition:• Removal of 25,124 GSF from the space inventory • Timetable TBD

Page 10: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 10 January 18, 2007

Parnassus Projects to be completed by 2012 (LRDP Horizon)Housing: • Older Aldea housing demolition TBD• 1486-88 5th Ave. renovation TBD• 374 and 735 Parnassus Ave. replacement TBD

Infrastructure Improvements:• Electrical Distribution System• West side Utilities• Telecom / Data improvements

Page 11: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 11 January 18, 2007

Parnassus Design Guidelines

Scope:Parnassus Design Guidelines and Campus Plan will address the developed southern portion of the Parnassus Heights campus site located below the Mount Sutro Open Space Reserve

Timetable:• Design Guidelines Completed• Campus Plan to be completed Fall 2007

Page 12: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 12 January 18, 2007

Parnassus Design Guidelines

Goals:

• To establish a more cohesive appearance

• To create a stronger identity

• To introduce more color to the campus

• To improve navigation and way-finding

• To ensure pedestrian safety and accessibility

• To enhance the quality of life on campus

Page 13: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 13 January 18, 2007

Mission Bay

Page 14: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 14 January 18, 2007

Helen Diller Cancer Research Building

Program includes:• UCSF Cancer Center, Urology, Neurological Surgery• 161,757 GSF / 97,168 ASF• $135,000,000 approved budget• $91,379,000 in gift funds• $13,621,000 in campus funds• $30,000,000 external financing• Projected completion: Fall 2008

Page 15: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 15 January 18, 2007

Cardiovascular Research Building (17 A/B)

Program includes:• Cardiovascular Research Institute and other related

programs• 137,000 ASF / 232,000 GSF• $247,000,000 estimated budget• Funding sources: gifts, Medical Center funds, external

financing• Projected completion: June 2011

Page 16: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 16 January 18, 2007

Neuroscience Research Building Phase 1

Project being replanned:• Neurologic and Neurodegenerative disease research

with Keck Center Neuroscience • Size and budget to be determined• Possible Developer-built

Page 17: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 17 January 18, 2007

Mission Bay Utilities and Distribution Phase I

Program includes:• First phase of a large Utility Plant to produce high-

temperature hot water, chilled water, and process steam for three research buildings

• $16,400,000 approved budget• $10,000,000 external financing• $6,400,000 campus funds

Page 18: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 18 January 18, 2007

Mission Bay Hospital

Planning underway includes:• Land acquisition of the south site is complete• Program includes 289-bed hospital for children, women, and cancer services;

ambulatory care center; central utilities plant. Parking and faculty offices separately funded.

• Architect selection and design• $1,200,000,000 estimated budget ($500,000,000 in gifts, $600,000,000 in debt,

and $100,000,000 other)• Projected completion: December 2014

Page 19: January 18, 2007 Campus Planning1 Update on Campus Planning and Construction Parnassus and Mission Bay Lori Yamauchi Assistant Vice Chancellor Campus Planning

Campus Planning 19 January 18, 2007

Mission Bay Phase 2 Site Planning

Planning for:• Street Layout• Infrastructure• Landscaping and Open Space