Harrisburg Overpass Construction Update January 5, 2016

Upload: others

Post on 20-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: January 5, 2016 - ride METRO · 2016-05-12 · January 5, 2016 . Utilities Completed 3,800 LF Total Installed % Completed 3,040 LF 80% All Utility Work East of Union Pacific Railroad

Harrisburg Overpass Construction Update January 5, 2016

Page 2: January 5, 2016 - ride METRO · 2016-05-12 · January 5, 2016 . Utilities Completed 3,800 LF Total Installed % Completed 3,040 LF 80% All Utility Work East of Union Pacific Railroad

Utilities Completed 3,800 LF

% Completed Installed Total

80% 3,040 LF

All Utility Work East of Union Pacific Railroad

Page 3: January 5, 2016 - ride METRO · 2016-05-12 · January 5, 2016 . Utilities Completed 3,800 LF Total Installed % Completed 3,040 LF 80% All Utility Work East of Union Pacific Railroad

Utilities Remaining to be Relocated East of Union Pacific Railroad

Page 4: January 5, 2016 - ride METRO · 2016-05-12 · January 5, 2016 . Utilities Completed 3,800 LF Total Installed % Completed 3,040 LF 80% All Utility Work East of Union Pacific Railroad

Concrete Paving East of Union Pacific Railroad

Page 5: January 5, 2016 - ride METRO · 2016-05-12 · January 5, 2016 . Utilities Completed 3,800 LF Total Installed % Completed 3,040 LF 80% All Utility Work East of Union Pacific Railroad

Paving Progress East of Union Pacific Railroad

Page 6: January 5, 2016 - ride METRO · 2016-05-12 · January 5, 2016 . Utilities Completed 3,800 LF Total Installed % Completed 3,040 LF 80% All Utility Work East of Union Pacific Railroad

All Utility Work West of Union Pacific Railroad

Utilities Completed 4,150 LF

% Completed Installed Total

85% 3,530 LF

Page 7: January 5, 2016 - ride METRO · 2016-05-12 · January 5, 2016 . Utilities Completed 3,800 LF Total Installed % Completed 3,040 LF 80% All Utility Work East of Union Pacific Railroad

Utilities Remaining to be Relocated West of Union Pacific Railroad

Page 8: January 5, 2016 - ride METRO · 2016-05-12 · January 5, 2016 . Utilities Completed 3,800 LF Total Installed % Completed 3,040 LF 80% All Utility Work East of Union Pacific Railroad

Concrete Paving West of Union Pacific Railroad

Page 9: January 5, 2016 - ride METRO · 2016-05-12 · January 5, 2016 . Utilities Completed 3,800 LF Total Installed % Completed 3,040 LF 80% All Utility Work East of Union Pacific Railroad

Paving Progress West of Union Pacific Railroad

Page 10: January 5, 2016 - ride METRO · 2016-05-12 · January 5, 2016 . Utilities Completed 3,800 LF Total Installed % Completed 3,040 LF 80% All Utility Work East of Union Pacific Railroad

Progress and Planned Activities

• Final Pavement Operations in Southeast Quadrant to start late January

• McCarthy will maintain driveways by adding crushed stone as required

• METRO/McCarthy continue to look for opportunities to compress schedule o Select construction activities will be built concurrently with major bridge activities during

the third phase of construction

• McCarthy is working extended hours to expedite completion of Phase 1

o Earthwork, Paving and Utility crews have been working 12 hour days

• McCarthy starts on drill shafts at Abutment #1 west of UPRR in mid January

10

Page 11: January 5, 2016 - ride METRO · 2016-05-12 · January 5, 2016 . Utilities Completed 3,800 LF Total Installed % Completed 3,040 LF 80% All Utility Work East of Union Pacific Railroad

30 Day Look Ahead

11

West of UPRR

Install remaining curb and sidewalk

Install temporary asphalt transitions from existing roadway to new concrete pavement

Seal and stripe pavement

Switch traffic to new pavement

Start drilling shafts for bridge columns

Asphalt pave permanent side street transition to new pavement

Install Phase 2 utilities

East of UPRR

Complete remaining storm sewer lines

Complete remaining sanitary sewer lines

Wet connects for water services

Complete demolition of existing pavement for new sidewalk and frontage concrete pavement

Grading, lime stabilization and placing concrete for new roadway, intersections and driveways

Install curb and sidewalk