Guadalupe-Blanco River Authority

Mid-Basin Water Supply Projects

August 26, 20151

Texas Groundwater SummitJames Lee Murphy, Esq.

Executive Manager for Water Resources & Utility OperationsGuadalupe-Blanco River Authority

Page 2: Jim murphy

Mid-Basin Water Supply Project is Part of the South Central Texas Regional Water Plan

Page 3: Jim murphy

South Central Texas Planning Region (Region L)

Page 4: Jim murphy

• Groundwater

• Edwards Aquifer

• Carrizo-Wilcox Aquifer

• Trinity Aquifer

• Gulf Coast Aquifer

• Others

Sources of Regional Water Supply

Surface Water•Canyon Reservoir•Power Supply Reservoirs•Coleto Creek Reservoir•Lake Dunlap, etc.•Calaveras Lake•Lake Braunig

•Run-of-River Water Rights

Reuse of Municipal Wastewater is a Reallocation of Existing Water Supply and is emphatically NOT a New Source of Water for Region L

HB 2031 – Seawater from the Gulf of Mexico is now a viable source of water supply for Region L

Page 5: Jim murphy

GBRA Water Supply Projects

Recommended Water Management Strategies (WMS)1

• Mid-Basin Water Supply Project (MBWSP)• Lower Basin Off-Channel Storage (LB OCR)• Integrated Water Power Project (IWPP)

Alternative Water Management Strategies2

• MBWSP/TWA/HCPUA Shared Facilities• Lower Basin Water Supply Project with Mid-Basin Delivery

1 Strategies in the South Central Texas Regional Water Planning Group Include Additional Recommended WMS: Conservation, Western Canyon WTP Expansion, Victoria County Steam-Electric Project, Wimberley/Woodcreek Project, & Lower Basin New Appropriation2 Additional Alternative WMS include: Luling ASR, Storage Above Canyon Reservoir (ASR)

All infrastructure and project costs were developed using Texas Water Development Board (TWDB) Unified Costing Model (UCM) for 2016 Regional Planning assumptions and associated cost curves.

Texas Groundwater Summit (August 26, 2015) 5

Page 6: Jim murphy

Mid-Basin Water Supply Project (MBWSP)

6Texas Groundwater Summit (August 26, 2015)

Page 7: Jim murphy

Potential Instream Flow ChangesGuadalupe River at Gonzales

7DRAFT (1-27-2015)

Page 8: Jim murphy

Integrated Regional Mid-Basin Project

Page 9: Jim murphy

MBWSP Engineering Feasibility Study

9DRAFT (1-27-2015)

Page 10: Jim murphy

MBWSP/TWA/HCPUA Shared Facilities

10Texas Groundwater Summit (August 26, 2015)

Page 11: Jim murphy

MBWSP/TWA/HCPUA Shared FacilitiesMAG Limited

• Sources and Firm Supply (86,513 acft/yr):– 50,000 acft/yr firm supply from Guadalupe River and ASR in GCUWCD

• Surface Water = 31,100 acft/yr (Average)• ASR = 18,900 acft/yr (Average)

– 21,833 acft/yr firm supply from HCPUA Wellfield, Carrizo Aquifer in GCUWCD and Plum Creek

– 14,680 acft/yr firm supply from TWA Wellfield, Carrizo Aquifer in GCUWCD

• Operations:– Treated groundwater and surface water delivered to participants and ASR

storage with stored surface water as back-up supply

• Facilities (1.5 peaking factor): – 27 production wells (1073 gpm – 2910 gpm)– 28 dual purpose wells (1,533 gpm peak/ 418 gpm average)– 140 cfs river intake– Groundwater Treatment Plant (48.9 MGD) & Surface WTP (67 MGD)– 6 mile 60-IN diameter raw water pipeline– 129 miles, 8-IN to 78-IN diameter finished water pipelines

11DRAFT (1-27-2015)

Page 12: Jim murphy

MBWSP Engineering Feasibility Study*

12Texas Groundwater Summit (August 26, 2015)

* Unit costs based on MBWSP 2013 estimates and assumptions

Page 13: Jim murphy

MBWSP/TWA/HCPUA Shared Facilities

13

Estimated Costs

Capital Costs $725,465,000

Project Costs $1,123,541,000

Annual Costs $150,227,000

Yield (acft/yr) 86,513

Unit Costs( $/acft)

$1,736

Note: Project analyzed using MAG Limited groundwater only.

DRAFT (1-27-2015)

Page 14: Jim murphy

Project Yields and Unit Costs(MAG Limited)

14

Page 15: Jim murphy

Surface Water w/ ASR (Option 3C)

• Sources and Firm Supply:– 50,000 acft/yr from Guadalupe River and ASR in GCUWCD– Sources of Supply (Average): Surface Water = 31,100 acft/yr

and Recovery = 18,900 acft/yr

• Operations:– Treated surface water delivered to participants and ASR storage

with stored surface water as back-up supply– Interim back-up supply needed in early years

• Facilities (2.0 peaking factor): – 40 dual purpose wells (1,533 gpm peak/ 348 gpm average)– 140 cfs river intake– Water Treatment Plant (89 MGD)– 6 mile 66-IN diameter raw water pipeline– 45 mile, 66-IN, 36-IN diameter finished water pipelines– Two delivery locations and potential for tie-ins along the route

• Unit Cost: $1,467/acft/yr15

$1,637/acft/yr (2016 SCTRWP)

Page 16: Jim murphy

Mid-Basin Surface/ASR to SAWS

16

Page 17: Jim murphy

MBWSP ASR to San Antonio

The MBWSP ASR to San Antonio option includes uniform delivery of 50,000 acre-feet/year to the proposed San Antonio Water System (SAWS) Vista Ridge Project delivery location. Facilities include a pump station and 66-inch diameter pipeline to deliver raw water 6 miles from an intake on the Guadalupe River to a 79 MGD water treatment plant (WTP) prior to delivery to SAWS or aquifer storage for subsequent recovery. A 71-mile, 48-inch diameter transmission system delivers treated supplies from the WTP or ASR to SAWS. Preliminary conceptual unit cost of water from this project is estimated at $1891/acre-foot.

17

Page 18: Jim murphy

Mid-Basin Surface/ASR to Austin

18

Page 19: Jim murphy

MBWSP ASR to Austin

The MBWSP ASR to Austin option includes the uniform delivery of 50,000 acre-feet/year to an Austin area delivery location near the intersection of IH-35 and SH-45. Facilities include a pump station and 66-inch diameter pipeline to deliver water 6 miles from an intake on the Guadalupe River to a 79 MGD WTP prior to delivery to Austin or ASR wells. The 49 mile, 48-inch diameter transmission system which generally follows a cross country route to Maxwell WSC used in the recent MBWSP Study and then turns north to the assumed Austin delivery location. Preliminary conceptual unit cost of water from this project is estimated at $1674/acre-foot.

19

Page 20: Jim murphy

Texas Groundwater Summit (August 26, 2015)20