Page 1: John Coughlan RUWG November 2005  0 Tracker FED Questionnaire Response Production Status Plans for 904 Plans for USC

John Coughlan RUWG November 2005 www.te.rl.ac.uk/esdg/cms-fed/qa_web

1

Tracker FED

Questionnaire Response Production Status Plans for 904 Plans for USC

Page 2: John Coughlan RUWG November 2005  0 Tracker FED Questionnaire Response Production Status Plans for 904 Plans for USC

John Coughlan RUWG November 2005 www.te.rl.ac.uk/esdg/cms-fed/qa_web

2

Questionnaire Response1. We already have FULL populated FED crates in 904 lab. Max of 16 x 9U FEDs in crate with associated 6U Transition cards to carry the CMCs.

There are 40 FEDs and 35 Transition cards at CERN.

2. The final system has 36 crates containing a total of ~450 FEDs.

We expect to deliver FEDs to CERN at about 50 per month. We have delivered 40 so far.

I believe we have up to 12 crates installed in 904 open area for FEDs.

3. All 36 crates in USC won't be populated before Nov 06. FEDs should be there but depends on Tracker Integration needs.

4. We do have fake data/pattern generation facilities inside our FED.

5. The first ~150+ FEDs will be re-tested at B904 before being taken for the surface Tracker Integration in B186.

Remaining will be re-tested at 904 and then direct to USC.

We should have enough FEDs to start populating crates in USC start of Q2/06.

6. We should be ready to start integration at USC during Q2/06.

On our side the minimum equipment we would require to send "fake" data would be ; Crates, cooling, CAEN controllers, TTC system.

Assuming DAQ has provided FRLs, FMMs and associated cabling.

But as you say difficult to give precise answers without more realistic installation planning.

Our intention was to install FEDs in USC before the Tracker optical cabling is in place.

Much depends on the Tracker Integration demands.

A Question for you... When will the production Transmitter CMCs be available in quantities ?

Ideally we would test the unit "FED + Transtion card + CMC" with FRL readout. Then keep that unit together for installing at USC.

We are naturally rather anxious to test FEDs with production electronics of Trigger and DAQ systems including final FRLs and FMMs.

Almost all tests so far have been with emulations of other systems.

Particularly the merging to FRLs which I don't believe was thoroughly done?

Page 3: John Coughlan RUWG November 2005  0 Tracker FED Questionnaire Response Production Status Plans for 904 Plans for USC

John Coughlan RUWG November 2005 www.te.rl.ac.uk/esdg/cms-fed/qa_web

3

FED Production Summary

• 1st batch of 50 FED boards are almost all at RAL• 2nd batch of 50 at test at Assembly Plant, many already at RAL.• 3rd batch of 50 in production in progress.

• 40 FEDs sent to CERN last week

• First ~ 150 will be used at Tracker Surface Integration Tests B186

• + 70 SLINK 6U VME Transition cards (35 of which at CERN)(to be tested with final DAQ link before completing production).

CMS Tracker FED Final Production Cumulative Delivery Schedule (NB figures do not include Pre-Series or Prototype FED deliveries)

0

100

200

300

400

500

600

To

tal N

r B

oar

ds

Planned at CERN

Actual at CERN

Planned at CERN 0 0 25 50 100 150 200 250 300 350 400 450 475 500 500 500

Actual at CERN 0 0 40 40 40 40 40 40 40 40 40 40 40 40 40 40

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

2005 2006

Total of 450 (+50 spare) x (9U FEDs + 6U Transition cards)

Housed in 36 crates in USC

Page 4: John Coughlan RUWG November 2005  0 Tracker FED Questionnaire Response Production Status Plans for 904 Plans for USC

John Coughlan RUWG November 2005 www.te.rl.ac.uk/esdg/cms-fed/qa_web

4

Acceptance Testing Flow

1. Custom Tests atAssembly Plant

BScan, VME crate

3. Tests at CERNPrevessin 904

Readout Integration

2. Tests at RAL

Optical, Full crate

4. Installation at CMSUSC55

0. Quality Controlsduring Assembly

processAOI, X-ray

RAL

Assembly Company FED

“Pipeline” with each stage taking ~ 1 month and containing 50 FEDs

Rear Transition cardon J2

Page 5: John Coughlan RUWG November 2005  0 Tracker FED Questionnaire Response Production Status Plans for 904 Plans for USC

John Coughlan RUWG November 2005 www.te.rl.ac.uk/esdg/cms-fed/qa_web

5

B904• 2 Racks (1 with 3 FED crates) in lab area

• 3? Racks with 12 FED crates in open area.

•Production boards are only intended for large scale Tracker commissioning and USC.

All FEDs are tested in UK before delivery to CERN.All Acceptance Full Crate Tests at B904 (weed out early failures)First ~ 150? to used for Surface Tests of TrackerRemaining will go direct to USC55

• “Vertical Slice” Design Test.

Test of Production FED/Transition card with other Production Tracker/CMS DAQ Electronic systems urgent.

Manufacture of 400 remaining Transition cards on hold. Awaiting tests with FRL/FMMs

• Acceptance testing at CERN 904.

Re-test all delivered FEDs in 904 crates (burn in). Aim to test and install: “FED + Transition card + SLINK Transmitter CMC” as unit ?

Page 6: John Coughlan RUWG November 2005  0 Tracker FED Questionnaire Response Production Status Plans for 904 Plans for USC

John Coughlan RUWG November 2005 www.te.rl.ac.uk/esdg/cms-fed/qa_web

6

USC55•Installation in USC

• Could start with 1 crate / 1 rack Q2/06 ?

• FED can generate Fake Events with programmed data.

• But needs TTC system, PC interface for setup.

• Tracker doesn’t have a detailed plan for installation yet.

• Availability of crates, cooling, CCs, TTC, PCs….

• Tracker Optical cabling front of rack. Mock up exists. Major job. Install FEDs first?

• DAQ FRL FMM cabling at rear of rack ?

• …other constraints.

Page 7: John Coughlan RUWG November 2005  0 Tracker FED Questionnaire Response Production Status Plans for 904 Plans for USC

John Coughlan RUWG November 2005 www.te.rl.ac.uk/esdg/cms-fed/qa_web

7

Spare Slides

Page 8: John Coughlan RUWG November 2005  0 Tracker FED Questionnaire Response Production Status Plans for 904 Plans for USC

John Coughlan RUWG November 2005 www.te.rl.ac.uk/esdg/cms-fed/qa_web

8

Test System Non Final Electronics

Slink Rx

Generic PCI Card

VME crate PC

Slink PC (PCI-X slots)

Access VME with SBS620 PCI-VME link

LVDS cableFED

Simulate Local Trigger Control System

FT (master)

FT (slave)

FT (slave)

FT (slave)

Slink-Tx

Clock & L1As from FT to FEDThrottle signals from FED to FT

Merg

e 9

6 fi

bre

s in

to 8

rib

bon

s o

f 12

fib

res

J0 Connector

J1 Connector

VME crate

J2 Connector

Page 9: John Coughlan RUWG November 2005  0 Tracker FED Questionnaire Response Production Status Plans for 904 Plans for USC

John Coughlan RUWG November 2005 www.te.rl.ac.uk/esdg/cms-fed/qa_web

9

6U SLINK Transition Card Carrier for slink

transmitter Buffers control and data

signals Buffers throttle signals

Status 70 manufactured and

tested with FEDKit. Of these 35 already

at B904 CERN Manufacture of

remaining 400 on hold. Awaiting tests with FRL/FMMs

DAQ – Slink Transmitter

FED

Slink data and control signals

Throttle signals to Fast Merge Module (FMM)

VM

E B

ackp

lan

e