jubilee riverside south mill lane, taplow remediation … · 2015. 6. 5. · report (ramboll,...
TRANSCRIPT
Intended for
Berkeley Homes (Three Valleys) Ltd
Document type
Report
Date
May, 2015
Job No
61033137
JUBILEE RIVERSIDE
SOUTH
MILL LANE, TAPLOW REMEDIATION
STRATEGY
REMEDIATION STRATEGY
Ramboll
240 Blackfriars Road
London
SE1 8NW
United Kingdom
T +44 (0)20 7631 5291
www.ramboll.co.uk
Revision I03
Date 14/05/2015
Made by Tom Smith
Checked by Niki Dubber
Approved by Simon Corness
Description Remediation Strategy
Ref 61033137.E.JRS.RS.I03
Revision History
Revision Date Purpose / Status
Document Ref. Comments
I01 02.04.2015 Draft for Discussion
61033137.E.JRS.RS.I01
I02 13.04.2015 Final Issue 61033137.E.JRS.RS.I02 Update following client comments
I03 14.05.2015 Re-issue 61033137.E.JRS.RS.I03 Update following Local Authority and Environmental Agency Consultations
Prepared By Reviewed By Approved By
Tom Smith Niki Dubber Simon Corness
Senior Environmental Consultant
Senior Environmental Consultant
Project Director
Remediation Strategy
CONTENTS
1. INTRODUCTION 1 1.1 Brief 1 1.2 Scope and Objectives 1 1.3 Proposed Development 1 1.4 Pertinent Information 2 1.5 Constraints and Limitations 2 1.6 Roles and Responsibilities 2 2. ENVIRONMENTAL SETTING SUMMARY 3 2.1 Site Setting 3 2.2 Site Zoning / Nomenclature 3 2.3 Site Location and Description 3 2.4 Site History 4 2.5 Ground Investigations 4 2.6 Geology 5 2.7 Visual / Olfactory Evidence of Contamination 6 2.8 Hydrogeology 6 2.9 Hydrology 6 2.10 Ground Gas 6 2.11 Ground Contamination 7 3. REMEDIATION STRATEGY 10 3.1 General Site Environmental Controls 10 3.1.1 Air Quality and Dust 10 3.1.2 Noise and Vibration 11 3.1.3 Oils, Fuels and Chemicals 12 3.1.4 Unforeseen Contamination Protocol 12 3.1.5 Surface Water Management 13 3.1.6 Baseline & Long Term Water Monitoring 14 3.1.7 Borehole Decommissioning 14 3.1.8 Material Re-use 15 3.1.9 Material Import 16 3.1.10 Waste Disposal 17 3.1.11 Groundwater in Excavations 18 3.2 Specific Stage 1 Remedial Works 19 3.2.1 Site Clearance and Underground Structures 19 3.2.2 Asbestos Management Procedures 20 3.2.3 Service Corridors 20 3.3 Site Conditon Requirements upon Completion of Stage 1
Remedial Works 21 3.4 Specific Stage 2 Remedial Works 21 3.4.1 Capping System 21 3.4.2 Foundation Works Risk Assessment 22 3.4.3 Ground Gas Protection Measures 22
Remediation Strategy
3.5 Site Conditon Requirements upon Completion of Stage 2
Remedial Works 23 4. VERIFICATION PLAN 24 4.1 Environmental Watching Briefs 24 4.2 Verification Plan 24 REFERENCES 26
APPENDICES
Appendix 1 Figures/Drawings
Appendix 2 Testing Suites and Chemical Criteria for Baseline and Long Term Water
Monitoring
Appendix 3 Chemical Criteria for the Protection of Human Health (Re-use or Importation) –
Private Gardens
Appendix 4 Chemical Criteria for the Protection of Human Health (Re-use or Importation) –
Communal Soft Landscaped Areas
Appendix 5 Chemical Criteria for the Protection of Human Health (Re-use or Importation) –
Clean Service Corridors
Appendix 6 Consultations With Regulators
Remediation Strategy
1. INTRODUCTION
1.1 Brief
Ramboll have been appointed by Berkeley Homes (Three Valleys) Ltd to provide engineering
consultancy services for the proposed redevelopment of the masterplan at the site known as Mill
Lane, Taplow, South Bucks shown in Figure 1.1. As part of this appointment Ramboll have been
requested to prepare a Remediation Strategy specific to the Jubilee Riverside South site also
shown in Figure 2.2.
At the time of preparing this strategy a planning application had not been submitted for the site.
However, it is understood that this document will be submitted in support of anticipated condition
discharge following submission and approval of planning permission.
During the preparation of this Strategy Ramboll has undertaken consultations and agreed the
strategy with the Regulators. Details of consultations are contained within Appendix 6.
This report presents an overview of the ground contamination data retrieved during the recent
ground investigations and proposed an approach for remediating the site to make it suitable for
its proposed end use.
1.2 Scope and Objectives
This Remediation Strategy has been prepared by Ramboll at the instruction Berkeley Homes
(Three Valleys) Ltd. The scope of this report comprises the following:
Summary of existing ground investigation data within the Jubilee Riverside South site;
Preparation of a Remediation Strategy for the site;
Outline of the Verification Plan for the site.
This strategy does not include geotechnical issues which will be addressed separately.
1.3 Proposed Development
The Jubilee Riverside South site forms part of the planning application A package of the wider Mill
Lane site which includes full application and conservation area consent for demolition of existing
mill buildings, warehouses, associated structures and former Skindles hotel to provide 141 new
dwellings and 40 senior living apartments, restaurant, improvements to existing boatyard,
enhanced open space, new pedestrian footway and cycle links, car parking, enhanced
biodiversity, flood mitigation measures, removal of TPO trees and re-provision on-site, retention
and refurbishment of historic buildings on site into 18 further dwellings, new road junction,
landscaping and associated works.
With specific reference to Jubilee Riverside South the proposed development includes demolition
of the former Severnside warehouses and associated structures and enabling works to provide 42
new dwellings, enhanced areas open space and associated infrastructure works.
Remediation Strategy
1.4 Pertinent Information
This report has been prepared with reference to the following sources of information which
Berkeley Homes (Three Valleys) Ltd either own or have been granted reliance upon.
Table 1.1 - Information Sources
Report Author Date
Ground Contamination Interpretative Report, Mill Lane, Taplow ref 61033137.E.GCIR.I01
Ramboll March 2015
Geoenvironmental and Geotechnical Desk Study, Mill Lane, Taplow ref 33137.E.DSA.I03
Ramboll March 2015
Site Investigation No 3600/14 Factual Report Terramech Investigations Ltd
February 2015
Zone 2 Taplow Mill ref 100866/RA-Z2/001. Provectus Group (Provectus)
December 2013
1.5 Constraints and Limitations
This report has been prepared for the exclusive use of Berkeley Homes (Three Valleys) Ltd and
should not be used in whole or in part by any third parties without the express permission of
Ramboll in writing. This Remediation Strategy has been prepared with reference to the
information sources presented in Table 1.1 which Berkeley Homes (Three Valleys) Ltd either own
or have reliance upon. Where external sources have been used Ramboll cannot offer any
guarantees or warranties for the completeness or accuracy of information.
1.6 Roles and Responsibilities
The Contractor will be required to develop this document to produce detailed protocols and
management plans including method statements for the works to be undertaken defining how
potentially contaminated soils will be managed and handled onsite and how the associated
environmental risks will be managed. The contractor will be responsible for the onsite testing
and verification process.
The details of these protocols will need to be agreed by the Contractor with the Regulators at
South Bucks District Council before works commence at the site and shall form part of the
Verification Report which will need to be prepared on completion of the ground works.
During the site works the Contractor will be responsible for undertaking regular (monthly)
dialogue with the regulators and for obtaining and maintaining a record of information required
for verification. These records will be checked by Ramboll during periodic site audits of relevant
site documentation. The Contractor will need to provide a copy of these records on completion of
the ground works to Ramboll and deal with any queries arising during the verification process.
Remediation Strategy
2. ENVIRONMENTAL SETTING SUMMARY
2.1 Site Setting
The site setting is covered in detail in the Geoenvironmental and Geotechnical Desk Study
Ground and Geotechnical Assessment (Ramboll, 2015) and Ground Contamination Interpretative
Report (Ramboll, 2015). The site location and proposed layout are contained in Figure 2.1 and
Drawing 406.PL.100 by Berkeley Homes dated January 2015.
2.2 Site Zoning / Nomenclature
Historically the Jubilee Riverside South site has been identified using several names, generally
related to geographical/historical context, the configuration of historical ground investigations
and averaging areas adopted as part of the risk evaluation process. A summary of this
nomenclature is provided in Table 2.1 below.
Table 2.1- Jubilee Riverside South Nomenclature
Development Area Pre Ramboll Desk Study (pre 2014)
Ramboll Desk Study Ramboll Ground Contamination Interpretative Report
Jubilee Riverside South
Severnside / Zone 2 Severnside / Zone 2 Averaging Area C.
2.3 Site Location and Description
The site is located approximately 350m west of the village of Taplow, and to the north of the A4
(Bath Road) at an approximate National Grid Reference of 490419, 181813. The site is roughly
triangular in shape and covers an area of approximately 2.5 ha.
Jubilee Riverside South (hereafter referred to as ‘the site’) is occupied by an area of concrete
hardstanding, two warehouses and associated outbuildings formerly used by Severnside
Recycling for paper recycling associated with the St Regis Paper Mill which ceased operations in
2007. The site is bound to the north and west by Mill Lane, to the east by the Jubilee River and to
the south by the Maidenhead Gas Holder Station.
The open concrete hardstanding formerly used as stock areas cover the majority of the site. The
buildings present are in the northwest and southern parts of the site. A large above ground water
storage tank formerly used for a fire suppression system is present in the northwest corner of the
site adjacent to a pump house and porta-cabins formerly used as the site security offices. Two
large portal framed warehouse buildings formerly used as the paper production sheds are present
in the central southern part of site with outbuildings formerly used as a canteen and offices also
present in the south. A fenced area with concrete pads that formerly supported an electricity
substation is present to the south of the production sheds.
Within the interior of the paper production sheds there are several large depressed areas of
hardstanding that are suspected to have formerly housed plant; these areas are now partially
infilled with rainwater and general waste including drums, polythene bags and several office
chairs. A small vehicle maintenance area is present in the north of the production shed which
contains two elongated rectangular inspection chambers and further evidence of general dumping
of waste. A raised concrete pad is present immediately to the north of the production shed which
is suspected to have formerly supported an above ground fuel storage tank. Evidence of
associated infrastructure (fuel gauge) was found remaining on the production shed wall. Due to
the age of the buildings it is also anticipated that material containing asbestos will be present
within the building fabric.
Remediation Strategy
The margins of the area have been fly-tipped with stockpiles of builder’s rubble, metal work, road
cones and barriers, car tyres, fabric, drums etc. noted throughout the area.
2.4 Site History
Prior to the 1960’s the site is understood to have been occupied by undeveloped open land with
Mill Lane located at the western boundary and a potential mill run to the east which was later
engineered into the Jubilee flood relief channel in the 2002 (Jubilee River). Since the 1960’s the
site is found in largely the same configuration as is currently present with warehouse structures
located in south which doubled in size by the 1999 OS Map. The site is understood to have been
operated by Severnside as a Recycling Facility during this period which ceased to operate in 2006
when the neighbouring St Regis Paper Mill closed down.
Within the vicinity of the site significant potentially contaminative end uses include the St Regis
Paper Mill (north), boatyards (west), garages (south) and the Mill Lane gas works and gas holder
station present to the south and southwest of the site.
2.5 Ground Investigations
A number of third party reports and ground investigations have been completed at the site since
the early 2000’s and have generally been undertaken as part of the sites closure, a subsequent
planning application and latterly as part of vendor due diligence ahead of a change in site
ownership. To date ground investigations have been undertaken by Conestoga Rovers Associates
(CRA) in 2006, AIG Engineering Group (AIG) in 2007 and Provectus in 2013. These ground
investigations are discussed fully within the Geoenvironmental and Geotechnical Desk Study
(Ramboll, 2015).
In order to further increase the understanding of the prevailing geoenvironmental conditions and
contamination issues at the site further ground investigation was undertaken at the site in
2014/15 by Terramech Investigations Ltd which was designed and monitored by Ramboll.
The Terramech/Ramboll ground investigation was undertaken between November 2014 and
March 2015 and within Jubilee Riverside South comprised 3No dynamically sampled and rotary
cored boreholes to a maximum depth of 20mbgl (RBH10 to RBH12), 5No windowless sampled
boreholes to a maximum depth of 6mbgl (RWS19 to RWS23) and 8No trial pits to a maximum
depth of 2.8mbgl (RTP03 to RT08 and RTP19 to RTP20). A series of static cone penetrations tests
were also undertaken for geotechnical purposes. Following the ground investigation an additional
6No rounds of ground gas and groundwater level monitoring was undertaken along with 3No
rounds of groundwater samples. A series of strategically located surface water samples were also
collected on 3No occasions. Chemical analysis of soil, groundwater and surface water samples
collected as part of the ground investigation was also undertaken.
A summary of the exploratory locations advanced as part of the Ground Investigations to date is
included in Figure 2.3.
Remediation Strategy
2.6 Geology
The stratigraphy encountered within Jubilee Riverside South is summarised below in Table 2.2.
Table 2.2 - Summary of Jubilee Riverside South Stratigraphy
Stratum Top Depth
(mbgl)
Top Depth
(mAOD)
Thickness
(m)
Typical Description
Made Ground Ground Level 25.01 to
23.42
0.29 to 3.2 Cohesive Made Ground - Firm brown slightly
sandy, gravelly clay or silt. Granular
inclusions are of flint, brick, concrete, slag,
coal and plastic.
Granular Made Ground - medium dense
grey and black to orangish/reddish brown
slightly sandy and locally clayey gravel of
flint, brick, concrete, slag, coal, tile and
plastic
Alluvium 0.8 to 1.8 23.81 to
22.53
0.3 to 1.4 Discontinuous of firm to locally stiff,
orangish brown to dark grey, sandy locally
gravelly clay with locally frequent rootlets.
Granular inclusions are of sub-angular and
rounded fine to coarse flint and rarely fine
to medium chalk
River Terrace
Deposits
0.29 to 3.2 24.58 to
21.39
3.35 to 6.6 Loose increasing to medium dense and
dense, orangish brown and brown, locally
clayey, sand and gravel with a low cobble
content. Gravel is angular to rounded, fine
to coarse of flint, locally chalk and rare
quartzite
Chalk –
Structureless
Grade
Dc/Dm
5.6 to 5.7 19.03 to
18.90
Unproven at
13.55
Grade Dm material was described as off
white sandy silt with fine to coarse gravel
size very weak, low density chalk clasts and
rinded flint, whilst the Grade Dc was
described as being, ‘recovered as’ slightly
sandy, clayey, off white, very weak, low
density sub-angular to sub-rounded fine to
coarse gravel size fragments in an off white
to yellowish brown clay of chalk matrix.
Remediation Strategy
2.7 Visual / Olfactory Evidence of Contamination
A summary of the significant visual / olfactory evidence of contamination within Jubilee Riverside
South is presented in Table 2.3.
Table 2.3- Summary of the Significant Visual & Olfactory Evidence of Contamination as part of the 2014 Ramboll and 2013 Provectus Ground Investigations
Exploratory Hole
Depth (mbgl)
Strata Description Potential Source
RBH11A 0.9 MG Possible asbestos containing materials.
Paper Recycling Activities
RTP03 0.3 to 1.0 MG Hydrocarbon odour Paper Recycling Activities
RTP05 1.0 to 2.0 MG Possible asbestos containing tile, clusters of brown fibres and a slight hydrocarbon odour.
Paper Recycling Activities
RTP10 0.35 MG Possible asbestos containing tile. Paper Recycling Activities
RWS20 0.65 1.2
MG MG
Possible asbestos containing materials. Mild hydrocarbon odour.
Paper Recycling Activities
2TP6 0.3 to 1.1 MG Hydrocarbon odour. Paper Recycling Activities
2TP7 0.25 to 1.7 MG Slight gasworks odour. Gasworks Notes
Italics indicated exploratory holes advanced historically by Provectus.
MG = Made Ground, ALV = Alluvium, RTD = River Terrace Deposits, UC = Upper Chalk
2.8 Hydrogeology
The Alluvial Deposits are classified by the Environment Agency as a Secondary A Aquifer while
the underlying River Terrace Deposits and Upper Chalk Formation are classified as Principal
Aquifers and are considered to be in hydraulic continuity due to the absence of a significant low
permeability layer separating the two strata. The majority of the site is situated in a Groundwater
Source Protection Zone I with Zones II and III located to the south of the site. It is understood
that the GSPZ designations relate to Thames Water Groundwater Abstractions to the north of the
site to the east of the Jubilee River. Several of these are understood to be disused and following
discussions with the Environment Agency are considered to be hydraulically up-gradient of the
site and not sensitive receptors.
During groundwater level monitoring water was identified within several of the stratum
underlying the site including the Made Ground, Alluvium, River Terrace Deposits and Upper
Chalk. From inspection of groundwater levels it is apparent that water is present as isolated
occurrences of perched water within the Made Ground between 23.44 and 23.52mAOD and as
the main groundwater body deeper within the Alluvium, River Terrace Deposits and shallow
Upper Chalk between 20.43 and 21.34 mAOD. Based on the observed groundwater levels a
general groundwater flow direction is assumed towards the south southwest.
2.9 Hydrology
The site is situated within a hydrologically sensitive area with the Jubilee River forming the
eastern boundary of the site with river levels found at an approximate elevation of +22.0mOD.
The River Thames is located approximately 85m west at its closest point and since 2003 the
highest recorded water level within the River Thames was recorded by the Environment Agency
at +22.87mOD. Both rivers flow in a north to south direction.
2.10 Ground Gas
A total of 6No ground gas monitoring visits had been undertaken on selected wells within the
area between 15th December 2014 and 13th March 2015. For the purposes of this assessment
the 2014/2015 has been supplemented with the results of 2No ground gas monitoring visits
undertaken by Provectus on 19th and 26th November 2013 which Berkeley Homes (Three
Valleys) Ltd have reliance on. Generally the monitoring visits were undertaken under periods of
Remediation Strategy
high, moderate, low and falling atmospheric pressure. A summary of the ground gas data within
Jubilee Riverside South is contained below in Table 2.4.
Table 2.4 - Jubilee Riverside South Ground Gas Data
ID No of Visits
Atmospheric Pressure Range (mb)
Max Gas Flow (l/hr)
Max CH4 (%v/v)
Max CO2 (%v/v)
Minimum O2 (%v/v)
Max H2S (ppm)
Max CO (ppm)
VOC (ppm)
RWS19A 6 987 to 1031 0.0 0.2 9.9 0.1 0 0 0
RWS20 6 987 to 1031 0.0 3.4 3.9 0.0 0 0 0
RWS21 6 987 to 1031 0.0 0.4 6.1 0.0 0 0 0
RWS22 6 987 to 1031 0.0 4.8 6.5 0.0 0 0 0
RWS23 6 987 to 1031 0.0 0.2 6.7 9.6 0 0 0
RBH10 6 987 to 1031 0.0 0.2 3.9 14.4 0 0 0
BH201S 8 987 to 1042 0.0 0.5 5.6 0.0 0 0 0
BH201D 2 987 to 1042 0.1 0.2 6.5 0.3 0 0 0
WS201 7 988 to 1042 0.0 0.0 6.5 0.3 0 0 10
The site is classified as a Characteristic Situation of 2 due to elevated concentrations of carbon
dioxide and methane being consistently recorded in excess of the 5% v/v and 1% v/v thresholds
(respectively) indicated in CIRIA C665 (CIRIA, 2007). Consequently ground gas protection
measures are required in new structures. In addition the observed concentrations of carbon
dioxide are above workplace exposure limits for short and long term exposure. Concentrations of
hydrogen sulphide and carbon monoxide are below workplace exposure limits.
As part of the Ground Contamination Interpretative Report (Ramboll, 2015) an assessment of the
risks from volatile organic compounds (VOCs) was undertaken which concluded that there is an
absence of significant soil or groundwater borne sources of VOCs and in the context of the
concentrations identified during monitoring, the risks were considered to be negligible.
2.11 Ground Contamination
As part of the ground investigations referred to in Section 2.5 a number of contamination issues
were identified which are summarised below and within Figures 2.4 to 2.16. These are also
comprehensively discussed within the Ground Contamination Interpretative Report (Ramboll,
2015).
Soils
Human Health
Isolated exceedences of the arsenic GAC were recorded in 2TP4 at 0.9m and RTP03 at 0.7m
up to a maximum of 77.3mg/kg. In addition a single isolated exceedence of the nickel GAC
was recorded within 2TP4 at 0.5m with a concentration of 3,700mg/kg. Exceedences of the
lead GAC were also predominantly recorded as isolated hotspots with 8No samples exceeding
from 2TP4 at (0.5 and 0.9m), RBH11A (0.9m), RBH12 (0.6m), RTP03 (0.7m), RTP04 (0.9m),
RTP07 (0.8m) and RWS19A (0.5m) up to maximum of 2,300mg/kg. Statistical analysis
indicated potential impacts from lead and nickel (UCLs of 506 mg/kg and 646 mg/kg
respectively).
Individual PAH species exceedences of GAC were recorded in 4No isolated locations in RTP03
(0.3m and 0.7m), RTP05 (0.9m), RTP07 (0.8m) and RTP20 (0.9m) for naphthalene,
benzo(a)anthracene, benzo(b)flouranthene, benzo(a)pyrene, chrysene and
dibenzo(a,h)anthracene. Statistical analysis indicates potential impacts from
benzo(a)anthracene (UCL of 13.29mg/kg), benzo(b)flouranthene (UCL of 13.81mg/kg),
benzo(a)pyrene (UCL of 10.84 mg/kg) and dibenzo(a,h)anthracene (UCL of 1.10 mg/kg).
Remediation Strategy
Petroleum hydrocarbon concentrations were recorded up to maximum of 6,000mg/kg within
the shallow soils (<1m). Concentrations elevated above laboratory detection limits were
recorded in several exploratory holes across the site with concentrations in excess of soil
saturation limits which are indicative of the presence of free phase hydrocarbons, however,
none were noted during the ground investigation works. While significantly elevated above
laboratory detection limits (LoD), it is important to note, however, that where speciated
analysis has been undertaken the observed concentrations do not generally exceed the
adopted GACs for speciated TPH for a residential end use. There is one exception within
RTP05 at 0.9m where a marginal exceedence of TPH Aromatic C16-C21 GAC (540 mg/kg) is
recorded with a concentration 560mg/kg. Statistical analysis indicates that site wide impacts
are not likely. Where concentrations in excess of LoD are recorded they are generally less
mobile heavier end hydrocarbons i.e.>C12 and are not accompanied by BTEX or volatile
organic compounds (VOCs or SVOCs).
Prevalent asbestos containing soils (ACM) within the shallow (<1m) Made Ground and to a
lesser extent within the deep (>1m) Made Ground across the area. Of the 35No soil samples
submitted for asbestos analysis, 17No returned a positive identification for Asbestos
Containing Material (ACM) in the form of chrysotile cement, bitumen and free fibres and
amosite insulation and fibres. Asbestos containing soils were widespread within the Area and
recorded within 2TP1 (0.6m), 2TP2 (0.5m), 2TP3 (0.8m), 2TP4 (0.9m), 2TP6 (0.7m), 2TP7
(0.6m), RBH10 (0.5m), RBH11A (0.9m), RBH12 (0.4m), RTP03 (0.3m and 0.7m), RTP04
(0.45m and 0.9m), RWS19A (0.5m), RWS20 (0.8m) and RWS22 (0.4m). Following the
positive identification of ACM, subsequent quantitative laboratory analysis was commissioned
on 9No positivity identified samples. The samples analysed reported ACM concentrations
between <0.001%w/w and 0.033%w/w. Subsequent dustiness testing indicated the potential
for fibre release at concentrations above background levels should soils be persistently
disturbed.
Phytotoxicity
Elevated concentrations of copper (1,880 mg/kg max), nickel (3,700mg/kg max) and zinc
(1,670 max) which could present a risk to future flora.
Water Supply Pipes
The aforementioned petroleum hydrocarbon concentrations which are in excess of thresholds
for PE water supply pipes in site soils.
In relation to soil impacts remedial measures are deemed necessary to mitigate impacts from
heavy metals, PAHs, phytotoxic contaminants, petroleum hydrocarbons in relation to water
supply pipes and asbestos containing materials with Made Ground.
Controlled Waters
Within soil leachate and groundwater no significant contamination sources have been identified,
however several marginal exceedences of GAC have been identified which are highlighted below
for transparency.
As part of soil leachate analysis concentrations of leachable lead (11 µg/l max) and mercury
(0.8 µg/l max) were identified in isolated locations.
Within groundwater marginally elevated concentrations of ammonium as NH4 were recorded
in RBH12 (760 µg/l max with GAC of 600 µg/l) along with marginal exceedences of the
mercury GAC within BH201S, BH201D, RBH11 and RBH12 (0.34 µg/l max with GAC of 0.05
µg/l). Due to isolated marginal nature of these exceedences they are not considered to be
representative of on-site sources of contamination.
Remediation Strategy
Marginally elevated concentrations of petroleum hydrocarbons above GAC were recorded in
BH201S (River Terrace Deposits) and BH201D (Upper Chalk) as part of monitoring
programme by Provectus in 2013. Maximum concentrations were recorded up 14 µg/l
(BH201S) and 45 µg/l (BH201D). As part of monitoring undertaken as part of the most recent
ground investigation (2No visits on 5No wells) no petroleum hydrocarbon impacts to
groundwater have been identified with concentrations consistently below LoD (10 µg/l)
including testing on samples collected from BH201S and BH201D.
Chemical analysis of surface water samples collected at strategically selected locations
hydraulically up-gradient and down-gradient of the site did not identify any contaminants in
excess of GAC.
On the basis of the soil leachate, groundwater and surface water chemical analysis no specific
remedial measures are deemed necessary in relation to controlled waters risks. However, given
the sensitivity of the site in terms of Controlled Waters strict adherence to environmental controls
are deemed necessary.
Summary
Following the identification of the contamination highlighted above a conceptual site model was
prepared for the site as part of the Ground Contamination Interpretative Report which identified a
number of potentially significant pollutant linkages which are summarised in Table 2.5.
Table 2.5 - Potentially Significant Pollutant Linkages
Contamination Identified Associated Potentially Significant Pollutant Linkages
Risk
Human Health Impacts of lead and the PAHs benzo(a)pyrene, benzo(b)flouranthene benzo(a)anthracene and dibenzo(a,h)anthracene) within the shallow (<1m) site soils.
Direct Contact and ingestion and inhalation of soils and dusts associated with future site users.
Moderate to Moderate / Low
Human Health Prevalent asbestos containing soils within the shallow (<1m) Made Ground and to a lesser extent within the deep (>1m) Made Ground across the area. ACM in the form of chrysotile cement, bitumen and free fibres, amosite insulation and fibres and crocidolite free fibres.
Ingestion of asbestos fibres, primary inhalation of airborne asbestos fibres and secondary inhalation from trafficked soils containing asbestos fibres or ACMs associated with future site users.
High
Water Supply Pipes Elevated concentrations of petroleum hydrocarbons that may preclude the use of PE pipes.
Direct contact with water supply pipes and tainting of drinking water supplies.
Moderate
Phytotoxicity Elevated concentrations of copper, nickel and zinc which could present a risk to flora.
Root uptake associated with future flora at the site.
Moderate/Low
Ground Gas Elevated concentrations of carbon dioxide resulting in the area being classified as a Characteristic Situation of 2 (CS-2).
Migration and subsequent inhalation of gases / vapours and accumulation enclosed spaces leading to impacts to human health and property.
Moderate to Low
These pollutant linkages have the potential to adversely impact end users, flora water supply
pipes and property should mitigation/remedial measures not be incorporated within the enabling
works, construction works and operational stages. This Remediation Strategy has been prepared
to address these pollutant linkages.
Remediation Strategy
3. REMEDIATION STRATEGY
Due to the development and construction programme the remedial strategy detailed within this
section will be required to be executed in two stages which broadly comprise:
Stage 1 – Site enabling works and the formation of a development platform to a minimum
level of +24.70mAOD beneath buildings and garden / soft landscaped areas and +24.85mOD
beneath roads.
Stage 2 – Construction works to deliver the final proposed development with a minimum
finished ground level of +25.20mOD and finished floor level of +25.35mOD.
Within each of these development stages a range of remedial activities will be required. Table 3.1
below provides a summary of the activities required in each stage which are described in detail in
the following section.
Table 3.1 - Required Remediation Measures
Remedial Action Stage 1 Stage 2
General Site Operations
General Site Environmental Controls
Unforeseen Contamination Protocol
Baseline & Long Term Water Monitoring
Borehole Decommissioning
Material Re-Use Strategy
Material Importation Strategy
Waste Management Strategy
Groundwater Management
Specific Stage 1 Remedial Works
Site Clearance and Underground Structures X
Asbestos Management Procedures X
Clean Service Corridor Construction X
Specific Stage 2 Remedial Works
Clean Capping X
Foundation Works Risk Assessment X
Ground Gas Protection Measures X
The remediation strategy described in the following sections is described in relation to these
development stages.
3.1 General Site Environmental Controls
The following Section provides an outline of the expectations of the Contractor to ensure
environmental compliance throughout the duration of enabling and remedial works. It is assumed
that demolition works are to be undertaken separately but the demolition contractor should
adhere to the general guidance provided as part of this strategy and should undertake works in
an environmental sound manner in accordance with industry best practice.
3.1.1 Air Quality and Dust
The Contractor shall be responsible for obtaining any necessary authorisations required by the
Local Authority including liaison for any monitoring requirements to be adopted.
The Contractor shall be responsible for the implementation of any air quality and dust monitoring
required by the Local Authority.
Remediation Strategy
The Contractor shall ensure that emissions to air are minimised and that all necessary
precautions to prevent the occurrence of smoke emissions, fumes or odours from site plant,
stored fuel or other substances and prevent any emissions for fumes drifting into the nearby
residences, workplaces or public open spaces.
A log of the activities being undertaken on the site to the Project Employer's Representative each
week together with a record of any complaints that have been received.
It will be necessary to ensure that mitigation measures are implemented to prevent off-site
migration of contaminants as dust/vapours or run-off during excavations and soil stockpiling.
It will be necessary to ensure that all plant is in good repair and conforms to the manufacturers
or legislative/British Standard emission standards. Plant shall not be left running for long periods
when not directly in use. Where appropriate or practical, electrically powered plant shall be used
instead of diesel.
Taking into consideration the positive identification of ACM within the underlying Made Ground,
adequate site-wide health and safety protocols (PPE/RPE) and dust suppression techniques are
considered integral to pollution prevention and methodologies and procedures should be selected
through consultations with a specialist asbestos contractor in accordance with best practice and
legislation current at the time of the works, plus any specific requirements of Local Authority and
the Health and Safety Executive. It is emphasised that ACM in widespread and specialist advice
should be sought from a specialist asbestos consultant/contractor.
Dust suppression techniques and monitoring requirements should be outlined in consultation with
a specialist asbestos Contractor. Suppression techniques and monitoring requirements are likely
to include (but not exclusive to) soil dampening with the use of a dedicate site water bowser, use
of dust curtains and air quality monitoring stations along site boundaries.
The following measures shall be used by to minimise the generation of dust where appropriate:
Wheel washing and street sweeping (where appropriate);
Loading/unloading within designated bays/areas;
Hoarding around site and/or appropriate locations such as plant;
Monaflex or similar sheeting around scaffolding;
Sheeting of lorries leaving site;
Maintenance of plant;
Liaison with neighbours; and
Highest standards of housekeeping.
No vehicles shall leave the site with earth, mud, etc. adhering to the wheels in a quantity which
may result in its being deposited on the public highway or footpath, and creating a nuisance, or
hazard to vehicles or pedestrians. Suitable wheel washing equipment to avoid such problems
shall be installed, operated and maintained on the site until the development is completed.
The written consent of the Environment Agency and Local Utility provider shall be obtained
regarding the disposal of wheel wash water to surface water drains.
3.1.2 Noise and Vibration
The Contractor shall be responsible for obtaining any necessary authorisations required by the
Local Authority including liaison for any monitoring requirements to be adopted. Any ‘Out of
hours’ work shall require prior agreement with South Bucks District Council.
Remediation Strategy
The Contractor shall be responsible for the implementation of any noise and vibration monitoring
required by the Local Authority.
The Contractor shall take all practical measures to minimise noise and vibration during the Works
and where relevant, comply with BS 5228 Noise Control on Construction and Open Sites.
The following measures should be implemented to minimise the generation of noise and
vibration:
Use of acoustic silencers on equipment;
Regular maintenance of plant;
Unloading and loading of material within designated areas;
Radio controlled lorry movements to avoid unnecessary vehicles on site; and,
Liaison with neighbours in conjunction with the employer’s agent.
3.1.3 Oils, Fuels and Chemicals
Oils, fuel and chemical storage facilities should be designed with regard to EA Pollution
Prevention Guidelines (PPG). Best practices with regard to controlling pollution and spillages
include (but are not limited to) the following:
designated facilities specially designed for the storage of fuels and oils in accordance with
PPG2;
an oil, chemical and product inventory for the site;
site drainage plans;
emergency procedures;
use of drip trays beneath stationary plant;
keeping plant well maintained;
site induction for all personnel on emergency procedures;
contact list of emergency services, water suppliers, EA, LA & HSE; and,
emergency response equipment (provision of adequate spill kits on-site and competent
emergency response staff).
Bunded areas should comprise at least 110% of the total storage capacity. For smaller storage
volumes, the volume of the largest container should be catered for.
The storage, itinerary, and use of hazardous materials on-site will be conducted in accordance
with the Control of Substances Hazardous to Health (COSHH) regulation 2002. In accordance
with COSHH, records held of all hazardous materials on-site will be maintained by the Contractor.
The Contractor is responsible for the completeness and accuracy of all records held.
3.1.4 Unforeseen Contamination Protocol
The Contractor shall be required to provide a method statement relating to any unexpected areas
of contamination encountered during the earthworks.
Potentially contaminated materials are those which via visual or olfactory evidence may be
suspected to be contaminated (i.e. the presence of staining, odours or deleterious materials).
The unforeseen contamination protocol is likely to include:
The Contractor stopping work in that area and immediately inform Berkeley Homes
(Three Valleys) Ltd or their representative and Ramboll to discuss the proposed action;
The Contractor liaising with the statutory authorities including the EA and South Bucks
District Council to agree proposals for dealing with this material;
Remediation Strategy
The implementation of measures to remove contaminated materials (where feasible) for
segregation, storage or stockpiling (of soils) within a bunded and polythene covered area
whilst testing is undertaken. Contaminated liquids should be stored in suitable containers;
A record should be made of the volume of material removed and the extent of any
required excavation;
The full extent of the contaminated material must be excavated (minimum 0.5m overdig)
and furthermore validated by a suitably qualified engineer;
Undertake laboratory testing of representative samples from the base and sides of the
excavation (minimum of 1 sample per 10m length of sides and 1 per 100m2 base) and
testing of the material for a suitable suite of contaminants. The suite and chemical criteria
for verification are to be defined in consultation with Ramboll and the regulatory
authorises based on the nature of the contamination encountered;
If the material fails comparison against the re-use thresholds this material should be
excluded from the re-use strategy and alternative scenarios should be sought for re-use.
The last option should be disposal of off-site in accordance with current waste regulations.
Records including laboratory analytical certificates, waste transfer notes, consignment
notes and volumes requiring removal should be retained by the Contractor; and
If the material passes comparison with re-use thresholds (and is geo-technically suitable),
the contactor should determine and record the location for placement of the material.
It will be necessary to retain all records relating to testing, quantity, depth and location of the
material identified. Where such material is re-used, it will be necessary to demonstrate suitability
through appropriate chemical testing and to retain records on where this material was placed.
If this material is removed off-site, then in addition to records on the source area outlined above,
it will also be necessary to retain duty of care records relating to waste transfer notes, quantities
and the receiving site.
3.1.5 Surface Water Management
The Contractor will be responsible for the preparation and implementation of a site-specific
Surface Water Management Plan.
The management plan must identify all potential risks posed to controlled waters during the
works and the mitigation measures to be adopted on-site.
Water accumulated at the surface must be prohibited from entering directly into the adjacent
surface water bodies.
The Contractor shall ensure that any discharges are only made with the appropriate discharge
consents. It is the Contractor’s responsibility to obtain the required discharge consents from the
Environment Agency and or local water authority including any Flood Defence Consent for works
within 8m of the Jubilee River.
The Contractor shall ensure regular inspection of all discharge points and associated pipe work,
drainage systems, collection ditches, lagoons, oil separator (and drip-trays) and watercourses to
check that these are in good order. Observations will be reported within weekly site inspection
records.
Remediation Strategy
The Contractor shall comply with BS 6031:1981, Code of Practice regarding the general control of
site drainage.
The surface water management plan shall also provide details of the contractor’s emergency
preparedness such as the provision of floating booms for use in the Jubilee River should a
pollution event occur to ensure that any floating hydrocarbons are constrained for removal with
absorbent materials.
3.1.6 Baseline & Long Term Water Monitoring
As enabling and construction works have the potential to mobilise contaminants to surface water
(Jubilee River) and groundwater within the Alluvium Secondary A and River Terrace
Deposits/Upper Chalk Principal Aquifers monitoring and sampling will be required during the
course of the works. Monitoring and sampling shall be undertaken prior to works commencing on
site, at one monthly intervals during and upon completion of ground disturbance activities e.g.
earthworks and piling.
The remediation and groundwork’s contractors will be responsible for undertaking monitoring
during their stage of operations i.e. the remediation contractor is responsible for monitoring in
advance of the works and during remediation and the bulk excavations (Stage 1) and the
groundwork’s contractor is responsible for monitoring during piling works and upon completion of
penetrative activities (Stage 2).
The sampling locations are highlighted below in Table 3.2 and shown on Figure 3.1.
Table 3.2 - Long Term Monitoring Locations
Location 50mm Slotted Standpipe and Response Zone (m)
Response Zone Strata
River Terrace Deposits
RBH10 2.5 to 6.0 River Terrace Deposits
RWS19A 1.8 to 6.0 Alluvium & River Terrace Deposits
BH202S 1.0 to 8.0 River Terrace Deposits
BH203 1.0 to 6.0 River Terrace Deposits
BH205 1.0 to 6.0 River Terrace Deposits
Upper Chalk Deposits
RBH11A 6.0 to 11.0 Upper Chalk
RBH12 10.0 to 15.0 Upper Chalk
Surface Water Samples
JBRS/SW01 - Jubilee River
JBRS/SW02 - Jubilee River
Should these wells not be in serviceable condition or in the event that the contractor cannot
locate the wells or damages them during the course of works it will be contractor’s responsibility
to replace them with suitable installations at spatial intervals agreed with Ramboll.
Water samples shall be collected in accordance with relevant British Standards i.e. BS ISO 5567-
11 and BS ISO 6068-6.11 (British Standards Institute, 2009) and subject to analysis for the
determinands and contaminant thresholds detailed within Table A2.1 within Appendix 2.
Should contaminants be identified in groundwater or surface water in excess of the thresholds
detailed in Table A2.1 within Appendix 2 the contractor will follow the Unforeseen Contamination
Protocol outlined in Section 3.1.4.
3.1.7 Borehole Decommissioning
Aside from the wells that are required for long term monitoring as outlined above, prior to
undertaking any remedial works any monitoring wells installed within the Alluvium, River Terrace
Remediation Strategy
Deposits and Upper Chalk Formation are required to be decommissioned in general accordance
with the Environment Agency Document ‘Good Practice on Decommissioning Redundant
Boreholes and Wells’.
Wells not required for long term monitoring will be decommissioned during Stage 1 by the
Remediation Contractor.
Wells that were required for long term monitoring will be decommissioned upon completion of
penetrative activities during Stage 2 by the Groundwork’s Contractor.
All decommissioned boreholes must be effectively grout sealed over its full length.
The Remediation and Groundwork’s Contractors shall agree the Method Statement of the Works
with the Environment Agency prior to works starting.
A summary of wells installed within Jubilee Riverside South is provided below in Table 3.3 and
Figure 3.2.
Table 3.3 - Summary of installed monitoring wells
Hole ID 50mm Slotted Standpipe and Response Zone (m)
19mm Piezometer Tip Depth (m)
19mm Piezometer Tip Depth (m)
Response Zone Strata for 50mm Standpipe / 19mm Piezometer
RBH10 2.5 to 6.0 18.0 - River Terrace Deposits / Upper Chalk
RBH11A 6.0 to 11.0 - - Upper Chalk
RBH12 10.0 to 15.0 - - Upper Chalk
RWS19A 1.8 to 6.0 - - Alluvium & River Terrace Deposits
RWS20 0.5 to 1.5 - - Made Ground
RWS21 1.5 to 6.0 - - River Terrace Deposits
RWS22 0.5 to 1.5 - - Made Ground
RWS23 1.0 to 2.5 - - Made Ground & Alluvium
BH201 1.0 to 7.0 15.0 to 20.0 - River Terrace Deposits / Upper Chalk
BH202 1.0 to 8.0 15.0 to 20.0 30.0 to 42.5 River Terrace Deposits / Upper Chalk / Upper Chalk
BH203 1.0 to 6.0 - - River Terrace Deposits
BH204 1.0 to 6.0 - - River Terrace Deposits
BH205 1.0 to 6.0 - - River Terrace Deposits
WS201 1.0 to 4.0 - - River Terrace Deposits
WS203 1.0 to 4.0 - - Alluvium & River Terrace Deposits
WS204 1.0 to 4.0 - - Made Ground, Alluvium & River Terrace Deposits
The Remediation and Groundwork’s Contractors shall submit all details to Ramboll relating to the
decommissioning works for inclusion in the Verification Report.
3.1.8 Material Re-use
It is recommended that the re-use of any site-won material be undertaken using the CL:AIRE
Definition of Waste Industry Code of Practice (CL:AIRE, 2012).
In brief, under the Code of Practice, it will be necessary to ensure:
The use of this material is protective of human health and the environment;
Materials are suitable for use (either with or without treatment);
There is certainty materials will be used; and
Only the required quantity is used.
Remediation Strategy
The excavation, movement, tracking and placement of materials at the site should be undertaken
in accordance with a Materials Management Plan (MMP) for the site under the CL:AIRE Code of
Practice v2 (CL:AIRE, 2012) to be produced by the Contractor and signed-off by a Qualified
Person.
The MMP ensures that material excavation is correctly recorded, materials are tested against
relevant criteria (chemically and geotechnically) prior to placement in suitable locations. The MMP
details the tracking system used and relevant records to be kept in order that verification of
material movements can be undertaken at a later date.
Opportunities for the Jubilee Riverside site to become a receiver site for suitable materials from
other sites under the terms of the CL:AIRE Code of Practice v2 (CL:AIRE, 2012) should be sought
by the Contractor. Similarly, opportunities for the recovery of recycled aggregate should be
sought by the Contractor under the WRAP Protocol.
The Contractor is responsible for ensuring the suitability of materials placed as fill or within
private gardens or communal soft landscaped areas and ensuring appropriate testing is
undertaken. Any materials re-used within the clean capping system are required to be subject to
certification and analysis against the testing suites and frequencies detailed within Tables A3.1 of
Appendix 3 and Table A4.1 of Appendix 4, depending on end-use.
Material re-used within service corridors are required to be subject to certification and analysis
against the testing suites and frequencies detailed within Table A5.1 of Appendix 5.
Aside from the clean capping system and service corridor re-use thresholds (and any
geotechnical criteria) there are no further chemical suitably criteria.
3.1.9 Material Import
In addition to any geotechnical specification, all materials and imported aggregates used beneath
buildings, under hardstanding and within the construction of private gardens or communal soft
landscaped areas should be sourced from a reputable supplier and require certification to
determine the materials suitability for use on site prior to importation. Separate certification is
required for each type of material utilised.
All imported materials will need to be accompanied with chemical certification to demonstrate its
suitability for use on-site.
Any imported materials for use in private gardens and communal soft landscaped areas shall
comply with British Standard for Topsoil (British Standards Institute, 2007) and the chemical
criteria detailed in Section 3.4.1 and Table A3.1 of Appendix 3 and Table A4.1 of Appendix 4,
depending on the end-use. The imported soil will be free from asbestos, metals, plastics, wood,
glass, tarmac, paper and odours associated with contaminated soils.
Any imported materials for use within service corridors are required to be subject to certification
and analysis against the testing suites and frequencies detailed within Section 3.2.3 and Table
A5.1 of Appendix 5. The imported soil will be free from asbestos, metals, plastics, wood, glass,
tarmac, paper and odours associated with contaminated soils.
Imported aggregate for uses such as temporary surfacing to haul roads or set-up areas or piling
mat etc. will need to adhere to the same site controls as outlined above (with the exception of
virgin quarried materials). Where recycled aggregates are sourced the producer of the aggregate
must show the material has been fully recovered and is no longer a waste. To do this the
producer must follow the quality protocol for the production of aggregate from inert waste, as
outlined by WRAP.
Remediation Strategy
The Contractor will be responsible for retaining accurate records of all imported material in
accordance with the requirement Verification Plan outlined in Section 4.
3.1.10 Waste Disposal
Waste Regulation and Classification
It is understood that during the works there may be the requirement to remove surplus material
from site. All waste for off-site disposal is subject to the Waste Framework Directive.
Any materials that are considered to be waste will need to be managed in accordance with the
Environmental Permitting Regulations.
Soils that are surplus to requirements must be removed off-site to an appropriately licensed
facility under the Duty of Care Regulations by an appropriately licensed waste carrier.
A preliminary waste assessment was undertaken by Ramboll as part of the Ground Contamination
Interpretative Report (Ramboll, 2015). As part of this assessment indicative percentage waste
stream splits were provided based on the proportion of samples indicated be hazardous as part of
the Hazwaste assessment and/or asbestos analysis. These are summarised below:
Made Ground – 50% Hazardous / Non Hazardous and 50% Inert;
Alluvium – 100% Inert;
River Terrace Deposits - 10% Hazardous / Non Hazardous and 90% Inert; and
Upper Chalk – 100% Inert.
The areas of hazardous / non-hazardous soils are spread throughout the Area and are
predominantly correlated to the presence of asbestos containing materials but also heavy metals,
PAHs and TPH in isolated locations within the Made Ground.
It should be acknowledged that the ratios stated above are indicative only, and based on a
statistical interpretation of the HazwasteOnline assessment and asbestos analysis results alone.
As such, the classification of materials excavated on-site as part of any future earthworks may
not necessarily reflect the likely waste streams.
It will be necessary to fully determine the waste classification of this material prior to removal
from site which is likely to involve Waste Acceptance Criteria (WAC) testing. This should be
undertaken by the Contractor.
Pre-treatment of waste prior to disposal is a legal requirement. The requirements for pre-
treatment should also be discussed with landfill operators as it is possible that sorting can in
some cases fulfil this requirement.
In order to remove hazardous material from the site for disposal to landfill, it will be necessary to
register the site with the Environment Agency as a producer of hazardous waste. It will also be
necessary to adopt the requirements of the duty of care regulations, transporting waste materials
using an approved waste carrier and waste transfer notes.
General Requirements
All general waste shall be stored in appropriate containers, for example compactors, covered
skips, wheelie bins, drums, etc, in designated waste storage areas within the hoarded site area.
All containers must be clearly labelled.
Remediation Strategy
As a minimum, the following materials should be segregated and collected for recycling, where
suitable, if an appropriate re-use on site is not available:
Metal;
Hardcore, Aggregate, Broken Bricks;
Glass;
Plastic;
Timber;
Plasterboard.
The following documentation must be completed and held on site in a designated file for the
removal of waste:
Waste Transfer Notes (Controlled Waste) including EWC classification,
Consignment Notes (Hazardous Waste).
The Transfer Note must include a description and the quantity of the waste and details of the
waste collection contractor who must be licensed. Copies of the waste carriers registrations shall
be held on site. Sufficient information shall be provided to ensure that the waste disposal
operator is aware of the potential hazards of the substance. All documentation shall be retained
for a minimum of 2 years and be available for inspection.
Any hazardous wastes identified during the Works shall be removed by a specialist contractor and
appropriate measures made for its disposal in accordance with environmental legislation.
The removal of notifiable asbestos shall be carried out only by appropriately licensed and
experienced specialist contractors, and should occur under fully controlled conditions, in
accordance with legislation current at the time of the Works, plus any specific requirements of
Ramboll UK, South Bucks District Council and the Health and Safety Executive.
Any material destined for landfill disposal shall comply with all of the requirements in the Landfill
Directive, including appropriate Waste Acceptance Criteria testing of the subject material where
necessary.
3.1.11 Groundwater in Excavations
Groundwater has been encountered within several of the strata underlying the site including the
Made Ground, Alluvium, River Terrace Deposits and Upper Chalk. Perched water is present as
isolated occurrences/lenses within the Made Ground between 23.44 and 23.52mAOD with the
main groundwater body deeper within the Alluvium, River Terrace Deposits and shallow Upper
Chalk between 20.43 and 21.34 mAOD.
Whilst it is unlikely that earthworks will encounter the main groundwater body there is the
potential for perched waters to enter excavations which will require management.
Where perched waters are encountered during excavation works these are likely to require
purging.
In the event that groundwater is encountered during earthworks it may be necessary to obtain a
licence from the Environment Agency to undertake any de-watering activities should quantities of
water removed be greater than 20m3 per day.
Should either groundwater or perched water be identified as contaminated from visual/olfactory
assessment, waters should be stored in a controlled manner for subsequent testing and
characterisation prior to disposal in accordance with chemical criteria detailed in Table A2.1 of
Appendix 2.
Remediation Strategy
Should disposal to surface water or public sewer be deemed appropriate the contractor will be
responsible for any pre-treatment, additional sampling and monitoring. Any specific testing
requirements will need to be agreed with the receiving site, the Environment Agency for
discharges to surface water, or if to public sewer, with the local authority & water authority, prior
to any disposal / discharge taking place.
3.2 Specific Stage 1 Remedial Works
The Stage 1 remedial works involve site clearance, grubbing out of below ground structures and
earthworks to enable the formation of a development platform at a minimum level of
+24.70mAOD beneath buildings and garden / soft landscaped areas and +24.85mOD beneath
roads.
The contractor should consider the requirement for undertaking the Stage 1 works in 2 phases in
accordance with the Berkeley Homes Build Strategy Overlay Plan ref O.406.017B due to
environmental programme constraints associated with the demolition (by others) of the
warehouse structures in the south of the site.
3.2.1 Site Clearance and Underground Structures
Considering the age of the buildings at the site which are scheduled for demolition there is the
potential that asbestos containing materials are present within their construction. Prior to
demolition demolition/refurbishment surveys are required to be undertaken in affected buildings
so appropriate management plans and procedures can be put in place. While demolition is not
considered part of the remediation works. Notwithstanding this the demolition contractor should
adhere to the requirements of this strategy.
As part of site clearance the contractor will be responsible for the removal of vegetation
(including any invasive species) and the fly-tipped material stockpiles at the margins of the site.
Due to the historical industrial nature of the site there is the potential that the enabling works will
encounter subsurface structures, underground bulk storage tanks, foundations, ductwork,
interceptors, sumps and pipework etc. These structures have the potential to contain potentially
contaminative solids and liquids and where encountered they should be assessed by competent
persons prior to their penetration and removal. Should contaminative materials be present the
structures should be dealt with in accordance with the unforeseen contamination protocol
described in Section 3.1.4.
Any encountered structures should be removed with excavations over-dug by a minimum to
500mm to ensure the area is clear.
Should bulk storage tanks, sumps and interceptors etc. be encountered they should be emptied
of their contents, chased and sealed at the site boundary and removed from site under an
appropriate duty of care by qualified contractors / persons. Through removal principal and
residual sources of contamination would be removed.
Through removal of any remaining underground structures and any associated impacted soils it is
considered that any residual sources of contamination would be removed.
The contractor should give consideration to the re-use of processed site won concrete from relic
foundations and slabs under the quality protocol for the production of aggregate from inert waste
as outlined by WRAP. The contractor will be responsible for demonstrating that re-used materials
are compliant with the criteria outlined in Section 3.1.8.
Remediation Strategy
3.2.2 Asbestos Management Procedures
Asbestos containing materials have been identified within the site soils in the form of chrysotile
cement, bitumen and free fibres, amosite insulation and fibres and crocidolite free fibres with
concentrations ranging from <0.001%w/w and 0.033%w/w.
The contractor (in conjunction with specialist advice) should produce detailed method statements
and a management plan for the works based on the principals of material management and
retaining asbestos impacted soils on site where suitable for use with a view to minimising the
volume of impacted soils being disposed of from site. The contractors detailed method
statements should incorporate but not be limited to the following:
All works associated with asbestos containing materials will be undertaken by
appropriately trained operatives;
The removal of notifiable asbestos shall be carried out only by appropriately licensed and
experienced specialist contractors, and should occur under fully controlled conditions, in
accordance with legislation current at the time of the Works, plus any specific
requirements of Local Authority and the Health and Safety Executive;
All non-notifiable asbestos disturbing operations should be undertaken under semi-
controlled conditions with suitable dust suppression systems in place and using
appropriate PPE and RPE and decontamination systems;
Consideration should be given to reducing the asbestos content of soils through non-
destructive methods such as hand picking where identifiable fragments are present.
Reassurance monitoring should be undertaken during all asbestos disturbing activities
with reference to guidance and exposure limits published by the Health and Safety
Executive and the Control of Asbestos Regulations, 2013.
Should significant concentrations of asbestos containing materials be encountered
consideration should be given to works being undertaken in isolated areas under fully
controlled conditions with reassurance clearance testing undertaken following removal;
Personal human health monitoring should be undertaken on operatives involved in
asbestos related activities; and
Should boundary monitoring detect fibres, all activities associated with the impacted site
soils should be ceased until the source of fibres is detected and mitigation measures are
implemented.
The contractor will be responsible for notifying the Health and Safety Executive and obtaining
relevant licenses to undertake the works.
All works should be undertaken in accordance with legislation current at the time of works
including any requirements of the South Bucks District Council and the Health and Safety
Executive including those of the Control of Asbestos Regulations, 2013.
3.2.3 Service Corridors
As part of the Ground Contamination Interpretative Report (Ramboll, 2015) elevated
concentrations of petroleum hydrocarbons were identified that are likely to preclude the use of PE
pipes. In addition potentially unacceptable risks to human health (construction workers and
maintenance workers) were also identified associated with the presence of asbestos containing
soils within the Made Ground (chrysotile cement, bitumen and free fibres, amosite insulation and
fibres and crocidolite free fibres) with concentrations ranging from <0.001%w/w and
0.033%w/w.
Consequently, a series of clean service corridors are required to be installed with a finished
development ground level of a minimum of +24.85mOD with the base of the corridor at
approximately +23.0mOD. The service corridors should be excavated and a marker layer (teram
or similar) placed at the base and sides of the trench before backfilling with material that meets
the chemical criteria detailed in Table A5.1 of Appendix 5. Consideration should be given to the
Remediation Strategy
re-use of site won materials through over digging of corridors into natural ground materials
providing that the chemical criteria are satisfied. Materials used for service trench infill should be
analysed for the determinands detailed in Table A5.1 of Appendix 5 at a rate of 1 per 500m3.
This frequency should be confirmed with Ramboll prior to reuse/import of materials based on site
specific conditions.
3.3 Site Conditon Requirements upon Completion of Stage 1 Remedial Works
Upon completion of Stage 1 it is required that the remedial works and material management
procedures provide a development platform at a minimum level of +24.70mAOD beneath
buildings and garden / communal soft landscaped areas and +24.85mOD beneath roads to allow
for piling and construction to commence. Compliance with these levels is required to be
demonstrated through provision of as-built surveyed drawings.
It is required that all in ground contamination risks are remediated during Stage 1 and all
underground structures so that pending completion of the specific remedial works required in
Stage 2 outlined below, the site would be considered suitable for use. In particular upon
completion of Stage 1 there should not be any residual in-ground contamination risks remaining
to construction workers during Stage 2 or future maintenance workers. The contractor will be
required to certify/provide warranties to that effect.
3.4 Specific Stage 2 Remedial Works
3.4.1 Capping System
Based on the localised elevated concentrations of lead, nickel and PAHs above GACs and the
prevalent occurrence of asbestos (chrysotile cement, bitumen and free fibres, amosite insulation
and fibres and crocidolite free fibres) within the Made Ground, remedial measures for private
gardens and soft landscaped areas at ground level are required to protect end users.
Private Gardens
Within private gardens a clean cap of 850mm is required which will incorporate a hard “no dig”
demarcation layer of a minimum of 250mm thick to separate the clean cap from the residual
Made Ground.
Communal Soft Landscaped Areas
Within communal soft landscaped areas a clean cap of 500mm is required which will incorporate
a hard “no dig” demarcation layer of a minimum of 100mm thick to separate the clean cap from
the residual Made Ground.
General
Prior to the placement of the capping system, the underlying Made Ground should be compacted
to provide an appropriately flat/level formation to inhibit root penetration, burrowing and
instability.
Any materials (whether site won or imported) used within the clean cap construction of private
gardens or communal soft landscaped areas (including that for the cover system) shall be
analysed chemically and geotechnically to ensure it is suitable for use. This should be
undertaken prior to reusing/bringing any such material onto the site.
In private gardens and communal soft landscaped areas materials should be verified for chemical
suitability according to the following sampling frequency:
Remediation Strategy
Topsoil – 1 sample per 100m3
Subsoil – 1 sample per 250m3
Furthermore the suitability of materials used will be subject to onsite verification of chemical
suitability at a rate of 1 sample per 5 gardens and 1 sample per communal soft
landscaped area.
All materials for use in private gardens and communal soft landscaped areas shall conform to the
contaminant thresholds detailed in Table A3.1 in Appendix 3 or Table A4.1 of Appendix 4,
depending on end-use. All chemical testing shall be undertaken at an appropriately accredited
laboratory (UKAS and MCERTs).
Verification of the thickness of clean capping installed is required at a rate of 1 inspection per 5
gardens and 1 inspection per soft landscaped area and the contactor shall maintain
documentation to demonstrate that this has undertaken successfully e.g. daily records and
photographic evidence for each area of soft landscaping clearly identifying the installed depth.
Note. These frequencies should be confirmed with Ramboll prior to reuse/import of materials
based on site specific conditions.
Documentation on the source, quantity and testing results shall be retained onsite for inspection
and subsequent inclusion in the verification report. The Contractor shall retain records on the
location, depth of excavations and how/where any imported material is placed.
3.4.2 Foundation Works Risk Assessment
Where foundation works penetrate into the Principal Aquifers of the River Terrace Deposits and
Upper Chalk a foundation works risk assessment will be required to be submitted to the
Environment Agency prior to works commencing. The foundation works risk assessment should
be prepared with reference to the Environment Agency’s document ‘Piling and penetrative ground
improvement methods on land affected by contamination: Guidance on pollution prevention’ ref.
NC/99/73.
3.4.3 Ground Gas Protection Measures
A total of 6No ground gas monitoring visits have been undertaken on selected wells within the
area between 15th December 2014 and 13th March 2015. As part of monitoring the site was
classified as a Characteristic Situation 2 / NHBC Amber 1 due to elevated concentrations of
carbon dioxide and methane being consistently recorded in excess of the 5% v/v (9.9% v/v max)
and 1% v/v (4.8% v/v max) thresholds (respectively) indicated in CIRIA C665 (CIRIA, 2007).
As a result ground gas protection measures providing 3 points of protection in accordance with
BS8485 (British Standards Institute, 2007)are required. These points could be achieved through
the following:
Passive sub floor ventilation with a venting layer constructed of no fines gravel, geo-
composites, polystyrene void formers etc. (1 to 1.5 points – performance related);
Reinforced concrete cast in-situ suspended OR ground bearing slab with minimal service
penetrations and taped and sealed penetrations at joints (1.5 points); and
Proprietary gas resistant membrane installed to reasonable levels of workmanship in line with
current good practice under independent inspection (CQA) in accordance with CIRIA (CIRIA,
2014) (1 point).
Remediation Strategy
In addition the observed concentrations of carbon dioxide are above workplace exposure limits
for short and long term exposure. Consequently the contractor is required to employ suitable
mitigation measures during works in the event that temporary enclosed spaces are created e.g.
confined spaces entry systems and potential use of personal alarms.
3.5 Site Conditon Requirements upon Completion of Stage 2 Remedial Works
Upon completion of the Stage 2 Remedial Works the site should be considered suitable for use for
a residential development with private gardens and risks to end users from impacted Made
Ground and ground gas should be adequately mitigated.
Remediation Strategy
4. VERIFICATION PLAN
4.1 Environmental Watching Briefs
It is recommended that a part-time environmental watching brief is undertaken by Ramboll
throughout groundworks and remediation at the site to verify the implementation of the remedial
strategy e.g. installation of ground gas protection, ensuring that service corridors and clean
capping are of an appropriate thickness and chemical suitability etc. and to provide guidance in
the event that unexpected or gross contamination is encountered.
Where Ramboll is not in attendance on site, it is expected that the Contractor be vigilant and
undertake verification works in accordance with this Remediation Strategy.
4.2 Verification Plan
It is likely that any planning approval will require the production of a verification plan providing
details of the data that will be collected in order to demonstrate that the works set out within this
Remediation Strategy are complete and to identify any requirements for longer-term monitoring
of pollutant linkages, maintenance and arrangements for contingency action.
In order to meet these requirements, the Contractor shall be required to obtain all necessary
information for Ramboll to complete a Verification Report, including (but not limited) to the
following:
Records of the implementation of clean capping including demonstration of the chemical
compliance, thickness placed and the presence of the “no-dig” hard demarcation layer
(including photographs);
Records of the implementation of clean service corridors including demonstration of the
chemical compliance and the presence of the membrane (including photographs);
Quantities of material imported to site;
Chemical testing results and information on any re-used materials and plans showing where
this material has been used;
Chemical testing results and information on the source of any imported material and plans
showing where this material has been used;
Plan showing location of any additional samples obtained for testing along with any
delineation of materials and quantities;
Results of any additional chemical and WAC testing undertaken along with method of sample
collection and transportation to laboratory, laboratory quality assurance and accreditation;
Quantities of any material disposed off-site as waste classification and details of the receiving
site/s and copies of all Waste Transfer Notes;
Records of the borehole decommissioning works (including photographs);
Records of the baseline and long term water monitoring programme (during an upon
completion of penetrative activities) and compliance with the required standards;
Records of the asbestos management measures employed;
Records of the ground gas protection measures installed at the site (including inspection
records and photographs) and independent verification in accordance with CIRIA C735;
Details of any areas of unexpected contamination and the actions undertaken;
Details of any water removed from excavations and disposed off-site, including chemical
testing;
Details and demonstration of any relevant permits or exemptions required by the
Environment Agency for re-using material or importing material, particularly where there is
the potential for material being considered waste;
Details on any protection measures installed for contamination and monitoring (if applicable)
of such measures – in particular records will be required to confirm whether protection
measures were required for contaminants present in excavations or water supply pipes; and
Details of regular (monthly) dialogue and any additional liaison and agreements with
Regulators.
Remediation Strategy
On completion, the report should be submitted to the Local Planning Authority for approval. A
copy of the Verification Report will need to be retained on-site within the health and safety file. It
is of note that a Verification Report is also a requirement of the CL:AIRE Code of Practice.
It is recommended that periodic site audits are conducted by Ramboll to ensure adequate site
records and documentation is being maintained throughout the construction works. The purpose
of which will be to monitor whether sufficient data collection is being collected for the purposes of
completing the site Verification Report.
Remediation Strategy
REFERENCES
British Standards Institute. (2007). Code of Practice for the Characterization and Remediation
from Ground Gas in Affected Developments ref BS8485:2007.
British Standards Institute. (2007). Specification for Topsoil and Requirements for Use ref
BS3882:2007.
British Standards Institute. (2009). BS ISO 5667-11:2009 and BS 6068-6.11:2009. Water
Quality - Sampling. Part 11: Guidance on Sampling of Groundwaters.
CIRIA. (2007). CIRIA C665. Assessing Risks Posed by Hazardous Ground Gases to Buildings.
CIRIA. (2014). Good Practice on the testing and verification of protection systems for buildings
againts hazardous ground gases ref CIRIA C735.
CL:AIRE. (2012). The Definition of Waste Industry Code of Praction Version 2.
Ramboll. (2015). Geoenvironmental and Geotehnical Desk Study. Ref 61033137.E.DSA.I03.
Ramboll. (2015). Ground Contamination Interpretative Report ref 61033137.E.GCIR.I01.
Remediation Strategy
APPENDIX 1
FIGURES/DRAWINGS
60 Newman Street,
London, W1T3DA
T: 020 7462 5332
Project:
Mill Lane, Taplow - 61033137
Status: Information
Date:
19/03/14
Title:
Site Location Plan
Scale: NTS Drawn: TS Checked: ND
Figure 1
Rev: I00
Site Location
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.2Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Site BoundaryJubilee Riverside South
Project Number
61033137
Client
Ü
0 10 20 30 40 505Metres
Berkeley Homes (ThreeValleys) Ltd
I01
LegendJubilee Riverside South Boundary
Approximate Redline Boundary
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
>
A
>
>
>
A
A
A
>
>
>
>
>
A
A
D
A
D
D
D
D
D
D
D
D
D
D
>
>
>
>
>
7
7
7 7
7
7
7
77
S
S
S
S
S
S
S
S
S
S
?
?
?
?
?
?
?
R
RWS132
BH204
WS205
WS302WS203
BH201
BH203
BH301
WS301
WS201
WS202
WS206
WS204
BH205
BH202
TP615
BH602
2TP10
2TP9
2TP7
2TP8
2TP5
2TP6
2TP42TP3
2TP1
2TP2
RBH10
RBH11RBH11A
RBH12
RCPT07
RCPT08A
RCPT09RCPT09A
RCPT10
RCPT11
RCPT12
RCPT13RCTP13A
RTP01
RTP02
RTP03
RTP04
RTP05
RTP06
RTP07
RTP08
RTP19
RTP20
RWS16
RWS17
RWS19
RWS20
RWS21
RWS22
RWS23
SW02
SW05
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.3Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Exploratory Hole PlanJubilee Riverside South
Project Number
61033137
Client
Ü
0 10 20 30 40 505Metres
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
Key
Ramboll GI 2014/15> Borehole
7 CPT
) Stockpile Sample
R Surface Water Sample
S Trial Pit
? Windowless Sample
Provectus GI 2013A Borehole
< Monitoring Well
D Trial Pit
> Window Sample
CRA GI 2006A Borehole
< Monitoring Well
D Trial Pit
> Window Sample
Jubilee Riverside South Boundary
Approximate Redline Boundary
Warehouse
Gas Holder
Jubilee River
24.5m
MILL LANE
Warehouse
25.7m
Jubilee River
El Sub Sta
MILL LANE
24.0m 2TP40.9mMG77.3mg/kg
RTP030.7mMG53mg/kg
Scale
Date:
13/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure2.4Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Jubilee Riverside SouthArsenic Distribution(GAC 37mg/kg)
Project Number
61033137
Client
Ü
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
1:750 @A4
Arsenic< GACGAC - 2x GAC2x GAC - 5x GAC5x - 10x GAC>10x GACJubilee Riverside South Boundary
Warehouse
Gas Holder
Jubilee River
24.5m
MILL LANE
Warehouse
25.7m
Jubilee River
El Sub Sta
MILL LANE
Gas Meter
24.0m
2TP102.5mMG209mg/kg
2TP40.9mMG445mg/kg
2TP40.5m
MG498mg/kg
RBH11A0.9mMG230mg/kg
RBH120.6mMG240mg/kg
RTP030.7mMG2300mg/kg
RTP040.9mRTD210mg/kg
RTP070.8mMG220mg/kg
RWS190.5m
MG460mg/kg
Scale
Date:
13/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.5Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Jubilee Riverside SouthLead Distribution (GAC 200mg/kg)
Project Number
61033137
Client
Ü
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
1:750 @A4
Lead<GACGAC - 2x GAC2x GAC - 5x GAC5x GAC - 10x GAC>10x GACJubilee Riverside South Boundary
Warehouse
Gas Holder
Jubilee River
24.5m
MILL LANE
Warehouse
25.7m
Jubilee River
El Sub Sta
MILL LANE
24.0m
2TP40.5mMG3700mg/kg
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.6Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Jubilee Riverside SouthNickel Distribution(GAC 180mg/kg)
Project Number
61033137
Client
Ü
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
1:750 @A4
Nickel< GACGAC - 2x GAC2x GAC - 5x GAC5x GAC to 10x GAC> 10xGACJubilee Riverside South Boundary
Warehouse
Gas Holder
Jubilee River
24.5m
MILL LANE
Warehouse
25.7m
Jubilee River
El Sub Sta
MILL LANE
24.0m
RTP030.4mMG6.8mg/kg
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.7Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Jubilee Riverside SouthNaphthalene Distribution(GAC 5.6mg/kg)
Project Number
61033137
Client
Ü
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
1:750 @A4
Naphthalene< GACGAC - 2x GAC2x - 5x GAC5x - 10x GAC>10x GACJubilee Riverside South Boundary
Warehouse
Gas Holder
Jubilee River
24.5m
MILL LANE
Warehouse
25.7m
Jubilee River
El Sub Sta
MILL LANE
24.0m
RTP050.9mMG47mg/kg
RTP070.8mMG15mg/kg
RTP200.9mMG15mg/kg
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.8Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Jubilee Riverside South Benzo(a)anthracene Distribution (GAC 11mg/kg)
Project Number
61033137
Client
Ü
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
1:750 @A4
Benzo(a)anthracene<GACGAC - 2x GAC2x GAC - 5x GAC5x GAC - 10x GAC>10x GACJubilee Riverside South Boundary
Warehouse
Gas Holder
Jubilee River
24.5m
MILL LANE
Warehouse
25.7m
Jubilee River
El Sub Sta
MILL LANE
24.0m
RTP030.7mMG5.5mg/kg
RTP050.9mMG36mg/kg
RTP070.8mMG16mg/kg
RTP200.9mMG11mg/kg
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.9Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Jubilee Riverside SouthBenzo(a)pyrene Distribution (GAC 2.7mg/kg)
Project Number
61033137
Client
Ü
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
1:750 @A4
Benzo(a)pyrene<GACGAC - 2x GAC2x GAC - 5x GAC5x GAC - 10x GAC>10x GACJubilee Riverside South Boundary
Warehouse
Gas Holder
Jubilee River
24.5m
MILL LANE
Warehouse
25.7m
Jubilee River
El Sub Sta
MILL LANE
24.0m
RTP030.7mMG5.9mg/kg
RTP050.9mMG47mg/kg
RTP070.8mMG19mg/kg
RTP200.9mMG13mg/kg
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.10Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Jubilee Riverside SouthBenzo(b)flouranthene Distribution (GAC 3.3mg/kg)
Project Number
61033137
Client
Ü
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
1:750 @A4
Benzo(b)flouranthene< GACGAC - 2x GAC2x GAC - 5x GAC5x GAC -10x GAC> 10x GACJubilee Riverside South Boundary
Warehouse
Gas Holder
Jubilee River
24.5m
MILL LANE
Warehouse
25.7m
Jubilee River
El Sub Sta
MILL LANE
Stage
24.0m
RTP050.9mMG45mg/kg
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.11Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Jubilee Riverside SouthChrysene Distribution (GAC 22mg/kg)
Project Number
61033137
Client
Ü
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
1:750 @A4
Chrysene< GACGAC - 2x GAC2x GAC - 5x GAC5x GAC- 10x GAC10x GACJubilee Riverside South Boundary
Warehouse
Gas Holder
Jubilee River
24.5m
MILL LANE
Warehouse
25.7m
Jubilee River
El Sub Sta
MILL LANE
Stage
24.0m
RTP030.7mMG0.8mg/kg
RTP050.9mMG3.8mg/kg
RTP070.8mMG1.3mg/kg
RTP200.9mMG0.84mg/kg
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.12Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Jubilee Riverside SouthDibenzo(a,h)anthracene Distribution (GAC 0.28mg/kg)
Project Number
61033137
Client
Ü
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
1:750 @A4
Dibenzo(a,h)anthracene<GACGAC - 2x GAC2x GAC - 5x GAC5x GAC - 10x GAC>10x GACJubilee Riverside South Boundary
Warehouse
Gas Holder
Jubilee River
24.5m
MILL LANE
Warehouse
25.7m
Jubilee River
El Sub Sta
MILL LANE
24.0m
RTP050.9mMG560mg/kg
Scale
Date:
13/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.13Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Jubilee Riverside SouthTPH Aromatic C16-C21 Distribution (GAC 540mg/kg)
Project Number
61033137
Client
Ü
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
1:750 @A4
TPH Aromatic C16-C21< GACGAC - 2x GAC2x GAC - 5x GAC5x GAC - 10X GAC>10x GACJubilee Riverside South Boundary
Warehouse
Gas Holder
Jubilee River
24.5m
Weir
MILL LANE
Warehouse
25.7mEl Sub Sta
MILL LANE
StageLanding
Landing Stage
24.0m
Lodge
RTP040.45mMGChrysotile FibresAmosite Fibres
0.033%w/w
0.002%w/w
0.005%w/w
0.013%w/w
0.004%w/w
<0.001w/w
<0.001w/w
<0.001w/w <0.001w/w
<0.001w/w
<0.001w/w
2TP10.6mMGAmosite
2TP20.5mMGAmosite
2TP30.8mMGChrysotile 2TP4
0.9mMGChrysotile & Amosite
2TP60.7mMGAmosite
2TP70.6m
MGChrysotile &
Amosite2TP81mMGChrysotile
Chrysotile Fibres
RBH100.5m
MGChrysotile Fibres
RBH11A0.9mMGChrysotile Cement& BoardRBH12
0.4mMG
Chrysotile Fibres
RTP030.4m
MGChrysotile Ladding
& Amosite Fibres
RTP030.7mMGChrysotile Fibres
RTP051.35m
MGChrysotile
Cement
RWS190.5mMGChrysotile & Amosite Insultation
RWS201.3m
MGChrysotile &
Crocidolite Fibres
RWS200.8mMGAmosite Fibres
RWS220.4m
MGChrysotile Fibres
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.14Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Jubilee Riverside SouthAsbestos Distribution
Project Number
61033137
Client
Ü
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
1:750 @A4
Asbestos Containing MaterialsNon DetectDetectedJubilee Riverside South Boundary
Warehouse
Gas Holder
Jubilee River
24.5m
MILL LANE
Warehouse
25.7mEl Sub Sta
MILL LANE
Stage
Gas Meter
Landing
24.0m
RTP030.4mRTD11ug/l
RTP040.45mMG9.1ug/l
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.15Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Jubilee Riverside SouthLeachable Lead Distribution (GAC 7.2ug/l)
Project Number
61033137
Client
Ü
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
1:750 @A4
Leachable Lead<GACGAC - 2x GAC2x GAC - 5x GAC5x GAC - 10x GAC>10x GACJubilee Riverside South Boundary
Warehouse
Gas Holder
Jubilee River
24.5m
MILL LANE
Warehouse
25.7mEl Sub Sta
MILL LANE
Stage
Gas Meter
Landing
24.0m
RTP060.75mMG0.8ug/l
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 2.16Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Jubilee Riverside SouthLeachable Mercury Distribution (GAC 0.05ug/l)
Project Number
61033137
Client
Ü
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
1:750 @A4
Leachable Mercury<GACGAC - 5x GAC5x GAC - 10x GAC>10x GACJubilee Riverside South Boundary
A
A
A
>
>
>
?
U
U
BH203
BH205
BH202
RBH10
RBH11A
RBH12
RWS19
JBRS/SW01
JBRS/SW02
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 3.1Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Groundwater and Surface Water Monitoring LocationsJubilee Riverside South
Project Number
61033137
Client
Ü
0 10 20 30 40 505Metres
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
Key
Ramboll GI 2014/15> Borehole
? Windowless Sample
U Surface Water Sample
CRA GI 2006A Borehole
Jubilee Riverside South Boundary
Approximate Redline Boundary
>
?
>
>
?
?
>
>
>
>
>
?
?
?
?
?
BH204
WS203
BH201
BH203
WS201
WS204
BH205
BH202
RBH10
RBH11A
RBH12
RWS19
RWS20
RWS21
RWS22
RWS23
Scale
Date:
31/03/15 TSFigure No.
Tel: 020 7631 5291Fax 020 7323 4645
Figure 3.2Project Title
rev.
Prepared by
Figure Title
Mill Lane, Taplow
Monitoring Wells for DecommissioningJubilee Riverside South
Project Number
61033137
Client
Ü
0 10 20 30 40 505Metres
Berkeley Homes (ThreeValleys) Ltd
I01
Map reproduced from Ordnance Survey map data by permission of the Ordnance Survey. Licence No: 100048749
Key
Ramboll GI 2014/15> Borehole
? Windowless Sample
CRA GI 2006> Borehole
? Windowless Sample
Jubilee Riverside South Boundary
Approximate Redline Boundary