Project Update
July 9, 2012
![Page 2: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/2.jpg)
Roadway Projects
![Page 3: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/3.jpg)
• Survey work completed
• Project submitted to Austin as a CE
• Engineer started design and adjusted alignment of
proposed Cowart’s Creek bridges to avoid existing
pipelines
• Met with reps from Shadycrest
• Public meeting scheduled for Tuesday, August 7th
– Pearland HS Cafeteria 5:30-7:30 pm
Pearland Parkway
![Page 4: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/4.jpg)
• Schematic drawings started early April
• Submitted 100% plans and project manual to TxDOT for
Austin review June 25
• Current cost estimate $3.6 million
• $3.955 is target construction budget per AFA
ITS Project
![Page 5: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/5.jpg)
• Max Road & Fite Road
– RFQ advertised
– Submittals Due July 26th
TIP Projects Update
![Page 6: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/6.jpg)
• Miller Ranch Road
– Scheduled for end of summer completion
– Open in 2-3 weeks
• O’Day Road
– Scheduled to be open by end of September
• Old Alvin Road
– Scheduled for end of summer completion
– Behind schedule
TxDOT Off-System Bridge
Replacements
![Page 7: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/7.jpg)
TxDOT Off-System Bridge
Replacements – Miller Ranch Rd
![Page 8: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/8.jpg)
TxDOT Off-System Bridge
Replacements
![Page 9: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/9.jpg)
TxDOT Off-System Bridge
Replacements
![Page 10: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/10.jpg)
• Re-construction of Hawk intersection scheduled
for the week of July 9th
• Paving of southbound lanes scheduled to be
completed last week
• Traffic switch planned for late August
Cullen Parkway – Phase II
![Page 11: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/11.jpg)
Phase I Streetlights– Blackhawk to Mary’s Creek Bypass
• Foundation work schedule for this week
Dixie Farm Road
![Page 12: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/12.jpg)
Phase II – Mary’s Creek Bypass to SH35
• Stream gauge verified to be in good working order
• Reviewed area for progress on punch list; water valve items resolved, paver band repair started
• Discussed punch list progress with TxDOT
Dixie Farm Road
![Page 13: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/13.jpg)
• Medians and ROW were mowed and placed on a schedule during the one year maintenanceone year maintenance schedule
• New traffic signal installation should be complete and traffic signal operational by July 12th
• Block-outs will be poured once old signal poles are removed
Walnut Reconstruction
![Page 14: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/14.jpg)
• Majority of outstanding issues are resolved
Orange Street
![Page 15: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/15.jpg)
• Permit under review by TxDOT – Mid August
approval expected
• Reviewing 100% plans
• CM/CI contract on Council Agenda
Business Center Drive
![Page 16: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/16.jpg)
• Paving work continues for center and median lanes
• Trucking shortages delaying paving and asphalt removal
• Contractor is preparing to begin work on the storm trunk lines along the east side of the project
• FM518 intersection work continues
SH35 – BW8 to FM518
![Page 17: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/17.jpg)
![Page 18: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/18.jpg)
• Executed design contract with consultant
• Currently coordinating with BNSF
• Staff is working on agreement with BNSF to extend crossing panels to the north for the widened highway cross section
• Plans scheduled to be submitted to TxDOT & BNSF by the end of July
Quiet Zone Railroad Crossing
![Page 19: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/19.jpg)
Drainage Projects
![Page 20: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/20.jpg)
Diversion Ditch
• DD4 continued excavation of diversion ditch west of CR 143 as weather permits
• DD4 Bidding slope paving portion of work
Pump Station
• Notice to Proceed issued for June 28, 2012
Re-grading of Roadside Ditches
• Consultant continued working to resolve utility conflicts on Wayne Dr. and depth of cover issues on Holland
Cowart Creek Diversion
![Page 21: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/21.jpg)
• Executing contract for design
Westchester Sidewalk and Drainage
![Page 22: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/22.jpg)
Facility Projects
![Page 23: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/23.jpg)
• Architect selected
• Negotiating scope and fee for design
Westside Library
![Page 24: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/24.jpg)
Parks
![Page 25: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/25.jpg)
• Final equipment for mid block crossing installed
• Closing out project
Trail Connectivity
![Page 26: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/26.jpg)
• Accepted bids on July 3rd
• Base Bid is 17% above Engineer’s Estimate ($815K)
– Detention facility significantly under budget ($3.2M)
– Park project close to budget
• Major Factors - $729K
– Trucking costs (site clearing & excavation haul) -
$306K over estimate
– Paving - $162K over estimate
– Bio-swales - $134K over estimate
– Grinder Pump Station (electrical costs) - $127K over
estimate
Sports Complex at Max Road
![Page 27: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/27.jpg)
• Options:
– Move ahead and deduct some items (bioswales &
grinder pump station) from contract (-$300K savings)
– Re-bid with more time
– Re-bid with more time and/or separate bid packages
• Concerns
– Construction cost inflation
– Other major dirtwork projects in the area
– Time delay in park opening (3-8 months)
– Multiple bid packages (cost, time, & risk)
Sports Complex at Max Road
![Page 28: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/28.jpg)
• Met with project architect regarding restroom
building; approved concept
Sports Complex at Max Road
![Page 29: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/29.jpg)
• Staff continuing review of 60% plans
Dolores Fenwick Nature Center Phase II
![Page 30: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/30.jpg)
• Construction contract scheduled for Council
award on 7/9
• 120 days to Substantial Completion
South Gate & Cypress Village Parks
![Page 31: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/31.jpg)
• Staff working to develop a full scope of services
for multiple discipline contract with a design firm
Shadow Creek Ranch Park
![Page 32: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/32.jpg)
Utility Projects
![Page 33: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/33.jpg)
30” Waterline Interconnect
• Closing out project
City of Houston Interconnect
![Page 34: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/34.jpg)
City of Houston Interconnect
Alice Street Water Plant
• Completing punch list (flow meters)
• Turbine facility startup will occur once the rest of the plant punch list is completed
• Interconnect Agreement with CPE for turbine system completed
![Page 35: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/35.jpg)
• Foundation for thickener started
• Contractor on schedule with equipment
submittals and major equipment buy out
Longwood WWTP Rehabilitation
![Page 36: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/36.jpg)
• Contractor on schedule with equipment
submittals and major equipment buy out
• Thickener demolition will begin in July
Barry Rose WWTP Rehabilitation
![Page 37: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/37.jpg)
• Staff reviewing 60% PS&E package
• Revised alignment of sanitary along Hatfield south
of FM 518 to be located in right of way
• Scheduling Public Meeting for August
Hatfield Basin Trunk Sewer
![Page 38: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/38.jpg)
• Pre-con held and NTP issued on June 12th
Twin Creek Regional Lift Station
![Page 39: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/39.jpg)
Far Northwest Wastewater Treatment
Plant Improvements
• Staff reviewing draft Preliminary Engineering
Report
• Manufacturer reviewing work plan for repairs to
decanters
![Page 40: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/40.jpg)
Old Alvin 20” Waterline
• Circulated and reviewed 90% plans
![Page 41: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/41.jpg)
BellaVita Waterline Interconnect
• Harris County continuing engineering review
process
• Engineer submitted 90% plans
• Requested ‘no objection letter’ from Pipelines
![Page 42: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/42.jpg)
SH35 South Water Line
• Installed waterline from north end of project to
middle of Weatherford site
• North end tied to existing waterline
![Page 43: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/43.jpg)
• Attended monthly progress meeting
• Approximately 80% of the ROE requests have been signed and returned by the property owners
• Survey work complete
McHard Road 16” Water Line &
Roadway PER
![Page 44: July Project Update](https://reader034.vdocument.in/reader034/viewer/2022051519/568c4a321a28ab4916972916/html5/thumbnails/44.jpg)
Project Update
Questions/Comments