![Page 1: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/1.jpg)
I-5 Aurora Donald Interchange (Exit 278) Phase 1
Presented by: Anna Henson, ODOT Project Manager Ed Chamberland, DEA Project Manager
JUNE 2019
![Page 2: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/2.jpg)
2
“Why are we here?”
To seek your feedback on the design, evaluation, and recommendation of a preferred
alternative as part of the IAMP process.
![Page 3: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/3.jpg)
Project Schedule
3
![Page 4: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/4.jpg)
4
SPISINGLE POINT INTERCHANGE
![Page 5: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/5.jpg)
5
![Page 6: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/6.jpg)
6
DDI DIVERGING DIAMOND INTERCHANGE
DDI DIVERGING DIAMOND INTERCHANGE
![Page 7: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/7.jpg)
7
![Page 8: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/8.jpg)
Bents Road intersection
8
![Page 9: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/9.jpg)
Dolores Way intersection
9
![Page 10: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/10.jpg)
10
EVALUATION CRITERIA
![Page 11: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/11.jpg)
11
EVALUATION CRITERIA
Recommended Alternative
![Page 12: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/12.jpg)
ODOT Staff and Consultant Recommendation:
Diverging Diamond Interchange
12
![Page 13: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/13.jpg)
What’s Next? Public Engagement Roadshow!
• June 6:
– Mid-Willamette Valley Area Commission on Transportation
• June 11:
– Marion County Board of Commissioners
– Aurora City Council
– Donald City Council
• June 12:
– Local stakeholder engagement meeting (4-5pm)
– Public open house (6-8pm)
• June 13:
– ODOT Mobility Advisory Committee
13
![Page 15: k19062 i-5 aurora donald june presentation 060419 edits · stations, and truck parking. BPA North-south transmission line and towers located on west side of the freeway. Freeway Bridges](https://reader035.vdocument.in/reader035/viewer/2022081522/5f7018896c4013157c7ff20a/html5/thumbnails/15.jpg)
Project Area and Issues