keqi ctg pollution en report

24
1 A Peek into the Dirty Secrets of China’s Flagship Coal-to-Gas Model Project Table of Contents Datang Hexigten Project Introduction ...........................................................................................................3 The ‘Legend’ of Zero Wastewater Discharge .................................................................................................4 Suspected Illegal Informal Pond..................................................................................................................4 Manmade Waste Water Lakes ....................................................................................................................8 Air Pollution ..............................................................................................................................................11 Policy Recommendations: No Active Promotion until a Working Model is Established ..............................14 References ....................................................................................................................................................16 Appendix 1: Financial Analysis of Datang Coal Chemical ..............................................................................18 Appendix 2: 54 Coal-to-Gas Projects Completed, Under Construction or Planned ......................................21

Upload: china-greenpeace

Post on 06-Apr-2016

234 views

Category:

Documents


4 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Keqi ctg pollution en report

1

A Peek into the Dirty Secrets of China’s Flagship Coal-to-Gas Model Project

Table of Contents

Datang Hexigten Project Introduction ........................................................................................................... 3

The ‘Legend’ of Zero Wastewater Discharge ................................................................................................. 4

Suspected Illegal Informal Pond .................................................................................................................. 4

Manmade Waste Water Lakes .................................................................................................................... 8

Air Pollution ..............................................................................................................................................11

Policy Recommendations: No Active Promotion until a Working Model is Established ..............................14

References ....................................................................................................................................................16

Appendix 1: Financial Analysis of Datang Coal Chemical ..............................................................................18

Appendix 2: 54 Coal-to-Gas Projects Completed, Under Construction or Planned ......................................21

Page 2: Keqi ctg pollution en report

2

In an effort to deal with air pollution and make up for insufficient natural gas supplies in the

east, China has been pushing a coal-to-gas program that has been fraught with debate

because of the pollution and greenhouse gas emissions that result from the production

process. According to statistics compiled by Greenpeace, as of October 2014 there were 54

coal-to-gas projects at different stages of development nationwide (See Appendix 2). The

total production volume of these projects currently stands at 240.8 billion cubic meters.

Over 80% of these projects are in China’s arid northwest.

However, since two model projects, namely the Datang Hexigten Coal-to-Gas Project and the

Kingho Coal-to-Gas Project in Ili, went into production late last year, they have been

consistently troubled by technical and environmental issues, including a reported accident in

January 2014 that killed two people as well as air pollution that has caused local residents to

lodge official complaints (Hexigten EPB, 2014; Zhang, 2014).

In order to give an initial assessment of the actual environmental performance of coal-to-gas

model projects, a team from Greenpeace East Asia (hereafter ‘Greenpeace’) carried out an

on-site survey of the Datang Hexigten Coal-to-Gas Project for a total of seven times between

April and October 2014. During two of these visits, the team took test samples of drinking

water1, water and sediment collected from an informal pond, as well as wastewater

collected in the vicinity of the plant. Greenpeace also interviewed nomadic families living

around the plant to understand how their lives have changed. Additionally, the team also

examined open flue gas emissions data available from government websites2.

Greenpeace’s survey found that wastewater treatment did not meet with the project’s

claimed ‘zero wastewater discharge’3 policy and even official data showed that flue gas

emissions had exceeded standard levels for extended periods of time4. The survey also

showed local residents’ strong opposition to the project. Based on the findings, Greenpeace

is concerned that, as one of the only two projects currently in operation in China’s

coal-to-gas sector which reflects the general technological levels across the sector, Datang

Hexigten project showcases the additional environmental and social challenges facing the

sector whose negative carbon implication is already a much debated issue (Gong & Li, 2014;

Yang & Jackson, 2013). Greenpeace strongly recommends the Chinese government seriously

1 Testing results of the drinking water samples are not discussed in this report. Based on the analytical results by both

Greenpeace Research Laboratories and an accredited independent third-party testing facility in China, concentration of metals and metalloids in most or all of the samples were below limits of detection and few organic compounds were identified overall. For details, please see http://www.greenpeace.org/eastasia/publications/reports/climate-energy/2014/keqi-ctg-pollution-en-report/ 2 See the Platform for the Self-monitoring and Information Disclosure by the Enterprises subject to Intensive Monitoring

and Control of the State in Inner Mongolia (http://nmgepb.gov.cn:8088/enterprisemonitor/webpage!indexPage.action); supervisory monitoring data disclosed by Chifeng Municipal Environmental Protection Bureau (http://www.cfhb.gov.cn/sjzx/hjsj/gkyjpsj/jdxjcsj/index.html). In order to tackle pollutions at sources, the Chinese government has created a list of key state monitored and controlled enterprises and put in place an emission data monitoring and information disclosure system where both environmental agencies in different levels and the enterprises are required to monitor and disclose emission data. 3 We cannot find any open sources about the project’s own definition of “zero wastewater discharge”. Anyway, there is a

good general overview of zero wastewater discharge in China written by China Water Risk http://chinawaterrisk.org/resources/analysis-reviews/zero-liquid-discharge-a-real-solution/. 4 Please see the section of Air Pollution below for details.

Page 3: Keqi ctg pollution en report

3

reconsider the development of coal-to-gas projects.

Datang Hexigten Project Introduction

The Datang Hexigten Coal-to-Gas Project is located in Hexigten near the city of Chifeng in the

Inner Mongolia Autonomous Region, only 15km from the Dalai Nur (“Dalinuoer” in

Mandarin) Nature Preserve, a national-level preserve established to protect a unique

ecosystem of lakes, wetlands, grasslands and forests that support many rare species of bird

(Inner Mongolia Dalinuoer Nature Reserve Managing Office, n.d.)

The synthetic natural gas produced by this project, which requires 40 million cubic meters of

water every year, is mostly transported by pipeline to Beijing and once fully completed the

project is expected to fulfill 1/4 of Beijing’s natural gas needs (Chifeng Municipal Water

Resources Bureau, n.d.; Wang, 2014 ).

The original scale of project investment was 22.6 billion RMB, but due to continual technical

adjustments and environmental considerations in actual implementation, total investment

has already surpassed 33 billion RMB and looks like it will continue to increase (Guo, 2014).

Comparatively, many coal chemical businesses, including the Datang coal-to-gas project,

continue to operate at a loss (See Appendix 1).

Figure 1: Relative Locations Surrounding the Coal-to-Gas Plant

Note: Based on Google Earth, Image © 2014 Digital Globe © 2014 Mapabc.com

① Coal-to-Gas Plant, ② Xilin Gol Coal Mine (coal source), ③ Dashimen Reservoir on the Xar

Moron River (water source), ④ Dalai Nur National Nature Preserve, ⑤ Waste Water Evaporation

Pools

Page 4: Keqi ctg pollution en report

4

The ‘Legend’ of Zero Wastewater Discharge

Datang has repeatedly said in promotional materials that this project has achieved ‘zero

wastewater discharge’ and in an interview with China Chemical Industry News on October

16th, the Director of Environmental Security for the Datang Energy and Chemical Company,

Mr. Hao Jun, said that ‘there is no drainage outlet at the Hexigten project and we have no

other option but to ensure zero discharge.’ (Chen, 2014)

Suspected Illegal Informal Pond

However, Greenpeace’s survey team found an informal pond in sandy soil near the Datang

Hexigten facility filled with contaminated water containing a number of hazardous

substances.

The rectangular informal pond is located 200 meters to the northwest outside the plant area

and measures 68m x 56m x 5m5 with no visible anti-seepage measures as seen on the edge

of the formal evaporation pond discussed below. The water in the pond was an inky black

with black powder-like solid waste floating on the top. There was also a very pungent odor

surrounding the pool. From the pit, a 150cm-diamter pipe extends from the direction of the

plant. There are no other active industrial projects within a radius of several kilometers in

the area of the plant.

Analysis of satellite images show that digging on the informal pond began before November

2010, but images did not show any water accumulation until May 3rd 2013. The water

accumulation in the pit was confirmed by site visits and satellite images from later dates.

5 The figures of 68m and 56m are based on GIS analysis by Greenpeace. The depth of 5m was estimated by Greenpeace

survey team during the field visits.

Page 5: Keqi ctg pollution en report

5

Figure 2: Location of the Informal Pond outside Western Wall of Plant

Note: Based on Google Earth, Image © 2014 Digital Globe © 2014 Mapabc.com

Figure 3: Satellite Image of the Informal Pond, Taken on November 6th, 2010

Page 6: Keqi ctg pollution en report

6

Figure 4: March 3rd, 2013 was the first time water was observed in the informal pond–

using LandSat8 satellites

Local herders had previously reported the informal pond to local environmental authorities

and on July 5th 2014, the Hexigten Environmental Protection Bureau (EPB) released a public

response that described the informal pond as a ‘initial rainwater runoff from a drainage pipe

to the west of the plant’, adding that ‘all runoff water has been retrieved by the plant and

sediment has been fully cleaned.’ (Hexigten EPB, 2014)

However, on three separate visits by the Greenpeace survey team on August 2nd, August 8th

and August 30th 2014, it was found that the informal pond was still filled with accumulated

water and there was no sign of any cleanup efforts. Moreover, the water level observed in

the visit on August 30th had risen by about one meter compared to the visit on August 8th.

Greenpeace also carried out sampling and chemical testing of the water and sediment in the

informal pond. Results showed that this turned out to be contaminated water that

contained heavy metals and hazardous organic pollutants, many of which could be from

coal-relevant production.

On August 2nd and 30th, Greenpeace workers collected two separate batches of water and

sediment samples from the informal pond using scientific methods, recording the entire

process. While the batch obtained on August 2nd was delivered the Greenpeace Research

laboratories, based at the University of Exeter in the UK, the batch on August 30th was sent

Page 7: Keqi ctg pollution en report

7

to an accredited national-level third party independent testing facility in China6.

Results from the third party testing facility show a range of PAHs including benzo[a]pyrene.

The concentration of benzo[a]pyrene was 41.5ng/L, 0.38 times higher than national

standard7. Other PAHs found in tests included phenanthrene, acenaphthene, fluorene,

pyrene, chrysene, fluoranthene, benz[a]anthracene, benz[b]fluoranthene,

indeno[1,2,3-cd]pyrene, dibenz[a,h] anthracene and benzo[g,h,i]perylene8.

Qualitative screening of the two waste water samples sent to Greenpeace Research

Laboratories for testing showed that both contained organic compounds with similarly

complex compositions. Compared with waste water samples that were taken far from the

discharge pipe (CN140015), samples taken nearer to the discharge pipe (CN140016)

contained more complex compounds. A total of 15 volatile organic compounds (VOCs) were

isolated, 13 of which could be reliably identified (i.e. compounds identified to better than 90%

match to mass spectrum libraries) as well as 44 semi-volatile organic compounds (SVOCs)

being isolated, 25 of which could be reliably identified, including multiple phenolic

compounds (e.g. cresol, xylenol, etc.) as well as phenanthrene, fluorene, fluoranthene and

several other PAH derivatives.

In addition, analysis from both sides9 indicated that sediment from the informal pond

contained similar heavy metals and a series of organic compounds including PAHs as found

in the wastewater samples.

Ultimately, regardless of the source of wastewater samples, the composition of the

contaminated water from the informal pond has caused a certain degree of hazardous

substances to accumulate in the sediment of the informal pond.

Based on the above findings, Greenpeace challenges the Datang Hexigten Coal-to Gas

Project to confirm whether or not the informal pond has been used as a seepage pit to

dispose of contaminated water with hazardous substances. According to China’s Water

Pollution Prevention and Control Law (2008)10, Amendment (VIII) to the Criminal Law

6 As to the detailed description of sample collection and analysis, please see

http://www.greenpeace.org/eastasia/publications/reports/climate-energy/2014/keqi-ctg-pollution-en-report/ 7 Here national standard refers to the Integrated Wastewater Discharge Standard (GB8978-1996). According to the

standard, benzo[a]pyrene is classified as Category One Pollutant, which is defined regardless of industry, discharge method or the function of the water. All samples are taken from discharge points outside factory workrooms or treatment facilities with discharge concentrations reaching no more than 0.00003mg/L, i.e. 30 ng/L. 8 The range of PAHs found here are not included in the Integrated Wastewater Discharge Standard (GB8978-1996) with the

exception of benzo[a]pyrene. However, due to the hazardous nature of these compounds, both the US EPA and EU have listed a number of PAHs as the priority substance to regulate. For details, please refer to US EPA, Priority Chemicals http://www.epa.gov/osw/hazard/wastemin/priority.htm; EU Directive 2000/60/EC. DECISION No 2455/2001/EC OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 20 November 2001. 9 Please seehttp://www.greenpeace.org/eastasia/publications/reports/climate-energy/2014/keqi-ctg-pollution-en-report/.

And please note that the testing results of Greenpeace Research Laboratories and the third-party testing facility are not directly comparable due to different methods employed in the analyses and that the sediment samples were not collected at the same time. 10

See http://www.gov.cn/flfg/2008-02/28/content_905050.htm.

Page 8: Keqi ctg pollution en report

8

(2011)11 and Environmental Protection Law (2014 revision)12, the use of seepage pits to

dispose of water with hazardous contaminants is explicitly banned and those who violate

can face penalties or even criminal charges in severe cases.

Manmade Waste Water Lakes

Greenpeace also found that a formal evaporation pond located 6km to the southeast of the

Datang Hexigten goal-to-gas plant had become a long-term holding pool for waste water.

According to the facility’s introduction and its own environmental impact report,

evaporation pools should be used for storing waste water only in the case of an emergency,

stating that “waste water may be temporarily be released into an evaporation pool for waste

water that has not met with reuse standards during testing periods or in the case of faults in

the waste water treatment process” (Datang Hexigten Coal-to-Gas Project, n.d.; Datang

International Power Generation Co., Ltd & Wuhuan Science and Technology Co., Ltd, 2008).

This clearly states that the evaporation pond is to be used only temporarily in the case of

emergencies and not as a place for the longer-term storage of industrial waste water.

During site surveys, the Greenpeace team found that the total area of the evaporation pond

covered an area of 1.1 square km. Though construction had not even been completed, in the

course of less than one year there were two evaporation pools nearly 5 meters deep13 that

had been filled with production waste water. Workers from Datang Chemical said that the

evaporation pools were currently at 70% capacity and that after phase two and three of the

project began production, even larger evaporation pools would be needed (Duan, 2014).

There was also a clear pungent odor surrounding the evaporation pools.

On August 30th 2014, the Greenpeace team collected waste water samples from this

evaporation pond, recording the entire process. All samples were collected using scientific

methods, and were also sent to a nationally accredited independent third party testing

facility as well as the Greenpeace Research Laboratories, based at the University of Exeter in

the UK for analysis.

Test results from the third party testing facility show that the waste water in the evaporation

pools contained similar heavy metals and organic compounds as were found in the waste

water taken from the informal pond, reaching levels that were several times (in the case of

some PAHs, hundreds of times) greater than latter. Meanwhile, current national standard,

i.e., the Integrated Wastewater Discharge Standard (GB 8978-1996)14, are not applicable for

evaporation ponds. However, as a point of reference, levels for volatile phenols, phenol,

benzo[a]pyrene and chemical oxygen demand (COD) in the sample were several times (up to

181 times for benzo[a]pyrene) above the national standards set for waste water discharges

11

See http://www.gov.cn/flfg/2011-02/25/content_1857448.htm. 12

See http://www.nnhb.gov.cn/web/201404/25/80012.htm. 13

Estimated by Greenpeace survey team in the field visits. 14

See http://kjs.mep.gov.cn/hjbhbz/bzwb/shjbh/swrwpfbz/199801/t19980101_66568.htm

Page 9: Keqi ctg pollution en report

9

(where they apply).

Results from Greenpeace Research Laboratories also showed that the waste water from the

evaporation pond contained a total of 154 different kinds of VOCs, 41 of which could be

reliably identified (i.e. compounds identified to better than 90% match to mass spectrum

libraries) as well as 209 SVOCs, 47 of which could be reliably identified. Compared with the

water samples taken from the informal pond, the waste water samples from this location

contained more types of phenol derivatives. Also found were a series of hazardous

pollutants including PAH derivatives, benzene derivatives (particularly alkylated benzenes),

substituted quinolones and pyridines, many of which are common to the highly hazardous

wastes arising from coal gasification operations (Gai, Jiang, Qian, & Kraslawski, 2008; Wang,

et al., 2011; Xu, Han, Hou, Jia, & Zhao, 2014).

Table 1: VOCs identified in wastewater sample of the formal evaporation pond

No. of chemicals isolated VOCs (154)

Compounds identified to better than 90%

Phenol & derivatives Other compounds

Phenol

Methylphenol

Ethylphenol

Azido‐phenol Dimethylphenol (3

isomers)

(E)‐3‐Phenyl‐2‐butenal

1‐(2‐Ethylphenyl)ethan‐1‐one

1‐Methyl‐2,3‐dihydroindene

2‐Cyclopenten‐1‐one, dimethyl‐

Methylbutane

Propanone

Benzaldehyde

Benzenemethanol

Toluene

Decane

Dodecane

Tetramethylhexadecane

Diisopropyl ether

Isopropyl(6‐phenylhex‐5‐ynyl)amine

N‐Benzyl‐3‐pyrroline‐N‐oxide

N‐Benzyl‐N‐(phenylethyl)amine

1,3,5‐Trimethyl‐1H‐Pyrazole

Dimethylthiophene

trans‐3‐Methoxy‐5‐(4‐methoxyphenyl)‐1,2,4‐

trioxolane

Tetrahydro‐2‐methyl‐2‐furancarboxaldehyde

5‐Phenyl‐2‐tetrahydrofurylmethyl 2'‐pyridyl sulfide

Benzene derivatives

Tetramethylbenzene

Difluorobenzene

Dimethylbenzene

1‐Methyl‐2‐(1‐propynyl)benzene

Propenylbenzene

4‐Ethenyl‐1,2‐dimethylbenzene

Pyridines derivatives

Methylpyridine

Dimethylpyridine

Trimethylpyridine

2‐Pyridinecarboxylic acid

Naphthalene & derivatives

Naphthalene

1‐Methylnaphthalene

2‐Methylnaphthalene

Note: Results from the Greenpeace Research Laboratories.

Page 10: Keqi ctg pollution en report

10

Table 2: SVOCs identified in wastewater sample of the formal evaporation pond

No. of chemicals isolated SVOCs (209)

Compounds identified to better than 90%

Phenol & derivatives PAHs & derivatives

Phenol

Methylphenol (2 isomers)

Dimethylphenol (3 isomers)

Trimethylphenol (2 isomers)

Ethylphenol

Diethylphenol (2 isomers)

Ethylmethylphenol (3 isomers)

Propylphenol

Methoxyphenol

Methylpropylphenol

9H‐Fluorene

Hydroxymethylnaphthalene

9H‐Fluorenol (2 isomers)

Other compounds

Methyl‐4‐indanol

Ethylanisole

1,1'‐Biphenylol (2 isomers)

Ethynylbiphenyl

2‐Cyclohexene‐1‐carbonitrile

2,3‐Dihydro‐2‐methylbenzo[b]thiophene

3,4,5,6,7,8‐Hexahydro‐(2H)‐

naphthalenone

Allyl toluenesulfonate

10‐Azatricyclo[4.3.1.0(1,6)]deca‐2,4‐diene

Hydroxyphthalide

2,3‐Dihydro‐1H‐inden‐5‐ol

(4‐Fluorophenyl)butynone

Benzo[d]isothiazole

(E)‐2‐(2H(1)‐4‐Methoxyphenylethene

Methoxyphenylacetone

1‐Methylene‐1H‐indene

Dimethyl‐3‐phenylaziridine

Pyridines derivatives

Phenylpyridine

9H‐Indeno[2,1‐b]pyridine

3,5‐Diacetyl‐1H‐pyrazole

5‐(Phenylmethyl)‐2‐pyridinamine

Quinoline derivatives

Isoquinoline

Methylisoquinoline

Methylquinoline

7,8‐Dihydro‐6‐methyl‐6H‐pyrrolo[2,3‐

g]quinoline

Note: Results from the Greenpeace Research Laboratories.

Figure 5: Total Ion Chromatograph for the sample collected from the formal evaporation

pond (SVOCs)

Note: Results from the Greenpeace Research Laboratories.

6 . 0 0 8 . 0 0 1 0 . 0 0 1 2 . 0 0 1 4 . 0 0 1 6 . 0 0 1 8 . 0 0 2 0 . 0 0 2 2 . 0 0 2 4 . 0 0

1 0 0 0 0 0 0

2 0 0 0 0 0 0

3 0 0 0 0 0 0

4 0 0 0 0 0 0

5 0 0 0 0 0 0

6 0 0 0 0 0 0

7 0 0 0 0 0 0

8 0 0 0 0 0 0

9 0 0 0 0 0 0

1 e + 0 7

1 . 1 e + 0 7

1 . 2 e + 0 7

1 . 3 e + 0 7

1 . 4 e + 0 7

1 . 5 e + 0 7

1 . 6 e + 0 7

1 . 7 e + 0 7

1 . 8 e + 0 7

1 . 9 e + 0 7

2 e + 0 7

2 . 1 e + 0 7

2 . 2 e + 0 7

2 . 3 e + 0 7

T im e - - >

A b u n d a n c e

T I C : S 1 4 1 0 0 8 0 1 . D \ d a t a . m s

Page 11: Keqi ctg pollution en report

11

Wastewater discharge standards used by the coal chemical industry are currently the

Integrated Wastewater Discharge Standard (GB 8978-1996) released in 1996. This covers

only a limited number of substances (39 indices are suitable for all industries) and permitted

levels are high. The test results from the Datang project show that these standards are not

suitable for today’s coal chemical industry and are in urgent need of being updated.

The way in which wastewater is being dealt with at the Datang facility shows that the ‘zero

wastewater discharge’ policy is merely a myth used in promotion and that this leading

‘model project’ in China’s coal chemical industry has serious problems that are not easily

resolved.

Air Pollution

Most of the synthetic natural gas products made by the Datang Hexigten project are used by

Beijing, which is already plagued by serious air pollution. However, according to local

residents Greenpeace interviewed, the exhaust produced by this ‘model project’ has also

created extremely serious air pollution for nearby residents. Herders living in Darihanwula

Sumu told Greenpeace that they have been plagued by air pollution since test production

began in December 2013.

In on-site interviews conducted by Greenpeace, most residents reacted strongly, saying that

as long as they were downwind from the Datang facility, there was a strong smell and they

couldn’t sleep at night. Some even said that they felt dizzy. Some pointed out that their

livestock have also been adversely affected with cows and horses gasping for air and

ultimately dying, with both ‘number and quality’ declining.

The air pollution problem has been recognized by the local government. In a response to a

complaint issued by the Hexigten EPB on July 3rd, it was admitted that the Datang coal-to-gas

project has produced a ‘strong odor in the test production phase’ (Hexigten EPB, 2014).

The environmental impact report for the Datang coal-to-gas project at Hexigten indicates

that there are two main sources of exhaust (Datang International Power Generation Co., Ltd

& Wuhuan Science and Technology Co., Ltd, 2008). One is the chemical portion, including

procedures like pressurized gasification, low-temperature methanol wash, coal gas wash and

separation, cooling, coal storage facilities and wastewater treatment, which emit organic

and inorganic pollutants such as carbon monoxide, sulfur dioxide, hydrogen sulfide,

ammonia gas, phenols, benzo[a]pyrene and particular matter.15 Another portion of the

process is the power generation facility, the typical pollutants of which are sulfur dioxide,

nitrogen dioxide and particulate matter.16

15

These emissions should comply with Malodorous Pollution Emissions Standards (GB14554-93) issued in 1994 and General Air Pollution Emissions Standards (GB16297-1996) implemented in 1997. 16

Thermal Power Plant Pollution Emissions Standards (GB13223-2003) implemented in 2004 applied to emission prior to July 2014 and afterward the new standards (GB13223-2011) that went into effect on July 1, 2014 applies.

Page 12: Keqi ctg pollution en report

12

In addition, based on the multiple VOCs that were found in waste water samples from the

informal pond and the evaporation pond, it is possible that volatile pollutants given off by

the pools could possibly contribute to air pollution in the surrounding areas.

However, open emission data available at government websites17 show that only emissions

from the thermal power plant are monitored, not inclusive of the other two main pollution

sources, the chemical plant and the wastewater treatment unit. However, even the limited

data from the thermal power plant indicate that levels of nitrogen oxide have been above

permitted levels for extended periods of time.

Greenpeace used open flue gas emission data disclosed at government websites18, including

both company self-monitoring and government monitoring data to analyze daily average

data for the Datang coal-to-gas project.

Based on the emission data monitored by the Datang Hexigten project itself, it was found

that in the 296 days between January 1st and October 23rd of this year, monitoring data for

facility was unavailable for the periods between April 5th-June 10th and August

26th-September 5th.

Data show that in the 203 monitored days, daily average nitrogen oxide levels exceeded

permitted levels19 for 196 days, constituting an extended period, and the highest

percentage above national standards were 303% (i.e. the daily average level of 805mg/m³ at

the Monitoring Site 2 on July 16th 2014 compared to the permitted level of 200mg/m³).

Particulate matter exceeded permitted levels for 23 days and at the highest percentage

above national standards were 208%. Sulfur dioxide exceeded permitted levels for 21 days

and the highest percentage above national standards was 632%.

On the other hand, the emission data monitored by the Chifeng Municipal Environmental

Protection Bureau (EPB) also indicated that daily average nitrogen oxide levels exceeded

permitted levels in the first three quarters of 2014.

However, despite compliance failures there is no denitration equipment installed in the plant,

as pointed out in a supervisory monitoring report on the Datang project’s emission data in

the third quarter of 2014 by the Chifeng Municipal EPB20.

17

See the footnote 2. 18

See the footnote 2. 19

Here Thermal Power Plant Pollution Emissions Standards (GB13223-2003) & (GB13223-2011) are applied. The limits are set for maximum allowed concentrations, not designated for daily average. 20

See http://www.cfhb.gov.cn/sjzx/hjsj/gkyjpsj/jdxjcsj/201408/P020140811631668800323.pdf

Page 13: Keqi ctg pollution en report

13

Figure 6: Daily Average Concentrations of Nitrogen Oxide (Monitoring Site 1)

Note: Prepared by Greenpeace based on data from Platform for the Self-monitoring and Information

Disclosure by the Enterprises subject to Intensive Monitoring and Control of the State in Inner Mongolia21

Figure 7: Daily Average Concentrations of Nitrogen Oxide (Monitoring Site 2)

Note: Prepared by Greenpeace based on data from Platform for the Self-monitoring and Information

Disclosure by the Enterprises subject to Intensive Monitoring and Control of the State in Inner Mongolia

Table 3: Above-Standard Nitrogen Oxide Levels at the Datang Coal-to-Gas Project

Note: Prepared by Greenpeace based on data from Chifeng Municipal EPB22.

21

See http://nmgepb.gov.cn:8088/enterprisemonitor/webpage!indexPage.action 22

See http://www.cfhb.gov.cn/sjzx/hjsj/gkyjpsj/jdxjcsj/index.html.

Nitrogen

Oxide

National Standard

(mg/m³) No. of days

above

Standard

(mg/m³)

Highest Recorded

Level ( mg/m³)

Highest % above

Standard Before July 1st

2014

After July 1st

2014

450 200 196

912 303

February 24th,

Monitoring Site 1

July 16th,

Monitoring Site 2

Page 14: Keqi ctg pollution en report

14

Policy Recommendations: No Active Promotion until a Working Model is

Established

The problem of concentrated greenhouse gas emissions from coal-to-gas technology has

received a great deal of attention and the issues of air pollution and waste water disposal at

Datang’s Hexigten project, a flagship model program in China’s coal-to-gas development

efforts, must not be overlooked (Gong & Li, 2014; Yang & Jackson, 2013). This issue warrants

close attention by the National Energy Administration and Ministry of Environmental

Protection. The truth is that Datang’s Hexigten Qi project and Kingho’s Yili project, two of

China’s four coal-to-gas model projects begun during the 11th Five Year Plan, still have many

problems that are not yet resolved. While construction has yet to begin on the other two

projects, production volume at the two operational projects remains far below design

specifications. Considering all this together, it would seem that China’s coal-to-gas industry

still lacks a successful model to follow.

The haze that shrouds nearly much of China should be a warning that the old path of

‘pollute first, clean up later’ is a mistake. As far as the coal-to-gas industry is concerned, we

should remain cautious and careful. Greenpeace calls on industry and government to

consider the following:

First, China’s National Energy Administration should adopt a more cautious policy by

establishing a model before expanding.

China’s energy policy under the 13th Five Year Plan is currently being developed and planned

coal-to-gas production has the potential to reach 50 billion cubic meters per year. This is the

wrong signal and may cause multiple projects to push ahead blindly. We recommend that

the National Energy Administration set production volume of China’s coal-based synthetic

natural gas to be below 20 billion cubic meters by 2020. The first four model projects can be

completed first and used as a platform to gain experience in production technique and

resolve technological bottlenecks like excessive energy and water use as well as pollution. At

the same time, this will allow for environmental standards to be established and sufficient

time to consider the next step of expansion.

Second, The Ministry of Environment Protection should implement a strict Coal Chemical

Pollution Emission Standards as soon as possible. Technology used to treat waste water in

the coal-to-gas industry is a global problem as there is a great deal of highly toxic waste

water and sediment created in the production process. It is easy to see through the lie of

‘zero wastewater discharge’ when evidence is so clear to the contrary in the form of huge

lakes filled with hazardous waste water that cannot be fully treated. This is also due to the

lack of discharge standards in the treatment of waste water. The Waste Water Discharge

Standards passed in 1996 are seriously outdated and are far from applicable to the

treatment of waste water produced by the coal chemical industry.

We call on the Ministry of Environment Protection to strengthen the monitoring of volatile

organics and other pollutants. The Ministry of Environmental Protection should also make

Page 15: Keqi ctg pollution en report

15

information more available to the public and place all coal chemical projects on the list of

national priority monitored institutions. The scope of public information should include gas

emissions, waste water and sediment that result from production processes in coal chemical

plants as well as pollutants produced by thermal power plants connected to them.

Third, the NDRC should implement practical controls on the increase in carbon emissions

by the coal chemical industry. The energy efficiency of coal-to-gas projects is far lower than

other technology pathways and produces extremely concentrated carbon emissions, nor

does it as of yet have a way of being economically viable(Ding, Han , Chai, Yang , & Shen,

2013; Li , Yang, Zhang, Kraslawski, & Qian, 2014). This is extremely detrimental to national

efforts to conserve energy and reduce emissions, very possibly leading to a new high carbon

lock-in effect and impact China’s ability to reach peak carbon emissions levels it has set by

2030.

The NDRC should work with China’s long-term environmental policies to strictly control the

development scale of coal chemical industries like coal-to-gas and integrate the coal

chemical industry into China’s coal market system as soon as possible. It should also begin

collecting a carbon tax.

Fourth, relevant government departments should give greater consideration to the

carrying capacity of water resources. China is a country with a serious water deficit and

water resources are unevenly distributed throughout the country with water necessary to

maintain ecosystems often being used for industrial purposes. The coal chemical industry,

including coal-to-gas manufacturing, uses massive amounts of water and most facilities are

located in inland regions of northwestern China, placing great pressure on local water

resources. In 2011, the State Council implemented a system to ensure the ‘strictest

management of water resources’, establishing three ‘red lines’ including total water usage

for each province, requiring that they to follow them explicitly23.

We recommend that national plans for coal chemical development are brought in line with

water resource management policies and that water intensive coal chemical projects be

strictly controlled. Local governments should reflect the true scarcity of water resources in

the water prices and consider very carefully the use of water transfer projects or water

rights exchange trials. They should also strictly forbid industrial use of agricultural or

ecological water resources.

23

See Opinions of the State Council on Applying the Strictest Water Resources Control System(2012) (http://www.gov.cn/zwgk/2012-02/16/content_2067664.htm)

Page 16: Keqi ctg pollution en report

16

References Bernton, H. (2014, May 3). China’s coal solution has carbon downside across globe. The Seatle Times.

Retrieved from

http://seattletimes.com/html/specialreportspages/2023517279_chinaenergyxml.html

Chen, D. (2014, October 17). 一个煤制气示范工程的真实面貌[The true face of a coal-to-gas model

project]. China Chemical Industry News. Retrieved from

http://mp.weixin.qq.com/s?__biz=MjM5OTI1NDg0OQ==&mid=201015024&idx=1&sn=1c325

2bd628acf972adc0000db838454&scene=2&from=timeline&isappinstalled=0#rd

Chifeng Municipal Water Resources Bureau. (n.d.). 赤峰市水利资源开发利用情况汇报 [Report on

water resources use and development in Chifeng City]. Chifeng: Chifeng Municipal Water

Resources Bureau.

Datang Hexigten Coal-to-Gas Project. (n.d.). 灰渣场蒸发塘简介[A brief introduction of evaporation

pond][Billboard]. Chifeng: Datang Hexigten Coal-to-Gas Project.

Datang International Power Generation Co., Ltd & Wuhuan Science and Technology Co., Ltd. (2008).

内蒙古大唐国际克旗日产 1200 万 m3 煤制天然气项目环境影响报告书简本[An abridged

environmental impact report of Datang Hexigton Coal-to-Gas Project with a daily capacity of

12 million m3]. Retrieved November 17, 2014, from Doc88:

http://www.doc88.com/p-772457570715.html

Ding, Y., Han , W., Chai, Q., Yang , S., & Shen, W. (2013). Coal-based synthetic natural gas (SNG): A

solution to China’s energy security and CO2 reduction? Energy Policy, 55, 445-453.

doi:10.1016/j.enpol.2012.12.030

Duan, X. (2014, August 8). 神华有意接手大唐克旗煤制气 更看重管道资产[Shenhua shows

interest in taking over Datang Hexigten Coal-to-Gas project: More valuing pipeline assets].

21st Century Business Herald. Retrieved from

http://money.21cbh.com/2014/8-8/xMMDAzMDdfMTI2MTcxMg.html

Gai, H., Jiang, Y., Qian, Y., & Kraslawski, A. (2008). Conceptual design and retrofitting of the

coal-gasification wastewater treatment process. Chemical Engineering Journal, 138(1-3),

84-94. doi:10.1016/j.cej.2007.05.032

Gong, M., & Li, H. (2014). High carbon emission risks of smog control measures——The case of

replacing coal with coal-to-gas. In Y. Qi (Ed.), Annual Review of Low-carbon Development in

China (2014) (pp. 62-76). Beijing: Social Sciences Academic Press.

Guo, L. (2014, September 10). 大唐发电煤化工项目巨亏调查 10 年砸 600 亿[Invistigation of huge

loss of Datang Power's coal-to-chemical projects: 60 billion in 10 years]. China Securities

Journal. Retrieved from

http://money.21cbh.com/2014/9-10/4MMDAzMDdfMTMwMjI4Mg.html

Hexigten Environmental Protection Bureau (EPB). (2014). 关于达日罕乌拉苏木牧民对大唐公司环

境信访案件办理情况的答复(克环发[2014]131 号[A reply to herders of Darihanwula Sumu

about the environmental complaint against Datang Company(Hexigten EPB No. [2014]131].

Chifeng: Hexigten EPB.

Inner Mongolia Dalinuoer Nature Reserve Managing Office. (n.d.). 自然保护区概况[Overview of the

Nature Reserve]. Retrieved November 17, 2014, from China's Dalinuoer:

http://www.kqdlh.com/view_zrbh_article.php?id=1204

Li , H., Yang, S., Zhang, J., Kraslawski, A., & Qian, Y. (2014). Analysis of rationality of coal-based

synthetic natural gas (SNG) production in China. Energy Policy, 71, 180-188.

Page 17: Keqi ctg pollution en report

17

doi:10.1016/j.enpol.2014.04.018

Wang, D. (2014, September 24). 内蒙古煤制气年底暖京城[Coal-based synthetic natural gas from

Innter Mongolia warms Beijing end of this year]. Beijing Daily, p. 5. Retrieved from

http://bjrb.bjd.com.cn/html/2013-09/24/content_111198.htm

Wang, W., Han, H., Yuan, M., Li, H., Fang, F., & Wang, K. (2011). Treatment of coal gasification

wastewater by a two-continuous UASB system with step-feed for COD and phenols removal.

Bioresource Technology, 102(9), 5454-5460.

Xu, P., Han, H., Hou, B., Jia, S., & Zhao, Q. (2014). Treatment of coal gasification wastewater by a

two-phase anaerobic digestion. Desalination and Water Treatment, 1-11.

doi:10.1080/19443994.2014.884474

Yang, C.-J., & Jackson, R. B. (2013). China's synthetic natural gas revolution. Nature Climate

Change(3), 852-854. doi:doi:10.1038/nclimate1988

Zhang, L. (2014, January 19). 内蒙古大唐国际克什克腾旗煤制天然气公司发生中毒事故已致 2死

4 伤[A poisoning accident in Inner Mongolia Datang International Hexigten Coal-to-Gas Co.,

Ltd killed 2 injured 4]. Retrieved from

http://inews.nmgnews.com.cn/system/2014/01/19/011398154.shtml

Page 18: Keqi ctg pollution en report

18

Appendix 1: Financial Analysis of Datang Coal Chemical

In addition to the problems of environmental pollution connected with the Datang Hexigten

coal-to-gas project, another point that should be of special interest to investors are the

continued losses of Datang Power’s entire coal chemical business unit, which can be mainly

attributed to high capital costs, the difficulty of operation and the lack of mature technology.

Financial reports of the Datang International Power Generation Co., Ltd. clearly show that

revenue from its coal chemical business unit is severely behind. In the company’s 2013

financial report, its coal chemical business showed the poorest performance out of all

business units with a total loss of 2.18 billion RMB, creating a striking comparison with its

high-revenue generating power production and coal product units.

2013 Power

Production

Coal

Products

Coal

Chemical

Other Units Total

Unit Revenue

External Transactions 65,629,209 4,210,348 4,937,628 450,273 75,227,458

Inter-unit Transactions 756,266 21,639,602 6,373 106,405 22,517,646

Total Revenue 66,394,475 25,849,950 4,944,001 556,678 97,745,104

Unit Performance 9,494,603 462,951 -2,186,275 435,511 8,206,790

Depreciation/Amortization 8,824,693 217,942 988,499 93,357 10,124,491

Revenue (Losses) from

Selling Off of Land,

Facilities and Equipment

43,630 33 -167 43,496

Revenue from Long-term

Investment

-16,926 -16,926

Losses from Asset

Depreciation

-717,657 -545,480 -674 -1,263,811

Interest Revenue 64,730 7,093 6,293 1,388 79,504

Interest Payments 6,794,882 292,225 1,009,725 87,676 8,184,508

Profit from Jointly

Operated Companies

24,329 438,513 214,979 677,821

Profit from Joint Ventures 133,030 114 133,144

Income Taxes 2,395,068 181,576 -249,920 63,284 2,390,008

Source: Datang International Power Generation Co., Ltd. 2013 Financial Report

However, despite being the worst performing business unit in the company, coal chemical

operations took up one of the largest portions of the company’s assets.

The following balance sheet shows coal chemical operations to hold the second largest

proportion of assets at Datang Power, reaching 23.7%, but contributes only 5.2% of its

revenue. Meanwhile, the coal chemical business unit ran at a loss in 2013, having a generally

negative impact on the company’s overall profitability.

Page 19: Keqi ctg pollution en report

19

Asset Ratios for 2013

Revenue Ratios for 2013

Profit Ratios for 2013

Power: 63.5%

Coal: 9.4%

Coal Chemical: 23.7%

Other: 3.4%

Power: 66.9%

Coal: 27.2%

Coal Chemical: 5.2%

Other: 0.6%

Power: 115.7%

Coal: 5.6%

Coal Chemical: Loss

Other: 5.3%

Source: Derived by Greenpeace from Datang International Power Generation Co., Ltd. Annual Report 2013

The disappointing performance of the coal chemical business unit caused Datang Power to

announce on July 8, 2014 that it had signed a ‘Restructuring Agreement for Coal Chemical

and Related Projects’ that would restructure operations at the Hexigten Qi coal-to-gas

project, Duolun coal chemical project, the Hulun Buir fertilizer project and Xilinhot mining

project in Inner Mongolia as well as the Fuxin coal-to-gas project in Liaoning Province24.

This news resulted in a massive 20% increase in the value of Datang Power stock, which

reached a new record high of 3.76 RMB at the end of the trading day.

Note: Based on open data available from Yahoo Finance.

Most investment analysts are optimistic about the deal and believe that the constant

problems and continued losses that the Datang Group faced in its coal chemical business,

which it viewed as a way to diversify its coal business, simply turned out to be more trouble

than it was worth.

24

See http://static.sse.com.cn/disclosure/listedinfo/announcement/c/2014-07-07/601991_20140708_4.pdf

Page 20: Keqi ctg pollution en report

20

Analysis by Nomura Securities titled “Goodbye Coal Chemical” states that delays and forced

technical conversions of the Datang coal chemical project ‘severely tested the patience of

investors’ and the divestment of this business took the pressure off that kept its stock price

so low25.

Analysis by Deutsche Bank also says that this was ‘good news for the company’ as the

market generally felt it was the coal chemical business that had caused losses for the

company, resulting in the stock price of Datang Power to drop 46%, 30% and 122% over

6-month, 12-month and 36-month periods26.

25

See Lam, J., & Tang, T. (2014). Quick Note - Datang International Power (991 HK, Buy) - Let it go – GOOD bye coal-chemical. Hongkong: Nomura. 26

See Deutsche Bank. 2014. Datang Int'l Power Alert - Significant value unlocking potential from coal chemistry business disposal.

Page 21: Keqi ctg pollution en report

21

Appendix 2: 54 Coal-to-Gas Projects Completed, Under Construction or

Planned

No. Project Name Province Capacity (billion cubic

meters(bcm)/year) Project Progress

1 Datang Coal-to-Gas Plant,

Hexigten Qi

Inner

Mongolia 4

Phase 1 of 1.33

bcm/year in

production; Phase 2

under construction

2 Kingho Coal-to-Gas Plant, Ili,

Xinjiang Xinjiang 5.5

Phase 1 of 1.375

bcm/year in

production; Phase 2

design tendering

3 Datang Coal-to-Gas Plant,

Fuxin Liaoning 4

Phase 1 under

construction

4 Huineng Coal-to-Gas Plant,

Ordos

Inner

Mongolia 1.6

Phase 1 under

construction

5 Inner Mongolia Mining

Coal-to-Natural-Gas Plant, Ili Xinjiang 2

Phase 1 under

construction

6 Guodian coal-to-gas plant,

Xing'an League Mongolia 4 In preparation

7 Xinmeng coal-to-gas plant,

Ordos

Inner

Mongolia 4 In preparation

8 Beikong coal-to-gas plant,

Ordos

Inner

Mongolia 4 In preparation

9 CNOOC coal-to-gas plant,

Ordos

Inner

Mongolia 4 In preparation

10 Hebei Jiantou coal-to-gas

plant, Ordos

Inner

Mongolia 4 In preparation

11 Huaxing coal-to-gas plant,

Ordos

Inner

Mongolia 4 In preparation

12 China Power Investment Corp

coal-to-gas plant, Huocheng Xinjiang 6 In preparation

Page 22: Keqi ctg pollution en report

22

13 Suxin Energy coal-to-gas

plant, Hefeng Xinjiang 4 In preparation

14 Guanghui coal-to-gas plant,

Kamusite Xinjiang 4 In preparation

15 Huaneng coal-to-gas plant,

Zhundong Xinjiang 4 In preparation

16 SINOPEC coal-to-gas plant,

Zhundong Xinjiang 8 In preparation

17 Longyu coal-to-gas plant,

Zhundong Xinjiang 4 In preparation

18 Zhejiang Energy Group

coal-to-gas plant, Zhundong Xinjiang 2 In preparation

19 Xinjiang Tianye Group

coal-to-gas plant, Zhundong Xinjiang 4 In preparation

20 CNOOC coal-to-gas plant,

Datong Shanxi 4 In preparation

21 Wanneng coal-to-gas plant,

Fengtai Anhui 2.2 In preparation

22 Shenhua coal-to-gas plant,

Ordos

Inner

Mongolia 4

Feasibility study being

compiled

23 Guodian Pingmei coal-to-gas

plant, Nilka Xinjiang 4 Being filed

24 China Power Investment Corp

coal-to-gas plant, Yinan Xinjiang 6 Being filed

25 TBEA coal-to-gas plant,

Zhundong Xinjiang 4 Being filed

26 Huadian coal-to-gas plant,

Zhundong Xinjiang 4 Being filed

27 China Coal coal-to-gas plant,

Zhundong Xinjiang 4 Being filed

28 Yan Mining coal-to-gas plant,

Xinjiang 4 Being filed

Page 23: Keqi ctg pollution en report

23

Zhundong

29 Kailuan coal-to-gas plant,

Zhundong Xinjiang 4 Being filed

30 Changji Shengxin coal-to-gas

plant Xinjiang 1.6 Being filed

31 Huahong Mining coal-to-gas

plant, Zhundong Xinjiang 2 Being filed

32 Shendong Tianlong

coal-to-gas plant, Zhundong Xinjiang 1.3 Being filed

33 Sanyi coal-to-gas plant,

Zhundong Xinjiang 4 Being filed

34 Beikong New Energy

coal-to-gas plant, Zhundong Xinjiang 4 Being filed

35 Ziguang coal-to-gas plant,

Hami Xinjiang 0.8 Being filed

36 Hongsheng New Energy

coal-to-gas plant, Zhangye Gansu 4 Being filed

37 Huaneng coal-to-gas plant,

Hulun Buir

Inner

Mongolia 4 Being filed

38 Jinneng Group coal-to-gas

plant, Shuozhou Shanxi 4 Being filed

39 Xinfeng Cement coal-to-gas

plant, Handan Hebei 1.8 Being filed

40 Xing'an Boyuan Coal-to-gas

plant, Xing'an League

Inner

Mongolia 4 Submitted to NEA

41 Huaneng coal-to-gas project,

Weinan Heyang Shaanxi 4

Contract signed Oct

2014

42 Anhui Jingwan coal-to-gas

project, Anqing Anhui 4

Contract signed Oct

2014

43 Zhendong New-Energy

coal-to-gas project, Baotou

Inner

Mongolia 6

Contract signed Aug

2014

Page 24: Keqi ctg pollution en report

24

44 Bohai Chemical coal-to-gas

plant, Ordos

Inner

Mongolia 8

Contract signed Feb

2014

45 Tianjin Energy Investment

coal-to-gas plant, Hulun Buir

Inner

Mongolia 16

Contract signed Jan

2014

46 Jinshajiang Chuangtou

coal-to-gas plant, Ningdong Ningxia N/A

Contract signed Jan

2014

47

Inner Mongolia Fortune

Energy coal-to-gas plant,

Bayannaoer

Inner

Mongolia 4

Contract signed Jan

2014

48 Hebei Jiantou coal-to-gas

plant, Hulun Buir

Inner

Mongolia 16

Contract signed Nov

2013

49 Xinjiang Energy coal-to-gas

plant Xinjiang 8

Feasibility study

tendered Oct 2013

50 Guoneng coal-to-gas plant,

Baotou

Inner

Mongolia 4

Contract signed Sep

2013

51 Guochu Energy coal-to-gas

plant, Alxa League

Inner

Mongolia 4

Contract signed Sep

2013

52

Shandong Energy Shenglu

Energy & Chemical coal-to-gas

plant, Ordos

Inner

Mongolia 10

Contract signed Sep

2013

53

Xinjiang Development and

Construction Corp Xiexin

Coal-to-gas Plant, Yining

Xinjiang 4 Contract signed Sep

2013

54 Inner Mongolia Mining

coal-to-gas plant, Hohhot

Inner

Mongolia 4

Contract signed Sep

2013

Data Sources and Processing: This list of coal-to-gas project at various stages of development (as of

October 2014) is an update to the list published by Greenpeace in June 201427, which is compiled

based on a wide range of public information available online, including government documents, EIA

reports and news reports, project lists created by other institutions. We eliminated projects that

have had no new information since 2012. For more information, please contact Greenpeace.

27

See the Chinese version http://www.greenpeace.org/china/zh/publications/reports/climate-energy/2014/chinese-coal-to-gas-industry-analysis/. Please contact Greenpeace for the English version.