King JamesConstruction Cost Estimating

Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Page 2: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Letter of Transmittal• Bid proposal for King James project

– 3-bedroom/2-bath/-1-car garage• Estimations broken down into several

categories• Proposed bid includes all materials, labor,

equipment, taxes and any other additional needed costs

Page 3: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Division of Duties

Page 4: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Breakdown of Bid by Components

Page 5: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

ConcreteAssumptions:• Use Earth as Forms• Use Chute to Pour

Concrete

Page 6: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Woods & Plastics

The Floor•The floor system consists of joists covered with OSB or plywood sheathing and bears on sills, walls, or girders supported by posts.

Page 7: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Walls•Walls consists of top and bottom plates, studs, headers, blockings, and sheathing. •Double top plate of untreated lumber, and one bottom plate of treated lumber.

Woods & Plastics

Page 8: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

The roofSales tax—6%Labor tax---25%OH & Profit---12%

Woods & Plastics

Page 9: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye
Page 10: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Thermal + Moisture

Waterproofing Insulation Batt Insulation in Wall R-30 Insulation above Ceiling Exterior Insulation Finish System

Building Paper and Vapor Barriers

Shingles Fiberglass roof shingle Metal Drip edge

Page 11: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Thermal + Moisture

1. Waterproofing Film Vapor Barrier Underlayment Area = 1460SF

2. R-30 Insulation above Ceiling Area = 1460SF

Page 12: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Thermal + Moisture

3. 3-1/2" Batt Insulation in Wall Exterior Wall 1052SF Interior Wall 313.31SF AreaWall = 1365.31 SF

Page 13: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Thermal + Moisture

4. Exterior Insulation Finish System

AreaWall = 1052SF

Page 14: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Thermal + Moisture5. Building Paper and Vapor Barriers (must be lapped to be effective)

To be lapped 12 inches on the ends 6 inches on the side

AreaBuilders paper = 3363.89SF

The Dormer

Page 15: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

6. Fiberglass Roof Shingles 5in exposure and 1in width Starter/Field/Hip&Valley/Cap Shingle Areashignles = 2053.27SF

7. Metal Drip Strip come in 11-foot length

need to be lapped 2 inches Length = 164.55LF Number = 16 each

Thermal + Moisture Hip Shingle

Page 16: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Thermal + Moisture

Page 17: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Plumbing

Plumbing (DWV)

Material cost priced through Home-Depot

Labor cost priced through RS-Means (Section 22)

Estimates broken up in the following sections:

Main Sewer Connection Central Bathroom Left Bathroom Garage and Kitchen

All PVC Schedule 40 for Sanitary

Page 18: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Plumbing

Plumbing (Water Line) Material cost priced through

Home-Depot Labor cost priced through RS-

Means (Section 22) Estimates broken up in the

following sections: Garage (WM) Kitchen (SINK) Living Room Central Bathroom (LAV,

SHW, WC) Left Bathroom (LAV, WC,

TUB) Hot Water (HW) lines in house

are all ½” CPVC Cold Water (CW) lines in house

are ¾” in-wall and reduce to ½” for fixture connections.

Page 19: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

HVAC

Page 20: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

HVAC

Page 21: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

HVAC

Page 22: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Electrical

Outlet:•12 GFI•2 Waterproof GFI Cover•1 J-Box•23 AFCI•35 GFI/AFCI Cover•3 220V Outlet•20 outlet•22 Outlet Box•2 Breaker for AC•3 Breaker for others•1 Electrical Panel

Page 23: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Electrical

Page 24: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

4 Fans2 Exhaust Fan8 Lighting Fixtures13 Single Pole Switches2 Three Pole Switches4 Smoke Detector1 Co/smoke Detector

Page 25: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

8’6’ 6’6’

4’

2’

3’7’

6’ 6’8’6’

3’

4’

6’10’6’

40ft

Electrical

Page 26: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Facilities:

•200ft #12 Electrical Wires•1 Washer•1 Dryer

Electrical

Page 27: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Final Cost

Electrical

Page 28: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Openings

Page 29: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Finishes

Assumptions:• Paint Rolled On• Carpet in Bedrooms• Vinyl in Bathrooms and Kitchen• Laminate in Halls and Living/Dining Room

Page 30: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Bid Summary

• Direct Costs

Page 31: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Bid Summary

• Indirect Costs

Page 32: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Bid Summary

• Total Cost Breakdown by Component

Page 33: King James Construction Cost Estimating Rob Himler, Ken Coutain, David Reger, Ruoyu Huang, Bei Xiong, Hanbing Ye

Questions?