labour inefficiency reasons
TRANSCRIPT
-
7/25/2019 Labour Inefficiency Reasons
1/8
MORALE AND ATTITUDE:Multiple contract changes and rework, disruption of labor rhythm and
scheduling, poor site conditions, etc.
STACKING OF TRADES:Operations take place within physically limited space with other
contractors. Results in congestion of personnel, inability to locate tools conveniently, increased loss
of tools, additional safety hazards and increased visitors. Optimum crew size cannot be utilized.
REASSIGNMENT OF MANPOWER:Loss occurs with move-on, move-off men because of
unepected changes, ecessive changes, or demand made to epedite or reschedule completion of
certain work phases. !reparation not possible for orderly change
CREW SIZE INEFFICIENCY:"dditional men to eisting crews #breaks up# original team effort, affect
labor rhythm. "pplies to basic contract hours also
DILUTION OF SUPERVISION:"pplies to both basic contract and proposed change. $upervisionmust be diverted to %a& analyze and plan change, %b& stop and re-plan affected work, %c& take off,
order and epedite material and e'uipment, %d& incorporate change into schedule, %e& instruct
foreman and (ourneyman, %f& supervise work in progress, and %g& revise punch lists, testing and start-
up re'uirements
LEARNING CURVE) !eriod of orientation in order to become familiar with changed condition. *f new
men are added to pro(ect, effects more severe as they learn tool locations, work procedures, etc.
+urnover of crew
ERRORS AND OMISSIONS) *ncreases in errors and omissions because changes usually performed
on crash basis, out of se'uence or cause dilution of supervision or any other negative factors
JOINT OCCUPANCY:hange causes work to be performed while facility occupies by other trades
and not anticipated under original bid
LOGISTICS:Owner furnished materials and problems of dealing with his storehouse people, no
control over material flow to work areas. "lso contract changes causing problems of procurement
and delivery of materials and re-handling of substituted materials at site.
-
7/25/2019 Labour Inefficiency Reasons
2/8
fve most important actors that impact negatively on labour productivity as
material shortages,
lack o experience o labour,
lack o labour surveillance,
and alteration o drawings
specifcation during execution.
Causes o Time Overrun on Construction Sites
The study had identifed ! actors rom literature which were chie among the
causes o time
overrun on construction sites. The study respondents were re"uired to rank these
! actors
according to their in#uence on time overrun on construction sites. The ranking was
thereore
based on the perception o the respondents which are grouped into two$ consultants
and
contractors. The result is presented in Table %.
&s indicated in Table %,
inade"uate und or pro'ects, i
inade"uate planning o pro'ects beore their commencement,
inade"uate tools and e"uipment,
delay in delivery o materials, and
design changes during pro'ect execution were ranked overall as the top ! actors
causing
time overrun on construction sites.
(nade"uate planning o pro'ect beore commencement
(nade"uate tools and e"uipment
)elay in delivery o materials
)esign changes during pro'ect execution
-
7/25/2019 Labour Inefficiency Reasons
3/8
Subcontractor incompetency
)elay in response to decision taking
(ncompleteness o technical documentation
*abour dispute in orm o strike or lock+out .- /
0nexpected subsoil1ground condition ./ th
Community issues ./ th
0nclear or inade"uate instructions to operators
Temporary work stoppages due to adverse weather
)elay in inspection and testing o completed work
2olitical instability or change in government policies
&ccidents
Obtaining building permit and approvals
This fnding also agrees with similar studies in other developing countries.
3or example
4ankings o causes o low productivity in construction site by organisation
2roductivity 3actor
Consultants Contractor Overall
5ean 4ank 5ean 4ank 5ean 4ank
0se o 6rong Construction 5ethod
(nade"uate Construction 5aterials
(naccurate )rawings1Specifcation
(nade"uate Tools and 7"uipment
2oor Supervision o Operatives
*ack o Skills rom the 6orkers
Tools17"uipment 8reakdown
)elay )ue to 0nclear or (nade"uate (nstructions
-
7/25/2019 Labour Inefficiency Reasons
4/8
0nriendly 6orking &tmosphere or 6eather Condition
0nbalanced )istribution o 4esources ./9 :
Correctional 6ork to (mprove 2oor or 8ad 6ork
2olitical (nsecurity or Change in ;overnment 2olicies
(n'ury or &ccident (nvolving a 6orker 6ages
0nexpectedly, wages, in'ury or accidents involving workers and political insecurity
or change
in government policies, were unanimously ranked as act
Table
-
7/25/2019 Labour Inefficiency Reasons
5/8
keep their eyes on these key actors during pro'ect execution as these actors could
result in
reasonable time overrun on pro'ects.
&mong several actors that a>ect productivity in the construction sites, use o
wrong
construction method, inade"uate construction materials and inaccurate
drawings1specifcation
were the most signifcant. &vailability o construction materials in the re"uired
"uantity and
"uality will avert production delay, while accurate drawings1specifcation will
prevent
rework, and good construction method enhances the production process in anyconstruction
site.
The predictive model emanating rom the current study indicates that signifcant
relationship
exists between time overrun and labour productivity in construction sites in =igeria.
7"ually,
the nature o the relationship is inversely proportional i.e. the higher the time
overrun the
lower the labour productivity and conversely the lower the time overrun the higher
the labour
productivity. 5ore precisely the study concludes that a . units? reduction @or
increaseA in
time overrun causes . unit increase @or decreaseA in labour productivity.
8ased on the outcome o the study, the ollowing recommendations are made
towards
improved productivity in the construction industry and to reduce time overrun on
pro'ects in
=igeria.
aA There should be e>ective unding o pro'ect by pro'ect owners to avoid
unnecessary time
-
7/25/2019 Labour Inefficiency Reasons
6/8
overrun with its attendant e>ect on cost. To guarantee achievement o the
construction
programme, the pro'ect owner could engage the service o a pro'ect manager to
manage
the pro'ect rom the design stage through tendering to completion.
bA Contractors and subcontractors should provide ade"uate and unctional working
tools1e"uipment or their workers to enable timely completion o pro'ects. 7"ually,
in
every medium to large scale pro'ects, the pro'ect team composition should include a
dedicated sta> trained on materials management and store keeping to ensure
e>ective and
eBcient management o construction materials. The contractor or sub+contractor
could
establish a maintenance department that is managed by experienced technician on
construction sites to ensure prompt repair o any damaged tools1e"uipment.
cA The pro'ect manager should ensure that both nominated and domestic sub+
contractors on
any pro'ect have the re"uisite experience and work plan to meet the re"uirements
o the
main contractor. 2re+"ualifcation o these sub+contractors would ensure that the
ones
engaged have suBcient experience, profciency and capacity to deliver not only
"uality
work but on time. The pro'ect owner @or pro'ect managerA must ensure completion
o all
design documentation with any associated value engineering analysis and
buildability
reports beore tendering, so that design changes during pro'ect execution is
minimised. (=T74=&T(O=&* O04=&* O3 CO=ST40CT(O= S022*D CE&(=
5&=&;757=T Folume =umber %
&meh, O.., G Osegbo, 7.7. @%A. Study o relationship between time overrun and
productivity on construction sites.
-
7/25/2019 Labour Inefficiency Reasons
7/8
(nternational ournal o Construction Supply Chain 5anagement @A. /9+9-.
99
dA The pro'ect manager should ensure the submission o method statements by the
contractors in the course o bidding or any construction pro'ect. This to a large
extent
would determine the contractor?s understanding o the work and the application o
good
construction method and technology that will guarantee prompt realisation o
pro'ect
ob'ectives.
eA ;overnment should encourage skill ac"uisition especially among the teaming
unemployed
youth through development o technical colleges or training o workers in various
construction trades. ;ood skills within and among the workers would exert
reasonable
"uantum o positive in#uence on labour productivity more especially when backed
by
ade"uate supervision o operatives. Contractors and sub+contractors should as a
matter o
policy train and retrain skilled and semi+skilled workers to enhance their skills which
will
eventually improve on the labour productivity.
A Contractors and subcontractors should ensure ade"uate training and supervision
o the
operatives on construction sites as it would improve on the "uality o output as wellas
minimiHe the chances o doing wrong work or even application o wrong
construction
method by the workers. 7"ually, supervisors should be well grounded in any aspect
o
-
7/25/2019 Labour Inefficiency Reasons
8/8
work they are in charge as it would not only earn them respect but add value to
"uality o
the completed work.
473747=C7S
&bd 7l+4aHek, 5.7., 8assioni, E.&., G 5obarak, &.5. @%!A. Causes o delays in
building const