Presentation by Device to the Launceston General Hospital CSSD ComiteeTRANSCRIPT

PRESENTATION HEADER
Copy for presentation
CLICK TO ADD TITLE
Launceston General Hospital
CSSD Redevelopment
James Kyriakou
22nd January 2013

PRESENTATION HEADER
Copy for presentation
Device Technologies Major Equipment Offer
Click to add text
Equipment Qty Offer Warranty
Steam Sterilizers incl. integrated boilers
3 $350,010 2 years15 years chamber2 year door seals
Washer Disinfectors incl accessories Conveyors Auto load/unload
3 $271,100 2 years
Cart Washer incl. accessories and instrument options
1 $197,816 2 years

PRESENTATION HEADER
Copy for presentation
Major New Equipment – Steam Sterilizer
Elliptical Chamber aids processing and drying
Enhanced user interface
316L Full Jacket Chamber – 15 Years warranty
Automation upgradeable

PRESENTATION HEADER
Copy for presentation
Major New Equipment – Cart Washer
Up to 4 carts every 12 minutes – DRY!
Thermal Disinfection Validation Process

PRESENTATION HEADER
Copy for presentation
Major New Equipment – Batch Washers
20 min utensils – 28 mins instruments DRY!
Variable Impingement based on load
Unique water filter system built in

PRESENTATION HEADER
Copy for presentation
Major New Equipment – Caviwave Ultrasonic
Automatic Drain Lumened Port CleaningAutomatic Fill
40kHz Cavitation
132kHz Cavitation
Standard Ultrasonic
Caviwave Ultrasonic
Unique Cavitation
Automatic Lifters
Hands Free Operation
Auto Detergent Dosing

PRESENTATION HEADER
Copy for presentation
Major New Equipment – Tracking System
300+ Contracted Sites in U.S.A, Canada and AustraliaScalable Solution with Multiple Entry PointsSupports Individual Instrument Scanning Compliant with GS1 or HIBCC StandardsInterface Capability to and from Multiple SystemsRegular Enhancements (2 – 4 per year Help Desk Support Services – Remote & Onsite 24 x 7Menu Design based on Workflow Process and Instrument LifecycleComprehensive, Flexible Reporting Capabilities

PRESENTATION HEADER
Copy for presentation
Major New Equipment – Tracking System

PRESENTATION HEADER
Copy for presentation
Our Total Solution – Option 1 Retain Equipment

PRESENTATION HEADER
Copy for presentation
Our Total Solution – Option 2 New Equipment

PRESENTATION HEADER
Copy for presentation
Project Management
Dedicated Project Manager for each Project
Separate Quality Assurance Manager for Each Project
Delivery Team approach
Internal Audit process for each Deliverable Project
Dedicated Project Installers
STERIS Planning Dept. backup and expertise

PRESENTATION HEADER
Copy for presentation
Project Management
Project Fee: Inclusive of the Installation
Inclusions:Design Expertise to Hospital ArchitectAdvise to EngineersAdvise to BuildersAdvise to BCA Documentation required for HandoverCo-ordination of Education
Exclusions:Project Manage Build incl. servicesBuilding Works
ID Task Mode S M T W T F S S M T W T F S S M T W T F S S M T W
14 Jan '13 21 Jan '13 28 Jan '13 4 Feb '13 11 Feb '13
Microsoft Project Document

PRESENTATION HEADER
Copy for presentation
AS/NZ 4187: 2013
Submission into Stds Committee
Rhonda Walck – Director of Education
Represents MTAA
All Equipment Offered complies with:
ISO 15883 p1,2,3,5EN285EN867ISO 14937
Compiles with NEW STANDARDS

PRESENTATION HEADER
Copy for presentation
Transition of Services
3 Step Process
Step 1: Handover all NEW Equipment
Step 2: Transition Service incl. existing equip.
Step 3: Decommission OLD Equipment

PRESENTATION HEADER
Copy for presentation
On Line Support
USL
LSL
Mean
Pre-Defined Parameters
Parameter Out-of-Spec
Internet
Long ChargePhase
Monitored Event Possible Causes Action Outcome
1. Long Pre-Vacuum Pulses Inadequate Water Supply On-Site Water Supply Check No Service Dispatch
S1 or S3 Valve Malfunction Dispatch Tech with S1/S3 Kit One Visit – 1st Time Fix
2. Long Pre-Vacuum Pulses S2 Valve Leaking Dispatch Tech with S2 Valve One Visit – 1st Time Fix w/Chamber Temp Increase
3. Long Charge Phases Inadequate Steam Supply On-Site Steam Supply Check No Service Dispatch
S2 Valve Leaking Dispatch Tech with S2 Valve One Visit – 1st Time Fix

PRESENTATION HEADER
Copy for presentation
Technical Support
Factory Trained Technical Staff
24 hour Support Service
National Network of Technical Support
30 specialist technical staff
Dedicated Factory Trained Tasmanian Technician
Complete IQ, OQ and PQ service
Factory Accredited Maintenance Programme

PRESENTATION HEADER
Copy for presentation
Plant Options
Various options available as part of design
Clean steam generation from Spirax
RO Plant from Culligan Water
Detergent Dosing System
Integrated options

PRESENTATION HEADER
Copy for presentation
Environmental Considerations
GO GREENWITH STERIS
Environmental Design has been incorporated into all our equipment.
Lowest utility usage for our washer disinfectors
All chambers sealed to retain thermal efficiencies
All equipment has drain discharge cool-down built in to comply with hospital/EPA discharge requirements
Recycled water options to assist with utility savings

PRESENTATION HEADER
Copy for presentation
Reference Sites
Current Projects:
Peel Health Campus WARoyal Melbourne Hospital VicMt Druitt Hospital NSWThe Valley Private VicFiona Stanley Hospital WA
Recent Completed Projects:
Blacktown District Hospital NSWWestmead Private Hospital NSWLiverpool District Hospital NSWNorthern Hospital Melbourne VicSt John’s Calvary Hobart Tas