lauren d. donofrio (313) 235-4017 lauren.donofrio@dteenergy
TRANSCRIPT
![Page 1: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/1.jpg)
April 27, 2020
Ms. Lisa Felice Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Lansing, Michigan 48917 Re: In the matter of the Application of DTE Electric Company for approval of
Certificates of Necessity pursuant to MCL 460.6s, as amended, in connection with the addition of a natural gas combined cycle generating facility to its generation fleet and for related accounting and ratemaking authorizations.
MPSC Case No. U-18419 Dear Ms. Felice: Attached for electronic filing in the above-captioned matter please find DTE Electric Company’s BWEC Interim Report. Very truly yours, Lauren D. Donofrio LDD/lah Encl.
Lauren D. Donofrio (313) 235-4017 [email protected]
DTE Energy Company One Energy Plaza, 1635 WCB Detroit, MI 48226-1279
![Page 2: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/2.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 1
Blue Water Energy Center
Interim Status Report
April 27, 2020
![Page 3: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/3.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 2
Contents Blue Water Energy Center Status Report to the Commission ...................................................................... 3
1.0 - Progress Summary ............................................................................................................................ 3
2.0 - Safety ................................................................................................................................................ 6
Table 2.1 Summary of Safety Performance to Date. ............................................................................ 6
3.0 - Schedule ............................................................................................................................................ 6
Figure 3.1 – Summary Schedule ............................................................................................................ 7
Figure 3.2 – Project Progress ................................................................................................................ 7
Table 3.1 Major Project Milestones ...................................................................................................... 8
4.0 - Cost ................................................................................................................................................... 8
Figure 4.1 – Project Financials .............................................................................................................. 8
5.0 - Quality ............................................................................................................................................... 9
6.0 - Risk .................................................................................................................................................. 10
7.0 – Commercial Operation ................................................................................................................... 10
Table 7.1 BWEC GIA Conditional Network Upgrades ......................................................................... 11
8.0 – Workforce Planning........................................................................................................................ 12
9.0 – Summary ........................................................................................................................................ 12
Appendix A – Permit Status ........................................................................................................................ 14
Appendix B – Risk Register .......................................................................................................................... 17
Appendix C – Progress Photos .................................................................................................................... 19
![Page 4: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/4.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 3
Blue Water Energy Center Status Report to the Commission
DTE Electric is suppling this report in compliance with the following provision.
MCL 460.6s (7)
The utility shall annually file, or more frequent if required by the commission, reports to the commission regarding the status of any project for which a certificate of necessity has been granted under subsection (4), including an update concerning the cost and schedule of that project.
1.0 - Progress Summary Certificates of necessity were approved by the Michigan Public Service Commission on April 27, 2018 for DTE Electric’s proposed Blue Water Energy Center (BWEC) granting that:
• The power to be supplied by the new facility is needed. • The new facility represents the most reasonable and prudent means of meeting
the power need. • The estimated capital and financing costs, and the estimated cost of power from
the facility will be recoverable in rates from the company’s customers.
The Commission approved recovery of up to $951.8 million for the construction of the new generating facility.
DTE Electric (the Company) authorized Kiewit Engineering (MI) Co. (its Engineering, Procurement, Construction (EPC) contractor) limited notice to proceed with the project on April 30, 2018 and full notice to proceed with the project on July 30, 2018. With the notices, Kiewit has commenced engineering of the facility, procurement of equipment and materials, and site construction. As of April 1, 2020, the overall project (including engineering, procurement, and construction) is approximately 52% complete.
On March 23, 2020, Executive Order 2020-21 was issued by Governor Whitmer requiring a temporary suspension of activities that are not necessary to sustain or protect life in response to the COVID-19 pandemic. The order was in effect from March 24, 2020 to April 13, 2020 and was subsequently extended to April 30, 2020 by Executive order 2020-42. Non-critical work was suspended on the BWEC construction site in response to the Governor’s order. Critical activities including site security, care and maintenance, and irrevocable deliveries were maintained. On April 24th, DTE Electric and Kiewit implemented a phased four week plan to restart construction in a safe and orderly manner. Week one focused on finalizing new safety protocols and
![Page 5: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/5.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 4
notifying parties of the restart including local governments and trade unions. The second week involves preparing the site for work to resume and initiating craft rehiring and orientation to new safety protocol. Construction resumes on the third week (beginning May 4th) with day shift only. Second shift work resumes on week four. As of April 27th, the project remains on schedule and on budget. However, the Company is still analyzing impacts of the pandemic and work suspension including extended staff, equipment rental, care and maintenance costs; subcontractor and supplier impacts; remobilization costs; and new government executive order compliance. The EPC is entitled by contract to a change order to recover expenses incurred as a result of the suspension. Any change order would require the use of project contingency. Permitting activities are ongoing. Critical permits, including the air permit, have been obtained. All other remaining permits are being obtained as needed and in a timely manner. The current status of all permits is included in Appendix A.
DTE Electric submitted a Generator Interconnection Agreement (GIA) application to MISO on June 5, 2017 for BWEC. The GIA process consists of three Definitive Planning Phases (DPPs) and execution of a GIA. The Company’s application is included in MISO’s August 2017 interconnection queue. All three of the DPPs are now completed for the August 2017 queue.
DTE Electric is working closely with MISO and the ITC to ensure the transmission interconnection is in place on time. A provisional GIA with MISO and ITC is in place to support the contractual date for DTE Electric to provide back feed power to the project. A permanent GIA and associated facilities construction agreement are expected to be finalized in the second quarter of 2020, as discussed below in section 7.0 – Commercial Operation.
Natural gas transportation, storage, and lateral pipeline/interconnection contracts have been executed. Construction of the natural gas lateral to BWEC is expected to be complete in the first quarter of 2021. Gas supply agreements will be negotiated and in place to supply the facility during startup and commissioning in 2021 and commercial operations in 2022.
Engineering of the BWEC is progressing as planned and is currently 88% complete. To date over 6,200 engineering drawings have been generated for review.
The most significant procurement component for the project is the power island, which includes the Combustion Turbines (CTs), Combustion Turbine Generators (CTGs), Heat Recovery Steam Generators (HRSGs), Steam Turbine (ST), Steam Turbine Generator (STG), and Distributed Control System (DCS). General Electric is under contract with Kiewit to provide the power island. The power island is on plan and is currently 96% engineered. Most of the major components of the power island have been delivered to
![Page 6: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/6.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 5
site with a final shipment expected in the first week of May 2020. The DCS is in final configuration and is expected to be provided to the site in the third quarter of 2020.
An incident occurred during the delivery of one of the HRSG modules in October of 2019, resulting in damage to the module. Repair of the module is progressing with no schedule impact to the project identified at this time. DTE is not responsible for the cost of the repairs.
In addition to the power island, the following major procurements have been awarded since our last report in April of 2019:
• Transmission lead line poles, conductors, and insulators • Low energy fabricated pipe • Warehouse structures and installation • Drilled piers for switchyard and lead line poles • Fire protection • Site security
Site construction activities have progressed. Since our last report in April of 2019 the following progress has been made:
• Raw water intake line placement has been completed • Deep foundations (H-pile) have been completed • Cooling tower basin has been placed and the structure has been erected • Foundations and pedestals for both CT trains and the ST have been placed • HRSG modules, CTs, CTGs have been set • HRSGs have been enclosed • Warehouse installation completed
In addition, the following construction activities are in progress:
• Underground piping, electrical duct bank installation, and electric cable pulls • Main and finger racks and above ground piping • Switchyard foundations placement • Air inlet structure erection • Administration building erection and internal finishing • Field fabricated tank assembly • Water treatment building foundations placement, equipment set, and building
erection • Auxiliary boiler installation • Steam turbine condenser assembly and steam turbine building erection • Cooling tower baffle and mechanical equipment installation
Progress photos of the project are included in Appendix C.
![Page 7: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/7.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 6
2.0 - Safety Safety is the number one priority for the Blue Water Energy Center. To date there have been two recordable injuries for the project. The Recordable Injury Rate (RIR) is currently 0.41 with more than 970,000 earned hours to date. In addition, there have been fourteen first aids and seven near misses for the project. Table 2.1 provides a summary of project safety metrics.
Two recordable injuries have occurred since our last report in April of 2019:
• During the setup of a tool used to perform a pipe fusion operation, the tool became locked in an incorrect position. While attempting to correct the position of the tool, a pipefitter’s finger was caught in a pinch point resulting in an injury to the finger.
• A boilermaker on a ladder experienced a lanyard release that struck them on the finger. The impact to the finger was initially categorized as a First Aid, it was later diagnosed as a fracture and reclassified as a recordable injury.
Kiewit has completed an investigation and has taken corrective action for all incidents that have occurred on the project.
Table 2.1 Summary of Safety Performance to Date. Table 2.1 – BWEC Safety Metrics
Recordable Injury Rate
Lost Time Incidents
First Aids
Near Misses
0.41 0 14 7
Both DTE Electric and Kiewit are dedicated to ensuring the construction project is managed in a safe manner in accordance with all applicable laws. Kiewit is solely responsible for initiating, maintaining, and supervising all safety precautions and programs in the performance of the work. Kiewit protocol requires that all individuals who enter the construction site must first complete safety orientation, including those who will be escorted. Proper personal protective equipment is also required at all times while on site.
In addition, BWEC and MIOSHA entered into a partnership agreement for the construction project in October of 2019.
3.0 - Schedule The new Blue Water Energy Center is expected to be commercially available and be included as a resource available to meet the Company’s capacity requirement for the MISO planning year beginning in June of 2022. The Company continues to analyze
![Page 8: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/8.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 7
impacts of the COVID-19 pandemic that may potentially impact the commercial operation date (COD). Figure 3.1 provides a summary schedule.
Figure 3.1 – Summary Schedule
A detailed integrated schedule is maintained for the project that comprehensively describes the activities and associated milestones required to complete the project. The schedule is managed by Kiewit. The schedule is reviewed in detail each month by the Company. The schedule has been baselined, so going forward any changes will require approval from the project’s Change Review Board.
Figure 3.2 compares actual construction progress earned (completed) to the baseline plan (approved schedule).
Figure 3.2 – Project Progress
The Schedule Performance Index (SPI) is a measure of schedule efficiency, or how well the project team is using time. An SPI greater than 1.0 indicates the project has earned (or completed) more work than planned. An SPI less than 1.0 indicates that less work has been earned versus the baseline plan or schedule. Currently, SPI for the project is slightly lower than plan due to the COVID-19 suspension but is not projected to impact project completion. Progress is being monitored by both the Company and Kiewit. Schedule impacts due to the COVID-19 pandemic are still being analyzed.
Milestones have been established for the project baseline schedule to track progress toward completion. Table 3.1 summarizes the major contractual milestones for the project.
Electrical Interconnection
Gas Lateral
Engineer, Procure, Construct
Performance Testing
Figure 3.1 - Summary Schedule2018 2019 2020 2021 2022
DPP-1 DPP-2 DPP-3 GIA Complete
CompleteUnder Contract
LNTP FNTP Mobilize Major Deliveries Complete
SubstantialCompletion
Demobilize
First Fire
Demonstrate Capacity
COD
April2020
![Page 9: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/9.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 8
Table 3.1 Major Project Milestones Table 3.1 Major Contract Milestones
Milestone Date Status Limited Notice to Proceed 04/27/18 Complete Full Notice to Proceed 07/30/18 Complete EPC Initial Mobilization 08/15/18 Complete EPC Full Mobilization 03/04/19 Complete Gas Lateral Complete 03/31/21 Site Back Feed Power Available 05/26/21 Fuel Gas Available 06/18/21 CCGT 1 First Fire 09/09/21 CCGT 2 First Fire 09/20/21 MISO Demonstration Test 03/01/22 Substantial Completion 03/31/22 Commercial Operation 06/01/22
4.0 - Cost On April 27, 2018, the Commission granted certificates of necessity assuring recovery of up to $951.8 million to construct the Blue Water Energy Center.
Figure 4.1 – Project Financials
A baseline financial forecast has been established for the project as shown in Figure 4.1 as the planned line. To date, the project is on plan indicated by the green bars in the figure. Spend to date on the project, including costs incurred prior to receiving the CON, is $601 million.
The project is managing several risks that are discussed below in section 6.0 - Risk. The project estimate at completion (EAC) remains at the Commission authorized spend. However, the impacts of the COVID-19 pandemic are still being analyzed and may impact the EAC.
Both DTE Electric and Kiewit are committed to ensure opportunities for Michigan and diversity enterprises. The Company and Kiewit continue to reach out to qualified Michigan and diversity businesses.
To that end, Kiewit has implemented a comprehensive plan to ensure that Michigan enterprises have opportunity to competitively bid on the supply of materials, equipment
![Page 10: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/10.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 9
and subcontracted work. Kiewit has agreed to a Michigan spend target of $200 million and is currently on track to meet the target. To date, Kiewit has achieved $145 million in Michigan spend.
DTE Electric and Kiewit are committed to the Michigan work force and the utilization of Michigan craft labor in the construction of the Blue Water Energy Center. The Company’s target is that 90% of the craft labor for the project will be comprised of Michigan residents. To date, Michigan craft labor has accounted for 95% of total craft labor for the project.
At the time of the CON filing, the Company believed that adequate craft labor from Michigan would be available for the project. Since the CON filing, a significant number of new large construction projects have been announced within the state. This is creating a strain on the availability of Michigan craft labor. This is a risk for the project that is being carefully monitored and managed by both the Company and Kiewit.
DTE meets regularly with Michigan labor union leadership to discuss current and future projects at DTE and across the state and the skilled trades needed for the work. These tripartite meetings help both the Company and unions understand and plan for the supply and demand for skilled resources. Kiewit is now participating in the tripartite meetings. In addition, Kiewit has established a monthly meeting cadence with the Michigan union locals.
5.0 - Quality The Company has worked closely with Kiewit to implement a quality program for the construction of the Blue Water Energy Center to ensure the facility meets all defined requirements. Kiewit’s Quality Management System (QMS) will be deployed throughout all phases of the project including engineering, procurement, construction, acceptance testing, and turnover to operations. QMS is consistent with ISO 9001-2008 standards.
The quality program includes observations and inspections at predetermined points during the manufacturing of the major equipment and during construction. Quality inspection specialists will document any non-conformances. Any reported non-conformances will be fully analyzed and resolved before closure. To date, there have been 255 equipment supplier inspections completed with 223 quality non-conformances reported of which 179 have been resolved. There have been 89 non-conformances in field construction of which 74 have been resolved. Additionally, Kiewit is inspecting all piping welds. To date, 8 welds have failed final inspection requiring remediation.
The Company continues to work very closely with Kiewit and GE on the performance and reliability of the HA-class combustion turbines since the turbine blade failure in 2018. There have been no significant failures on the combustion turbine components since the last report to the Commission. The BWEC project team also maintains our engagement in a user group forum where GE discusses learnings on a regular basis.
![Page 11: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/11.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 10
6.0 - Risk Risk identification, qualitative and quantitative analysis, management and control is an iterative process that will continue throughout the life of the project. As mentioned in the Cost section of this report, significant risk remains for the project. The COVID-19 pandemic is a significant risk to the project that has occurred for which the full impact is still being analyzed.
Two risk events have occurred resulting in the use of MPSC authorized contingency, including the effects of tariffs imposed after the contract was signed for $5.0M and additional costs for remediating differing soil conditions for $0.4M. Both events were included in the project risk register and have been formally reviewed and approved by the project change review board. The remaining MPSC authorized contingency for the project is $12.4M.
The current risk register for the project includes 23 potential risks that are being actively managed. This is a reduction of two from the last report filed on April 26, 2019. Since the April 2019 report, the risk associated with hydrostatic test water requiring offsite disposal has been resolved and closed. The risk associated with potential dock improvements required to accommodate heavy loads delivered by barge did not occur and has been closed. As the project team continues to actively manage project risk, the overall Expected Monetary Value (EMV) of the risk register has been adjusted accordingly.
The Company along with Kiewit will continue to manage all project risks. The current project risk register is included in Appendix B.
7.0 – Commercial Operation The new Blue Water Energy Center currently remains on target to be commercially available for the MISO planning year beginning in June of 2022. However, impacts to the schedule resulting from the COVID-19 pandemic are still being analyzed. To be included as a new generation resource for the planning year, BWEC will require a Generator Interconnection Agreement (GIA) to be in place and the facility must be registered in the MISO June Commercial Model for the planning year. The GIA for BWEC is expected to be in place in June of 2020, per the current MISO schedule, and BWEC will be registered for the June 2022 planning year. The Commission staff was informed by the Company in September of 2019 that MISO DPP3 study results indicate that several large-scale network upgrades will be included as conditional projects for the BWEC GIA. The conditions could limit BWEC from injecting and delivering its full output onto the transmission grid until the conditional projects are completed. Some of these conditional projects are related to ITC rating reductions on its transmission facilities in DTE’s service territory that occurred in 2018 (after BWEC entered the August 2017 generator interconnection planning cycle). Others
![Page 12: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/12.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 11
are related to past MISO reliability projects that were approved, but not constructed due to implementation issues. Completion of ITC’s Blue Water Reinforcement project (a.k.a. Crimson or Romeo) which involves rebuilding of the north area grid is one significant condition imposed on BWEC’s GIA. Other conditions include the rebuild of portions of the Lincoln-North East/North West transmission line, rebuild of the MTEP17 Whiting-Custer transmission line project, and construction of the 345kV Meyer substation. As it relates to the Whiting-Custer project, ITC has encountered some challenges implementing the originally proposed solution and proposed a design change on March 24, 2020. MISO is currently evaluating the design change and will notify DTE of the impact on BWEC. As noted in Table 7.1 below, the currently published in-service date for one conditional project exceeds the planned commercial operation date of BWEC. Recently, ITC completed its review of the capital project schedule with DTE and is targeting completion of all conditional projects before BWEC commercial operation. The Company is continuing to work with MISO and ITC regarding in-service dates of all conditional projects and will keep the Commission staff informed of progress.
Table 7.1 BWEC GIA Conditional Network Upgrades
Table 7.1 BWEC GIA Conditional Network Upgrades Network Upgrade In-Service Date Status
MTEP19 Project #15878 Sag Remediation 12/31/21 MTEP Approved
MTEP18 Project #13814 Monroe 345 kV – Lallendorf 345 kV Station Equipment Upgrades
05/01/20 Long Lead Materials Ordered
MTEP19 Project #16028 Caniff – Saturn 120 kV Sag Remediation
12/31/21 MTEP Approved
MTEP19 Project #17164 Blue Water Reinforcement
05/31/22 MTEP Approved
MTEP project #16023 Lincoln-Northeast-Northwest 120 kV Rebuild (overhead portion only Facility ID: 25271)
12/31/22 MTEP Approved
Pontiac - Placid NRIS required sag remediation
12/31/21 Facility Study Complete
Pontiac – Wixom NRIS required sag remediation
12/31/21 Facility Study Complete
MTEP Project #8144 - Construct new 345 kV, double circuit structures, and loop the Kenowa - Argenta 345 kV line into Meyer
06/01/21 Long Lead Materials Ordered
MTEP Project #9864 - Rebuild 9.98 from the Whiting – Custer 120 kV circuit
TBD Awaiting Design Finalization
![Page 13: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/13.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 12
Table 7.1 BWEC GIA Conditional Network Upgrades Network Upgrade In-Service Date Status
MTEP Project #9887 Pontiac – Wixom 345 kV line sag limit increase
06/01/20 Long Lead Materials Ordered
MTEP Project #13814 Upgrade Monroe 345 kV station equipment
05/01/20 Long Lead Materials Ordered
BWEC will also have to demonstrate that the plant capacity is available by March 1, 2022. Demonstration of capacity is achieved by meeting MISO Generation Verification Tested Capacity (GVTC) testing requirements. Both DTE and Kiewit have mitigation plans in place for potential risks that could impact achieving capacity demonstration. Capacity demonstrations will occur prior to MISO commercial operation during a testing period. The output of the generating unit will not be limited due to required conditional network upgrades during this test period as MISO will manage all issues in real-time operation. In the event that BWEC has not demonstrated capacity by March 1, 2022, a deferral can be obtained. The deferral will require DTE to post credit with MISO for an amount equal to 90 days of the daily Cost of New Entry (CONE) for MISO Zone 7. Should the deferral occur, the GVTC requirements would need to be met by May 31, 2022. At this time, DTE does not anticipate requesting a deferral.
8.0 – Workforce Planning To prepare for BWEC commercial operations, a comprehensive staffing plan has been developed to ensure that roles and responsibilities are well defined and that new positions are filled in a timely manner. In addition to the staffing plan, the BWEC project team is developing necessary training, job instructions, and procedures for the new facility. Some of the employees needed at BWEC have been hired, with all employees expected to be in place by the end of 2020. BWEC personnel will undergo 18-24 months of training. The employees will be trained so that they can be deployed to perform startup activities for the plant beginning in 2021, to prepare for full commercial operations in 2022.
DTE Electric has announced the retirement of four power plants by 2022. The employees displaced by the closures will be reassigned to other work within DTE Energy. The Company is committed to its employees and has no intention of layoffs as a result of the future plant closings.
9.0 – Summary The Company is pleased with the progress to date on the new Blue Water Energy Center project. At this time the project remains on schedule and on budget, but the Company continues to analyze the impacts of the COVID-19 pandemic. The project
![Page 14: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/14.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 13
team is working well with Kiewit and GE to resolve challenges as they occur and to safely maintain schedule. Over the next six months, the team will be working diligently to set and assemble major components, pull electrical wiring, install piping, and erect buildings.
The Company is available to the MPSC for further discussion and to answer questions about this report.
![Page 15: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/15.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 14
Appendix A – Permit Status Current permit status is show in Table A-1 below.
Table A-1 Project Permit Matrix Permit Applicant Agencies Status
Air Quality Federal Not Required Air Quality State (Permit to Construct) DTE MDEQ Recvd. 07/18 Boiler Permit (Non-HVAC) DTE/EPC E China Recvd. 06/19 Building Permits – Electrical DTE/EPC E China Recvd. 07/19 Building Permits – Elevator DTE/EPC State Need Q2/20 Building Permits – Fire Protection DTE/EPC E China Recvd. 03/20 Building Permits – Mechanical DTE/EPC E China Recvd. 07/19 Building Permits – Mechanical (HVAC) DTE/EPC E China Recvd. 07/19 Building Permits – Sewer Tap DTE St Clair Co Recvd. 03/19 Building Permits – Structural DTE E China Recvd. 05/19 Building Permits – Water Tap DTE E China Recvd. 03/20 Coastal Zone Management Not Required Cultural Resources (SHPO) Not Required Dam Safety Permits Not Required Demolition – General DTE/EPC E China Not Required Demolition – Asbestos (MIOSHA/NESHAPS) DTE MDEQ Not Required Demolition – Explosives (Transport/Storage) Not Required Demolition – Fuel Storage Tanks Not Required Demolition – Lead Abatement Not Required Drains (County) DTE St Clair Co Recvd. 02/19 Drains (Municipal) Not Required Endangered Species Federal Not Required Endangered Species State DTE State Recvd 08/18 Erosion Control Sedimentation County DTE St Clair Co Recvd 07/18 Erosion Control Sedimentation State Not Required Fence Permits DTE/EPC E China Not Required Flood Plain Management DTE/EPC JPA Not Required Ground Water Discharge DTE JPA Recvd 5/19 Hazardous Materials (HAZMAT) Not Required International Waterways Not Required Local Woodlands Not Required Marking & Lighting of Tall Structures (FAA) DTE/EPC FAA Not Required Marking & Lighting of Waterways Not Required Mineral Management Not Required NPDS – Major/Minor DTE MDEQ Recvd 08/18 Nuclear Equipment DTE NRC Need Q2/20 Paving Permit (Local Ordinance) DTE E China Not Required Planning/Zoning (Local Ordinance) DTE E China Recvd 03/19 Public Lighting (Interruption/Modification) DTE E China Need Q1/21
![Page 16: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/16.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 15
Table A-1 Project Permit Matrix Permit Applicant Agencies Status
Railroad Crossings Not Required Right of Way Easements DTE Recvd. 06/19 Road Crossings / Curb Cut – Local Not Required Road Crossings / Curb Cut – County Not Required Road Crossings / Curb Cut – State DTE/EPC MDOT Recvd. 11/18 Signage Permits (Local Ordinance) DTE/EPC E China Recvd. 11/19 Sanitary Discharge / Removal (Pump/Haul) Not Required Stream / Drain Crossing County Not Required Stream Crossing Federal Not Required Stream Crossing State DTE JPA Not Required Storm Water Discharge (Run-off) DTE JPA See SESC Wild & Scenic Rivers Not Required Wetlands – Local Not Required Wetlands – State DTE/EPC JPA Recvd. 08/18 Certificate of Occupancy DTE E China Need Q3/21
![Page 17: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/17.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 16
![Page 18: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/18.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 17
Appendix B – Risk Register
![Page 19: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/19.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 18
BW
EC C
ombi
ned
Cyc
le P
P Ri
sk R
egis
ter
Wed
nesd
ay A
pril
1, 2
020
Fina
ncia
l Ana
lysi
s
IDR
isk
Even
t Des
crip
tion
Wha
t is
the
even
t?C
ateg
ory
Sub
Cat
egor
ySt
atus
Likelihood
Schedule
Cost
Quality
Safety
Scope
Total Score
Ris
k Ev
ent D
river
s (M
onito
r)R
espo
nse/
Miti
gatio
n St
rate
gy
(Pla
nned
Act
ions
)C
ontin
genc
y Pl
an
(Pla
nned
Act
ions
)R
isk
Ow
ner
Not
es &
Com
men
ts
FA Review Required?
$ Im
pact
(m
illio
ns)
Sour
cePr
obab
ility
EMV
Scheduler Review Required?
2D
TE s
cope
pric
ing
varie
s fro
m C
ON
filin
g (c
urre
nt e
stim
ates
are
RO
Ms)
Pric
e-Fi
nanc
ial
Con
tract
OP
EN
ML
HL
LM
33In
tern
al e
stim
ates
are
stil
l und
er
deve
lopm
ent f
or it
ems
to s
tart
in 2
021
and
2022
, MD
OT
actio
ns
DTE
and
OE
det
aile
d re
view
of o
wne
rs
scop
e an
d es
timat
es, c
ompe
titive
RFP
pr
oces
s
Adj
ust s
cope
, com
petit
ive b
id,
or C
RB
pro
cess
Ran
dall
J K
ulha
nek
Con
tinue
to m
onito
rY
2.5
$
PM
inpu
t0.
50
1.
3$
N
3N
atur
al g
as c
omm
odity
and
tran
spor
tatio
n pr
ices
are
hig
her t
han
plan
ned
incr
easi
ng
star
tup
/ com
mis
sion
ing
cost
Pric
e-Fi
nanc
ial
Fuel
Sup
ply
OP
EN
HL
HL
LL
45M
ajor
dis
rupt
ions
in m
arke
ts, g
as fu
ture
sM
onito
r for
ecas
ts a
s th
at ti
me
com
es
clos
er
Est
ablis
h fir
m g
as s
uppl
y an
d tra
nspo
rt ag
reem
ents
thro
ugh
com
petit
ive b
iddi
ng
proc
ess
CR
B p
roce
ssD
avid
Sw
iech
Y3.
0$
P
M in
put
0.10
0.3
$
N
4C
hang
es in
trad
e ag
reem
ents
impa
ct ta
riffs
fo
r im
porte
d go
ods,
incr
easi
ng p
rices
re
sulti
ng in
a c
hang
e or
der
Pric
e-Fi
nanc
ial
Con
tract
OP
EN
ML
HL
LL
27S
tate
and
Fed
eral
legi
slat
ion
and
agen
cy
activ
ities
Mon
itor S
tate
and
fede
ral l
egis
latio
n an
d ag
ency
act
ivitie
s.E
xplo
re o
ptio
ns, C
RB
Pro
cess
Den
nis
B D
ecat
orY
4.3
PM
inpu
t0.
20
0.
9$
N
5A
n in
sura
ble
even
t cau
sing
dam
age
to th
e fa
cilit
y oc
curs
requ
iring
DTE
to p
ay a
de
duct
ible
Pric
e-Fi
nanc
ial
Em
erge
nt E
vent
OP
EN
mm
mM
ML
39H
uman
per
form
ance
, site
con
ditio
nsIn
sura
nce
clai
m p
roce
ssS
afet
y pl
an, s
afet
y ob
serv
atio
ns. H
uman
P
erfo
rman
ce o
bser
vatio
nsO
btai
n in
sura
nce
Pla
nned
trai
ning
with
new
sta
ffC
risis
Inci
dent
Res
pons
e P
lan
Inve
stig
ate
even
t and
take
ap
prop
riate
act
ions
and
file
in
sura
nce
clai
m, C
RB
Pro
cess
Ran
dall
J K
ulha
nek
N2.
0
P
M in
put
0.05
0.1
$
N
6A
n ev
ent c
ausi
ng d
amag
e to
the
faci
lity
belo
w
the
insu
ranc
e de
duct
ible
occ
urs
requ
iring
D
TE to
pay
for r
epai
rs
Pric
e-Fi
nanc
ial
Em
erge
nt E
vent
OP
EN
MM
ML
ML
33H
uman
per
form
ance
, site
con
ditio
nsS
afet
y pl
an, s
afet
y ob
serv
atio
ns. H
uman
P
erfo
rman
ce o
bser
vatio
nsO
btai
n in
sura
nce
Pla
nned
trai
ning
with
new
sta
ffC
risis
Inci
dent
Res
pons
e P
lan
Inve
stig
ate
even
t and
take
ap
prop
riate
act
ions
, CR
B
Pro
cess
Ran
dall
J K
ulha
nek
N2.
0
P
M in
put
0.05
0.1
$
N
7S
ubm
ittal
revie
w tu
rnar
ound
is s
low
cau
sing
E
PC
del
ays/
cost
(eng
inee
ring
and
othe
r do
cum
ent r
evie
ws
requ
ire m
ore
time)
Ow
ner D
elay
sO
wne
r Cau
sed
OP
EN
ll
LL
LL
5In
tern
al re
sour
ce a
vaila
bilit
y, s
ched
ule
Wor
k w
ith C
OE
's to
ens
ure
adeq
uate
re
sour
ces
are
avai
labl
e w
hen
need
ed, p
lan
reso
urce
s in
IRP
, DTE
rely
on
HD
R fo
r de
sign
revie
ws,
min
imiz
e re
quire
d re
view
s.
Util
ize
sche
dule
floa
t, C
RB
P
roce
ssC
athe
rine
E
Woo
dsN
1.0
$
PM
inpu
t0.
02
0.
0$
N
8In
terv
ener
s ar
e ab
le to
cau
se C
ON
app
rova
l de
lays
(with
sch
edul
e re
cove
ry p
ossi
ble)
. O
r, in
terv
ener
s ar
e ab
le to
cau
se a
pau
se o
r de
lay
in th
e sc
hedu
le th
roug
h pe
rmitt
ing
or
appe
als
thro
ugh
the
cour
ts
Ow
ner D
elay
sC
ON
Fili
ngO
PE
NL
HH
LL
L13
Mon
itor I
nter
veno
rs fo
r pot
entia
l act
ivity
ar
ound
env
ironm
enta
l per
mitt
ing
Inte
rven
ors
and
prot
esto
rs
Inte
rven
or p
artic
ipat
ion
and
PS
CR
and
ot
her r
ate
case
s.
Man
age
regu
lato
ry a
nd le
gal p
roce
sses
Util
ize
sche
dule
floa
t, R
educ
e re
view
s re
quire
d, C
RB
Pro
cess
Ran
dall
J K
ulha
nek
CO
N a
ppro
ved,
but
inte
rven
ers
have
file
an
appe
al.
Con
tinue
to m
onito
r.
Y10
6.0
$
P
M in
put
0.01
0.5
$
Y
9D
TE/c
raft
unio
n la
bor s
trike
Ow
ner D
elay
sC
raft
Labo
rO
PE
NL
MH
LL
L11
DTE
Lab
or a
gree
men
ts fo
r uni
ons
Labo
r Trip
artit
e M
eetin
gsM
anag
e D
TE c
ontra
cts,
mon
itor o
ther
co
ntra
cts,
mai
ntai
n re
latio
nshi
p w
ith c
raft
labo
r uni
ons
(trip
artit
e)
Util
ize
sche
dule
floa
t, C
RB
P
roce
ssD
enni
s B
Dec
ator
Y2.
5$
P
M in
put
0.05
0.1
$
N
10S
tart
up /
com
mis
sion
ing
dela
ys in
clud
ing
lack
of s
pare
par
ts a
nd s
uppl
ies,
MIS
O G
IA
proc
ess
dela
ys, I
TC d
esig
n an
d co
nstru
ctio
n de
lays
cau
sing
the
need
for a
ltern
ative
bac
k fe
ed p
ower
to m
aint
ain
com
mis
sion
ing
sche
dule
Ow
ner D
elay
sS
tartu
p &
C
omm
issi
onin
gO
PE
Nm
MH
LL
L33
Del
ivery
of s
pare
par
ts a
nd s
uppl
ies,
MIS
O
GIA
, ITC
con
stru
ctio
n, F
ER
C a
ppro
vals
, G
as S
uppl
y co
ntra
ct a
nd c
onst
ruct
ion;
S
tart
up s
ched
ule
coor
dina
tion
Mon
itor a
nd in
fluen
ce e
xter
nal p
roce
sses
(M
ISO
, ITC
FE
RC
), M
anag
e sp
are
parts
pr
ocur
emen
t, M
anag
er s
tart
up
coor
dina
tion
activ
ities
Util
ize
sche
dule
floa
t, im
plem
ent a
ltern
ative
sou
rces
fo
r bac
k fe
ed p
ower
, inc
ur
colla
tera
l pay
men
ts, C
RB
P
roce
ss
Den
nis
B D
ecat
or
Y27
.0$
PM
inpu
t0.
20
5.
4$
N
11A
djac
ent h
azar
d(s)
cau
se p
oten
tial f
or
shut
dow
n of
con
stru
ctio
n an
d sc
hedu
le
dela
ys re
sulti
ng in
a c
hang
e or
der
Ow
ner D
elay
sE
mer
gent
Eve
ntO
PE
NM
Mm
mm
m45
Mai
ntai
n aw
aren
ess
of a
djac
ent f
acili
ties
plan
sD
ean
Pea
kers
ope
ratio
ns.
Vec
tor g
as li
ne
cros
sing
the
Dea
n ga
s la
tera
l
Coo
rdin
ate
plan
s w
ith a
djac
ent f
acili
ties.
Mai
ntai
n es
tabl
ishe
d si
te s
epar
atio
n ag
reem
ent
Exp
lore
opt
ions
, CR
B P
roce
ssS
cott
D S
obas
N2.
5
P
M in
put
0.01
0.0
$
Y
12O
wne
r del
ays/
susp
ends
site
wor
k O
wne
r Del
ays
Ow
ner C
ause
dO
PE
NL
hh
LL
L13
Con
tract
or s
afet
y pe
rform
ance
and
co
mpl
ianc
e w
ith la
ws
and
perm
its.
Con
tract
or c
onfo
rman
ce to
con
tract
sp
ecifi
catio
ns.
Mon
itor c
ontra
ctor
saf
ety
prog
ram
.Mon
itor
cont
ract
or c
ompl
ianc
e w
ith p
erm
its, l
aws,
re
gula
tions
Exp
lore
opt
ions
, CR
B P
roce
ss
- Kie
wit S
afet
y Te
am is
on
site
m
onito
ring
activ
ities
and
wo
rkin
g wi
th c
ontra
ctor
s on
sa
fe w
ork
prat
cies
Sco
tt D
Sob
as
Y1.
0
P
M in
put
0.05
0.1
$
Y
13O
wne
r cau
sed
labo
r con
stra
ints
(res
ourc
es
pulle
d to
wor
k on
out
ages
or o
ther
prio
rity)
Ow
ner D
elay
sO
wne
r Cau
sed
OP
EN
MM
LL
LL
21P
lann
ed, o
r sig
nific
ant f
orce
d, o
utag
es a
t ot
her f
acili
ties.
Hiri
ng le
vels
ava
ilabl
e fro
m
loca
ls (t
ripar
tite
mee
tings
)
Coo
rdin
ate
plan
s w
ith o
ther
faci
litie
s.E
xplo
re o
ptio
ns, C
RB
Pro
cess
Mic
hael
E B
anks
Will
con
tinue
to m
onito
r as
the
hirin
g pl
an is
ex
ecut
edN
5.0
PM
inpu
t0.
02
0.
1$
Y
14O
wne
r's c
ost f
or s
tartu
p fu
el in
crea
se d
ue to
a
perfo
rman
ce re
-test
Sco
peS
cope
OP
EN
ML
HM
LL
33S
tart
up re
adin
ess,
com
mis
sion
ing
activ
ities
Mon
itor c
omm
issi
onin
g ac
tiviti
es a
nd s
tart
up re
adin
ess
utili
zing
PD
RI p
roce
ssC
RB
Pro
cess
Mic
hael
E B
anks
Y3.
3$
P
M in
put
0.05
0.2
$
N
15D
iffic
ulty
ope
ratin
g ne
w te
chno
logy
ext
endi
ng
star
t-up
/ com
mis
sion
ing
reso
urce
s fro
m
PIE
/EP
C
Sco
peE
quip
men
t-Te
chno
logy
OP
EN
MM
LM
LL
27O
pera
tor t
rain
ing
and
read
ines
sP
riorit
ize
& M
onito
r pro
gres
s of
pro
cedu
res
Mon
itor t
rain
ing
activ
ities
and
sta
rt up
re
adin
ess
utili
zing
PD
RI p
roce
ss,
W
e ar
e br
ingi
ng in
3 d
iffer
ent 3
rd p
arty
tra
iner
s in
Oct
201
9, to
und
erst
and
thei
r su
ppor
t in
train
ing
our s
taff
on p
roce
dure
w
ritin
g, w
ritin
g pr
oced
ures
and
dev
elop
ing
Web
Ex
styl
e tra
inin
g gu
ides
S
ched
ule
Writ
er's
wor
ksho
p so
we
can
take
ow
ners
hip.
CR
B P
roce
ssJe
rry D
Sou
cy II
N0.
1$
P
M in
put
0.10
0.0
$
N
19O
wne
r req
uire
s eq
uipm
ent s
ubst
itutio
ns o
r sc
ope
chan
ges
afte
r neg
otia
tion
are
com
plet
ed (u
nfor
seen
sco
pe c
hang
es)
Sco
peS
cope
OP
EN
HM
HM
LM
75Te
chni
cal s
peci
ficat
ion
nego
tiatio
ns,
engi
neer
ing
and
proc
urem
ent p
roce
sses
co
ntin
ue w
ith n
egot
iatio
ns o
n co
st im
pact
s
DTE
and
OE
det
aile
d re
view
of b
id
tech
nica
l offe
ring,
sco
pe a
nd e
xcep
tions
Req
uire
bus
ines
s ca
se to
su
ppor
t cha
nge,
CR
B P
roce
ssM
icha
el E
Ban
ksO
n-go
ing
proc
ess.
Util
izin
g bu
sine
ss c
ase
eval
uatio
n fo
r app
ropr
iatio
n of
fund
s.Y
10.0
$
P
M in
put
0.90
9.0
$
Y
20C
hang
es in
cod
e / r
egul
atio
ns re
sult
in
addi
tiona
l cos
tS
cope
Sco
peO
PE
NM
LM
LL
M27
Reg
ulat
ors
chan
ge a
cod
e or
regu
latio
nE
ast C
hina
& C
hina
Tow
nshi
ps o
rdin
ance
New
sta
te g
over
nmen
t
Mon
itor r
egul
atio
ns a
nd c
ode
Req
uest
wai
ver,
expl
ore
alte
rnat
ives,
CR
B P
roce
ssD
enni
s B
Dec
ator
N5.
0$
P
M in
put
0.20
1.0
$
N
21U
nkno
wn
unde
rgro
und
cond
ition
s /
cont
amin
atio
n ca
use
proj
ect d
elay
s /
miti
gatio
n co
st
Sco
peS
cope
OP
EN
Lm
lL
LM
9S
oil b
orin
gs id
entif
y is
sue,
exc
avat
ion
iden
tifie
s is
sue
Ele
ctric
T-L
ine,
Gas
Lat
eral
Hea
vy h
aul r
oute
Mon
itor a
dditi
onal
soi
l bor
ings
, mon
itor
exca
vatio
n pr
oces
sE
xplo
re o
ptio
ns fo
r miti
gatio
n,
CR
B P
roce
ssS
cott
D S
obas
UG
act
iviti
es a
re m
ostly
com
plet
e as
of
12/2
/201
9 - R
ecom
men
d re
duci
ng th
e lik
lieho
od, s
ched
ule,
cos
t & s
cope
to "
L"
N6.
0$
P
M in
put
0.03
0.2
$
N
22D
isco
very
of a
rtifa
cts
on s
ite c
ause
co
nstru
ctio
n de
lays
/ co
stS
cope
Sco
peO
PE
NL
LL
LL
L5
Soi
l bor
ings
iden
tify
issu
e, e
xcav
atio
n id
entif
ies
issu
eE
lect
ric T
-Lin
e, G
as L
ater
al
Pha
se 1
arc
haeo
logy
sur
vey
if ne
eded
, re
view
NH
RP
if n
eede
d, m
onito
r add
ition
al
soil
borin
gs, m
onito
r exc
avat
ion
proc
ess
Exp
lore
opt
ions
for m
itiga
tion,
ne
gotia
te p
lan
with
Sta
te, C
RB
P
roce
ss
Sco
tt D
Sob
asTh
is ri
sk it
em o
nly
assu
mes
an
even
t tha
t can
be
ove
rcom
e an
d st
ill m
eet t
he d
esire
d C
OD
. S
imila
r to
Ris
k 21
; the
UG
sco
pe is
nea
rly
com
plet
e an
d ex
posu
re to
unc
over
ing
artif
acts
ha
s be
en g
reat
ly re
duce
d. R
ecom
men
d re
duci
ng th
e ris
k va
lues
to "
L"
N0.
5$
P
M in
put
0.01
0.0
$
Y
23M
ISO
DP
P S
tudi
es in
dica
te a
ffect
ed s
yste
m
upgr
ade
cost
s or
add
ition
al IT
C c
osts
that
are
no
t rei
mbu
rsab
le
Sco
peM
ISO
OP
EN
lM
HL
LM
13M
ISO
GIA
pro
cess
Num
ber o
f app
lican
ts in
the
cue
MIS
O P
GIA
pro
cess
Mon
itor t
he P
JM a
ffect
ed s
yste
ms
stud
y Tr
ack
thro
ugh
Issu
e Lo
g/M
ngm
t
Act
ively
mon
itor M
ISO
and
PJM
pr
oces
ses,
Com
mun
icat
e as
app
ropr
iate
w
ith IT
CN
egot
iatin
g w
ith M
ISO
and
affe
cted
sys
tem
pa
rties
on
iden
tifie
d ite
ms
Wor
k w
ith IT
C o
n op
tions
, CR
B
Pro
cess
Exe
cute
cha
nge
requ
est;
requ
iring
use
of c
ontin
genc
y.
Ran
dall
J K
ulha
nek
GIA
exp
ecte
din
June
202
0. M
PFC
A p
roce
ss
near
ing
conc
lusi
on
Y5.
0$
P
M in
put
0.05
0.3
$
N
27Is
sues
occ
ur w
ith p
erm
itsS
cope
Per
mitt
ing
OP
EN
mL
LL
LL
15P
erm
ittin
g re
quire
men
tsG
as la
tera
l per
mitt
ing
Ele
ctric
T-L
ine
perm
ittin
g
Mon
itor p
erm
ittin
g pr
oces
ses.
Exp
lore
opt
ions
, CR
B P
roce
ssS
cott
D S
obas
As
of 1
1/15
/19
AH
J ha
ve is
sued
per
mits
for t
he
"T"
lline
towe
r sco
pe. W
ill c
ontin
ue to
co
ordi
nate
with
Vec
tor/D
TE G
as o
n th
e st
atus
of
per
mits
for t
heir
scop
e.
N0.
5
P
M in
put
0.05
0.0
$
Y
28E
xtre
me
cond
ition
s oc
cur i
nclu
ding
forc
e m
ajeu
re e
vent
s re
sulti
ng in
con
stru
ctio
n de
lays
Sco
peE
mer
gent
Eve
ntO
PE
Nh
hh
Lh
L85
Wea
ther
Forc
e m
ajeu
re e
vent
, CO
VID
-19
pand
emic
Mon
itor w
eath
er fo
reca
st to
min
imiz
e im
pact
s. M
onito
r CO
VID
-19
pand
emic
de
velo
pmen
ts
CR
B P
roce
ssS
cott
D S
obas
Larg
e am
ount
of U
G C
ivil
work
is c
ompl
ete
- W
eath
er is
stil
l a ri
sk.
Y15
.0
PM
inpu
t0.
70
10
.5$
Y
31V
alue
of g
ener
atio
n du
ring
star
t-up
and
test
ing
is lo
wer
than
exp
ecte
d in
crea
sing
net
co
st
Pric
e-Fi
nanc
ial
Con
tract
OP
EN
HL
HL
LL
45P
rice
of e
nerg
y at
tim
e of
gen
erat
ion
Mon
itor G
en O
ps F
orec
asts
Mon
itor p
rice
of e
nerg
yC
RB
Pro
cess
Ran
dall
J K
ulha
nek
Gen
Ops
risk
. W
ill tr
ack
dow
n ap
prop
riate
co
ntac
t tha
t our
Ris
k O
wne
r will
wor
k w
ith.
Y2.
1$
P
M in
put
0.40
0.8
$
N
32M
ajor
equ
ipm
ent s
uppl
iers
are
una
ble
to
prov
ide
timel
y de
liver
y an
d or
acc
epta
ble
qual
ity re
quire
men
ts.
Non
-Ow
ner
Del
ays
Equ
ipm
ent-
Tech
nolo
gyO
PE
NL
HH
HL
L17
Sup
plie
r fin
anci
al p
ositi
ons
Sup
plie
r equ
ipm
ent i
ssue
s an
d vib
ratio
nM
onito
r sup
plie
rs fi
nanc
ial p
ositi
ons
Insp
ectio
n po
ints
thro
ugho
ut tr
avel
pat
hH
ave
Kie
wit
engi
neer
at p
ipe-
fab
war
ehou
se
Kie
wit
Y5.
0$
D
efau
lt0.
05
0.
3$
Y
32.0
$
Impa
cts
![Page 20: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/20.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 19
Appendix C – Progress Photos
April 2019
May 2019
June 2019
![Page 21: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/21.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 20
July 2019
August 2019
September 2019
![Page 22: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/22.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 21
October 2019
November 2019
December 2019
![Page 23: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/23.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 22
January 2020
February 2020
![Page 24: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy](https://reader030.vdocument.in/reader030/viewer/2022012714/61ac8c850af509414b7c3a12/html5/thumbnails/24.jpg)
Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report
Page | 23
March 2020