lauren d. donofrio (313) 235-4017 lauren.donofrio@dteenergy

24
April 27, 2020 Ms. Lisa Felice Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Lansing, Michigan 48917 Re: In the matter of the Application of DTE Electric Company for approval of Certificates of Necessity pursuant to MCL 460.6s, as amended, in connection with the addition of a natural gas combined cycle generating facility to its generation fleet and for related accounting and ratemaking authorizations. MPSC Case No. U-18419 Dear Ms. Felice: Attached for electronic filing in the above-captioned matter please find DTE Electric Company’s BWEC Interim Report. Very truly yours, Lauren D. Donofrio LDD/lah Encl. Lauren D. Donofrio (313) 235-4017 [email protected] DTE Energy Company One Energy Plaza, 1635 WCB Detroit, MI 48226-1279

Upload: others

Post on 05-Dec-2021

11 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

April 27, 2020

Ms. Lisa Felice Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Lansing, Michigan 48917 Re: In the matter of the Application of DTE Electric Company for approval of

Certificates of Necessity pursuant to MCL 460.6s, as amended, in connection with the addition of a natural gas combined cycle generating facility to its generation fleet and for related accounting and ratemaking authorizations.

MPSC Case No. U-18419 Dear Ms. Felice: Attached for electronic filing in the above-captioned matter please find DTE Electric Company’s BWEC Interim Report. Very truly yours, Lauren D. Donofrio LDD/lah Encl.

Lauren D. Donofrio (313) 235-4017 [email protected]

DTE Energy Company One Energy Plaza, 1635 WCB Detroit, MI 48226-1279

Page 2: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 1

Blue Water Energy Center

Interim Status Report

April 27, 2020

Page 3: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 2

Contents Blue Water Energy Center Status Report to the Commission ...................................................................... 3

1.0 - Progress Summary ............................................................................................................................ 3

2.0 - Safety ................................................................................................................................................ 6

Table 2.1 Summary of Safety Performance to Date. ............................................................................ 6

3.0 - Schedule ............................................................................................................................................ 6

Figure 3.1 – Summary Schedule ............................................................................................................ 7

Figure 3.2 – Project Progress ................................................................................................................ 7

Table 3.1 Major Project Milestones ...................................................................................................... 8

4.0 - Cost ................................................................................................................................................... 8

Figure 4.1 – Project Financials .............................................................................................................. 8

5.0 - Quality ............................................................................................................................................... 9

6.0 - Risk .................................................................................................................................................. 10

7.0 – Commercial Operation ................................................................................................................... 10

Table 7.1 BWEC GIA Conditional Network Upgrades ......................................................................... 11

8.0 – Workforce Planning........................................................................................................................ 12

9.0 – Summary ........................................................................................................................................ 12

Appendix A – Permit Status ........................................................................................................................ 14

Appendix B – Risk Register .......................................................................................................................... 17

Appendix C – Progress Photos .................................................................................................................... 19

Page 4: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 3

Blue Water Energy Center Status Report to the Commission

DTE Electric is suppling this report in compliance with the following provision.

MCL 460.6s (7)

The utility shall annually file, or more frequent if required by the commission, reports to the commission regarding the status of any project for which a certificate of necessity has been granted under subsection (4), including an update concerning the cost and schedule of that project.

1.0 - Progress Summary Certificates of necessity were approved by the Michigan Public Service Commission on April 27, 2018 for DTE Electric’s proposed Blue Water Energy Center (BWEC) granting that:

• The power to be supplied by the new facility is needed. • The new facility represents the most reasonable and prudent means of meeting

the power need. • The estimated capital and financing costs, and the estimated cost of power from

the facility will be recoverable in rates from the company’s customers.

The Commission approved recovery of up to $951.8 million for the construction of the new generating facility.

DTE Electric (the Company) authorized Kiewit Engineering (MI) Co. (its Engineering, Procurement, Construction (EPC) contractor) limited notice to proceed with the project on April 30, 2018 and full notice to proceed with the project on July 30, 2018. With the notices, Kiewit has commenced engineering of the facility, procurement of equipment and materials, and site construction. As of April 1, 2020, the overall project (including engineering, procurement, and construction) is approximately 52% complete.

On March 23, 2020, Executive Order 2020-21 was issued by Governor Whitmer requiring a temporary suspension of activities that are not necessary to sustain or protect life in response to the COVID-19 pandemic. The order was in effect from March 24, 2020 to April 13, 2020 and was subsequently extended to April 30, 2020 by Executive order 2020-42. Non-critical work was suspended on the BWEC construction site in response to the Governor’s order. Critical activities including site security, care and maintenance, and irrevocable deliveries were maintained. On April 24th, DTE Electric and Kiewit implemented a phased four week plan to restart construction in a safe and orderly manner. Week one focused on finalizing new safety protocols and

Page 5: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 4

notifying parties of the restart including local governments and trade unions. The second week involves preparing the site for work to resume and initiating craft rehiring and orientation to new safety protocol. Construction resumes on the third week (beginning May 4th) with day shift only. Second shift work resumes on week four. As of April 27th, the project remains on schedule and on budget. However, the Company is still analyzing impacts of the pandemic and work suspension including extended staff, equipment rental, care and maintenance costs; subcontractor and supplier impacts; remobilization costs; and new government executive order compliance. The EPC is entitled by contract to a change order to recover expenses incurred as a result of the suspension. Any change order would require the use of project contingency. Permitting activities are ongoing. Critical permits, including the air permit, have been obtained. All other remaining permits are being obtained as needed and in a timely manner. The current status of all permits is included in Appendix A.

DTE Electric submitted a Generator Interconnection Agreement (GIA) application to MISO on June 5, 2017 for BWEC. The GIA process consists of three Definitive Planning Phases (DPPs) and execution of a GIA. The Company’s application is included in MISO’s August 2017 interconnection queue. All three of the DPPs are now completed for the August 2017 queue.

DTE Electric is working closely with MISO and the ITC to ensure the transmission interconnection is in place on time. A provisional GIA with MISO and ITC is in place to support the contractual date for DTE Electric to provide back feed power to the project. A permanent GIA and associated facilities construction agreement are expected to be finalized in the second quarter of 2020, as discussed below in section 7.0 – Commercial Operation.

Natural gas transportation, storage, and lateral pipeline/interconnection contracts have been executed. Construction of the natural gas lateral to BWEC is expected to be complete in the first quarter of 2021. Gas supply agreements will be negotiated and in place to supply the facility during startup and commissioning in 2021 and commercial operations in 2022.

Engineering of the BWEC is progressing as planned and is currently 88% complete. To date over 6,200 engineering drawings have been generated for review.

The most significant procurement component for the project is the power island, which includes the Combustion Turbines (CTs), Combustion Turbine Generators (CTGs), Heat Recovery Steam Generators (HRSGs), Steam Turbine (ST), Steam Turbine Generator (STG), and Distributed Control System (DCS). General Electric is under contract with Kiewit to provide the power island. The power island is on plan and is currently 96% engineered. Most of the major components of the power island have been delivered to

Page 6: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 5

site with a final shipment expected in the first week of May 2020. The DCS is in final configuration and is expected to be provided to the site in the third quarter of 2020.

An incident occurred during the delivery of one of the HRSG modules in October of 2019, resulting in damage to the module. Repair of the module is progressing with no schedule impact to the project identified at this time. DTE is not responsible for the cost of the repairs.

In addition to the power island, the following major procurements have been awarded since our last report in April of 2019:

• Transmission lead line poles, conductors, and insulators • Low energy fabricated pipe • Warehouse structures and installation • Drilled piers for switchyard and lead line poles • Fire protection • Site security

Site construction activities have progressed. Since our last report in April of 2019 the following progress has been made:

• Raw water intake line placement has been completed • Deep foundations (H-pile) have been completed • Cooling tower basin has been placed and the structure has been erected • Foundations and pedestals for both CT trains and the ST have been placed • HRSG modules, CTs, CTGs have been set • HRSGs have been enclosed • Warehouse installation completed

In addition, the following construction activities are in progress:

• Underground piping, electrical duct bank installation, and electric cable pulls • Main and finger racks and above ground piping • Switchyard foundations placement • Air inlet structure erection • Administration building erection and internal finishing • Field fabricated tank assembly • Water treatment building foundations placement, equipment set, and building

erection • Auxiliary boiler installation • Steam turbine condenser assembly and steam turbine building erection • Cooling tower baffle and mechanical equipment installation

Progress photos of the project are included in Appendix C.

Page 7: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 6

2.0 - Safety Safety is the number one priority for the Blue Water Energy Center. To date there have been two recordable injuries for the project. The Recordable Injury Rate (RIR) is currently 0.41 with more than 970,000 earned hours to date. In addition, there have been fourteen first aids and seven near misses for the project. Table 2.1 provides a summary of project safety metrics.

Two recordable injuries have occurred since our last report in April of 2019:

• During the setup of a tool used to perform a pipe fusion operation, the tool became locked in an incorrect position. While attempting to correct the position of the tool, a pipefitter’s finger was caught in a pinch point resulting in an injury to the finger.

• A boilermaker on a ladder experienced a lanyard release that struck them on the finger. The impact to the finger was initially categorized as a First Aid, it was later diagnosed as a fracture and reclassified as a recordable injury.

Kiewit has completed an investigation and has taken corrective action for all incidents that have occurred on the project.

Table 2.1 Summary of Safety Performance to Date. Table 2.1 – BWEC Safety Metrics

Recordable Injury Rate

Lost Time Incidents

First Aids

Near Misses

0.41 0 14 7

Both DTE Electric and Kiewit are dedicated to ensuring the construction project is managed in a safe manner in accordance with all applicable laws. Kiewit is solely responsible for initiating, maintaining, and supervising all safety precautions and programs in the performance of the work. Kiewit protocol requires that all individuals who enter the construction site must first complete safety orientation, including those who will be escorted. Proper personal protective equipment is also required at all times while on site.

In addition, BWEC and MIOSHA entered into a partnership agreement for the construction project in October of 2019.

3.0 - Schedule The new Blue Water Energy Center is expected to be commercially available and be included as a resource available to meet the Company’s capacity requirement for the MISO planning year beginning in June of 2022. The Company continues to analyze

Page 8: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 7

impacts of the COVID-19 pandemic that may potentially impact the commercial operation date (COD). Figure 3.1 provides a summary schedule.

Figure 3.1 – Summary Schedule

A detailed integrated schedule is maintained for the project that comprehensively describes the activities and associated milestones required to complete the project. The schedule is managed by Kiewit. The schedule is reviewed in detail each month by the Company. The schedule has been baselined, so going forward any changes will require approval from the project’s Change Review Board.

Figure 3.2 compares actual construction progress earned (completed) to the baseline plan (approved schedule).

Figure 3.2 – Project Progress

The Schedule Performance Index (SPI) is a measure of schedule efficiency, or how well the project team is using time. An SPI greater than 1.0 indicates the project has earned (or completed) more work than planned. An SPI less than 1.0 indicates that less work has been earned versus the baseline plan or schedule. Currently, SPI for the project is slightly lower than plan due to the COVID-19 suspension but is not projected to impact project completion. Progress is being monitored by both the Company and Kiewit. Schedule impacts due to the COVID-19 pandemic are still being analyzed.

Milestones have been established for the project baseline schedule to track progress toward completion. Table 3.1 summarizes the major contractual milestones for the project.

Electrical Interconnection

Gas Lateral

Engineer, Procure, Construct

Performance Testing

Figure 3.1 - Summary Schedule2018 2019 2020 2021 2022

DPP-1 DPP-2 DPP-3 GIA Complete

CompleteUnder Contract

LNTP FNTP Mobilize Major Deliveries Complete

SubstantialCompletion

Demobilize

First Fire

Demonstrate Capacity

COD

April2020

Page 9: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 8

Table 3.1 Major Project Milestones Table 3.1 Major Contract Milestones

Milestone Date Status Limited Notice to Proceed 04/27/18 Complete Full Notice to Proceed 07/30/18 Complete EPC Initial Mobilization 08/15/18 Complete EPC Full Mobilization 03/04/19 Complete Gas Lateral Complete 03/31/21 Site Back Feed Power Available 05/26/21 Fuel Gas Available 06/18/21 CCGT 1 First Fire 09/09/21 CCGT 2 First Fire 09/20/21 MISO Demonstration Test 03/01/22 Substantial Completion 03/31/22 Commercial Operation 06/01/22

4.0 - Cost On April 27, 2018, the Commission granted certificates of necessity assuring recovery of up to $951.8 million to construct the Blue Water Energy Center.

Figure 4.1 – Project Financials

A baseline financial forecast has been established for the project as shown in Figure 4.1 as the planned line. To date, the project is on plan indicated by the green bars in the figure. Spend to date on the project, including costs incurred prior to receiving the CON, is $601 million.

The project is managing several risks that are discussed below in section 6.0 - Risk. The project estimate at completion (EAC) remains at the Commission authorized spend. However, the impacts of the COVID-19 pandemic are still being analyzed and may impact the EAC.

Both DTE Electric and Kiewit are committed to ensure opportunities for Michigan and diversity enterprises. The Company and Kiewit continue to reach out to qualified Michigan and diversity businesses.

To that end, Kiewit has implemented a comprehensive plan to ensure that Michigan enterprises have opportunity to competitively bid on the supply of materials, equipment

Page 10: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 9

and subcontracted work. Kiewit has agreed to a Michigan spend target of $200 million and is currently on track to meet the target. To date, Kiewit has achieved $145 million in Michigan spend.

DTE Electric and Kiewit are committed to the Michigan work force and the utilization of Michigan craft labor in the construction of the Blue Water Energy Center. The Company’s target is that 90% of the craft labor for the project will be comprised of Michigan residents. To date, Michigan craft labor has accounted for 95% of total craft labor for the project.

At the time of the CON filing, the Company believed that adequate craft labor from Michigan would be available for the project. Since the CON filing, a significant number of new large construction projects have been announced within the state. This is creating a strain on the availability of Michigan craft labor. This is a risk for the project that is being carefully monitored and managed by both the Company and Kiewit.

DTE meets regularly with Michigan labor union leadership to discuss current and future projects at DTE and across the state and the skilled trades needed for the work. These tripartite meetings help both the Company and unions understand and plan for the supply and demand for skilled resources. Kiewit is now participating in the tripartite meetings. In addition, Kiewit has established a monthly meeting cadence with the Michigan union locals.

5.0 - Quality The Company has worked closely with Kiewit to implement a quality program for the construction of the Blue Water Energy Center to ensure the facility meets all defined requirements. Kiewit’s Quality Management System (QMS) will be deployed throughout all phases of the project including engineering, procurement, construction, acceptance testing, and turnover to operations. QMS is consistent with ISO 9001-2008 standards.

The quality program includes observations and inspections at predetermined points during the manufacturing of the major equipment and during construction. Quality inspection specialists will document any non-conformances. Any reported non-conformances will be fully analyzed and resolved before closure. To date, there have been 255 equipment supplier inspections completed with 223 quality non-conformances reported of which 179 have been resolved. There have been 89 non-conformances in field construction of which 74 have been resolved. Additionally, Kiewit is inspecting all piping welds. To date, 8 welds have failed final inspection requiring remediation.

The Company continues to work very closely with Kiewit and GE on the performance and reliability of the HA-class combustion turbines since the turbine blade failure in 2018. There have been no significant failures on the combustion turbine components since the last report to the Commission. The BWEC project team also maintains our engagement in a user group forum where GE discusses learnings on a regular basis.

Page 11: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 10

6.0 - Risk Risk identification, qualitative and quantitative analysis, management and control is an iterative process that will continue throughout the life of the project. As mentioned in the Cost section of this report, significant risk remains for the project. The COVID-19 pandemic is a significant risk to the project that has occurred for which the full impact is still being analyzed.

Two risk events have occurred resulting in the use of MPSC authorized contingency, including the effects of tariffs imposed after the contract was signed for $5.0M and additional costs for remediating differing soil conditions for $0.4M. Both events were included in the project risk register and have been formally reviewed and approved by the project change review board. The remaining MPSC authorized contingency for the project is $12.4M.

The current risk register for the project includes 23 potential risks that are being actively managed. This is a reduction of two from the last report filed on April 26, 2019. Since the April 2019 report, the risk associated with hydrostatic test water requiring offsite disposal has been resolved and closed. The risk associated with potential dock improvements required to accommodate heavy loads delivered by barge did not occur and has been closed. As the project team continues to actively manage project risk, the overall Expected Monetary Value (EMV) of the risk register has been adjusted accordingly.

The Company along with Kiewit will continue to manage all project risks. The current project risk register is included in Appendix B.

7.0 – Commercial Operation The new Blue Water Energy Center currently remains on target to be commercially available for the MISO planning year beginning in June of 2022.  However, impacts to the schedule resulting from the COVID-19 pandemic are still being analyzed.  To be included as a new generation resource for the planning year, BWEC will require a Generator Interconnection Agreement (GIA) to be in place and the facility must be registered in the MISO June Commercial Model for the planning year.  The GIA for BWEC is expected to be in place in June of 2020, per the current MISO schedule, and BWEC will be registered for the June 2022 planning year.  The Commission staff was informed by the Company in September of 2019 that MISO DPP3 study results indicate that several large-scale network upgrades will be included as conditional projects for the BWEC GIA. The conditions could limit BWEC from injecting and delivering its full output onto the transmission grid until the conditional projects are completed. Some of these conditional projects are related to ITC rating reductions on its transmission facilities in DTE’s service territory that occurred in 2018 (after BWEC entered the August 2017 generator interconnection planning cycle). Others

Page 12: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 11

are related to past MISO reliability projects that were approved, but not constructed due to implementation issues. Completion of ITC’s Blue Water Reinforcement project (a.k.a. Crimson or Romeo) which involves rebuilding of the north area grid is one significant condition imposed on BWEC’s GIA. Other conditions include the rebuild of portions of the Lincoln-North East/North West transmission line, rebuild of the MTEP17 Whiting-Custer transmission line project, and construction of the 345kV Meyer substation. As it relates to the Whiting-Custer project, ITC has encountered some challenges implementing the originally proposed solution and proposed a design change on March 24, 2020. MISO is currently evaluating the design change and will notify DTE of the impact on BWEC. As noted in Table 7.1 below, the currently published in-service date for one conditional project exceeds the planned commercial operation date of BWEC. Recently, ITC completed its review of the capital project schedule with DTE and is targeting completion of all conditional projects before BWEC commercial operation. The Company is continuing to work with MISO and ITC regarding in-service dates of all conditional projects and will keep the Commission staff informed of progress.

Table 7.1 BWEC GIA Conditional Network Upgrades

Table 7.1 BWEC GIA Conditional Network Upgrades Network Upgrade In-Service Date Status

MTEP19 Project #15878 Sag Remediation 12/31/21 MTEP Approved

MTEP18 Project #13814 Monroe 345 kV – Lallendorf 345 kV Station Equipment Upgrades

05/01/20 Long Lead Materials Ordered

MTEP19 Project #16028 Caniff – Saturn 120 kV Sag Remediation

12/31/21 MTEP Approved

MTEP19 Project #17164 Blue Water Reinforcement

05/31/22 MTEP Approved

MTEP project #16023 Lincoln-Northeast-Northwest 120 kV Rebuild (overhead portion only Facility ID: 25271)

12/31/22 MTEP Approved

Pontiac - Placid NRIS required sag remediation

12/31/21 Facility Study Complete

Pontiac – Wixom NRIS required sag remediation

12/31/21 Facility Study Complete

MTEP Project #8144 - Construct new 345 kV, double circuit structures, and loop the Kenowa - Argenta 345 kV line into Meyer

06/01/21 Long Lead Materials Ordered

MTEP Project #9864 - Rebuild 9.98 from the Whiting – Custer 120 kV circuit

TBD Awaiting Design Finalization

Page 13: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 12

Table 7.1 BWEC GIA Conditional Network Upgrades Network Upgrade In-Service Date Status

MTEP Project #9887 Pontiac – Wixom 345 kV line sag limit increase

06/01/20 Long Lead Materials Ordered

MTEP Project #13814 Upgrade Monroe 345 kV station equipment

05/01/20 Long Lead Materials Ordered

BWEC will also have to demonstrate that the plant capacity is available by March 1, 2022.  Demonstration of capacity is achieved by meeting MISO Generation Verification Tested Capacity (GVTC) testing requirements.  Both DTE and Kiewit have mitigation plans in place for potential risks that could impact achieving capacity demonstration. Capacity demonstrations will occur prior to MISO commercial operation during a testing period. The output of the generating unit will not be limited due to required conditional network upgrades during this test period as MISO will manage all issues in real-time operation. In the event that BWEC has not demonstrated capacity by March 1, 2022, a deferral can be obtained.  The deferral will require DTE to post credit with MISO for an amount equal to 90 days of the daily Cost of New Entry (CONE) for MISO Zone 7.  Should the deferral occur, the GVTC requirements would need to be met by May 31, 2022.  At this time, DTE does not anticipate requesting a deferral.

8.0 – Workforce Planning To prepare for BWEC commercial operations, a comprehensive staffing plan has been developed to ensure that roles and responsibilities are well defined and that new positions are filled in a timely manner. In addition to the staffing plan, the BWEC project team is developing necessary training, job instructions, and procedures for the new facility. Some of the employees needed at BWEC have been hired, with all employees expected to be in place by the end of 2020. BWEC personnel will undergo 18-24 months of training. The employees will be trained so that they can be deployed to perform startup activities for the plant beginning in 2021, to prepare for full commercial operations in 2022.

DTE Electric has announced the retirement of four power plants by 2022. The employees displaced by the closures will be reassigned to other work within DTE Energy. The Company is committed to its employees and has no intention of layoffs as a result of the future plant closings.

9.0 – Summary The Company is pleased with the progress to date on the new Blue Water Energy Center project. At this time the project remains on schedule and on budget, but the Company continues to analyze the impacts of the COVID-19 pandemic. The project

Page 14: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 13

team is working well with Kiewit and GE to resolve challenges as they occur and to safely maintain schedule. Over the next six months, the team will be working diligently to set and assemble major components, pull electrical wiring, install piping, and erect buildings.

The Company is available to the MPSC for further discussion and to answer questions about this report.

Page 15: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 14

Appendix A – Permit Status Current permit status is show in Table A-1 below.

Table A-1 Project Permit Matrix Permit Applicant Agencies Status

Air Quality Federal Not Required Air Quality State (Permit to Construct) DTE MDEQ Recvd. 07/18 Boiler Permit (Non-HVAC) DTE/EPC E China Recvd. 06/19 Building Permits – Electrical DTE/EPC E China Recvd. 07/19 Building Permits – Elevator DTE/EPC State Need Q2/20 Building Permits – Fire Protection DTE/EPC E China Recvd. 03/20 Building Permits – Mechanical DTE/EPC E China Recvd. 07/19 Building Permits – Mechanical (HVAC) DTE/EPC E China Recvd. 07/19 Building Permits – Sewer Tap DTE St Clair Co Recvd. 03/19 Building Permits – Structural DTE E China Recvd. 05/19 Building Permits – Water Tap DTE E China Recvd. 03/20 Coastal Zone Management Not Required Cultural Resources (SHPO) Not Required Dam Safety Permits Not Required Demolition – General DTE/EPC E China Not Required Demolition – Asbestos (MIOSHA/NESHAPS) DTE MDEQ Not Required Demolition – Explosives (Transport/Storage) Not Required Demolition – Fuel Storage Tanks Not Required Demolition – Lead Abatement Not Required Drains (County) DTE St Clair Co Recvd. 02/19 Drains (Municipal) Not Required Endangered Species Federal Not Required Endangered Species State DTE State Recvd 08/18 Erosion Control Sedimentation County DTE St Clair Co Recvd 07/18 Erosion Control Sedimentation State Not Required Fence Permits DTE/EPC E China Not Required Flood Plain Management DTE/EPC JPA Not Required Ground Water Discharge DTE JPA Recvd 5/19 Hazardous Materials (HAZMAT) Not Required International Waterways Not Required Local Woodlands Not Required Marking & Lighting of Tall Structures (FAA) DTE/EPC FAA Not Required Marking & Lighting of Waterways Not Required Mineral Management Not Required NPDS – Major/Minor DTE MDEQ Recvd 08/18 Nuclear Equipment DTE NRC Need Q2/20 Paving Permit (Local Ordinance) DTE E China Not Required Planning/Zoning (Local Ordinance) DTE E China Recvd 03/19 Public Lighting (Interruption/Modification) DTE E China Need Q1/21

Page 16: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 15

Table A-1 Project Permit Matrix Permit Applicant Agencies Status

Railroad Crossings Not Required Right of Way Easements DTE Recvd. 06/19 Road Crossings / Curb Cut – Local Not Required Road Crossings / Curb Cut – County Not Required Road Crossings / Curb Cut – State DTE/EPC MDOT Recvd. 11/18 Signage Permits (Local Ordinance) DTE/EPC E China Recvd. 11/19 Sanitary Discharge / Removal (Pump/Haul) Not Required Stream / Drain Crossing County Not Required Stream Crossing Federal Not Required Stream Crossing State DTE JPA Not Required Storm Water Discharge (Run-off) DTE JPA See SESC Wild & Scenic Rivers Not Required Wetlands – Local Not Required Wetlands – State DTE/EPC JPA Recvd. 08/18 Certificate of Occupancy DTE E China Need Q3/21

Page 17: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 16

Page 18: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 17

Appendix B – Risk Register

Page 19: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 18

BW

EC C

ombi

ned

Cyc

le P

P Ri

sk R

egis

ter

Wed

nesd

ay A

pril

1, 2

020

Fina

ncia

l Ana

lysi

s

IDR

isk

Even

t Des

crip

tion

Wha

t is

the

even

t?C

ateg

ory

Sub

Cat

egor

ySt

atus

Likelihood

Schedule

Cost

Quality

Safety

Scope

Total Score

Ris

k Ev

ent D

river

s (M

onito

r)R

espo

nse/

Miti

gatio

n St

rate

gy

(Pla

nned

Act

ions

)C

ontin

genc

y Pl

an

(Pla

nned

Act

ions

)R

isk

Ow

ner

Not

es &

Com

men

ts

FA Review Required?

$ Im

pact

(m

illio

ns)

Sour

cePr

obab

ility

EMV

Scheduler Review Required?

2D

TE s

cope

pric

ing

varie

s fro

m C

ON

filin

g (c

urre

nt e

stim

ates

are

RO

Ms)

Pric

e-Fi

nanc

ial

Con

tract

OP

EN

ML

HL

LM

33In

tern

al e

stim

ates

are

stil

l und

er

deve

lopm

ent f

or it

ems

to s

tart

in 2

021

and

2022

, MD

OT

actio

ns

DTE

and

OE

det

aile

d re

view

of o

wne

rs

scop

e an

d es

timat

es, c

ompe

titive

RFP

pr

oces

s

Adj

ust s

cope

, com

petit

ive b

id,

or C

RB

pro

cess

Ran

dall

J K

ulha

nek

Con

tinue

to m

onito

rY

2.5

$

PM

inpu

t0.

50

1.

3$

N

3N

atur

al g

as c

omm

odity

and

tran

spor

tatio

n pr

ices

are

hig

her t

han

plan

ned

incr

easi

ng

star

tup

/ com

mis

sion

ing

cost

Pric

e-Fi

nanc

ial

Fuel

Sup

ply

OP

EN

HL

HL

LL

45M

ajor

dis

rupt

ions

in m

arke

ts, g

as fu

ture

sM

onito

r for

ecas

ts a

s th

at ti

me

com

es

clos

er

Est

ablis

h fir

m g

as s

uppl

y an

d tra

nspo

rt ag

reem

ents

thro

ugh

com

petit

ive b

iddi

ng

proc

ess

CR

B p

roce

ssD

avid

Sw

iech

Y3.

0$

P

M in

put

0.10

0.3

$

N

4C

hang

es in

trad

e ag

reem

ents

impa

ct ta

riffs

fo

r im

porte

d go

ods,

incr

easi

ng p

rices

re

sulti

ng in

a c

hang

e or

der

Pric

e-Fi

nanc

ial

Con

tract

OP

EN

ML

HL

LL

27S

tate

and

Fed

eral

legi

slat

ion

and

agen

cy

activ

ities

Mon

itor S

tate

and

fede

ral l

egis

latio

n an

d ag

ency

act

ivitie

s.E

xplo

re o

ptio

ns, C

RB

Pro

cess

Den

nis

B D

ecat

orY

4.3

PM

inpu

t0.

20

0.

9$

N

5A

n in

sura

ble

even

t cau

sing

dam

age

to th

e fa

cilit

y oc

curs

requ

iring

DTE

to p

ay a

de

duct

ible

Pric

e-Fi

nanc

ial

Em

erge

nt E

vent

OP

EN

mm

mM

ML

39H

uman

per

form

ance

, site

con

ditio

nsIn

sura

nce

clai

m p

roce

ssS

afet

y pl

an, s

afet

y ob

serv

atio

ns. H

uman

P

erfo

rman

ce o

bser

vatio

nsO

btai

n in

sura

nce

Pla

nned

trai

ning

with

new

sta

ffC

risis

Inci

dent

Res

pons

e P

lan

Inve

stig

ate

even

t and

take

ap

prop

riate

act

ions

and

file

in

sura

nce

clai

m, C

RB

Pro

cess

Ran

dall

J K

ulha

nek

N2.

0

P

M in

put

0.05

0.1

$

N

6A

n ev

ent c

ausi

ng d

amag

e to

the

faci

lity

belo

w

the

insu

ranc

e de

duct

ible

occ

urs

requ

iring

D

TE to

pay

for r

epai

rs

Pric

e-Fi

nanc

ial

Em

erge

nt E

vent

OP

EN

MM

ML

ML

33H

uman

per

form

ance

, site

con

ditio

nsS

afet

y pl

an, s

afet

y ob

serv

atio

ns. H

uman

P

erfo

rman

ce o

bser

vatio

nsO

btai

n in

sura

nce

Pla

nned

trai

ning

with

new

sta

ffC

risis

Inci

dent

Res

pons

e P

lan

Inve

stig

ate

even

t and

take

ap

prop

riate

act

ions

, CR

B

Pro

cess

Ran

dall

J K

ulha

nek

N2.

0

P

M in

put

0.05

0.1

$

N

7S

ubm

ittal

revie

w tu

rnar

ound

is s

low

cau

sing

E

PC

del

ays/

cost

(eng

inee

ring

and

othe

r do

cum

ent r

evie

ws

requ

ire m

ore

time)

Ow

ner D

elay

sO

wne

r Cau

sed

OP

EN

ll

LL

LL

5In

tern

al re

sour

ce a

vaila

bilit

y, s

ched

ule

Wor

k w

ith C

OE

's to

ens

ure

adeq

uate

re

sour

ces

are

avai

labl

e w

hen

need

ed, p

lan

reso

urce

s in

IRP

, DTE

rely

on

HD

R fo

r de

sign

revie

ws,

min

imiz

e re

quire

d re

view

s.

Util

ize

sche

dule

floa

t, C

RB

P

roce

ssC

athe

rine

E

Woo

dsN

1.0

$

PM

inpu

t0.

02

0.

0$

N

8In

terv

ener

s ar

e ab

le to

cau

se C

ON

app

rova

l de

lays

(with

sch

edul

e re

cove

ry p

ossi

ble)

. O

r, in

terv

ener

s ar

e ab

le to

cau

se a

pau

se o

r de

lay

in th

e sc

hedu

le th

roug

h pe

rmitt

ing

or

appe

als

thro

ugh

the

cour

ts

Ow

ner D

elay

sC

ON

Fili

ngO

PE

NL

HH

LL

L13

Mon

itor I

nter

veno

rs fo

r pot

entia

l act

ivity

ar

ound

env

ironm

enta

l per

mitt

ing

Inte

rven

ors

and

prot

esto

rs

Inte

rven

or p

artic

ipat

ion

and

PS

CR

and

ot

her r

ate

case

s.

Man

age

regu

lato

ry a

nd le

gal p

roce

sses

Util

ize

sche

dule

floa

t, R

educ

e re

view

s re

quire

d, C

RB

Pro

cess

Ran

dall

J K

ulha

nek

CO

N a

ppro

ved,

but

inte

rven

ers

have

file

an

appe

al.

Con

tinue

to m

onito

r.

Y10

6.0

$

P

M in

put

0.01

0.5

$

Y

9D

TE/c

raft

unio

n la

bor s

trike

Ow

ner D

elay

sC

raft

Labo

rO

PE

NL

MH

LL

L11

DTE

Lab

or a

gree

men

ts fo

r uni

ons

Labo

r Trip

artit

e M

eetin

gsM

anag

e D

TE c

ontra

cts,

mon

itor o

ther

co

ntra

cts,

mai

ntai

n re

latio

nshi

p w

ith c

raft

labo

r uni

ons

(trip

artit

e)

Util

ize

sche

dule

floa

t, C

RB

P

roce

ssD

enni

s B

Dec

ator

Y2.

5$

P

M in

put

0.05

0.1

$

N

10S

tart

up /

com

mis

sion

ing

dela

ys in

clud

ing

lack

of s

pare

par

ts a

nd s

uppl

ies,

MIS

O G

IA

proc

ess

dela

ys, I

TC d

esig

n an

d co

nstru

ctio

n de

lays

cau

sing

the

need

for a

ltern

ative

bac

k fe

ed p

ower

to m

aint

ain

com

mis

sion

ing

sche

dule

Ow

ner D

elay

sS

tartu

p &

C

omm

issi

onin

gO

PE

Nm

MH

LL

L33

Del

ivery

of s

pare

par

ts a

nd s

uppl

ies,

MIS

O

GIA

, ITC

con

stru

ctio

n, F

ER

C a

ppro

vals

, G

as S

uppl

y co

ntra

ct a

nd c

onst

ruct

ion;

S

tart

up s

ched

ule

coor

dina

tion

Mon

itor a

nd in

fluen

ce e

xter

nal p

roce

sses

(M

ISO

, ITC

FE

RC

), M

anag

e sp

are

parts

pr

ocur

emen

t, M

anag

er s

tart

up

coor

dina

tion

activ

ities

Util

ize

sche

dule

floa

t, im

plem

ent a

ltern

ative

sou

rces

fo

r bac

k fe

ed p

ower

, inc

ur

colla

tera

l pay

men

ts, C

RB

P

roce

ss

Den

nis

B D

ecat

or

Y27

.0$

PM

inpu

t0.

20

5.

4$

N

11A

djac

ent h

azar

d(s)

cau

se p

oten

tial f

or

shut

dow

n of

con

stru

ctio

n an

d sc

hedu

le

dela

ys re

sulti

ng in

a c

hang

e or

der

Ow

ner D

elay

sE

mer

gent

Eve

ntO

PE

NM

Mm

mm

m45

Mai

ntai

n aw

aren

ess

of a

djac

ent f

acili

ties

plan

sD

ean

Pea

kers

ope

ratio

ns.

Vec

tor g

as li

ne

cros

sing

the

Dea

n ga

s la

tera

l

Coo

rdin

ate

plan

s w

ith a

djac

ent f

acili

ties.

Mai

ntai

n es

tabl

ishe

d si

te s

epar

atio

n ag

reem

ent

Exp

lore

opt

ions

, CR

B P

roce

ssS

cott

D S

obas

N2.

5

P

M in

put

0.01

0.0

$

Y

12O

wne

r del

ays/

susp

ends

site

wor

k O

wne

r Del

ays

Ow

ner C

ause

dO

PE

NL

hh

LL

L13

Con

tract

or s

afet

y pe

rform

ance

and

co

mpl

ianc

e w

ith la

ws

and

perm

its.

Con

tract

or c

onfo

rman

ce to

con

tract

sp

ecifi

catio

ns.

Mon

itor c

ontra

ctor

saf

ety

prog

ram

.Mon

itor

cont

ract

or c

ompl

ianc

e w

ith p

erm

its, l

aws,

re

gula

tions

Exp

lore

opt

ions

, CR

B P

roce

ss

- Kie

wit S

afet

y Te

am is

on

site

m

onito

ring

activ

ities

and

wo

rkin

g wi

th c

ontra

ctor

s on

sa

fe w

ork

prat

cies

Sco

tt D

Sob

as

Y1.

0

P

M in

put

0.05

0.1

$

Y

13O

wne

r cau

sed

labo

r con

stra

ints

(res

ourc

es

pulle

d to

wor

k on

out

ages

or o

ther

prio

rity)

Ow

ner D

elay

sO

wne

r Cau

sed

OP

EN

MM

LL

LL

21P

lann

ed, o

r sig

nific

ant f

orce

d, o

utag

es a

t ot

her f

acili

ties.

Hiri

ng le

vels

ava

ilabl

e fro

m

loca

ls (t

ripar

tite

mee

tings

)

Coo

rdin

ate

plan

s w

ith o

ther

faci

litie

s.E

xplo

re o

ptio

ns, C

RB

Pro

cess

Mic

hael

E B

anks

Will

con

tinue

to m

onito

r as

the

hirin

g pl

an is

ex

ecut

edN

5.0

PM

inpu

t0.

02

0.

1$

Y

14O

wne

r's c

ost f

or s

tartu

p fu

el in

crea

se d

ue to

a

perfo

rman

ce re

-test

Sco

peS

cope

OP

EN

ML

HM

LL

33S

tart

up re

adin

ess,

com

mis

sion

ing

activ

ities

Mon

itor c

omm

issi

onin

g ac

tiviti

es a

nd s

tart

up re

adin

ess

utili

zing

PD

RI p

roce

ssC

RB

Pro

cess

Mic

hael

E B

anks

Y3.

3$

P

M in

put

0.05

0.2

$

N

15D

iffic

ulty

ope

ratin

g ne

w te

chno

logy

ext

endi

ng

star

t-up

/ com

mis

sion

ing

reso

urce

s fro

m

PIE

/EP

C

Sco

peE

quip

men

t-Te

chno

logy

OP

EN

MM

LM

LL

27O

pera

tor t

rain

ing

and

read

ines

sP

riorit

ize

& M

onito

r pro

gres

s of

pro

cedu

res

Mon

itor t

rain

ing

activ

ities

and

sta

rt up

re

adin

ess

utili

zing

PD

RI p

roce

ss,

W

e ar

e br

ingi

ng in

3 d

iffer

ent 3

rd p

arty

tra

iner

s in

Oct

201

9, to

und

erst

and

thei

r su

ppor

t in

train

ing

our s

taff

on p

roce

dure

w

ritin

g, w

ritin

g pr

oced

ures

and

dev

elop

ing

Web

Ex

styl

e tra

inin

g gu

ides

S

ched

ule

Writ

er's

wor

ksho

p so

we

can

take

ow

ners

hip.

CR

B P

roce

ssJe

rry D

Sou

cy II

N0.

1$

P

M in

put

0.10

0.0

$

N

19O

wne

r req

uire

s eq

uipm

ent s

ubst

itutio

ns o

r sc

ope

chan

ges

afte

r neg

otia

tion

are

com

plet

ed (u

nfor

seen

sco

pe c

hang

es)

Sco

peS

cope

OP

EN

HM

HM

LM

75Te

chni

cal s

peci

ficat

ion

nego

tiatio

ns,

engi

neer

ing

and

proc

urem

ent p

roce

sses

co

ntin

ue w

ith n

egot

iatio

ns o

n co

st im

pact

s

DTE

and

OE

det

aile

d re

view

of b

id

tech

nica

l offe

ring,

sco

pe a

nd e

xcep

tions

Req

uire

bus

ines

s ca

se to

su

ppor

t cha

nge,

CR

B P

roce

ssM

icha

el E

Ban

ksO

n-go

ing

proc

ess.

Util

izin

g bu

sine

ss c

ase

eval

uatio

n fo

r app

ropr

iatio

n of

fund

s.Y

10.0

$

P

M in

put

0.90

9.0

$

Y

20C

hang

es in

cod

e / r

egul

atio

ns re

sult

in

addi

tiona

l cos

tS

cope

Sco

peO

PE

NM

LM

LL

M27

Reg

ulat

ors

chan

ge a

cod

e or

regu

latio

nE

ast C

hina

& C

hina

Tow

nshi

ps o

rdin

ance

New

sta

te g

over

nmen

t

Mon

itor r

egul

atio

ns a

nd c

ode

Req

uest

wai

ver,

expl

ore

alte

rnat

ives,

CR

B P

roce

ssD

enni

s B

Dec

ator

N5.

0$

P

M in

put

0.20

1.0

$

N

21U

nkno

wn

unde

rgro

und

cond

ition

s /

cont

amin

atio

n ca

use

proj

ect d

elay

s /

miti

gatio

n co

st

Sco

peS

cope

OP

EN

Lm

lL

LM

9S

oil b

orin

gs id

entif

y is

sue,

exc

avat

ion

iden

tifie

s is

sue

Ele

ctric

T-L

ine,

Gas

Lat

eral

Hea

vy h

aul r

oute

Mon

itor a

dditi

onal

soi

l bor

ings

, mon

itor

exca

vatio

n pr

oces

sE

xplo

re o

ptio

ns fo

r miti

gatio

n,

CR

B P

roce

ssS

cott

D S

obas

UG

act

iviti

es a

re m

ostly

com

plet

e as

of

12/2

/201

9 - R

ecom

men

d re

duci

ng th

e lik

lieho

od, s

ched

ule,

cos

t & s

cope

to "

L"

N6.

0$

P

M in

put

0.03

0.2

$

N

22D

isco

very

of a

rtifa

cts

on s

ite c

ause

co

nstru

ctio

n de

lays

/ co

stS

cope

Sco

peO

PE

NL

LL

LL

L5

Soi

l bor

ings

iden

tify

issu

e, e

xcav

atio

n id

entif

ies

issu

eE

lect

ric T

-Lin

e, G

as L

ater

al

Pha

se 1

arc

haeo

logy

sur

vey

if ne

eded

, re

view

NH

RP

if n

eede

d, m

onito

r add

ition

al

soil

borin

gs, m

onito

r exc

avat

ion

proc

ess

Exp

lore

opt

ions

for m

itiga

tion,

ne

gotia

te p

lan

with

Sta

te, C

RB

P

roce

ss

Sco

tt D

Sob

asTh

is ri

sk it

em o

nly

assu

mes

an

even

t tha

t can

be

ove

rcom

e an

d st

ill m

eet t

he d

esire

d C

OD

. S

imila

r to

Ris

k 21

; the

UG

sco

pe is

nea

rly

com

plet

e an

d ex

posu

re to

unc

over

ing

artif

acts

ha

s be

en g

reat

ly re

duce

d. R

ecom

men

d re

duci

ng th

e ris

k va

lues

to "

L"

N0.

5$

P

M in

put

0.01

0.0

$

Y

23M

ISO

DP

P S

tudi

es in

dica

te a

ffect

ed s

yste

m

upgr

ade

cost

s or

add

ition

al IT

C c

osts

that

are

no

t rei

mbu

rsab

le

Sco

peM

ISO

OP

EN

lM

HL

LM

13M

ISO

GIA

pro

cess

Num

ber o

f app

lican

ts in

the

cue

MIS

O P

GIA

pro

cess

Mon

itor t

he P

JM a

ffect

ed s

yste

ms

stud

y Tr

ack

thro

ugh

Issu

e Lo

g/M

ngm

t

Act

ively

mon

itor M

ISO

and

PJM

pr

oces

ses,

Com

mun

icat

e as

app

ropr

iate

w

ith IT

CN

egot

iatin

g w

ith M

ISO

and

affe

cted

sys

tem

pa

rties

on

iden

tifie

d ite

ms

Wor

k w

ith IT

C o

n op

tions

, CR

B

Pro

cess

Exe

cute

cha

nge

requ

est;

requ

iring

use

of c

ontin

genc

y.

Ran

dall

J K

ulha

nek

GIA

exp

ecte

din

June

202

0. M

PFC

A p

roce

ss

near

ing

conc

lusi

on

Y5.

0$

P

M in

put

0.05

0.3

$

N

27Is

sues

occ

ur w

ith p

erm

itsS

cope

Per

mitt

ing

OP

EN

mL

LL

LL

15P

erm

ittin

g re

quire

men

tsG

as la

tera

l per

mitt

ing

Ele

ctric

T-L

ine

perm

ittin

g

Mon

itor p

erm

ittin

g pr

oces

ses.

Exp

lore

opt

ions

, CR

B P

roce

ssS

cott

D S

obas

As

of 1

1/15

/19

AH

J ha

ve is

sued

per

mits

for t

he

"T"

lline

towe

r sco

pe. W

ill c

ontin

ue to

co

ordi

nate

with

Vec

tor/D

TE G

as o

n th

e st

atus

of

per

mits

for t

heir

scop

e.

N0.

5

P

M in

put

0.05

0.0

$

Y

28E

xtre

me

cond

ition

s oc

cur i

nclu

ding

forc

e m

ajeu

re e

vent

s re

sulti

ng in

con

stru

ctio

n de

lays

Sco

peE

mer

gent

Eve

ntO

PE

Nh

hh

Lh

L85

Wea

ther

Forc

e m

ajeu

re e

vent

, CO

VID

-19

pand

emic

Mon

itor w

eath

er fo

reca

st to

min

imiz

e im

pact

s. M

onito

r CO

VID

-19

pand

emic

de

velo

pmen

ts

CR

B P

roce

ssS

cott

D S

obas

Larg

e am

ount

of U

G C

ivil

work

is c

ompl

ete

- W

eath

er is

stil

l a ri

sk.

Y15

.0

PM

inpu

t0.

70

10

.5$

Y

31V

alue

of g

ener

atio

n du

ring

star

t-up

and

test

ing

is lo

wer

than

exp

ecte

d in

crea

sing

net

co

st

Pric

e-Fi

nanc

ial

Con

tract

OP

EN

HL

HL

LL

45P

rice

of e

nerg

y at

tim

e of

gen

erat

ion

Mon

itor G

en O

ps F

orec

asts

Mon

itor p

rice

of e

nerg

yC

RB

Pro

cess

Ran

dall

J K

ulha

nek

Gen

Ops

risk

. W

ill tr

ack

dow

n ap

prop

riate

co

ntac

t tha

t our

Ris

k O

wne

r will

wor

k w

ith.

Y2.

1$

P

M in

put

0.40

0.8

$

N

32M

ajor

equ

ipm

ent s

uppl

iers

are

una

ble

to

prov

ide

timel

y de

liver

y an

d or

acc

epta

ble

qual

ity re

quire

men

ts.

Non

-Ow

ner

Del

ays

Equ

ipm

ent-

Tech

nolo

gyO

PE

NL

HH

HL

L17

Sup

plie

r fin

anci

al p

ositi

ons

Sup

plie

r equ

ipm

ent i

ssue

s an

d vib

ratio

nM

onito

r sup

plie

rs fi

nanc

ial p

ositi

ons

Insp

ectio

n po

ints

thro

ugho

ut tr

avel

pat

hH

ave

Kie

wit

engi

neer

at p

ipe-

fab

war

ehou

se

Kie

wit

Y5.

0$

D

efau

lt0.

05

0.

3$

Y

32.0

$

Impa

cts

Page 20: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 19

Appendix C – Progress Photos

April 2019

May 2019

June 2019

Page 21: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 20

July 2019

August 2019

September 2019

Page 22: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 21

October 2019

November 2019

December 2019

Page 23: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 22

January 2020

February 2020

Page 24: Lauren D. Donofrio (313) 235-4017 lauren.donofrio@dteenergy

Michigan Public Service Commission Case No.: U-18419 DTE Electric Company April 27, 2020 Blue Water Energy Center Interim Status Report

Page | 23

March 2020