ldpp 02 - e

Upload: quangspkt

Post on 03-Jun-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 LDPP 02 - E

    1/50

    Power Distribution Systemsand Its Characteristics

  • 8/12/2019 LDPP 02 - E

    2/50

    Distribution System Characteristics

    The Electric Power System is usually divided into

    three segments, which are generation,

    transmission, and distribution.

    In a broad definition, the distribution system is

    that part of the electric utility system between the

    bulk power source and the customers serviceswitches.

  • 8/12/2019 LDPP 02 - E

    3/50

    Distribution System Characteristics

  • 8/12/2019 LDPP 02 - E

    4/50

    Distribution System

    A distribution system includes the following

    components

    1. Sub-transmission system;

    2. Distribution substations;

    3. Distribution primary feeders;

    4. Distribution transformers;

    5. Secondary circuits;

  • 8/12/2019 LDPP 02 - E

    5/50

    Distribution System

    Some distribution system engineers define the distributionsystem as that part of the electric utility system between

    the distribution substations and the consumers service

    entrance.

  • 8/12/2019 LDPP 02 - E

    6/50

    Distribution Substation

    Distribution substations consist of an almostinfinite number of designs considerations:

    Load density;

    High side voltage;

    Low side voltage;

    Land availability

    Reliability requirements;

    Load growth;

    Voltage drop

    Emergency conditions;

    Cost and losses

  • 8/12/2019 LDPP 02 - E

    7/50

    Distribution Substation

    A Typical distribution substation arrangement.

  • 8/12/2019 LDPP 02 - E

    8/50

    Distribution Substation

    The voltage of the high side bus can be anywhere from34.5 kV all the way to 345 kV and beyond.

    The average or preferred high side voltage level is

    approximately 115 to 138 kV.

    The average substation consists of two transformers withan impedance of approximately 10 percent (0.1 p.u.).

    The low voltage bus in a multiple transformer substation is

    usually split (contains a normally openbreaker or switch)to alleviate circulating currents as well as reduce the short

    circuit current seen by the system.

  • 8/12/2019 LDPP 02 - E

    9/50

    Distribution Substation

    Normally, Two or more feeders are connected toeach bus through a feeder breaker.

    On smaller substations where short circuit levels

    are lower, a recloseris sometimes used instead ofa breaker.

    Short circuit levels at the terminals of the low

    voltage bus are generally kept at 12 000 amperes

    or less although there are many systems wheremuch higher levels can be found.

  • 8/12/2019 LDPP 02 - E

    10/50

    Distribution Substation

    A typical substation may include the followingequipment:

    Power transformers

    Circuit breakers

    Disconnecting switches

    Station buses and insulators

    Current limiting reactors

    Shunt reactors Current and potential transformers

    Capacitor voltage transformers

  • 8/12/2019 LDPP 02 - E

    11/50

    Distribution Substation

    A typical substation may include the followingequipment:

    Coupling capacitors

    Series capacitors

    Shunt capacitors

    Grounding systems

    Lightning arrestors/gaps

    Line traps Protective relays

    Station batteries

  • 8/12/2019 LDPP 02 - E

    12/50

    Distribution Substation

    The electrical and physical arrangements of theswitching and busing at the sub-transmission

    voltage level are determined by the selected

    substation scheme.

    The selection of substation scheme is based upon

    Safety

    Reliability

    Economy

    Simplicity

    Other considerations

  • 8/12/2019 LDPP 02 - E

    13/50

    Distribution Substation

    The most commonly used substation bus schemes

    Single bus scheme

    Double bus double breaker scheme

    Main and transfer bus scheme

    Double bus single breaker scheme

    Ring bus scheme

    Breaker and a half scheme

  • 8/12/2019 LDPP 02 - E

    14/50

    Substation Location

    The location of a substation is dictated by:

    The voltage levels,

    Voltage regulation considerations

    Sub-transmission costs

    Substation costs

    Cost of primary feeders, main feeders and distribution

    transformers. It is also restricted by other non technical factors.

  • 8/12/2019 LDPP 02 - E

    15/50

    Substation Location

    The following rules should be observed inselecting an ideal location for a substation.

    Locate the substations closer to the load centers

    Locate substations such that proper voltage regulation

    can be obtainable without taking extensive measures

    Proper access for incoming sub-transmission lines and

    out going primary feeders and also allow future growth.

    Should provide enough space for the future substation

    expansion.

  • 8/12/2019 LDPP 02 - E

    16/50

    Substation Location

    The following rules should be observed inselecting an ideal location for a substation.

    Should not be opposed by land use regulations, local

    ordinances and neighbors.

    Should help to minimize the number of customers

    affected by service discontinuity.

    Other considerations such as adaptability, emergency

    etc.

  • 8/12/2019 LDPP 02 - E

    17/50

    Distribution Feeders

    There are various feeder designs that can improvecustomer service:

    Simple radial feeder (system)

    In this system, a given secondary feeder is fed from only one

    transformer and one primary cable. Each substation operates independently and there is no

    duplication of equipment.

    No extra tie cables, circuit breakers or transformers with largereserve capacityare needed.

    System investment is usually the lowest of all circuitarrangements.

    For a well-planned and well-maintained system, the servicereliability of the radial system is usually high.

  • 8/12/2019 LDPP 02 - E

    18/50

    Distribution Feeders Simple radial feeder (system)

    The radial system is exposed to many interruption possibilities

    (the most important of which are those due to primary

    overhead or underground cable failure or transformer failure).

    The loss of a primary cable or transformer will cut off service

    to the affected loads until repairs can be made.

    This is often the reason for design engineers to select one of

    the other circuit arrangements, which can minimize production

    shutdown.

    The system will be satisfactory only if the interruptions

    frequency is very low and if there are ways to operate the

    system without planned outages.

  • 8/12/2019 LDPP 02 - E

    19/50

    Distribution Feeders A typical Simple radial system

  • 8/12/2019 LDPP 02 - E

    20/50

    Distribution Feeders Expanded radial system

    May be applied to larger loads by using a radial primary

    distribution system to supply a number of unit substations

    located near the centers of load, supplying the load throughradial secondary systems.

    This would result in better voltage regulation and in lower

    power loss than in a system using heavy low-voltage feeders of

    extensive length

    If the transformers are installed without individual primary

    protection, a fault in any one transformer will result in loss of

    the entire system.

  • 8/12/2019 LDPP 02 - E

    21/50

    Distribution Feeders Typical Expanded Radial System

    (a) (b) (c)

  • 8/12/2019 LDPP 02 - E

    22/50

    Distribution Feeders

    Secondary Selective System

    This is the next widely used system to radial system

    A pairs of unit substations are connected through a normally open

    secondary tie circuit breaker. Use of this type of system result in reliability increase.

    It providesflexibilityin operation, particularly when equipment is

    being maintained or serviced.

    Any part of a primary feeder, or transformer and associated

    equipment, can be de-energized for inspection or maintenance

    without service interruption.

  • 8/12/2019 LDPP 02 - E

    23/50

    Distribution Feeders

    Secondary Selective System

    (a) (b)

  • 8/12/2019 LDPP 02 - E

    24/50

  • 8/12/2019 LDPP 02 - E

    25/50

    Distribution Feeders

    Secondary Selective System

    Transformers used in this system are often equipped with cooling

    fans to provide additional capacity during emergency operations.

    The tie breaker should be interlocked with the transformersecondary breakers to prevent the transformers from being

    operated in parallel.

    Parallel operation of the transformers would increase the available

    secondary short-circuit current and would risk the loss of power to

    both secondary busesin the case of a transformer fault or primarycable fault.

  • 8/12/2019 LDPP 02 - E

    26/50

    Distribution Feeders

    Primary Selective System

    This system is another way of reducing the time required to restore

    voltage to a load in the event of loss of a primary feeder as

    compared with a radial system. In this system, two or more primary feeders are provided.

    Two primary feeders are extended to each transformer, and

    selector switches are provided so that any transformer may be

    connected to either of the two primary feeders.

    Eachprimary feedermust have sufficient capacity to carry themaximum load that may be connected at one time.

  • 8/12/2019 LDPP 02 - E

    27/50

  • 8/12/2019 LDPP 02 - E

    28/50

    Distribution Feeders

    Primary Selective System

    Under normal operation:

    The system is operated with the load divided approximatelyequally on each primary feeder.

    When a fault occurs on one primary feeder, there will be aninterruption of power to the load connected to that feeder.

    The interrupter switch connected to the faulted feeder will beopened and the respective transformer will be reconnected to theenergized feeder.

    The two switches associated with one transformer should bemounted in separate individual metal enclosures in order that a de-energized feeder may be safely maintained while the other feeder isenergized.

  • 8/12/2019 LDPP 02 - E

    29/50

    Distribution Feeders

    Primary Selective System

    The primary selective system has a higher first costthan a radial

    system and is usually lower than that of a comparable secondary

    selective system. The service reliability of this system lies between that of a radial

    system and that of a secondary selective system.

    This scheme is in popular use on many underground systems.

    It also offers little remedy for computer problems caused by

    temporary faults to the overhead system.

  • 8/12/2019 LDPP 02 - E

    30/50

    Distribution Feeders

    Looped Primary System

  • 8/12/2019 LDPP 02 - E

    31/50

    Distribution Feeders

    Looped Primary System

    In Figure (a) looped primary system:

    The primary loop is fed by a single medium - voltage circuit

    breaker. One loop-sectionalizing interrupter switch is located at the primary

    of each transformer.

    One section of the primary loop is connected directly to the

    primary of each transformer.

    In case of a fault in a transformer or on the primary loop, theprimary circuit breaker will open and clear the fault.

    After the fault is located, the two interrupter switched at the ends

    of the faulted section are opened and the remainder of the loop is

    again energized.

  • 8/12/2019 LDPP 02 - E

    32/50

    Distribution Feeders

    Looped Primary System

    In Figure (b) looped primary system:

    Two medium-voltage circuit breakers are used, one on each end of

    the loop, and two interrupted switches are used at each transformerlocation.

    With this arrangement, the only time that any part of the load is

    without service for a extended period is when a fault takes place in

    a transformer or its secondary bus.

    Any fault on a section of the primary loop will not affect thetransformers supplying their respective loads.

  • 8/12/2019 LDPP 02 - E

    33/50

    Distribution Feeders

    Looped Primary System

    The disadvantage of this arrangement lies in a complex and time-

    consuming operation in locating a faulton the primary loop or on any

    transformer, because the entire system must be de-energized for a time,

    and the time required to restore service may also be lengthy.

    When the load centers are located relatively far apart, the looped

    primary system will cost little more than a comparable radial system.

    The initial cost can be reduced by using fused interrupter switchedinstead of medium-voltage circuit breakers.

  • 8/12/2019 LDPP 02 - E

    34/50

    Distribution Feeders

    Secondary Network System

    This system can provide a very high degree of service reliability to all

    the loads.

    The difference with the secondary selective system is in the way thesystem is operated.

    In the SSS, the tie circuit between secondary buses is normally open

    and each transformer supplies its own load.

    In the SNS, the secondary buses are tied together and the transformers

    operate in parallel to supply the entire load. In the SNS, the transformer secondary switching and protective device

    is a special low-voltage power circuit breaker known as a network

    protector.

  • 8/12/2019 LDPP 02 - E

    35/50

  • 8/12/2019 LDPP 02 - E

    36/50

    Distribution Feeders

    Secondary Network System

  • 8/12/2019 LDPP 02 - E

    37/50

    Distribution Feeders

    Secondary Network System

    Under normal condition

    The total load is shared by all of the transformers operating in parallel .

    For a Fault in a primary feeder or in a transformer or if voltage fail The power flow from the secondary bus to the transformer will cause

    the network protector to open, thus disconnecting the transformer from

    the secondary bus.

    The remaining energized transformers will continue to supply power

    to the bus, and there will be no interruption of power to the loads.

  • 8/12/2019 LDPP 02 - E

    38/50

    Distribution Feeders

    A Spot Network Arrangement

    In this system, there are two or more transformers connected to a

    single bus through network protectors.

    The transformers and primary feeders must have sufficient capacity tocarry all loads connected to the bus with one transformer out of

    service.

    For larger installations, a system having a primary selective and

    secondary network arrangementcan be an advantage.

    Each of the primary feeders must have sufficient capacity to supply theentire load that is connected to it.

    If two primary feeders are used to supply the primary selective

    network system, half of the transformers would normally be connected

    to each feeder with adjacent transformers on different feeders.

  • 8/12/2019 LDPP 02 - E

    39/50

    Distribution Feeders

    A Spot Network Arrangement

    In case of a primary feeder fault, the fault is isolated from the system

    by automatic tripping of the primary feeder circuit breaker and all the

    network protectors associated with the faulted circuit. Maintenance switching of primary feeders can be done without

    customer interruption or involvement.

    Spot networks are common in downtown, high density areasand are

    being applied frequently in outlying areas for large commercial

    serviceswhere the supply feeders can be made available. This system also represents the most compact and reliable arrangement

    of components and is the most reliable for all classes of loads.

  • 8/12/2019 LDPP 02 - E

    40/50

    Distribution Feeders

    A Spot Network Arrangement

  • 8/12/2019 LDPP 02 - E

    41/50

    Factors Effecting Primary Feeder

    Rating

    The nature of the load connected.

    The load density of the area served.

    The growth rate of the load.

    The need for providing spare capacity for emergencyoperation.

    The type and cost of circuit construction employed.

    The design and capacity of the substation involved.

    The type of regulating equipment used.The quality of the service required.

    The continuity of the service required.

  • 8/12/2019 LDPP 02 - E

    42/50

    Factors Effecting Feeder Routing

    Future load growth.

    Load density.

    Physical barriers.

    Voltage drops.

    development patterns.

    Feeder configuration.

    Total cost.

  • 8/12/2019 LDPP 02 - E

    43/50

    Factors Effecting Number of Feeders

    Conductor size.

    Voltage drop.

    Substation capacity.

    Primary voltage levels.

    Load density.

    Feeder length.

    Feeder limitations.

  • 8/12/2019 LDPP 02 - E

    44/50

    Factors Effecting Conductor Size

    Selection

    Power losses.

    load growth rate.

    load forecast.

    voltage drops.

    Transformer rating.

    Conductor rating.

    Total cost.

  • 8/12/2019 LDPP 02 - E

    45/50

    Unit Substations

    Unite substations are small, self-contained, metal-clad units,usually installed in residential areas where large sites are

    unobtainable.

    They are usually well landscaped, and their incoming and

    outgoing feeders are placed underground.Primary feeders from one substation extend to meet those

    from other, adjacent unit substations, this is just to make sure

    a continuous supply in case of a unit substation out of service.

    Each substation, therefore, must be designed with sparecapacity to enable this transfer of load to made during

    contingency conditions.

  • 8/12/2019 LDPP 02 - E

    46/50

    Unit Substations

    A Unite substation consists of the following sections.

    1. Primary section: This provides for the connection of one or

    incoming high voltage circuits, each of which may or not be

    provided with a switching device or a switching and interruptingdevice.

    2. Transformer section: This includes one or more Transformers with

    or without automatic load-tap-changing equivalent.

    3.Secondary section:This provides for the connection of one or more

    secondary feeders, each of which is provided with a switching and

    interrupting device.

  • 8/12/2019 LDPP 02 - E

    47/50

    Unit Substations

    Different Type of Unite substations.

    Radial:One primary feeder to a single step-down Transformer with a

    secondary section for connection of one or more outgoing radial

    feeders. Secondary selective:Two step-down Transformers, each connected to

    a separate primary source. The secondary of each transformer is

    connected to a separate but through a suitable switching and protective

    device.

    Primary selective and primary loop:Each step-down transformerconnected to two separate primary sources through switching

    equivalent to provide a normal and alternate source. Upon failure of

    the normal source, the Transformer is switched to the alternate source.

  • 8/12/2019 LDPP 02 - E

    48/50

    Unit Substations

    Different Type of Unite substations. Secondary spot network:

    Two step-down Transformers, each connected to a separate primary

    source.

    The secondary side of each transformer is connected to a common bus

    through a network protector that is equipped with relays to trip the

    protector on reverse power flow to the Transformer and phase sequence at

    the Transformer secondary.

    The bus has provisions for one or more secondary radial feeders.

    Distribution network:

    A single step down transformer having its secondary side connectedto a bus through a network protector, which is equipped with relays

    to trip it on reverse power flow and reclose upon restoration of the

    correct voltage, phase angle, and phase sequence at the Transformer

    secondary.

  • 8/12/2019 LDPP 02 - E

    49/50

    Unit Substations

    Different Type of Unite substations.

    Duplex:

    Two step down Transformers, each connected to a separate primary

    source. The secondary side of each Transformer is connected to a radial feeder

    These feeders are joined on the feeder side of the power circuit breaker by

    a normally open tie circuit breaker.

    This type is used primarily on electric utility primary Distribution

    Systems.

  • 8/12/2019 LDPP 02 - E

    50/50

    Unit Substations

    Advantages Unite substations.

    Unit substation has been widely accepted for industrial power

    distribution mainly because the engineering of the components is

    coordinated by the manufacturer. The cost of field labor, and installation time are greatly reduced, and it

    is safer to operate.

    The operating costs are reduced due to the reduced power losses from

    shorter secondary feeders.

    Besides, a unit substation is very flexible and easy to expand. Unit substations are available for either indoor or outdoor locations.

    Primary unit substations may be located outdoors, particularly when

    the primary supply is above 34.5 kV.