lecture # 3 - universitas brawijaya · example 1: determine the hourly average production of...
TRANSCRIPT
EARTHMOVING VEHICLES
CIVIL ENGINEERING DEPARTMENT
UNIVERSITY OF BRAWIJAYA
LECTURE # 3
Topics :
Bulldozer
Ripper
Backhoe
Power shovel
Dragline
Clamshell
Loader
LAND CLEARING VEHICLE DOZER
This vehicle can be used for:
Land clearing
Dozing (pushing material)
Ripping
Assisting Scrapper
…dozing…
…ripping
…
Assisting Scrapper
TYPE OF DOZER
BLADE ADJUSTMENT
Tiltin
g
Angle
BLADE ADJUSTMENT
Pitch
BLADE ADJUSTMENT
TYPE OF BLADE :
A. Straight Blade (S-Blade)
For scrapping and stockpiling the soil. It can be used for hard soil as well.
B. Universal Blade (U-Blade)
Used for:
- Soil Reclamation
- Material preparation activity, etc.
C. Angling Blade (A-Blade)
Used for:
To dump the unwanted material aside
To open a driveway
To dig a channel
D. Cushion Blade (C-Blade)
to push the scrapper
Steps to calculate Bulldozer Productivity
A. By Using The Company Chart / Brosure
1. Calculate all correction factors (E) :
1. Correction for Work Condition (tabel E.01 [2] )
2. Correction for Soil Slope (chart E.02 [2] )
3. Correction for Soil Compaction to Standard (p. 38 [2] )
etc…
2. total of correction factor is the result from multiplying all
related correction factor.
3. Get the value of bulldozer max production from tabel E.1.01 [2]
according to vehicle type and span of moving.
4. Actual production = Max Production Total of correction factor
n
i
iEE1
MAXIMUM PRODUCTION OF BULLDOZER BY TYPES
MAXIMUM PRODUCTION OF BULLDOZER BY TYPES
1. Efficiency 100%
2. Steady time for changing gear
0.05 mnt
3. Soil Density 2300 lb/LCY or
1790 kg/m3 (BM) or 1370
kg/m3 (LM)
4. Swell 30%
5. Traction Coefficien :
a. Whell : 0.4 atau lbh
b. Track : 0.5 atau lbh
6. Hydraulic controlled
1. Calculate all correction factors (E)
(table E.01 [2] )
2. Correction for soil slope (graphic E.02 [2] )
Ideal production values are based on a soil density of 2,300 lb/LCY.
tunit weigh material Actual
(standard) Y2,300lb/LC correctweightMaterial
3. Correction for soil compaction (page. 38 [2] )
EXAMPLE 1:
Determine the hourly average production of Crawler Bulldozer D8 S-type Cat. (with a tilt cylinder) that being used for hard clay soil with an average thrust distance of 150 ft (45 m), the road slope 15%. Please use the method of 'slot dozing' (one way). Material density 2650 lb / LCY, the ability of the operator is MODERATE, the efficiency of the working time of 50 minutes / hour.
1. Calculate all correction factors (E)
(table E.01 [2] )
(table E.01 [2] )
2. Correction of land slope (graphic E.02 [2] )
Ideal production values are based on a soil density of 2,300 lb/LCY.
tunit weigh material Actual
(standard) Y2,300lb/LC correctweightMaterial
Correction of soil campation (page. 38 [2] )
= 2300/2650
= 0,87
Answer :
Correction of slope : 1,19 (graphic E.02 [2] )
Hard Clay : 0,80 (table E.01 [2] )
Slot dozing : 1,20 „
Operator ability (moderate) : 0,75 „
Time efficiency (50 mnt/hour) : 0,84 „
Weight Correction = 2300/2650 : 0,87
Answer :
Correction of slope : 1,19 (graphic E.02 [2] )
Hard Clay : 0,80 (table E.01 [2] )
Slot dozing : 1,20 „
Operator ability (moderate) : 0,75 „
Time efficiency (50 mnt/hour) : 0,84 „
Weight Correction = 2300/2650 : 0,87
Correction Factor = 1,19 x 0,8x 1,2x 0,75x 0,84 x 0,87 = 0,626
MAX PRODUCTION OF BULLDOZER BASE ON TYPE
Answer :
Correction of slope : 1,19 (graphic E.02 [2] )
Hard Clay : 0,80 (table E.01 [2] )
Slot dozing : 1,20 „
Operator ability (moderate) : 0,75 „
Time efficiency (50 mnt/hour) : 0,84 „
Weight Correction = 2300/2650 : 0,87
Correction Factor = 1,19 x 0,8x 1,2x 0,75x 0,84 x 0,87 = 0,626
Max Production of bulldozer = 550 LCY/hour
Answer :
Correction of slope : 1,19 (graphic E.02 [2] )
Hard Clay : 0,80 (table E.01 [2] )
Slot dozing : 1,20 „
Operator ability (moderate) : 0,75 „
Time efficiency (50 mnt/hour) : 0,84 „
Weight Correction = 2300/2650 : 0,87
Correction Factor = 1,19 x 0,8x 1,2x 0,75x 0,84 x 0,87 = 0,626
Max Production of bulldozer = 550 LCY/hour
Actual Production = 550 x 0,626 = 344 LCY/hour
B. Theoritical Method:
1. Calculate Blade Capacity per siklus : q = LH2
2. Calculate Wight Load
3. Compare with critical traction whether the vehicle can be used or not
4. If possible to be used, then :
- Determine speed when pushing forward (va) and move backword (vb)
- Calculate Circle Time : (minute)
5. Calculate all correction :
1. Correction of work condition (tabel E.01 [2] )
2. Correction of land slope (grafik E.02 [2] )
Total Correction Factor :
6. Actual Production :
tv
d
v
dW
ba
s
n
i
iEE1
EW
qQs
60
EXAMPLE
Calculate the estimated production of bulldozers using the following data:
Topsoil unit weight : 2300 lb/BCY with Swell = 43%
Coeffien of Traction : 0,9
Pushing Distance : 60 m = 0,0373 mil
Bulldozer Power : 105 HP
S-Blade : length 3,15 m and height 0,96 m
Total weight of bulldozer : 11.700 kg (25.800 lb)
Steady time (gear changing) : 0,1 mnt
Answer :
1. Blade capacity per siklus :
q = LH2 = 3,15 (0,96)2 = 2,9 Lm3 (1 yar kub = 0.76455 m3)
= 3,79 LCY
= 3,79/1,43 = 2,65 BCY
2. Weight Load = 2300 lb/BCY x 2,65 BCY = 6095 lb
3. Pushing Power = 6095 lb
Critical Traction = 0,9 x 25.800 lb = 23.220 lb > 6095 lb …
- bulldozer can be used..
Answer :
4. Cycle time:
DBP = 6095 lb
See table E.2.01 (2)
Answer :
Speed to push forward and backward
Push Speed = 4,92 mph
(interpolating from table E.2.01 [2] )
Backward Speed, use 3rd gear = 4,4 mph
Cycle Time
Push until 60 m, v = 4,92 mph :
= 0,455 mnt
Backward 60 m, v = 4,4 mph, :
= 0,51 mnt
Steady Time = 0,1 menit
Siclus time = 0,455 + 0,51 + 0,1 = 1,065
mnt 6092,4
0373,0at
mnt 604,4
0373,0bt
5. Correction Factor :
Hard Clay : 0,80 (table E.01 [2] )
Slot dozing : 1,20 „
Operator Capability (moderate) : 0,75 „
Time Efficiency (50 mnt/hour) : 0,84 „
Correction Factor = 0,8x1,2x0,75x0,84 = 0,605
6. Actual Production of Bulldozer :
= = 90,3 BCY/hour
605,0065,1
6065,2
60 E
WqQ
s
If hard soil is founded in land clearing, then ripper will be used
Ripper :
- It can be pulled by a tractor
- As an attachment in the tractor
RIPPER PRODUCTION
1. Calculate production capacity of ripping device per trip :
q = length distance depth
2. Calculate Circular Time :
(t = steady time = backward time)
3. Calculate total correction: working time efficiency and work condition factor and procedure (table IV.4.01.05 page. 64 [2] )
4. Calculate Production per hour :
5. Actual Production = 80 % s/d 90 % of hourly production (Q).
tv
dWs
EW
qQs
60
EXAMPLE
Calculate ripper single shank production that being pulled by tractor type D9H CAT. with data as follow:
•Space of ripping : 0,915 m
•Depth of ripping : 0,610 m
•Length of ripping : 91 m
•Speed of ripping : 1,6 km/jam = 26,6 m/mnt
•Comeback time : 0,25 mnt
•Work time efficiency : 60 mnt/hour
1. Calculate production per trip
Production per trip:
q = 91x0,915x0,61 = 50,8 Bm3/trip
2. Calculate cycle time :
Ws = = 3,67 mnt
Total trip per hour = 60/3,67 = 16,35 trip/hour
25,06,26
91
tv
dWs
Ws = = 3,67 mnt
Total trip per hour = 60/3,67 = 16,35 trip/hour
3. Production per hour :
Q = 50,8x16,35 = 830,6 Bm3/hour
25,06,26
91
The result is still 10% - 20% higher.
So, actual production = 80% x 830,6 = 664,5 Bm3/hour or = 90% x 830,6 = 747,5 Bm3/hour
So, the real production between 664.5 to 747.5 Bm3/jam (not yet being multiply with correction factor)
BACKHOE
hoe
back shovel,
pull shovel
GERAKAN-GERAKAN BACKHOE
1. Put pressure on the boom to force the bucket teeth or
cutting edge into the ground
2. Raise the
stick and roll
the bucket
until it is full
3. Dump
the
excavated
material
4. Swing
the
bucket
back to
the
starting
position
BACKHOE
Factors that affect hoe production are the :
-Width of the excavation
-Depth of the cut
-Material type
-Working radius for digging and duming
-Required bucket dumping height
Steps to calculate hourly production of backhoe
1. Calculate Bucket Capacity
2. Determine cycle time
3 Calculate correction factor: E = Ei
4 Calculation backhoe production: Q = q 60/Ws E
PRODUCTION CALCULATION
Correction factors(Ei) :
1. Working time efficiency
2. Working condition efficiency (table IV.4.01.05 [2] pp. 64)
3. Bucket fill factor (table IV.4.01.06 [2] pp. 64)
4. Check Swing factor and depth of cut ;
- Determine optimum depth of cut for a hoe (depends on the type of material being excavated and bucket size, see table IV.4.01.04 [2] pp. 63)
- Determine the ratio of the actual depth of cut and the optimum depth of cut, expressed as a percent
- Determine swing factor and depth of cut (table IV.4.1.03 [2] pp. 63).
%100cut ofdepth optimum
cut ofdepth actual(%)Optimum depth
EXAMPLE
Determine the hourly output for 1 ¾ -cu-yd backhoe.
Notes :
-Material : sand
-swell 43%
-depth of cut: 6 feet, -Angle of swing : 90
-Job Condition : average
Jawab :
1. Bucket Capacity (q)
Bucket 1,75 cu.yd = 2 cu yd (heaped bucket volume)
Swell : 43%
Bucket Capacity : q = 2/1,43 = 1,399 BCY
2. Cycle Time
Bucket fill : 7 detik
Loading haul and swing : 10 detik
Dumping : 5 detik
Back to the starting position : 5 detik
Fix time : 4 detik
Total Cycle Time : 31 detik = 0,517 menit
3. Calculate correction factor: E = Ei
Working hour efficiency= 50/60 : 0,84
Working condition average : 0,65
Bucket fill factor (soil) : 0,85
Optimum depth of cut= 9,7 feet
b. Percentage of Optimum depth of cut:
c. Determine swing factor and depth of cut (table IV.4.1.03 [2] pp 63).
: 0,91
%60%8,61%1009,7
6cut ofdepth Optimum
%100cut ofdepth optimum
cut ofdepth actual(%)Optimum depth
Total correction factor : E = 0,840,650,850,91 = 0,42
6.Hourly Production
42,0517,0
60399,1
60 E
WqQ
s
= 68,19 BCY/jam
LOADERS
WHEEL & TRACK LOADERS
LOADERS PRODUCTION
STEP 1: BUCKET SIZE
LOADERS can
usually be
equipped with
several
different size
and type
buckets.
STEP 1: BUCKET SIZE
Buckets are rated in both
Heaped and Struck
capacities.
HEAPED CAPACITY is
the rating of interest for PRODUCTION ESTIMATING.
STEP 2: FILL FACTOR
HEAPED CAPACITY is based
on the SAE standard of a 2:1
material repose angle.
The FILL FACTOR adjusts
HEAPED CAPACITY in LCY
based on the type of material
being handled.
STEP 2: FILL FACTOR
The FILL FACTORS for
wheel and track loaders
are different because of
differences in the
breakout force that can be
developed.
STEP 2: FILL FACTOR
HEAPED BUCKET CAPACITY
X FILL FACTOR
= VOLUME
(LCY)
STEP 3: MATERIAL CONVERSION
The bucket load was in
LCY. It should be
converted to TONS in order
to check tipping load. We
may require the load in
BCY.
LOADER CAPACITY
STEP 4: CHECK TIPPING
A loader must maneuver
and travel with the load.
WHEEL LOADER
OPERATING WEIGHT is
limited to 50% of full-turn
static tipping load.
STEP 4: CHECK TIPPING
A loader must maneuver
and travel with the load.
TRACK LOADER
OPERATING WEIGHT is
limited to 35% of static
tipping load.
STEP 4: CHECK TIPPING
WHEEL LOADER:
Volume X Material Unit Wt
< 0.50 Static Tipping Load full-
turn
STEP 4: CHECK TIPPING
TRACK LOADER:
Volume X Material Unit Wt
< 0.35 Static Tipping Load
STEP 5: CYCLE TIME
LOADER CYCLE TIME has
three components :
(1) Fixed Time to load,
Maneuver with four reversals of
direction (min. travel), and
Dump.
(2) Travel Time
(3) Return Time
LOADER PRODUCTION
STEP 5: FIXED CYCLE TIME
(1) Fixed Time
Time to load
Maneuver with four reversals
of direction (min. travel)
Dump
LOADER PRODUCTION
STEP 5: CYCLE TIME
(2) Travel Speed
(3) Return Speed
Check
Manufactures’ data
for gear speeds.
STEP 5: CYCLE TIME
Travel Speed with a loaded bucket -
Average speed should be about 80%
of maximum in low range.
STEP 5: CYCLE TIME
Return Speed with an empty bucket -
Average speed should be about 60% of
maximum in intermediate range.
STEP 5: CYCLE TIME
(2) Travel Time TRAVEL DISTANCE (FT)
88 TRAVEL SPEED (MPH)TRAVEL TIME (MIN)
(3) Return Time RETURN DISTANCE (FT)
88 RETURN SPEED (MPH)RETURN TIME (MIN)
STEP 5: CYCLE TIME
TOTAL CYCLE TIME =
Fixed Time
+ Travel Time
+ Return Time
STEP 6: EFFICIENCY FACTOR
When selecting a minutes per
hour efficiency factor visualize
the work site and consider:
• Materials being handled, bank or
broken
•Size of the loader’s dumping
target,
(large or small)
STEP 7: PRODUCTION
Working mins / hr
Total cycle time (min)
X Heaped Capacity (LCY)
X Fill Factor
= Production (LCY/hr)
PRACTICAL EXERCISE
You are using a track loader to
load uniform 1½ in. aggregates
from a stockpile. The loader is
equipped with a 2.6 cy bucket
(heaped). What is the minimum
loose volume production that can
be expected per loader cycle?
PE NO. 1
STEP 1: BUCKET SIZE:
• The loader is equipped with a
2.6 cy bucket (heaped).
HEAPED CAPACITY is the rating
of interest for PRODUCTION
ESTIMATING.
PE NO. 1
STEP 2: FILL FACTOR
The FILL FACTORS for wheel and track
loaders are different because of
differences in the breakout force that can
be developed.
Fill Factor: 90 to 110
PE NO. 1
STEP 2: FILL FACTOR
Fill Factor: 90 to 110
What is the minimum loose volume production?
Therefore use the lower value:
Fill Factor: 90
PE NO. 1
HEAPED BUCKET CAPACITY
X FILL FACTOR
= VOLUME (LCY)
2.6 LCY X 0.9 = 2.34 LCY
PE NO. 2
Estimate the best production in tn/hr for
a CAT 938F loader using the largest
possible general purpose bucket w/
bolted on cutting edges. The loader is
being used to load trucks from a
stockpile of mixed dry aggregates
(gravel). Assume a 55 min-hr efficiency.
PE NO. 2
STEP 1: BUCKET SIZE:
• CAT 938G - largest possible
general purpose bucket w/
bolted on cutting edges
3.65 cy heaped capacity
PE NO. 2
STEP 2: FILL FACTOR
• Mixed dry aggregates
(gravel).
• CAT 938G is a wheel loader
Fill Factor: 95 to 100
PE NO. 2
STEP 2: FILL FACTOR
Fill Factor: 95 to 100
• Estimate the best production
Therefore use the higher
value:
Fill Factor: 100
PE NO. 2
HEAPED BUCKET CAPACITY
X FILL FACTOR
= VOLUME (LCY)
3.65 LCY X 1.0 = 3.65 LCY
PE NO. 2
STEP 3: MATERIAL CONVERSION
Material unit weight
• mixed dry aggregates (gravel).
2,490 lb/cy Table 4.3
3.65 cy X 2,490 lb/cy = 9,089
lb
PE NO. 2
STEP 4: CHECK TIPPING
WHEEL LOADER:
Volume X Material Unit Wt
< 0.50 full-turn Static Tipping
Load
20,260 lb
PE NO. 2
STEP 4: CHECK TIPPING
WHEEL LOADER:
Volume X Material Unit Wt
< 0.50 Static Tipping Load full-
turn
9,089 lb < 0.5 X 20,130 lb
9,089 lb < 10,065 lb ok
PE NO. 2
STEP 5: CYCLE TIME (1) Fixed Time to load, maneuver with four reversals of
direction and dump.
27 to 30 sec
• best production
Therefore use 0.45 min
PE NO. 2
STEP 6: EFFICIENCY FACTOR
•55 min-hr efficiency.
STEP 7: PRODUCTION
Working mins / hr
Total cycle time (min)
X Heaped Capacity (LCY)
X Fill Factor
= Production (LCY/hr)
PE No. 2
STEP 7: PRODUCTION
55 mins / hr
0.45 min X 3.65 LCY X 1.0
= 397 LCY/hr
PE No. 2
STEP 7: PRODUCTION
lb/tn 2,000
lb/LCY 2,490LCY/hr 397
= 494 tn/hr
PE No. 2
THE END